Home / Financial Firm (Unknown - Insurer) / Determination 503000

Determination 503000

Storm claim settlement amounts for building, mould, contents and delay

FirmFinancial Firm (Unknown - Insurer)
Decided2019-03-20
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$45,453
Non-financial loss$500
Amount claimed$135,313
SourceAFCA PDF

Summary

Complainants disputed the insurer's storm claim settlement for building, mould, contents and temporary accommodation. AFCA ordered increased building, mould and contents payments, consequential and assessment costs, $500 non-financial loss and further interest, but rejected air-conditioning, sewer pipe and additional temporary accommodation claims.

The insurer's contents assessment was incomplete and delay was shared, while policy exclusions and limits applied to the rejected heads.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay compensationpay interestpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination | Case number: 503000 Page 1 of 14 Determination Case number: 503000 20 November 2018 1 Determination overview 1.1 Complaint The complainants lodged two claims for damages to their building and contents following a storm in July 2016. The financial firm (the insurer) accepted liability for the claims and made an offer to pay for building repairs, contents, mould remediation and temporary accommodation. The complainants dispute the extent of the insurer‟s settlement offer and would like to be reimbursed and compensated for other related costs. 1.2 Issues and key findings What is the insurer ’s liability for the building claim? The insurer is to increase its liability for the building claim to allow for the following:  a variation to account for the cedarwood panels in the master bedroom  an increase to its allowance for mould remediation to $61,044.50  contributing $2,345 towards the cost of replacing the built-in drawers and shelves What is the insurer ’s liability for the contents claim? The insurer is required to do the following:  contribute $6,166.50 towards the cost of replacing the blinds  pay an additional $20,000 for the complainants‟ non -salvageable contents What other amounts are the complainants entitled to? The complainants are entitled to the following:  a contribution of $330 towards CS‟s cost  $1,650 payment for consequential financial loss  an additional $500 for non-financial loss  a further award of interest as set out in section 2.3 Determination | Case number: 503000 Page 2 of 14 1.3 Determination This determination is substantially in favour of the complainants. The complaint should be resolved in the manner set out in sections 2.1, 2.2 and 2.3 of this Determination. Determination | Case number: 503000 Page 3 of 14 2 Reasons for determination 2.1 What is the insurer ’s liability for the building claim? Cash settling the claim was appropriate During the course of the claims, the insurer was prepared to repair the claim related damage. However, this was subject to the complainants addressing substantive issues with the roof not covered by either claim. In August 2017, the insurer communicated to the complainants that it would cash settle the claim. The insurer has maintained this position since. The policy provides the insurer with the discretion as to whether it will repair or cash settle a claim. Such a discretion should be exercised reasonably, fairly and consistently with the principles of utmost good faith. The substantive issues with the roof have not been remedied. There is no dispute they are not covered by the claim. It is clear that internal repairs cannot be completed until they are addressed. Given this, the panel is satisfied the insurer‟s decision to cash settle the claim is fair in all the circumstances. This is further supported by the fact the complainants acknowledged that they were open to a cash settlement as they were uncertain if they would renovate or demolish (whole or in part) the property. Amount offered for building repairs is generally adequate The insurer‟s builder, PB, prepared two scope of works, one for each claim. The insurer paid interest on these scopes and added a 10% loading for unforeseen costs. The insurer accepts it may have further liability if during the course of repairs the complainants identify previously uncontemplated areas damaged by the claim events that is not covered by the 10% variation. The complainants say they are satisfied with the amounts offered, except in respect of the master bedroom. The complainants say the scope of works allows for removing and replacing plasterboard walls, whereas two of the walls in the master bedroom are made of cedarwood panelling. The insurer says this change has been noted and updated in PB‟s scope of works. The panel has reviewed the documents carefully. PB‟s scope of works refe rs to the engineer‟s (F) document. F‟s scope of w orks talks about plasterboard in the master bedroom (noted as bedroom 1). There is no reference in F‟s scope of works that this was changed to include the cedarwood panelling. Determination | Case number: 503000 Page 4 of 14 Therefore, the insurer is to make a variation for the two cedarwood panel walls in the master bedroom scope of works and settle the complainants for the same. Insurer not required to pay for air-conditioning rectification or sewer pipe The complainants have asked the insurer to rectify the faulty workmanship for the air- conditioning and recover this from their previous insurer. This faulty workmanship was the subject of one of the two claims. The policy does not respond to the cost of rectifying faulty wo rks from another