Text of the determination
Determination | Case number: 501515 Page 1 of 20
Determination
Case number: 501515 3 May 2019
1 Determination overview
1.1 Complaint
In 2004, the complainant lodged a claim with her financial firm (insurer) for damage to
her house caused by a leaking pipe. After several assessments, the claim was
accepted with the repairs finishing in 2005.
In 2007, the complainant advised the insurer of further damages. The insurer
reattended and found several items which they attributed to the original claim. Several
other areas where identified which were deemed the complainant ’s responsibility.
In 2015, the complainant lodged a new claim for new damages which she believed to
be due to inadequate repairs conducted in 2004. After assessing the damages, the
insurer declined the claim as there was no insured event which caused the damage.
1.2 Issues and key findings
Is the insurer entitled to deny the complainant’s claim ?
The insurer is entitled to deny the complainant’s claim because the available
information does not establish on the balance of probabilities the claimed damage
was caused by an insured event or by the repairs.
1.3 Determination
This determination is in favour of the insurer.
The insurer is not required to take any further action in relation to the complaint or the
claims.
Determination | Case number: 501515 Page 2 of 20
2 Reasons for determination
2.1 Is the insurer entitled to deny the complainant’s claim
Circumstances of the 2004 loss
The complainant must establish on the balance of probabilities she has suffered a
loss caused by an event to which the policy responds. This is known as a prima facie
claim. In the context of this claim, the complainant must establish the claimed damage
was caused by water leaks or by the insurer ’s inadequate repairs.
In May 2004, the complainant lodged a claim. She said she had noticed minor
cracking when she moved into the house a few years earlier but in the last three
weeks the cracking and movement became worse.
A plumber told her the main sewer located outside the laund ry was probably cracked.
The insurer arranged its adjuster/builder (EA) and builder (AA) to attend the property
and assess the damages. Both EA and AA attended the property in June 2004.
A summary of all attendances and reports by all experts is provided in supporting
section 3 of this determination.
AA arranged their own contractor to test the sewer drain system. A leak was located.
The major failures were in the general location of the kitchen and laundry. AA
recommended the complainant replace the whole external sewer system.
EA described the extensive floor damage in the laundry and bathroom and adjacent
paving. As for the cracking damage, EA recommended it be repaired after the
plumbing was repaired. EA described extensive wall damage to the kitchen, hallway,
laundry, bathroom, toilet and dining room.
AA provided a quotation to repair this work in the sum of $32,406. It included the cost
of exposing the earthenware drain to allow replacement by the complainant and
backfill and consolidation of the trench after the new drain was laid.
AA also provided a quotation to repair the leaking sewer pipes in the sum of $1,606.
The quotation is marked private. EA indicated the complainant accepted the quote for
her own costs involved in replacing the leaking sewer.
It was agreed the sewer would be replaced first and the repairs to the building would
take place at the end of summer to allow settling of the property.
In July 2005, EA sent a letter to the complainant advising repairs had been complete .
However, EA indicated to the complainant further damage may occur, noting:
Determination | Case number: 501515 Page 3 of 20
As you are aware from our several discussions, whilst all repairs related to the defined
event are now complete, we anticipate there will be some movement to your dwelling of
an environmental nature on an ongoing basis due to –
a The type of soil your house is constructed on
b Close proximity of council trees and other non-related factors such as weather
conditions, drying of soil
No available material indicates there were any problems with the repairs at this time.
Insurer paid for further repairs in 2009
However, further problems arose in early 2007. During the past summer, the
complainant said the house began to move.
EA reattended and inspected inside and outside the house.
EA described cracking in the hallway, bedroom, lounge, kitchen and entrance. He
also referred to reinstatement of brickwork outside the lounge room and the kitchen
and laundry.
Relevantly EA stated:
The dwelling itself has no signs of leaking pipe work. The insured has tested the water
meter and confirmed that no mains pressure pipes are leaking.
All of the movement is consistent with shrinkage caused by gum trees on the rear and
eastern side of the dwelling on council property.
Photographs show extremely dry land surrounding the house and mature gum trees
on council land at the rear and side of the house.
On this basis the claim was denied.
