Home / Financial Firm (Unknown - Insurer) / Determination 500274

Determination 500274

Cash settlement for home cracking and garage slab denial

FirmFinancial Firm (Unknown - Insurer)
Decided2018-12-05
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$3,994
Non-financial loss—
Amount claimed$62,125
SourceAFCA PDF

Summary

The complainant claimed for cracking to his home and garage floor from leaking pipes. AFCA held the insurer liable for 100% of the home repairs and ordered a $3,993.89 cash settlement plus interest, but upheld the denial of the garage slab as concrete shrinkage.

Leaking pipes were the dominant cause of the home damage, so the tree-root exclusion did not reduce liability, while the garage cracking was excluded as shrinkage rather than an insured water escape.

Issues

Subjects and remedies

home or building damagepay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination | Case number: 500274 Page 1 of 6 Determination Case number: 500274 5 November 2018 1 Determination overview 1.1 Complaint The complainant lodged a claim under his home insurance policy with the financial firm (insurer) for cracking damage to his home and garage. The complainant says the damage was caused by water run-off at the property. The insurer accepted liability for 95% of the cracking damage to the home and offered to cash settle the complainant for the estimated cost of repairs. However, the insurer denied liability for the remaining 5%, on the basis that trees located near the home had contributed to the damage. The insurer also denied liability for the cracking damage to the garage floor, on the basis that this damage was caused by concrete shrinkage, which is excluded from cover under the policy. The complainant disputes the insurer’s decision and seeks cover for the cost of repairing all of the damage to his home and garage. 1.2 Issues and key findings Is the cash settlement for the home fair and reasonable? The proximate cause of the cracking damage to the home was the escape of water from leaking pipes at the property. In these circumstances, the insurer is liable for 100% of the cost of repairs. Is the insurer liable for the damage to the garage? The damage to the garage was caused by concrete shrinkage and not by the sudden escape of water (or any other insured event under the policy). Accordingly, the insurer is not liable for the damage. Determination | Case number: 500274 Page 2 of 6 1.3 Determination This determination is partly in favour of the complainant. The insurer is required to cash settle the complainant’s claim for damage to the home for $3,993.89, plus interest as set out in section 2.1 below. The insurer is not liable for the damage to the garage. Determination | Case number: 500274 Page 3 of 6 2 Reasons for determination 2.1 Is the cash settlement for the home fair and reasonable? Policy provides cover for escape of liquid subject to exclusions The complainant is required to show that, on the balance of probabilities, he has suffered a loss caused by a risk insured against under the policy. This is known as a valid (or prima facie ) claim. If the complainant is able to establish a prima facie claim, then the onus shifts to the insurer to show that, on the balance of probabilities, it is entitled to rely on a n exclusion under the policy to deny the claim. The complainant’s policy provides cover for damage caused by the e vents listed in the policy, subject to the conditions and exclusions set out in the policy. The insured events for which cover is provided include the sudden and unexpected escape of water from pipes at the complainant’s property. However, the property contains general exclusions for damage caused by naturally occurring earth movement and/or tree roots. Insurer accepted liability for 95% of damage The insurer’s engineer (CE) advised that the internal cracking damage to the property was due to differential earth movement, as a result of changes in the moisture content of the reactive clay foundation soils. CE considered that the changes in moisture content had been caused by the following factors:  water leaking from broken and blocked stormwater pipes (as to 70%)  water leaking from dilapidated sewer pipes (as to 25%), and  the drying effects of trees located on neighbouring properties (as to 5%). CE advised that the combined effect of the broken pipes and nearby trees had caused the foundations to undergo a cycle of expansion and contraction, resulting in the cracking damage observed. Based on CE’s report, the insurer accepted liability for 95% of the damage. Proximate cause of damage is leaking pipes Given the findings in CE’s report, the complainant has cl early established a prima facie claim for damage caused by leaking pipes. Determination | Case number: 500274 Page 4 of 6 Accordingly, the insurer is only entitled to reduce its liability for the claim if it can show that part of the damage was caused