Home / Financial Firm (Unknown - Insurer) / Determination 504618

Determination 504618

Claim for rainwater damage to townhouse declined

FirmFinancial Firm (Unknown - Insurer)
Decided2018-12-20
ProductGeneral Insurance · Other general
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

A construction firm claimed under its project insurance for rainwater damage to a townhouse and sought legal fees. AFCA found only the June 2013 damage was within the period of insurance and already settled, so the insurer is not liable and need not pay legal fees.

The complainant could not establish a second covered water event within the period of insurance, and legal costs fall outside Section One cover and the small business product scope.

Issues

Subjects and remedies

home or building damagesmall businessno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination | Case number: 533545 Page 1 of 14 Determination Case number: 504618 20 December 2018 1 Determination overview 1.1 Complaint The complainant is a construction firm and was the builder of three double-storey townhouses. One of the townhouses (unit 3) suffered damage as a result of water entering the roof, which was poorly laid by the complainant ‟s contracted plumber. The complainant, represented by its director, lodged a claim with the financial firm (the insurer) for the resultant damage. The insurer appointed several assessors to the case, and the matter still has not been resolved. The complainant wants the insurer to pay for the resultant damage to the building, plus interest and legal costs. The complainant is represented by its director. Submissions from the complainant ‟s representative are taken to have been made by the complainant. 1.2 Issues and key findings Is the insurer liable for resultant damage to the insured building? The insurer is not liable for resultant damage to the insured building because:  the only evidence of any damage being sustained during the policy period was around June 2013  the insurer previously covered a claim for floorboard damage that occurred around June 2013  the available information does not show that there was a second event during this time or, if there was, the complainant suffered any financial loss from it. Should the insurer pay the complainant’s legal fees? The insurer is not required to pay the complainant‟s legal fees for building damage because:  the hearings which the complainant attended were not with respect to unit 3  Section One of the policy does not provide cover for legal fees. Determination | Case number: 533545 Page 2 of 14 1.3 Determination This determination is in favour of the insurer. The insurer is not liable for any resultant damage and is not required to pay the complainant‟s legal fees. Determination | Case number: 533545 Page 3 of 14 2 Reasons for determination 2.1 Is the insurer liable for resultant damage to the buildings? Policy provides cover for accidental damage The policy provides cover under Section One for Material Damage, described as: „ sudden and accidental physical loss or damage, that you could not have expected to happen to Insured Property…during the Period of Insurance.‟ The complainant has claimed for damage to the internal structure of the insured building, caused by the ingress of rainwater. The poorly laid roof and flashing created the circumstances under which the rainwater was allowed to enter the building. The panel accepts this damage would be sudden and accidental physical damage, and that the complainant did not expect it to happen. Period of insurance The insurer says:  the claimed damage occurred from 22 November 2013, until around 2016  the period of insurance began on 16 June 2012, which was the scheduled commencement of work on the project.  as the period of insurance ended in June 2013, which is before the date of alleged damage, the policy does not respond. For the type of cover the complainant held, the period of insurance is defined as: Period of Insurance begins for the Project when it starts during the Policy Period. It ends with Practical Completion or on expiry of the Maximum Project Duration specified in the Schedule, whichever occurs first. Clause 8.1 of the building contract sets out when the commencement date begins. This provides two different dates. One is based on the date specified in item 9.1 of the building contract. The other says the builder will do everything to ensure that construction begins within 14 days of receiving a number of documents. One of those documents is the building permit. The complainant has provided a copy of the building permit, dated 18 September 2012. The complainant said the project could not commence until the building permit was issued. The insurer has not provided anything to refute this. There is no evidence to suggest the works commenced earlier or were deemed to have done so according to the building contract. Determination | Case number: 533545 Page 4 of 14 Therefore, the panel accepts the project commenced on 18 September 2012. The Maximum Project Duration specified in the schedule is 12 months. The definition of “Practical Completion” includes the date an occupancy certificate is issued. The complainant provided a copy of the occupancy certificate, dated 17 September 2013. Given all this, the panel accepts the „period of insurance‟ commenced on 18 September 2012 and continued until 