insurer. Therefore, there is no basis for the insurer to cover this. The complainants have also asked for the insurer to repair the cracked sewer pipe. This type of event is covered under the policy as an escape of liquid. However, this cover contains this specific provision: the cost of repairing or replacing the item from which the liquid escaped; Therefore, the insurer is not liable for this cost. Insurer is to increase the amount for remediation The complainants ask the insurer to cover the quote for mould remediation provided by their preferred mould remediator (CS) totalling $61,044.50 (dated 30 January 2018). The insurer has paid the complainants $46,082.82 for mould remediation based on a number of quotes from its preferred specialist, CR. The panel has reviewed their scope of works. They are mostly similar. The discrepancies appear to be the following:  CS has allowed for the removal and disposal of all blinds whereas CR quoted for cleaning and sanitising  CS allowed for the removal and disposal of shelves and drawers in the built-in wardrobe whereas CR simply said the shelving should be disassembled  CS‟s scope of works appeared to include the “office/spare room” – this appears to be missing from CR‟s scope of works  CS allowed for 1.2 metres of plaster to be removed from bedroom 2 whereas CR allowed for 300mm. Having carefully considered the available information, the panel prefers to base a cash settlement on CS‟s quote for these reasons. First, and of significance, the complainants sa y CR was not prepared to do the works for them. This means CR‟s quote is not an actionable quote. Second, CS‟s scope of works appears more complete. F or instance, it allowed for works in the “office/spare room” which was missing from CR‟s scope of works Determination | Case number: 503000 Page 5 of 14 This does not mean the panel agrees with all the discrepancies in favour of CS. For reasons to follow, the panel does not accept the disposal and removal of blinds and the shelves in the built-in robe should be allowed in full. However, the panel does not accept these differences would have increased the cost given the following:  the cost of disassembling the shelving compared to disposing of it should not result in any material difference in pricing  it is likely the cost of cleaning and sanitising all the b linds would be higher than simply removing and disposing of them. Therefore, the panel accepts it is fair in all the circumstances that the insurer increases its settlement for the mould remediation to $61,044.50. Complainants want $5,000 to replace built in shelves and drawers The complainants ask the insurer to provide an additional amount to replace the mould affected built in shelves and drawers from their master bedroom. CR‟s report included the following works for this: MASTER BEDROOM … Disassemble wardrobe shelving to access plaster Remove and dispose of mould affected plaster in the wardrobe CS‟s report says: Main bedroom … Remove and dispose of mould affected plaster in the wardrobe. Remove and dispose of shelves and draws in the BIR, due to moisture swelling CS‟s report was provided more than a year after CR. Based on these discrepancies, the panel considers it is likely that the requirement to replace the built- in shelves and drawers is due to the passing of time between CS‟s inspection and CR‟s report. The complainants say the delay was caused by the insurer. The insurer disputes this. Parties are equally responsible for the delay CR ‟s report and scope of works are dated 13 December 2016. The insurer emailed the complainants on 20 February 2017 with a number of settlement options. One included a cash settlement. The complainants did not respond with their preference. Instead, discussions after this date mainly focused on the contents. It was not until August 2017 that the insurer informed the complainants they would now cash settle the claim. Determination | Case number: 503000 Page 6 of 14 This prompted a number of email exchanges. The complainants queried a number of aspects of the insurer‟s position. Much of their focus was on the contents settlement, why the insurer now decided to cash se ttle the claim and temporary accommodation. The insurer ultimately provided payment to the complainants on 8 January 2018. The amount paid for the two claims totalled $253,823.09. Prior to this payment being made, the panel does not accept the complainants were in a position to mitigate their loss. Particularly when the mould remediation costs that the complainants would have to incur would be above $60,000. There is nothing to suggest the complainants had access to such funds. However, the panel does not accept that the delay in receiving this payment is entirely due to the insurer. The insurer offered a number of settlement options to the complainants regarding building damage on 20 February 2017. This was not responded to. Instead, much of the focus afte r this was assessing the contents. Whilst this is understandable to a degree, the short-term focus needed to be on the mould remediation to the building. Particularly given its likelihood of increasing and spreading when left unchecked. Therefore, the pan el accepts that the complainants‟ conduct did contribute to the delay in finalising a cash settlement. The panel also accepts the insurer contributed to this. It is not clear why the contents were not fully assessed prior to the email being sent on 20 February 2017. Particularly given the storm claim was lodged on 8 August 2016. Further, it is not clear what efforts the insurer made to make available the funds for the mould remediation and