The complainant then indicated there was sewage overflows and flooding of the
sewer system which had occurred on several occasions over the last five years
leading to water flooding underneath the house.
The complainant wanted the vanity unit in the bathroom repaired, the repair of areas
which were previously repaired and repairs to a new area on the opposite side of the
house.
In response, a structural engineer was engaged. The appointed engineer (MP)
attended in July 2007. He described the damage. He looked through a floor trap in the
hallway and he noted no discernible indication of past or present moisture.
He undertook a level survey of the building. The building had settled. He said the
recent movement was minimal and there was no sign of obvious heave near the
replaced sewer. He said the damage could be due to several factors including:
Determination | Case number: 501515 Page 4 of 20
long-term movement because of tree and environmental drying of the reactive
foundation soils
a recent settlement rebound due to rear tree removal
minor reduction in previous heave due to pipe fracture repair.
He thought it was possible the earlier cosmetic repairs may have been undertaken
prematurely. Giving the complainant the benefit of the doubt, he said internal crack
repair and painting should be allowed for. He recommended reattendance in six
months.
In March 2008, MP reattended. He undertook a further level survey which indicated
minimal change. Cracking had closed. There was no new cracking within the area
close to the sewer leakage. He recommended crack repairs could be undertaken.
MP confirmed some damages could be claim related and provided a scope of work
relating to repairs to the brickwork, some sections of concrete and a timber sill
between the toilet and hallway.
EA sent several letters to the complainant advising quotes would need to be obtained
for these repairs to commence.
MP re-attended in February 2009 and provided a list of repairs to rectify damage for
which the insurer was responsible. A scope of works was sent to the complainant in
April 2009.
AA provided a quote in May 2009 in the sum of $7,695.60. Almost all the repairs were
completed by November 2009. However, the complainant declined to have a PVC
inspection point and a crack in the rear bedroom repaired as she believed further
repairs were required outside the scope provided by MP.
The complainant advised she would obtain her own report.
EA sent two letters to the complainant in early 2010 to follow up on her report.
However, as nothing was received, the claim was closed.
No further complaint until March 2015
No contact was made by the complainant until 6 March 2015, when she complained
of further water damage because of a blocked toilet drain. The complainant said the
shower drain blocked sometimes as well.
Plumbers and engineers engaged to report on causation
The insurer appointed a plumber (LH) who found no issues with the main sewer drain.
However, he indicated there were issues with the toilet branch connection and
possibly with the bathroom connection. He said the joint between the lead and PVC
Determination | Case number: 501515 Page 5 of 20
pipe had either broken down or had not been installed properly. Several tree roots
had entered this joint causing blockages. He found no other leaks.
He concluded:
I do believe the damaged and blocked sewer drains could have contributed to damage
within the property as the fittings do leak when in use and especially when blocked
and holding water as they have been.
He made certain recommendations in relation to further work which he said was
required to the drainage system.
Another plumber (JH) was engaged in May 2015. JH conducted tests. Most of the
plumbing (including sewer drainage) was not leaking. However, there was leakage
from the bath waste pipe and the WC branch drain.
The insurer engaged an engineer to determine the cause of the recent cracking and
the relationship to these leaks. A further level survey was conducted. The engineer
concluded the recent leaks had not caused the damage as there was no localised
heave around the toilet area. His level survey showed the toilet area had remained in
a similar elevation to that in previous surveys. He also considered the leaks were not
severe enough to cause the claimed movement.
Further meetings were held between EA and the complainant.
As a result, the insurer agreed to engage another engineer (GP) who inspected and
provided another level survey in May 2016.
GP also concluded the water leak was not severe enough to cause the damage which
he said was supported by the lack of any localised recent distress near to the leak.
GP referred also to the findings from the level survey he undertook and concluded:
A general overview of the level plan shows that the movement of the house is
consistent with the environmental influence on the property and indicates no localised
movement at the location of the water leak which, if influencing the movement in
anyway, should be expected.
Based on the reports, the insurer declined the claim on 27 June 2016 as no insured
event had been established. The complainant disputed the findings and requested a
review. EA re-attended the property to discuss the claim further with the complainant.
The insurer upheld its decision, which it confirmed in writing on 24 July 2017.