17 September 2013. There is also a „defects liability period‟ allowed in the policy. This is three months as the period is defined to be the lesser of 12 months (as noted on the policy schedule) or the period specified in the building contract (which was three months). This means that the defects liability period operated from 18 September 2013 until 17 December 2013. Evidence shows there was water ingress in June 2013 It is difficult to establish whether the rainwater ingress occurred as one event, or multiple events over an extended period of time. The complainant has provided a photograph showing a water stain to floorboards into the unit on 7 June 2013. There is a second photograph showing the floorboards cupping and swelling on 25 June 2013. The complainant says the photograph on 7 June 2013 shows water coming from a skylight. The complainant has also provided images of text messages (dated 7 June 2013) between him and the plumber talking about the skylight leaking. The panel is satisfied water caused damage to floorboards on 7 June 2013. This occurred within the period of insurance, and with respect to this damage, the complainant has established a valid claim under the policy. The complainant has also provided other information which indicates the tenants of the unit were sending him text messages about further water ingress. However, thi s information is in the form of photographs of the phone on which the text messages are displayed. While the day of the week and the time of day is visible, no information about the date on which these messages were exchanged is available. The panel therefore cannot be satisfied that any other water ingress events occurred within the period of insurance (that is, up to 17 September 2013), which caused damage. Defects Liability Period does not assist the complainant The panel notes that the cover afforded by the „Defects Liability Period‟ (accepted to be between 18 September and 17 December 2013) is limited to loss or damage:  which the complainant caused to the project while rectifying defects; or Determination | Case number: 533545 Page 5 of 14  that happens to the project during the Defects Liability Period but was caused during the physical performance of the project and prior to practical completion. For the first part, although it is acknowledged that the complainant sought to have his plumber rectify the defects to the roof, there is no suggestion this resulted in any damage to the building. The second part does not advance the complainant‟s position. This responds to damage that manifested in the Defects Liability Period but was caused by an event during the project and prior to the occupancy permit being issued. There is no evidence showing any damage manifesting during the Defects Liability Period, let alone one that was caused by an event during the project and prior to the occupancy permit being issued. The panel is therefore satisfied the Defects Liability Period provides no additional benefit to the complainant for the purpose of this disputed claim. Insurer’s liability limited to the damage shown in June 2013 The complainant says he has other photos and videos showi ng water ingress into the property after the expiration of the defects liability period. However, this is not covered because those damages occurred outside the period of insurance and defect liability period. It is accepted the complainant has established damage to the floorboards of the unit occurred as displayed in the photographs of 7 and 25 June 2013. However, in the absence of information that shows any other damage falling within the period of insurance, no other damage can be accepted as forming part of this claim. Insurer says claimed damage was previously settled The insurer says that the photographs provided by the complainant of the damage appear to relate to a previous claim the complainant lodged and which the insurer settled. Alternatively, the insurer says if it is accepted that a second event occurred, it would appear the initial damage had not been repaired prior to this second event. Therefore, it would appear the complainant is claiming twice for the same damage. The complainant says the first claim was for a severe storm on or around 1 June 2013. This is supported by the insurer‟s release for this claim noting the date of loss to be 1 June 2013. The photographs provided on 7 June and 25 June 2013 were for an event separate to this. Having carefully considered all the available information, the evidence appears to support the insurer‟s arguments for the following reasons. Determination | Case number: 533545 Page 6 of 14 Not clear if there was a second event or that a loss was suffered from it First, the information does not show the damage for the first claim was repaired before the alleged second event. The complainant provided a chronology showing what floorboards works were done between 14 May and 16 July 2013. This was supported by diary e xcerpts. This shows the floorboards were initially installed before 1 June 2013. However, it does not show any works were done to the floorboards between 1 and 24 June 2013. Therefore, this supports the insurer‟s arguments that the damage done by the first event was not repaired prior to the second alleged event. Second, when looking at the claim form, it appears to nominate a date of loss of “7 -6- 13” with a