The applicant sought the FSP to pay for waterproofing and retiling a shower recess and to carry out repairs rather than cash settle. AFCA found the shower recess waterproofing was excluded, the cash settlement of $6,495.44 was fair, and the assessor's inconsistent report caused no detriment.

The shower recess waterproofing is excluded maintenance, the policy allows cash settlement at the FSP's discretion, and no estoppel arose because the applicant did not rely on the assessor's error to his detriment.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 503570 Determination Page 1 of 4 Case number: 503570 21 March 2018 1 Overview 1.1 Dispute The applicant (and his wife) holds a landlord insurance policy with the financial services provider (FSP) to cover their investment property against certain insured events, such as an escape of liquid. Leakage from a copper pipe connected to the hot water system in the laundry affected carpet in the adjoining area. The property manager sent out a plumber who cut a hole in the laundry wall and replaced the copper pipe. The FSP has accepted the cost of repairing the wall. This aspect of the claim is not in dispute. Leakage from a failed waterproof membrane in the shower recess affected the particle-board bathroom sub-floor. Although the F SP’s assessor originally noted waterproofing and retiling the shower recess as part of the insurable repairs, the scope of works has since been amended to exclude such repairs. However, the FSP agreed to replace the particle-board flooring in the entire bathroom. The FSP says that maintenance works such as waterproofing the bathroom are excluded from the policy, and are required to be done by the applicant. The FSP decided to cash settle the applicant because he has not yet performed such maintenance. The FSP waived any applicable excess and paid the applicant $6,495.44 for damage to the carpet, particle-board, and other items. The applicant says the copper pipe to the hot water system caused the bathroom damage and so the FSP should be responsible for waterproofing and tiling the bathroom. The applicant says it is not reasonable to cash settle his claim. 1.2 Issues and key findings Has the FSP fulfilled its policy obligations? The FSP has fulfilled its policy obligations because:  the copper pipe leak in the laundry did not damage the bathroom floor  the cost of waterproofing and tiling the shower recess floor is not covered  the FSP is entitled to cash settle the applicant in discharge of its policy obligations, and the cash settlement amount is fair and reasonable. 1.3 Determination This determination is in favour of the FSP. The FSP is not required to pay any compensation to the applicant. Case No: 503570 Determination Page 2 of 4 2 Reasons for determination 2.1 What is the first issue? The applicant has the onus of proving the loss was caused by an insured event The applicant has the onus of proving on the balance of probabilities the insured event occurred and that the event caused the loss or damage claimed. This is known as establishing a prima facie claim. It is not disputed that the applicant has suffered damage to the particle-board flooring in the bathroom. It is also not disputed that an insured event of an escape of liquid occurred. In order to be successful in his claim, the applicant must show that the escape of liquid from the laundry copper pipe caused damage to the bathroom flooring. In order to defeat the claim, the FSP must show that the escape of liquid from the failed waterproof membrane in the shower recess (which is an exclusion under the policy) caused damage to the bathroom flooring. The copper pipe leak in the laundry did not damage the bathroom floor There were two escapes of liquid. One leak came from a copper pipe on the hot water system located in the laundry. The applicant says the leaking copper pipe in the laundry caused the damage to the bathroom flooring. However, the applicant has provided no documents or evidence to support his position. The FSP appointed professionals to inspect and assess the property. The FSP’s assessor noted only the access hole but into the laundry wall by the insured’s plumber in order to replace the copper pipe, but otherwise there were no signs of water damage to the laundry. The assessor did not identify any possible damage to the bathroom from the laundry leak. The available information limits the damage from the copper pipe leak to the laundry. Although the laundry is next to the bathroom, I am not satisfied that the copper pipe leak in the laundry damaged the bathroom floor. The failed waterproofing in the shower recess damaged the bathroom floor The second leak came from the failure of the waterproof membrane in the shower recess. The FSP’s assessor used thermal imaging to identify the fixing of a grab rail in the shower had caused water entry and swelling of the bottom plate of the timber wall and particle-board sub-floor. Water pressure tests revealed that the failed waterproofing was not caused by any leaks in the potable or hot water pipes. The applicant has not provided any contrary information or reports. I am satisfied that