building repairs once it decided to cash settle the claim. Given this, the panel considers it is fair in all the circumstances that the parties be considered evenly responsible for the delays in making available the funds. However, the panel accepts that once the funds were available, any additional damage that has incurred is due to the complainants‟ failure to mitigate their loss. This is because by that stage, they were in a financial position to mitigate their circumstances. Insurer is to pay $2,345 for the built-in robes and drawers The complainant provided a quote to replace the built-in robes and drawers. This set out two replacement options, one for $5,100 and the other at $4,690. The panel is satisfied the complainants‟ quote is fair and reasonable. The insurer is to pay the complainants a further $2,345, being 50% of the lower quote. Determination | Case number: 503000 Page 7 of 14 2.2 What is the insurer ’s liability for the contents claim? Insurer to pay 50% of the cost to replace the blinds The complainants say the insurer ‟s offer to remediate and re -use their blinds is inadequate . CS‟s report dated 30 January 2018 says the blinds need to be disposed of. The insurer relies on reports from its remediator, CR, from August and December 2016, which say the blinds can be removed, sanitised and reinstated. The insurer goes on to say the complainants have not mitigated their loss by failing to remediate their property during the course of the complaint. The panel is satisfied the blinds were at one time restorable, but now must be disposed of and replaced. The panel is also satisfied the need to replace them flows on from the delay in cash settling the claim. Given this, the panel accepts it is fair in all the circumstances the insurer pays 50% of the cost of replacing the blinds. This totals $6,166.50. Insurer to settle the non-salvageable contents in the following way The complainants say the amounts offered by the insurer for non-salvageable contents is inadequate. The complainants provided their own list of non-salvageable contents on 31 January 2018. This totalled $66,564.01. This list includes items from throughout the entire property including kitchen items, linen, clothing and footwear. The insurer paid the complainants $31,059 (plus interest) for items it identified as non-salvageable during the course of considering the claim. The insurer maintains it properly assessed its liability for non-restorable contents and does not believe the complainants are entitled to further cover. The insurer did not provide a list or costings as to what its settlement figure was based on. The insurer has provided two inventories taken by CR on 8 May 2017 and 20 June 2017 in support. These inventories go through a number of items with a conclusion as to whether they are restorable or non-salvageable. No pricing was provided of the items deemed non-salvageable. When comparing CR‟s inventories with the complainants, there are clearly items missing. Much of this includes the complainants‟ clothing which tot als over $32,000 of their list. Receipts and proof of this list was not provided to AFCA. The complainants say the two mould technicians sent by the insurer to catalogue the non-salvageable items were not given enough time to complete the task and left Determination | Case number: 503000 Page 8 of 14 ear ly. This is consistent with the fact that CR‟s inventories did not include the clothing affected or the other items in the complainants‟ list. The insurer‟s claim notes indicated most of the complainant‟s contents could be cleaned. This appears to be base d on CR‟s scope of works which referred to dry cleaning the clothing. However, CR did not provide any specific reasoning as to why it considered the clothing was restorable given the presence of mould in the bedroom and the home. It is also not clear CR inventoried or considered all of the clothing in the bedroom. Therefore, this is not persuasive. Given this, the panel accepts it is fair in all the circumstances that the complainants‟ non-salvageable contents claim be settled by an additional payment of $20,000. This is due to the following:  the insurer had sufficient opportunity to fully assess and catalogue all of the contents being claimed but did not appear to do so  the complainants‟ position about non -salvageable items that are not addressed in CR‟s in ventories is unrefuted  it is difficult to accept most of these items could be salvageable when the building requires extensive mould remediation  it would be unfair to expect the parties to go through all of the items individually and price them when the claim is over two years old  the complainants have not substantiated the price of all the items claimed with receipts despite being asked to do so and the panel does not agree there is sufficient basis to accept the prices claimed on face value  the extra allowance of $20,000 provides a total amount of $51,059 for the contents – the panel considers this is fair given the findings set out above. 