time of 11.00pm. In describing the damage, the claim form said: Unit 3 downstairs flooded and floorboards + ply got wet which has caused the floorboards to cup and swell This type of damage describes the damage in the photograph dated 25 June 2013. The date of loss corresponds with the date of the first photograph. Third, the complainant‟s diary notes s how works were done to replace damaged floorboards from 24 June 2013 until 16 July 2013. It does not distinguish for which event these works were associated with. Also, these works were conducted around the time the insurer settled the first claim given the release was signed on 9 July 2013. Fourth, the claim form was signed on 11 June 2013. This was after the alleged second event. A release was signed on 9 July 2013. This was after both photographs were taken and repairs were almost complete. It is not clear why no discussions or negotiations were undertaken for the alleged second event during this period of time given it also involved water damage to floorboards. Fifth, the amount paid by the insurer for the first event was $24,533.19 exclusive of GST and net of the $5,000 policy deductible. It is not clear what this figure was based on. The only contemporaneous information about the cost incurred by the complainant is two invoices for the floorboards. One was dated 14 May 2013. According to the complainant, this first invoice was associated with the installation of the floorboards before the first event. Therefore, this is not payable. The second invoice was dated 5 July 2013. This was plainly after the two events. However, it is not clear which claim this invoice is associated with. Further, the Determination | Case number: 533545 Page 7 of 14 amount of this invoice (exclusive of GST) is $6,148.54. This is well within the amount paid by the insurer for the first claim. The complainant says that there were leftover floorboards from the first invoice that was used for this claim. Even if that was the case, the amount for the floorboards in total is still well within the insurer‟s settlement. Given all this, the panel is not satisfied the information shows there was a second event in June 2013 or, if there was, the complainant suffered any financial loss from it given the settlement received on 9 July 2013. Therefore, on this basis, the panel does not accept the complainant has shown the insurer is liable to pay for any resultant damage to unit 3. 2.2 Should the insurer pay the complainant’s legal fees? Section One of the policy does not provide cover for legal fees Proceedings have been issued against the complainant at the Victorian Civil and Administrative Tribunal (VCAT). This is with respect to issues relating to other properties being constructed. The complainant says these properties encountered similar problems to the unit in dispute here. The complainant has provided copies of letters from a solicitor („KO‟) dated 15 January 2016 and 2 March 2016. These were addressed to the insurer, advising that the complainant was attending compulsory conferences at VCAT for these other properties. The complainant says the letters from KO put the insurer on notice, as KO believed the insurer should be representing him throughout his claim at VCAT and all related matters. Section One of the policy does not provide cover for legal fees The complainant asks why his legal fees have not been covered. The complainant has referred to Section One which includes cover for:  Professional Fees  Expediting Costs  Mitigation Costs. These benefits are associated with either reinstating the damaged property or taking emergency action to reduce the size of an insured less. The legal costs being claimed are associated with defending claims being made against the complainant by other properties he has constructed. This would not fall within any of the above sections. Instead, such a claim is more likely to fall within the scope of Section Two of the policy. Determination | Case number: 533545 Page 8 of 14 Information presented does not indicate legal fees incurred for Unit 3 Section Two (Public Liability) provides cover for all sums that the complainant becomes legally liable to pay as compensation for personal injury or property loss that:  happens during the period of insurance; and  results from an Occurrence in connection with the Business. This section will also cover legal and other costs incurred in connection with any liability or allegation of liability. The complainant‟s claim for legal costs would arguably fall within this. However, FOS does not have jurisdiction to deal with this section of the policy. As set out in section 3.2, this dispute was dealt with as a “Small Business Insurance Product”. That definition specifically excludes cover in relation to “Legal Liability (incl uding Public Liability and Products Liability”). Further, even if the complainant‟s legal costs were to be considered, there is no evidence to show they were to defend an action associated with the damage to unit 3. The pleadings provided do not show any c laim being made by unit 3. KO‟s letter dated 2 March 2016 only talked about a pending claim for unit 3. The complainant confirmed in an email that the proceedings do not involve unit 3. Given all this, the panel is not satisfied the complainant has incurred any legal fees with respect to compensation for public liability or