Home / Financial Firm (Unknown - Insurer) / Determination 502155

Determination 502155

Lift repairs and tenant business interruption claim refused in part

FirmFinancial Firm (Unknown - Insurer)
Decided2018-10-16
ProductGeneral Insurance · Business / commercial
OutcomeFor the complainant in part
Amount awarded$18,808
Non-financial loss—
Amount claimed$207,766
SourceAFCA PDF

Summary

A trust that owns a commercial building claimed under its business policy for lift repairs and lost rent after an air conditioner failure. AFCA ordered payment of the drive and encoder cost and business interruption cover for 15 January to 11 February 2017, with interest, but rejected the other repairs and later losses.

The resulting damage exception applies where the air conditioner failure was the proximate cause of damage otherwise excluded for breakdown or temperature change.

Issues

Subjects and remedies

business interruptionsmall businesspay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 502155 Determination Page 1 of 10 Case number: 502155 27 September 2018 1 Overview 1.1 Dispute The applicant is the corporate trustee of a trust which owns a tenanted commercial property. The property is insured under a business insurance policy with the financial services provider (FSP). The applicant lodged a claim under the policy after the lift at the premises stopped working in January 2017. The applicant says the problems with the lift occurred due to overheating of the lift drive caused by the failure of the air conditioning unit in the plant room. The applicant seeks cover for the costs of repairing the lift. The applicant also seeks cover for losses incurred due to the effects of the lift failure on the business of one of its tenants. The FSP says it is not liable for the applicant’s claim because the damage to the lift was caused by factors which are excluded under the policy (such as mechanical breakdown, wear and tear and high temperatures). 1.2 Issues and key findings Is the FSP liable for the lift repairs? The available information establishes that the damage to the lift drive (and initial damage to the lift encoder) was caused by overheating as a result of the failure of the air conditioner in the plant room. The FSP has not shown that this damage would otherwise be excluded under the policy. Accordingly, the FSP is liable for the cost of replacing the lift drive and the lift encoder. The FSP is not liable for the remaining repairs because this damage did not result from the failure of the air conditioner (but was caused by factors which are excluded under the policy). Is the applicant entitled to cover for business interruption? The applicant is entitled to cover for loss of income for the period from 15 January 2017 to 11 February 2017, when the lift was out of service awaiting the replacement of the overheated drive unit. The applicant’s entitlement to cover during this period is limited to the loss of rental and outgoings which would otherwise have been received from the tenant during this Case No: 502155 Determination Page 2 of 10 period (taking into account) any discounts or rebates which were already in place for other reasons. Is the applicant entitled to compensation? The applicant is not entitled to compensation as the FSP managed the claim reasonably overall. The delays experienced during the claim process were primarily due to a lack of co- operation by the applicant’s repairer (O). 1.3 Determination This determination is partially in favour of the applicant. The FSP is required to:  pay the applicant the amount of $18,808 in full and final settlement of its property damage claim, and  settle the applicant’s business interruption claim for the period from 15 January 2017 to 11 February 2017 (inclusive), as outlined in section 2.2 below and otherwise in accordance with the terms of the policy. The FSP is required to pay interest on the settlement amounts at the rate calculated in accordance with section 57 of the Insurance Contracts Act 1984 (the Act), from 27 July 2017 until the payment date. Case No: 502155 Determination Page 3 of 10 2 Reasons for determination 2.1 Is the FSP liable for the lift repairs? Policy provides cover for property damage subject to exclusions The applicant is required to show that, on the balance of probabilities, it suffered a loss caused by a risk insured against under the policy. This is known as a valid (or prima facie ) claim. If the applicant is able to establish a valid claim, then the onus shifts to the FSP to show that, on the balance of probabilities, it is entitled to rely on an exclusion under the policy to deny the claim. The property damage section of the applicant’s policy provides cover for accidental, physical damage to the insured property. In this context, accidental damage means damage that is unintentional and unexpected. However, this cover is subject to general exclusions for damage caused by:  mechanical, electronic or electrical breakdown, and  gradually operating causes such as wear and tear and changes in temperature. The above exclusions are subject to a proviso, which states that the FSP will pay for any damage to the insured property that results from damage caused directly by one of the excluded factors (and is itself not otherwise excluded). The proviso effectively operates as an exception to the exclusions. The applicant had elected not to take out the optional cover available under other sections of the policy for damage to engineering plant and electronic equipment. These sections provide broader cover for damage caused by breakdown than is provided under the property damage section. Lift required repairs between January and May 2017 The applicant’s property is a four storey, commercial building with a single lift. The lift controller and lift drive are located in a cabinet contained in the plant room, which is located on the roof of the premises. The