Complainant engaged a building surveyor in January 2018
In January 2018, the complainant engaged a building surveyor (DK) to inspect the
property and provide a report. He reviewed material provided by the complainant. He
recommended a further investigation to determine why there was still movement.
Determination | Case number: 501515 Page 6 of 20
He says the repairs conducted in 2004 were insufficient as the footings and
foundations in the bathroom and laundry and kitchen were not undertaken. He also
says the opinion of a structural engineer should have been obtained in 2004. He
criticises the inspections and analysis conducted by the insurer’s engineer.
Repairs conducted were not insufficient or inadequate
I have carefully considered all the available material. I am not persuaded the repairs
conducted in 2004 were insufficient.
The 2004 claim was the subject of several inspections and attendances by the insurer
and their experts at which time these contentions were not made.
Moreover, the available material establishes the damage was inspected in 2004 by
two builders (EA and AA) both of whom have the expertise to assess the damage and
required repairs. I am not satisfied in these circumstances the opinion of the structural
engineer was required.
The available material also indicates the 2004 inspection by EA and quotations
provided by AA are comprehensive and include all areas which were damaged by
water at that time and the work which DK says was not done.
Leaking water pipe in 2015 not the proximate cause of the claimed damage
DK also says the leaking water pipe in 2015 caused damage. He notes the repair
recommendations made by the insurer’s plumber were not undertaken.
However, the insurer’s policies clearly provide the insurer is not responsible for
damage to pipes which leak.
DK also challenges the findings of the insurer’s experts because he says their
conclusion that the leaks were too minimal to cause damage was based on the
normal use test which does not take into consideration blockages.
I am not persuaded by these contentions either. This is because DK does not take
into account the expert evidence of the insurer’s engineer in relation to the level
survey conducted after the 2015 leak. The expert opinion i n the survey shows there
was no localised movement at the location of the water leak.
I acknowledge the opinion of the plumber LH. However, I am not sufficiently
persuaded by his opinion in view of the expert opinion of the insurer’s engineers and
the findings from the level surveys.
DK also contends the repairs should have considered further movement caused by
removal of trees. However, the insurer acknowledged it may have undertaken repairs
prematurely and paid a further $6,966 for repairs in October 2009.
Determination | Case number: 501515 Page 7 of 20
Insurer entitled to deny the claim
I have carefully considered all the material provided by the parties over the extended
history of this matter. I am not persuaded by the complainant’s various contentions.
T he insurer’s policies clearly state the insurer does not cover an insured for lo ss or
damage to the pipe which causes the damage.
On the available material, and for the reasons stated, I am satisfied the repairs which
were undertaken and/or paid for in 2004 and 2009 were adequate.
Further, I am not satisfied the available material establishes the repairs to the sewer
were inadequate. The material provided by EA and AA indicate the connections of the
lead waste to the PVC drain were completed adequately and there is no persuasive
evidence from the complainant to challenge this.
In any event, even if the plumbing repairs were inadequate, the complainant was
responsible for the sewer repairs.
Finally, while both DK and the complainant say a further investigation is required to
determine the cause of further movement, I am not satisfied this is required in view of
the substantial investigation which has already been undertaken since 2004.
I am satisfied the available information and the substantial investigations over several
years do not support the complainant’s contentions. I am not satisfied the complainant
has established a prima facie claim or that the claimed damage is caused by the
insurer’s repairs.
In the circumstances, on the available information, and for the stated reasons, I am
satisfied the insurer is not required to take any further action in relation to the
complaint or in relation to the complainant’s claims.
Determination | Case number: 501515 Page 8 of 20
3 Supporting information
3.1 The determination is made under FOS Terms of Reference
The Australian Financial Complaints Authority ( AFCA) has commenced managing
disputes previously lodged with F inancial O mbudsman S ervice (FOS) .
This determination is made under FOS Terms of Reference but has adopted the
following terminology for consistency with AFCA. In this determination the AFCA
terms have the same meaning as the FOS terms defined in paragraph 20.1 and
Schedule 1, 2 & 3 of the FOS Terms of Reference.
FOS definitions AFCA term
applicant complainant
financial services provider financial firm
dispute complaint
claim claim
3.2 Our Approach
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other. All the material provided by the parties has been reviewed and
considered for the purposes of this determination.