property loss for unit 3. Determination | Case number: 533545 Page 9 of 14 3 Supporting information 3.1 The determination is made under FOS Terms of Reference The Australian Financial Complaints Authority ( AFCA) has commenced managing disputes previously lodged with F inancial O mbudsman S ervice (FOS) . This determination is made under FOS Terms of Reference but has adopted the following terminology for consistency with AFCA. In this determination the AFCA terms have the same meaning as the FOS terms defined in paragraph 20.1 and Schedule 1, 2 & 3 of the FOS Terms of Reference. FOS definitions AFCA term  applicant  complainant  financial services provider  financial firm  dispute  complaint 3.2 Other issues FOS Jurisdiction The insurer submits this policy is for „contractors all risks‟ and therefore excluded from the definition of „Small Business Product‟ under FOS Terms of Reference (TOR). Under its TOR, FOS may only consider a Dispute in relation to a General Insurance Policy that is a: a) Retail General Insurance Policy; b) Residential Strata Title Insurance Product; c) Small Business Insurance Product; d) Medical indemnity insurance product. The panel is satisfied that the policy issued by the insurer in this matter is not a Retail General Insurance Policy, a Residential Strata Title Insurance Product or a Medical Indemnity Insurance Product. The TOR provides that a Small Business Insurance Product is a policy that provides insurance cover (whether or not the cover is limited or restricted in any way) in respect of: (i) Computer and Electronic Breakdown; (ii) Fire or Accidental Damage – but, in a Dispute about an insurance claim that has been made by the Applicant, only to the extent that the insurance cover relates to a Specified Defined Event; (iii) Loss of Profits/Business Interruption; Determination | Case number: 533545 Page 10 of 14 (iv) General Property; (v) Glass; (vi) Land Transit; (vii) Machinery Breakdown; (viii) Money; and (ix) Theft, but excluding cover in relation to any of the following: (x) Contractors All Risks; (xi) Fidelity Guarantee; (xii) Legal Liability (including Public Liability and Products Liability); (xiii) Professional Indemnity; and (xiv) Industrial Special Risks. The panel has considered the insurer ‟s arguments in this regard, and notes the definition of Small Business Insurance Product within the TOR, excludes cover in relation to Contractors All Risks, and in relation to Legal Liability. However, the panel accepts that:  the policy includes cover for „material damage‟, which it describes as „ sudden and accidental physical loss or damage‟ which the complainant could not have expected to happen to the insured property, within the territorial limit during the period of insurance.  the claim by the complainant is for damage to the internal structure of the insured building, caused by rainwater which entered the building as a result of a poorly laid roof and flashings  the claim is for the Specified Defined Event of „Storm/Tempest/Rainwater‟  the insurer has not provided a submission explaining what „Contractors All Risks‟ cover means and why its policy satisfies this description – particularly given there is no reference to such a description in the policy  the exclusion for Legal Liability does not prevent the complainant ‟s claim from being considered with respect to the Specified Defined Event of „Storm/Tempest/Rainwater‟ under the material damage cover Accordingly, the panel is satisfied that the dispute regarding the claim for material damage falls within the TOR and can be determined by FOS. 3.3 Policy provisions Policy schedule PERIOD OF INSURANCE 29 May 2012 to 29 May 2013 at 4pm Local Time BASIS OF INSURANCE OF PROJECTS Run-off PROJECT DETAILS Building Residential: New Determination | Case number: 533545 Page 11 of 14 Description of Projects Residential building including alterations and additions Maximum Project Duration 12 mont hs Maximum Defects Liability Period 12 mont hs Policy wording Glossary of terms used … „ Defects Liability Period ‟ means, for any Project, the lesser of the period specified in the Schedule and the period specified in the contract for that Project. During the Defects Liability Period, cover under Section One of the Policy is limited to loss or damage: (a) that you cause to the Project while rectifying defects; or (b) that happens to the Project during the Defects Liability Period but was caused by an event during the physical performance of the Project and prior to Practical Completion. … „ Occurrence ‟ means an event that you neit her ex pect nor int end. It includes any continued or repeated exposure of people or property to conditions that are generally the same. … „ Period of Insurance ‟ has the following meaning in Section One of the Policy. … (b) Project Run-Off Basis: Where the insurance is on this basis, the Period of Insurance begins for the Project when it starts during the Policy Period. It ends with Practical Completion or on expiry of the Maximum Project Duration specified in the Schedule, whichever occurs first. The Defects Liability Period (if applicable) will immediately follow Practical Completion. Notwithstanding the above, the Period of Insuranc e for each part of the Project will end at the time the part attains Practical Completion or is taken over by the principal or put into servic e, whichever