plant room contains a dedicated air- conditioning unit which maintains the temperature for the lift control room. The applicant contracted responsibility for the regular maintenance of the lift to a specialist provider (O), who arranged for its sub -contractor (K) to provide the maintenance services. The lift room log book (maintained by K) confirms that a fault with the lift was reported on 15 January 2017, after a period of hot weather. The lift was reported to have stopped above the top level, with the lift controller noted as being ‘very hot’. K reset the power but found that the lift continued to stop above the top level. The log book records a similar fault on 16 January 2017 (although it is not clear whether a second event occurred). K attended the property on 19 January 2017, Case No: 502155 Determination Page 4 of 10 cleared the fault and reported that the lift ‘tested OK’. However, he was called back to the property after the lift once again stopped above the limit for the top floor. On 25 January 2017, O provided a quotation for the supply and installation of a replacement lift drive. These works were completed on 9 and 10 February 2017. During the installation of the lift drive, the lift encoder was found to be faulty and was replaced at that time. A fault was also identified with the choke in the lift controller. Accordingly, the choke was removed and the speed of the lift was reduced to minimise the flow of current until it could be replaced. Further repairs to the lift were undertaken on 8 May 2017, when the choke was replaced and a new encoder was installed (after the existing one was reported to be noisy). At this time, the replacement lift drive installed in February 2017 was found to be ‘arcing’ and a further (third) drive was ordered. During May 2017, the lift was again reported to be stopping incorrectly at the top floor. The lift drive was replaced under warranty on 27 May 2017. During this period, further issues were experienced with the lift cabin shuddering during the ride, which apparently continued into June 2017. Applicant says damage to lift was caused by failure of air conditioner The applicant seeks cover for the cost of some of the repairs to the lift (totalling $24,126.30) which were undertaken between January and May 2017. It says these repairs were required after the lift components overheated. As outlined above, the policy contains an exclusion for damage caused by gradually operating causes, including changes in temperature. Accordingly, the FSP is not liable for damage caused by overheating which occurs solely due to hot weather. However, in the present case, the applicant says that the lift components overheated because the air conditioner in the plant room failed. The lift log room book confirms that the lift maintenance sub-contractor (K) noted that the air conditioner was not working when he attended the premises on 19 December 2016. However, K did not advise the applicant or take any other steps to address this issue. It is unclear exactly when the air conditioner failed, as K’s previous attendance was on 28 July 2016 and no one else was authorised to access the plant room. The applicant accepts that the policy does not provide cover for the damage to the air conditioner itself, due to the general exclusions for breakdown and/or wear and tear (and its decision not to take out optional cover for engineering plant). However, the applicant says that the damage to the lift should be covered under the resulting damage exception to these exclusions (as outlined above), which provides cover for damage to other property that results from the failure of the air conditioner. The FSP disputes it is liable for the damage to the lift. The FSP says that: Case No: 502155 Determination Page 5 of 10  the damage to the lift was due to gradually operating causes such as wear and tear and high temperatures, which are excluded under the policy  the ‘resulting damage’ exception d oes not operate to provide cover for damage which is otherwise excluded under the policy, and  in any event, the damage was not ‘accidental’ as the applicant was aware of the risk that overheating may occur. Damage to lift drive was caused by failure of air conditioner As outlined above, the lift required repairs over an extended period of time due to the failure of various components. There is limited information available to determine the cause of the damage to each component. The applicant did not lodge its claim under the policy until 3 March 2017 (after the initial repairs had been carried out). Accordingly, the FSP was unable to appoint its own contractor to assess the damage. The FSP sought a detailed, written report from the applicant’s lift ma intenance contractor (O) to confirm the manner in which the damage occurred. However, O failed to respond to the FSP’s repeated requests over a period of several months. The FSP has provided a file note which records a discussion between its loss adjustor (CL) and an employee of O in July 2017. The applicant has provided copies of quotations and invoices provided by O in relation to the lift repairs. Having carefully reviewed the available information, the panel is satisfied that the initial damage to the lift drive in January 2017 was caused by overheating due to the failure of the air conditioner. The quotation for the initial repairs provided by O on 25 January 2017 stated that a replacement drive was required due to the air conditioning unit having failed, which caused the drive to overheat. This is consistent with the entry in the log book when the repairs were carried out, which stated that the MCB board on the lift drive was ‘blown’. CL’s file note indicates that O later confirmed that the MCB board had been ‘cooked’, which caused the failure of the lift in January 2017. He advised that, when K attended in January 2017, he found that the cabinet housing the