This complaint has been decided on its merits, having regard to the relevant law,
good industry practice, codes of practice and previous decisions.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, commentary has been restricted to those issues considered
directly relevant to the outcome only.
The complainant is represented. References in this determination to the complainant
include references to the complainant’s representative.
It is an accepted principle of general insurance law that an insured bears the onus to
establish on the balance of probabilities that they have suffered a loss caused by an
event to which the policy responds. This is known as a prima facie claim. Once so
established, the onus shifts to the insurer to prove on the balance of probabilities that
an exclusion applies if it seeks to deny or limit its liability for the loss.
3.3 Proximate cause
Case law establishes:
Determination | Case number: 501515 Page 9 of 20
the proximate cause of loss is the dominant (or effective or operative) cause of the
loss, whether or not the cause is last in time or the sole cause
where several causes operate at the same time, each cause must be examined for
the qualities of reality, predominance and efficiency as the active, efficient cause
that sets a relevant chain of events in action
if one cause results in harm in any case, and the other would not in the absence of
the first, the first is the proximate cause
a common-sense approach is taken to determine proximate cause.
3.4 Key policy terms
The relevant policy extracts are referred to correspondence between the parties in
both claims and in the insurer’s Notice of Response. Both the policy documents and
the Notice have been exchanged with the complainant.
Extracts from policy applicable to 2004 claim
Insured events
7. Bursting, leaking, discharging or overflowing of water or liquid at the insured address from:
drainage and sewerage systems;
pipes or plumbing apparatus fixed to the pipes;
......
and we will not pay for the repair or replacement of the:
tank, pipe, part, container or waterbed that cause the damage;
Extracts from policy applicable to 2015 claim
Insured events
These are the following events that lead to loss or damage:
1. Fire (including bushfire)
2. Explosion
3. Burglary, theft or attempted theft
4. Lightning
5. Earthquake or tsunami
6. Storm and rainwater runoff
Determination | Case number: 501515 Page 10 of 20
7. Bursting, leaking, discharging or overflowing of water or liquid
8. Malicious damage, intentional damage or damage by vandals
9. Riot or civil commotion
10. Impact
11. Damage by an animal
12. Flood
[…]
7. Bursting, leaking discharging or overflowing of water or liquid
loss or damage as a result of bursting, leaking, discharging or overflowing water or liquid
from:
drainage and sewerage systems at the home
fixed baths, sinks, basins and toilets at the home
pipes or plumbing apparatus fixed to pipes
…….
Will not cover you for loss or damage:
to a tank, pipe, part, container or waterbed that cause the damage
General Exclusions
[…]
Earth Movement
We will not cover you for loss, damage or liability caused by or arising out of
erosion, vibration, subsidence, landslip, landslide, mudslide, collapse, shrinkage
or any other earth movement.
But we will cover you for:
explosion – insured event 2
earthquake or tsunami – insured event 5
bursting, leaking, discharging or overflowing of water or liquid – insured event 7
flood – insured event 12.
Determination | Case number: 501515 Page 11 of 20
[…]
What you must do
You must:
establish that an insured event or incident has occurred
3.5 Expert reports and chronology – First claim
Record Key points
Insurer’s adjuster (EA)
Report
2 June 2004
Inspected and described damage 1 June 2004.
Cracking damage consistent with suspected leaking sewer.
Liaise with plumber. Subject to their findings obtain quotes for
reinstatement of wat er damaged surfaces.