occurs first. This will be so even if the Project as a whole has not yet attained Practical Completion. The Defects Liability Period (if applicable) for that part will then follow. Where this Policy is not renewed, insurance does not extend beyond the Policy Period for Cont ractor‟s Plant, Tools and Reusable Equipment insured under Item 1.05. … „ Policy Period ‟ means the current period for whic h the Policy is in for ce. The period begins and ends on the dates specified in the Schedule. ‘Practical Completion’ means: (a) the stage at whic h a Project is complete except for minor omissions and defects that do not prevent it from being reasonably capable of use for its int ended purpose; or Determination | Case number: 533545 Page 12 of 14 (b) where the Project is subject to issue of a Certificat e of Practical Completion or an Occupancy Certificate or equivalent, the date upon which the certificate or permit is issued, or would have been issued but for reas ons that do not involve construction work. … ‘Property Loss’ means physical loss of or damage to tangible property resulting from an Occurrence. It includes consequent loss of us e of the property. … SECTION ONE – MATERIAL DAMAGE Insurance Provided 1.00 [FSP] will indemnify you for sudden and accidental physical loss or damage, that you could not have expected to happen to Insured Property, within the Territorial Limit during the Period of Insuranc e. Cover under this Section of the Policy is subject to all terms of this insuranc e in so far as they can apply. Except where stated to the contrary, [FSP]s liability will not exceed the sum insured on the lost or damaged property. … Basis Upon Which Claims Are Paid … 3.03 Loss resulting from earthquake, Storm, fire, Flood, water, rain, landslip, erosion, subsidence or collaps e during any period of seventy-t wo consecutive hours will be deemed one loss for the purpose of applying a Deductible. You may choose the time at which a 72-hour period commences, but no two periods may overlap. … Section One Exclusions 4.00 Cover under Section One of the Policy is subject to the following exclusions: … 4.04 De sign, Material and Workmanship (a) This insurance does not cover the cost of correcting defective property irresp ective of whet her the defect results from defective mat erials, incorrect specification, defective workmanship or defective design. For the avoidance of doubt, such shortcomings in any works are not „damage‟. If damage occurs involving defective property, the amount payable for the damage will be reduced by the amount that would have been incurred in correcting the defect before the damage occurred. (b) This insurance does not cover damage caused by defective workmanship. However, this only applies to the part directly damaged by the defective work performed on it, and not to any consequent damage to any other part of the Project. … Determination | Case number: 533545 Page 13 of 14 SECTION TWO – PUBLIC LIABILITY Insurance Provided 5.00 [FSP] will indemnify you for all sums that you become legally liable to pay as compensation for Personal Injury or Property Loss that: (a) happens within the Territ orial Limit during the Period of Insuranc e; and (b) results from an Occurrence in connection with the Business. Cover under this Section of the Policy is subject to all terms of this insuranc e in so far as they can apply. [FSP] will also indemnify you for the following costs, but only if they are incurred by [FSP] or with [FSP]‟s consent, which will not be unreasonably withheld. Cover for these costs is in addition to the Limit of Indemnity specified in the Schedule. 5.01 Legal and ot her costs incurred in connection with any liability or allegation of liability to which this insurance applies. 5.02 The cost of your legal representation at any coroner‟s inquest held in connection with the Occurrence. … Section Two Exclusions 8.00 Cover under Section Two is subject to the following exclusions. … 8.10 Project This insurance does not cover liability for damage to any property insured under Section One of this Policy, nor damage to any property under construction on a contract site where you are, or have been, working and where damage results from work you have performed on that property. For the avoidance of doubt, Existing Structures are not considered to be property under construction. 8.11 Property in Care, Custody or Control This insurance does not cover liability arising out of Property Loss: a) Caus ed to any part of property by work that you have done on that part; … GENERAL CONDITIONS 10.00 These conditions must be complied with before you become entitled to any benefit under this Policy. If you fail to observe any of them and the failure increases [FSP]‟s exposure to any insured loss, [FSP] may reduce the amount of your claim or decline to pay it altogether. … Determination | Case number: 533545 Page 14 of 14 10.04 Claim Conduct If any loss, damage or allegation of liability occurs that may give rise to a claim under this Policy, you must: (a) inform [FF] of this as soon as you can; … (c) take all steps within your power to minimise the extent of loss, damage or liabil ity; … 10.08 Risk Management Without exception, you and your Employees must: … (d) take all reasonable steps to prevent incurring any loss, damage or liability;

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.