lift drive was extremely hot. On this basis, the panel is satisfied that the failure of the air conditioner was the proximate cause of the damage to the lift drive (that is, the dominant, effective or operating cause). The panel does not consider that the damage to these components is ‘otherwise excluded’ under the policy exclusions for breakdown a nd/or gradually operating causes. In this regard, the panel notes that:  the policy definition of ‘breakdown’ only applies to damage caused by a ‘ mechanical, electrical or electronic defect ’ (and not overheating), and  while the damage was triggered by the high temperatures experienced in January 2017, it would not have occurred had the air conditioner been Case No: 502155 Determination Page 6 of 10 operating as intended (given its express purpose was to maintain the temperature of the lift control room). The lift encoder was also replaced when the initial repairs were carried out in February 2017. In these circumstances, the panel is satisfied that the need to replace the lift encoder arose as a result of the failure of the air conditioner On this basis, the FSP is liable for the cost of replacing the lift drive and the lift encoder ($18,808). FSP is not liable for remaining repairs The FSP is not liable for additional costs incurred by the applicant, including the cost of replacing the transformer. The panel is not satisfied that this damage was caused by the failure of the air conditioner (rather than due to mechanical breakdown and/or wear and tear) . Neither the invoices provided by O for the repairs nor the notes in the lift room log book link the damage to overheating. Further, the file note provided by the FSP reflects that O advised that:  the damage to the choke was discovered when the lift drive was replaced and was identified as a maintenance issue which was not related to the high temperatures, and  the shuddering issues with the lift were caused by a lack of lubrication to the lift guides. The panel acknowledges that the information contained in CL’s file note has not been independently substantiated. However, this is in part due to the failure by O (the applicant’s repairer) to provide a written report, despite repeated requests. The panel has also taken into account the fact that the FSP did not have the opportunity to conduct its own assessment of the damage, as the c laim was not lodged until after the initial repairs had been completed. The FSP is not liable for any further issues arising from the initial repairs as these repairs were carried out by the applicant and not by the FSP. 2.2 Is the applicant entitled to cover for business interruption? Policy provides cover for business interruption The policy schedule reflects that the applicant had elected to take out cover for business interruption on an income basis. In these circumstances, the policy provides cover for rental income lost by the applicant during the period while the business was adversely affected by damage to the property which is covered under the policy. For this purpose, rental income includes any rent or outgoings payable by the tenant under the lease agreement. Case No: 502155 Determination Page 7 of 10 Applicant seeks cover for loss of income due to impact on tenant The applicant seeks cover for income lost due to the effect that the damage to the lift had on the business of its fourth floor tenant (a restaurant). The applicant says that:  the failure of the lift in January 2017 (and the ongoing issues over subsequent months) irreparably damaged the restaurant business, such that it ultimately ceased trading in August 2017  during this period, the tenant did not pay any rent or outgoings, and  the applicant did not secure a new tenant until December 2017 (and then only at a discounted rate). The applicant seeks a total amount of $183,639.34 for income lost during the period from 1 January 2017 to 31 December 2017 (including the rental discount provided to the new tenant). Applicant is entitled to cover for limited period only As outlined above, the applicant is only entitled to cover for loss of rent (and outgoings) not paid by the tenant, to the extent that the loss was caused by the failure of the lift due to overheating. The panel has been provided with limited information about the arrangements for payment of rent agreed between the applicant and the restaurant tenant during the relevant period. However, the FSP’s lawyer (SR) acknowledge d that the lease agreement contained a clause which arguably required the applicant to reduce the rent and outgoings where access to the premises was restricted. Further, the panel accepts that, given the nature of the business and its location on the fourth floor, it was reasonable for the applicant to waive payment during the period when the lift was not operating at all. The applicant did so in order to support the ongoing operation of the business (in an attempt to mitigate its own future loss). Accordingly, the panel considers the applicant is entitled to cover for loss of income for the period from 15 January 2017 to 11 February 2017, when the lift was out of service awaiting the replacement of the overheated drive unit. However, the applicant’ s entitlement to cover is limited to the loss of rental and outgoings which would otherwise have been received from the tenant during this period. Accordingly, the amount payable under the lease should be reduced by any discounts or rebates which were already in place for other reasons. The applicant is not entitled to cover for loss of income for any period after 11 February 2017, as the ongoing issues with the lift were not caused by overheating due to the failure of the air conditioner (or any other factors which are subject to cover under the policy). Case No: 502155 Determination Page 8 of 10 2.3 Is the applicant entitled to compensation? FOS may award compensation for financial and