Insurer’s builder ( A A)
Report
2 June 2004
Tested the sewer drain system by video following previous
test which located leakage without clear definiti on o f problem
or exact location
Major failure points are in the general location of kitchen and
laundry
Recommend replacement of t he whole external sewer
system
Table attached highlighting many failure points of the
pipework. Comments included roots and fi ne roots
Location of the building and paving damage is consistent with
soil expansion due to the excessive moisture at a subsurface
level causing upheaval and cracking and ot her structural
damage
Described scope of works including “expose earthenware
drain to allow replacement by owner”
Insurer’s builder ( A A)
Quote job number 804A
2 June 2004
Endorsed private s cope of works
Remove old drain pipes
Reconnect with new PVC
Connect to existing waste with rubber connectors (endorsed
by AA : connection to lead toilet waste to PVC drain done with
approved epoxy FerroPRE)
Test drain and protect with suitable backfill material for
300mm
E xtent of the above work may alter once original frameworks
is exposed
Total price $1,606
Insurer’s builder ( A A)
Quote job number 804
2 June 2004
Scope of works to repair w ater damage to building $32,406
Determination | Case number: 501515 Page 12 of 20
Record Key points
Insurer’s adjuster (EA)
Report
9 August 2004
Sewer has broken directly und erneath the kitchen and
laundry
Caus e of the damage d sewer rela ted and trees or drying of
soil
Obtained quotations for replacement of the sewer at
complainant’s cost and associated excavations and
reinstatement at insurer’s cost
Insuranc e related repairs and excavations $32 ,406 and these
works proceeding
Amount quoted to complainant by the c ontractor for her cost
involving replacement of th e sewer accepted by complainant
Anticipate repairs to be undertaken for replacement of all the
sewer within two weeks
Major repairs to the building will take place at the end of
summer to allow settlement o f the b uilding
Insurer’s adjuster (EA)
Report
9 September 2004
Understand t hat sewer repairs are underway
Property requires time to settle before repairs can start
Repair date set for end of February 2005
Insurer’s adjuster’ s
letter to complainant
Report
6 July 2005
Repairs in relation to water damage claim complete
Complainant advised of possible future uninsured movement
risks caused by the type of soil and proximity of trees and
weat her conditions
Insurer’s adjuster (EA)
Report
1 March 2007
Inspected and photographed inside and outside house
Described cracking damage in various rooms in the house
Photographs show cracking damage and dry land and mature
gum trees
During this pa st summer, house began to move
Cracks closed in winter and opened i n summer
No signs of leaking pipes - complainant tested the water
meter and confirmed no mains pressure pipes ar e leaking
Damage possibly caused by large trees on Council reserve at
the rear and eastern side of the house
Decline recommended
Letter from in surer to
complainant
8 March 2007
Claim deni ed as no apparent insured event
Insurer’s adjuster (EA)
Report
30 May 2007
Reattended after new information provided about sewage
overflows a nd flooding of the sewer system
This has occurred on several occasions over the last five
years leading to wate r flooding underneath the house
Seeking confirmation from SA Wa ter
Photographs were apparently provided of damage to
Determination | Case number: 501515 Page 13 of 20
Record Key points
bathroom vanity unit and damage to previously repaired
areas and new areas on the opposit e side of the building
from the sewer
Recommended engineer be appoint ed
Insurer’s engineer (MP)
Report
9 July 2007
Attended 21 July 2007
Some years ago, Council removed trees to the north of the
building. A root barrier was installe d next to the eastern
b oundary
Described damage. Some repaired cracking has become
wider. Repaired cracking in laundry not reope ned
Through a floor trap inspected soil under the hallway which
was not moist
Hous e built on reactive clay soils
Level survey undertaken. Building has settled but no signs of
heave near the replaced sewer or past main supply leakage.
Areas of the house are high er than those near the leakage
Time lag since the sewer replacement made diagnosis of
recent minimal movement difficult
The recent movement could have been contributed to by a
reduction in soil heave caused by repairs to sewer fractures
Recommended reattendance after six months
Insurer’s engineer (MP)
Report
21 July 2008
Reins pected 8 June 2008
Undertook further level survey which shows minimal cha nge
since last survey so cra ck repair can now be undertaken
Some cracking closed. No new cracking or movement within
the wet areas closest to past leaking
Understand c omplainant cash settled for internal cosmetic
repair s and she can repair and paint
Futur e movement inevitable because of highly reactive nature
of soil and presence of signifi cant trees
Insurer’s adjuster’ s
letter to complainant
24 November 2008
“ AA say you have denied access, so they can provide a
quote in accordance wit h recommendations of MP.
Please contact MP to discuss concerns so we can arrange
appropriate quot ation repairs.