the proximate cause of the damage to the bathroom flooring was the failed waterproof membrane in the shower recess. The policy does not cover the cost of retiling the walls or floor of the shower recess in circumstances where liquid escaped from a shower recess. Case No: 503570 Determination Page 3 of 4 The FSP is not liable for waterproofing and tiling the shower recess The FSP’s assessor noted in the body of his initial report that the insured must engage his own tradesperson to fix the failed waterproofing. However, under the scope of works at the end of the same report, the assessor noted water proofing and retiling as an insurable repair: … we have considered the repair to the shower recess to be (sic) render [it] water tight as maintenance and has been advised to the insured to carry out works at their expense prior to insurable repairs can be engaged. We recommend acceptance of this claim under the defined event of escape of liquid pending the insured engaging a suitably qualified specialist to repair the failed water proof membrane to the shower recess. Insurable repairs 1. Engage suitably qualified tradesman to strip out the shower recess, install affective water proofing and retile shower recess. This reference to stripping out, water proofing and retiling the shower recess was removed from the scope of works in a later (corrected) report. The applicant noticed the inconsistency in the assessor’s initial report and seeks to hold the FSP to its assessor’s mistake by making the FSP bear the cost of water proofing and retiling the shower recess. The applicant also says the assessor told his tenant that the shower recess would need to stripped. By doing so, the applicant says the FSP is prevented from denying liability for repairs. Estoppel arises where a contracting party unequivocally represents that he will not be relying on contractual rights or remedies, and there is detrimental reliance upon that statement by the other contracting party. The FSP has not unequivocally represented that it would bear the cost of waterproofing and retiling the shower recess. It is clear from the context of the assessor’s report that the applicant was responsible for the cost to fix the failed waterproofing. Further, the applicant has not relied upon the representation to his detriment. The applicant has taken no steps nor suffered any loss as a result of the assessor’s mistake. The FSP is not liable for the cost of stripping out, water proofing and retiling the shower recess. The FSP is entitled to cash settle the applicant Although the applicant has received the FSP’s $6,495.44 cash settlement cheque, he has not yet presented it because he prefers the FSP to undertake repairs rather than cash settle. The applicant wants the FSP to conduct the repairs because he is concerned that tradespeople might find further water damage to the sub-floor. Even if there was water damage beyond the immediate vicinity of the shower recess, the FSP increased its allowance to repair the particle board bathroom flooring from 1m 2 to 5m 2 . This anticipates that the entire bathroom sub-floor might need to be replaced, and takes into account any additional water da mage elsewhere in the bathroom. The applicant suffers no loss because the FSP has elected to cash settle. When settling the claim the policy allows the FSP a discretion to either repair the loss or damage, or pay a cash amount representing the reasonable cost to repair or Case No: 503570 Determination Page 4 of 4 replace such damaged property. In circumstances where the applicant has not yet performed the underlying and necessary waterproofing, the applicant is best placed to coordinate the tradespeople engaged to perform works where some of the works are not part of his insurance claim. I am not persuaded that it is fair for the FSP to be held responsible for coordinating tradespeople to conduct the repairs. The cash settlement amount of $6,495.44 was determined based on the previous quotes of the FSP’s provider, and the FSP elected to waive any applicable excess. The applicant has not said this settlement amount is insufficient to perform the insurable repairs. In the absence of any quotes provided by the applicant to the contrary, I consider the cash settlement amount to be fair and reasonable. 3 Supporting information 3.1 FOS approach This dispute has been determined based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions (which are not binding). There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered. While the parties have raised numerous issues in their submissions, for the purposes of this determination, commentary has been restricted to those issues which are considered directly relevant to the outcome only. The applicant says that the FSP’s assessor’s initial report noted estimat ed start and finish dates which did not turn out to be true. The applicant also says that despite promises to return telephone calls, emails and the like, the FSP’s various agents did not do so. These matters do not affect the outcome of the dispute and do not warrant additional compensation.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.