2.3 What other amounts are the complainants entitled to? Complainants not entitled to additional temporary accommodation cover The complainants say the temporary accommodation allowance provided by the insurer is inadequate. The policy relevantly provides: When an insured event damages your home to the extent you cannot live there, and we agree, we will pay for your reasonable temporary accommodation costs for the time it will take to repair or rebuild your home to a liveable condition. There is no dispute the complainants‟ home is presently unliveable as a result of water entry and mould. Determination | Case number: 503000 Page 9 of 14 PB says it will take eight weeks to complete the repairs necessary for both claims. CR says mould remediation will take a further four weeks. CS did not specify a timeframe for its proposed remediation. Given the available information, a reasonable estimate for reinstating the property to its pre-claim condition is three months. It would of course be appropriate to allow some extra temporary accommodation coverage in case of any delays. The insurer paid the complainants for six months temporary accommodation at $700 per week, for $18,600. The complainants say this was inadequate when the available leases are all for 12 months and properties which would meet their needs are in high demand. The complainants say they will incur costs for leaving the rental property early. The complainants say they will not be able to arrange reinstatement as quickly as the insurer. The additional three months paid for by the insurer adequately addresses the complainants‟ concerns regarding the repair timeframe. The panel also notes the insurer has agreed to cover any break costs which the complainants may incur. Given this, the panel accepts the insurer‟s position on temporary accommodation is reasonable. CS’s costs The complainants seek reimbursement of CS‟s fee of $902. This charge included: Assessment on site x 2 $300 Labour to prepare and read reports (8 hours) $520 CS‟s fee appears to be mainly associated with providing a quotation and scope of works. CS provided no report setting out its reasons as to why it disagreed with CR‟s scope of works. We may require the insurer to contribute to the professional costs incurred by a complainant. This normally occurs when the professional costs assisted the complainant‟s position. CS‟s quote did assist in ascertaining the likely cost the complainants w ould incur to remediate the property. However, it provided no substantive opinion or commentary on the issues in dispute. It is therefore unclear what assistance the labour cost generated. Therefore, the panel considers it fair for the insurer to only contribute to the assessment cost. This totals $330. Determination | Case number: 503000 Page 10 of 14 Insurer to compensate the complainants $1,650 for consequential loss We may compensate complainants for consequential losses which arise from the insurer‟s conduct. Whether a loss is consequential is decide d on a case by case basis and depends on all the circumstances of the complaint. Claims for compensation for consequential loss are capped at $3,300 per claim. The complainants ask to be compensated for electricity, gas, water bills as well as phone and internet. This is because these costs have accrued at the insured property while they been living elsewhere. The complainants provided bills for the electricity, gas and water totalling $1,802.76. The complainants say the internet and phone charges are take n out automatically. The complainants also ask to be compensated for an estimated additional 150 kilometres travelled per week necessitated by their living separately. The panel does not accept it is clearly established that the complainants had to travel an additional 150 kilometres per week. It is also not clear if all the utilities they are seeking were losses caused by the insurer‟s handling of the claim. For instance, it is not clear:  why the phone and internet could not be disconnected given the property is unliveable  to what extent the water bills includes rates that are normally payable by owning the property. However, the panel also acknowledges that the complainants‟ decision to live with their parents substantively mitigated the insurer‟s potential losses. For instance, if the complainants had to pay alternative accommodation whilst pursuing this dispute, the n it is likely the insurer would have at least had to contribute 50% towards these costs in recognition of its part in delaying the cash settlement. Therefore, the panel considers it is fair in all the circumstances the insurer pays $1,650 to the complainants for consequential financial loss. This is based on the following:  it is likely most of the utility costs were incurred due to the delay in cash settling the claim  whilst it is not clear there was an additional 150 kilometres travelled each week given the two properties are about 5 kilometres apart, it is likely additional fuel costs were incurred as the complainants were living separately – the panel considers it is fair to allow for this  it is possible these consequential losses would reach the $3,300 cap  a 50% deduction should be made given the panel accepts there was a 50/50 contribution to the delay of cash settling the claim. Determination | Case number: 503000 Page 11 of 14 Insurer to compensate the complainants additional $500 for non-financial loss We may decide the insurer compensate the complainants when, as a result of an act or omission by the insurer, they suffer an unreasonable degree of physical inconvenience, time taken to resolve a situation, interference with their peace of mind or loss of enjoyment of an asset. These are called „non -f inancial losses‟. The maximum amount of compensation payable for non-financial loss is capped at $3,000. The insurer previously paid the complainants $2,000 compensation for the time taken to resolve the claim, the health impacts on the complainants‟ child ren arising from mould exposure and the displacement of the complainants‟ family. Having regard to the circumstances of the claim, the panel notes the complainants‟ family life has been significantly disrupted. The male complainant lives