Wrote to you on 29 August 20 08. We have not heard from
you.“
Insurer’s engineer (MP)
Report
13 March 2008
Attended property wi th complainant 18 February 2009
L isted repairs for which the complainant was responsible and
repairs which should be undertaken by the insurer to re ctify
damage caus ed by the leak
Insurer’s repairs included “open PVC inspection point
adjacent rear gully and ensure correct operation. Adjus t if
necessary.”
Determination | Case number: 501515 Page 14 of 20
Record Key points
Insurer’s adjuster’ s
letter to complainant
2 April 2009
Enclosed M P’s scope of works
Insurer to arrange AA to quote on the repairs .
“ AA to contact you shortly to m ake the necessary
arrangements.”
AA quotation number
5587 1H
22 May 2009
Scope of works to straighten eastern side fence, repair step,
open PVC inspection point etc. Total price $7,695 which
included an allowance to adjust PVC upon inspection $400
AA tax invoice
22 October 2009
Job summary regarding water damage
Cost to com plete repairs as per quotation number 5587 1H
$6,966
Less allowance to open PVC inspection point adjacent rear
gully an d ensure correct operation $400
Less allowance to repair crack and paint one wall to back
bedroom $273
Insurer’s adjuster (EA)
Report
26 November 2009
Repairs completed in accordance with MP specification and
AA quo te
Two items unrepaired as complainant believes further work
should be undertaken outside the scope provided by the
engineer. One ite m was the PVC inspection point
Directed the complai nant to the insurer’s engineer
Complainant indicat ed she would seek an independent
inspection and will co mmunicate their findings later
Insurer’s adjuster’ s
letter to complainant
18 January 2010
Enquired regarding independent inspection for final works so
insurer ca n arrange completion of repairs
Insurer’s adjuster’ s
letter to complainant
23 March 2010
A djuster followed up complainant
3.6 Material from South Australian Water
Date Key points
Report 8 January 2012
Report 17 April 2012
Report 12 June 2012
Report 18 September 2012
Report 10 June 2013
Report 9 January 2014
Report 3 June 2014
IP partially blocked
Inspection point overflow outside boundary
Inspection point ove rflow outside boundary
Blockage with int ernal plumbing - slow drainag e
IP servic e slow drainage
IP servic e slow drainage
IP servic e slow drainage
Determination | Case number: 501515 Page 15 of 20
Date Key points
Report 10 December 2014
Report 9 November 2017
Report 22 February 2017
IP servic e slow draina ge cause connection/tree roots
IP servic e slow drainage cause privat e pipework
IP servic e no drain age cause connection/tree roots
3.7 Expert reports and chronology – Second claim
Record Key points
Insurer’s plumber (LH)
Report
13 March 2015
Inspected and photographed property 10 March 2015
Government inspection opening, and main sewer dra in - no
major blockages located
Could not unblock the toilet drain because of the previous
installation of the main drain connection to the toilet waste
pipe consisting of a section of lead
Main sewer drain and toilet branch drain inspected wit h
CCTV camera. N o is sues with the main sewer drain
Issues with toilet branch connection. Appears joint bet ween
the lead and PVC pipe is either broken down or not
installed properly. Roots have entered throu gh this joint
causing blockages
Lead pipe was disfigured whi le try ing to unblock the drain
Could not inspect the bathroom drain with the CCTV
camera but suspect bathroom connected to the main sewer
gully using the same method. Thus, roots entered the joint
causing the d rains to block in the bathroom
No other leaks found
Damaged and blocked sewer drains could have contributed
to damage as the fittings leak when in use and especially
when blocked and h olding water as they have been
All sewer drainage within the toilet and bathroom is to be
replaced with PVC pip e. Recommende d and costed works
Insurer’s adjuster ( EA )
Report
16 March 2015
Complainant not ed additional movement which is
described in the report clai ming relevant to old water leak
Inspected and photographed property 1 1 March 2015
Complainant said tree ro ots got into the sewer system n ow
removed.