non-financial loss FOS can award compensation (capped at $3,300) for consequential financial loss suffered by an applicant in connection with their claim. In addition, FOS can award compensation (capped at $3,000) for non-financial loss where an applicant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind. However, FOS takes a conservative approach to compensation for non-financial loss and expects an applicant to be moderately robust and bear the usual degree of inconvenience when managing an insurance claim. Circumstances do not justify award of compensation The applicant is dissatisfied with the manner in which the FSP handled his claim. In particular, the applicant says the FSP unnecessarily delayed making a decision on his claim. The applicant say s the FSP’s delay has prevented him from taking alternative steps to recover his loss (such as pursuing action against its lift maintenance contractor (O)). However, having reviewed the history of the claim, the panel considers that the bulk of the delays occurred due to O’s failure to respond to the FSP’s enquiries. Given the nature of the damage to the lift, it was reasonable for the FSP to seek a detailed report from the contractor who had carried out the repairs. The FSP acted promptly to seek information from O and followed up at regular intervals when a response was not received. The FSP was unable to undertake its own assessment as the repairs had been completed before the claim was lodged. In these circumstances, the panel does not consider that the applicant is entitled to compensation. Case No: 502155 Determination Page 9 of 10 3 Supporting information 3.1 FOS approach to dispute This dispute has not been the subject of a FOS recommendation. Due to the nature of the dispute, it has been referred directly to a panel for determination, in line with the Operational Guidelines to the FOS Terms of Reference. The panel consists of an Ombudsman and two representatives with consumer and insurance experience. The panel has decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous Financial Ombudsman Service (FOS) decisions. There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. The panel has reviewed and considered all of the material provided by the parties. While the parties have raised numerous issues in their submissions, for the purposes of this determination the panel has restricted its commentary to those issues which it considers directly relevant to the outcome only. The applicant is the corporate trustee of a trust which owns the insured property. For the purposes of this determination, the applicant and its representative are referred to co llectively as ‘the applicant’. 3.2 Terms of policy Subject Terms Cover for property damage We will pay up to the limit of liability in accordance with the Basis of Settlement for property that is damaged at the premises during the period of ins urance. Damage or Damaged means accidental physical damage, destruction or loss. Property damage – exclusions Exclusions …  We will not pay for consequential loss of any kind  We will not pay for damage caused directly by or arising directly from: - breakdown - gradually operating causes such as, but not limited to, wear and tear, mildew, mould, corrosion, disease, oxidisation, fading, tree roots, evaporation, change in flavour, colour, temperature or texture … Provided that we will pay for any damage to property that is not otherwise excluded that results from damage caused directly by or arising directly from any of these causes. Property damage - definitions Breakdown means the actual breaking, seizing, deformation or melting of any part of the property while it is in use that is caused by mechanical, electrical or electronic defect that results in sudden and total loss of operation that requires repair or replacement before the property can resume normal operation. Consequential loss means loss of us e, loss of earning capacity and any other Case No: 502155 Determination Page 10 of 10 Subject Terms consequential financial loss of any kind including an increase in costs and expenses caused directly or indirectly or result from:  delay or interruption of business … or  any other indirect result of consequenc e of a breakdown. Cover for business i nterruption Cover We will pay in accordance with the Basis of Settlement, for loss of income that results from an interruption of your business caused by any insured damage that happens at the premises. Basi s of Settlement  Additional expenditure We will also pay for additional expenditure necessarily incurred for the sole purpose of reducing loss of income that is covered by this cover section and/or resuming and/or maintaining your normal business operations or services. Provided that this expenditure is limited to the amount that would otherwise be lost had the additional expenditure not been incurred .  Loss of income Loss of income will be calculated by subtracting the income earned during the indemnity period from the i ncome you would have earned during the indemnity period had the damage not occurred. Provided that the income you would have earned during the indemnity period had the damage not occurred … will be calculated by reference to … Business interruption - definitions Income means … income received from the renting or leasing of any part of the premises including monies paid by the lessee as outgoings under the terms of the rental or leasing agreement … Indemnity period means the period that starts of the da te of the damage and ends not later than the number of weeks or months stated in the schedule aft er the date of the damage during which results of your business are affected as a consequence of the damage. Interruption means interruption or interference. Loss of income mea ns loss or reduction of your income that occurs during the indemnity period

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.