separately from his wife and children. They have less time together as a family and must spend time travelling between their respective locations. This situation has been exacerbated by the insurer‟s failure to properly assess the contents. This was clearly an issue the co mplainants had raised numerous times and based on the information available, was not completely addressed. It is clear these events have taken a significant toll upon the complainants. However, the panel accepts that the cause of delay in cash settling the claim was contributed by the complainants. Further, after receiving the cash settlement, the complainants were in a position to mitigate their circumstances. In addition, the delays and inconveniences suffered in disputing the insurer‟s decision would fal l within the normal degree expected of anyone challenging an insurer‟s decision. Given all this, the panel is satisfied it is appropriate for the insurer to pay the complainants a further $500 compensation. Complainants entitled to a further limited award of interest The insurer paid the complainants statutory interest on the settlement amounts from 20 February 2017 to 24 November 2017. This encompasses from when the insurer originally proposed cash settlement to when the insurer actually issued cheques to the complainants. The complainants say the insurer confirmed they delayed the originally proposed settlement by 41 days. The complainants therefore ask for interest to also be awarded for this period. The panel confirms this acknowledgement is set out in the insurer‟s file note dated 28 September 2017. Determination | Case number: 503000 Page 12 of 14 Given this, the panel accepts the complainants are entitled to a further 41 days of interest on the payments made. This does not include business days as the file note makes no reference to this. This means interest should be payable from 10 January 2017. Interest is also payable for the additional amounts awarded in this determination for the non-salvageable contents, the variation to the building scope of works and the additional mould remediation. This is because those amounts ought to a have been included in the insurer‟s settlement. Interest is not payable for the insurer‟s contribution towards the blinds and built -in wardrobe. This is because the panel has based the amount on an estimate of t he insurer‟s contribution to the delay rather than a liability under the policy. Interest is also not payable on RC‟s costs, consequential financial losses or non - financial losses. It is not plain RC‟s costs substantively assisted the complainants‟ positi on. Consequential financial loss was an estimate provided in the complainants‟ favour and not payable under the policy. Interest does not flow in any award for non- financial loss. Determination | Case number: 503000 Page 13 of 14 3 Supporting information 3.1 The determination is made under FOS Terms of Reference The Australian Financial Complaints Authority ( AFCA) has commenced managing disputes previously lodged with Financial Ombudsman Service (FOS). This determination is made under FOS Terms of Reference but has adopted the following terminology for consistency with AFCA. In this determination the AFCA terms have the same meaning as the FOS terms defined in paragraph 20.1 and Schedule 1, 2 & 3 of the FOS Terms of Reference. FOS definitions AFCA term  a pplicant  complainant  financial services provider  financial firm  dispute  complaint  claim  claim 3.2 Our approach This complaint was not subject to a FOS recommendation. Due to the nature of the complaint, including the issues raised and complexity, it was referred directly to a panel for determination. The panel consists of an Ombudsman and two representatives with consumer and insurance experience. The panel decided this complaint based on what is fair in the circumstances, having regard to the relevant legal principles, the terms of the policy, good industry practice including relevant codes of practice and prior determinations where applicable. There has been a full exchange of all material relied upon in this determination. Each party has had the opportunity to address any issues raised by the other. The panel reviewed and considered all of the material provided by the parties. While the parties have raised numerous issues in their submissions, for the purpose of this determination, the panel restricted its commentary to those issues it considered directly relevant to the outcome only. Determination | Case number: 503000 Page 14 of 14 3.3 Policy terms Temporary accommodation when you have home cover When an insured event damages your home to the extent you cannot live there, and we agree, we will pay you for your reasonable temporary accommodation costs for the time it will take to repair or rebuild your home to a liveable condition. Limits – Classic The most we will pay under this feature is 10% of the home sum insured and the longest period you can claim for is 12 months. 3.4 Expert reports Record Key points Insurer’s mould remediator (CR) Water & Organic Growth Report 17 August 2016  Mould present throughout a large area of the home.  Carpet in the master bedroom and plaster in the walls indicate a high level of mould, yet there is no moisture indicating this was occurring over a long period of time.  Bottom wall plat es and studs beneath the kitchen cabinets depict high level of mould.  Inspection was non - invasive and so there may mould present in inaccessible ar eas (such as wall cavities).  Clothing in master bedroom wardrobe can be dry cleaned.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.