Toilet blocked. Blockage and roots within the toilet pipe so
invasive unable to be removed by plumber (LH) . Anot her
plumber (GP) engaged
Issue with piping - new sewer system was of PC V
construction and joins up to the original lead pipe coming
out from the hom e
W ill refer to original assessor
Determination | Case number: 501515 Page 16 of 20
Record Key points
Insurer’s adjuster ( EA )
Report
18 March 2015
GP used CCTV equipment. Confirmed crack in the lead
pipe under the footin g area where the roots ente red
Damage to the lead joints in the PVC. This occurred during
the initial phase of removing the roots
Referring fin dings back to original assessor
Insurer’s engineer (MP)
Report
28 April 2015
Inspected premises 7 April 2015 to determine the cause of
the recent cracking in the eastern and western sides of the
house and r elationship to the discovered l eak in the toilet’s
waste pipe
Noted cracks and signs of movement throughout the home
External wall cracks wor sened to western external wall
Level survey of the perimet er brickwork undertaken
Nort h - east corner of home settl ed since house was built
Google Eart h shows significant native trees surrounded the
home in May 2 003 which were removed in 2004
R emoval of the trees caused a significant change altering
the moisture of the soil causing cracking to that part of the
hous e
Leakage from the toilet waste pipe leak has not caused
damage as there is no localised heave around the toilet
area. The survey sh ows the toilet area has remained in a
similar elevati on to that in previous surveys
Possible other leaks have contributed to recent movement
Recommend testing the sewer, storm water and mains
water supply pip ework to determine if any leaks
Insurer’s plum ber (JH)
Report
19 May 2015
Waste pipes were noted to be copper, lead and PVC
material, the sewer drainage PVC material and all
downpipes were n oted to discharge above ground
Undertook testing
Sewer drainage - tests static
Leak of 1 litre per minute from bathroom waste pipe from
shower alcove floor bas e
Leak rec orded at 2 litres p er minute from WC branch drain
Plug could not be pushed upstream as the lead waste pipe
appeared misaligned where connected to the PVC pipe
work
N o other leaks detected
Insurer’s engineer (MP)
Report
23 June 2015
Leaks are not severe enough to cause upward movement
in the building’s nort h - eastern corner
Recent movement damage caused by rebound heave of
the previously settled soil beneath the corner because of
increase in soil mois t ure caused by 2004 tree removal
Rebound heave in the foundation soil would have occurred
regardless of the leaks
Determination | Case number: 501515 Page 17 of 20
Record Key points
Letter from insurer to
complainant
30 June 2015
Relying on reports, and policy terms, claim is denied as no
insured event established
Insurer claim file note
6 July 2015
Discussio n regarding denial of the claim
Complainant invited to call a djuster
Claim can be escalat ed via the complaints procedure
Insurer claim file note
26 April 2016
Discussio n regarding denial of the claim
Complain ant invited to contact adjuster
Advis ed of complaint and IDR process
Insurer’s adjuster ( EA )
Report
27 April 2016
Extensive meeting with complainant and her father - in - law
whic h involved review of old claims
WC which is connected to sewer which was replaced in
2003 is now leaking
LH plumber re - attended and says there is a lead junction
between the old and new pipework which is failing
Complainant could have replac ed in 2003 but d id not due
to limited finances
Insurer had agreed to a partial cash settlement of the claim
to redecorat e aft er repairs carried out by AA
Cash settlement used by complainant to pay for the
pipework and replace the sewer
Insurer not liable to replace the pipework to the WC but
recommende d an independent engineer review
Insurer’s engineer ( G P)
Report
6 June 201 6
Attended , undertook level survey and photographed
damage and previous repairs on 9 May 2016
Considered plumber’s reports. Leaks of 4 li t res per minut e
or below are not unusual and have little or no effect on the
surrounding soils as the leaks are not constant
Even if there was a blockage, as the connection of the lead
to the PVC pipes is close to the WC with only a relatively
short part length upstream of the blockage the amount of
water available to leak from the pipes is small
Survey shows the movement of the home is consistent with
the environmental influence on the property with no
localised movement at the locat ion of the wat er leak
Concluded water leak is not severe enough to cause
localised heave at the leak location which is supported by
the lack of any local ised recent distress near to it
Damage caused by environmental conditions (reactive
soils and nearby mat ure gum trees)
Determination | Case number: 501515 Page 18 of 20
Record Key points
Letter from insurer to
compla inant
27 June 2016
Relying on recent expert reports, insurer denied the claim
on the basis no insured event or incident as occurred.
Insurer claim file note
17 May 2017
Complainant’s father telephoned to discuss the claim.
Original work in 2004 was n ot completed correctly because
the water pipe was not fixed.
Adjuster will discuss with complainant and father.
If not happy can go to int ernal dispute resolution.
Insurer’s adjuster (EA)
Report
Re - attended property with complainant’s father who
criticised pipes used to replace the sewer and said water
gained entry under the hous e from the original leak and
subsequent overflows from the external sewer resulting in
tree roots following the water under the house.
Complainant indicat ed may seek recov ery from local
council for the damage caused by council trees.
Engineer’s reports were provided at the time but would be
provided again to assist complainant.
Matter not change in any material way since attendance
with GP in 2016.
Insurer’s IDR letter
2 4 July 2017
Lengthy exposition of the claims history.
Claim denied as an insured event has not occurred to
cause the new damage.
Repairs under 2004 claim are satisfactory.
Damage caused by environmental influenc es.
Insurer’s adjuster (EA)
email
7 December 2017
Insurer appointed no contractors to affect any repairs .
C laim was cash settled in its entirety.
O nly contractors who affected any work did so on the
instruction direct from the member and we understand
these were limited to pipe repairs.
Complainant arranged for the pipe repairs to be affected in
PVC which we understand is compliant with the required
codes.
Referenc e to stainless steel couplings relates to the
recommendation that flexible couplings which incorporate
stainless steel compone nts which could be installed to
minimise the risk of the PVC repairs failing.
Pipe repairs affected by the complainant without the
flexible couplings based on previous plumbing reports held.
Insurer’s adjuster (EA)
letter and photographs
U ndated but in r esponse to
email 5 February 2018
Could not retrieve all records from 2004 claim but was able
to speak with senior adjuster and repairer from AA.
Repairs completed by AA in 2005.
Main sewer replaced at the complainant’s cost.
Addresses criticisms made by complainant’s expert .
Determination | Case number: 501515 Page 19 of 20
Record Key points
Concludes since completion of repairs in 2007 no single
plumbing leak has been identified as causing damage.
Thrust of enginee rs’ reports is that the home has been
subject to adverse environmental influences predominantly
due to the position of trees surrounding the property.
Complainant ’s builder
(DK)
Report and photographs
Undated
Inspected the property 7 January 2018.
Repairs conducted in 2004 were ins ufficient because
footings/foundations were not repaired in the bathroom,
laun dry and kitchen.
No guarantee the house would settle in its original position
particularly as the house is on a known highly reactive soil .
A structural engineer was not asked to address the
problem in a definitive manner in 2004.
Nothing to indicate inter nal footings, surrounding soil, walls,
had settled into original position.
Insuranc e engineer did not inspect the internal footings.
Displacement occurred becaus e of misalignment of
external footings on western side of building.
Inspected this footing whi ch was not realigned or repaired.
As soil is highly reactive clay and with a high density of
large trees close to the house further movement
displacement of affected footings was likely.
Continuous moisture from broken pipes would have drawn
the tree roots to the footings under the house. Not clear
this was checked.
A soil report would have been useful to analyse if the
correct flexible pipework needed was to be used.
Reviewed reports fr om engineer, adjuster and plumber. In
2015 the water pipe was the cause of the damage, but
r epairs recommended by LH were not undertaken.
C onclusion that leaks were too minimal were bas ed on a
normal use test, which does not take into consideration
blockages, or full pipes. B elieve water was discounted as a
cause, particularly from bat h waste pipe, due to this
oversight.
B ath waste pipe is close to the northwest corner and may
have contributed to further movement in same. This is
certainly a possibility given earlier leak from 2004 was
considered a contributor of damage in northwest corner.
Engineer stated between May 2004 to March 2004 several
large neighbouring trees had been removed . If repairs are
inadequate, and do not consid er soil erosion, or collapse
due to root shrinkage, continued movement and damage is
inevit able. Further leaking only m ake s matters worse .
Determination | Case number: 501515 Page 20 of 20
3.8 Other relevant material considered and relied on
Parties’ submissions, emails , photographs, quotations, invoices and all
attachments to all submissions.
Correspondence between the parties.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.