by factors which are excluded from cover under the policy (such as tree roots). In order do to so, the insurer must show that tree roots were a proximate cause of part of the damage (that is, a dominant, effective or operating cause). In the present case, it is clear that the dominant cause of the damage was the effect of water from the leaking pipes. CE considered that the leaking pipes made a 95% contribution to the damage. Further, the complainant’s engineer (ST) carried out floor level surveys of the house, which identified heave (upwards movement) in the areas where cracking was observed. The pattern of the cracking (compression cracking) was also consistent with having been caused by heave. Heave is caused by an increase in the moisture content of reactive clay soils (for example, from leaking pipes). By contrast, the drying effects of trees result in downwards movement (settlement) of reactive clay soils. Given the results of the level surveys and the nature of the cracking, I am satisfied that the proximate cause of the damage was leaking pipes at the property (and not the effect of tree roots). Accordingly, the insurer is liable for 100% of the damage. Insurer is required to cash settle complainant for $3,993.89 The insurer has provided a scope of works prepared by its builder (LG) for the repair of the cracking damage to the home. LG provided a quotation of $4,003.89 for the necessary works. I am satisfied that LG’s scope of works reflects the repairs required to repair the cracking damage to the home (as identified by the parties’ engineer s). The complainant’s engineer (ST) confirmed that only cosmetic repairs were required, once a sufficient period had been allowed for the soil to dry out. The complainant has not provided any independent information (for example, a quotation from his own builder) which indicates that LG’s quotation is insufficient. For the reasons outlined above, I consider the insurer is liable to pay 100% of the cost of repairs (less the $100 policy excess). Accordingly, the insurer is required to pay the complainant the amount of $3,993.89 in settlement of his claim. The insurer is required to pay interest on the cash settlement amount at the rate determined in accordance with section 57 of the Insurance Contracts Act 1984 (Cth) from 31 October 2017 until the payment date. Determination | Case number: 500274 Page 5 of 6 2.2 Is the insurer liable for the damage to the garage? Damage was not caused by escape of water The garage was inundated by water on several occasions during early 2017. The complainant says that water entering the garage caused the concrete floor slab to crack. After inspecting the property, the insurer’s engineer (CE) advised that the cracking to the concrete slab had not been caused by water entry, but was due to normal concrete shrinkage. CE’s findings were confirmed by the complainant’s engineer (ST). Level surveys of the floor slab conducted by ST did not identify any movement. ST also carried out surveys of the brickwork of the garage walls, which did not reveal any cracking or movement damage. ST agreed with CE that the cracks in the floor slab were due to concrete shrinkage. The complainant says ST’s report is inconsistent with the views he expressed while at the site. However, in the absence of any conflicting information from ST himself, I am only able to consider the findings in his report. The complainant has provided a quotation for $58,121 prepared by his builder (AL) for rectification works to the garage. AL’s quotation is based on a scope of works provided by another engineer (PG). However, PG’s scope of works does not clearly identify how th e damage occurred. PG recommends that an agricultural drain should be installed along the side of the garage, which suggests that the existing drainage is inadequate. However, he also states that the existing footing was not designed to support the loads p laced on it. Having carefully reviewed the available information, I am satisfied that the cracks to the slab were caused by concrete shrinkage (as advised by CE and ST) and not by an escape of water (or any other insured event). Insurer is not liable for damage to floor slab As outlined above, the policy only provides cover for damage caused by the insured events listed in the policy. The policy does not provide cover for damage caused by concrete shrinkage. Accordingly, the insurer is not liable for the damage to the garage. Determination | Case number: 500274 Page 6 of 6 3 Supporting information 3.1 The determination is made under FOS Terms of Reference The Australian Financial Complaints Authority ( AFCA) has commenced managing disputes previously lodged with F inancial O mbudsman S ervice (FOS) . This determination is made under FOS Terms of Reference but has adopted the following terminology for consistency with AFCA. In this determination the AFCA terms have the same meaning as the FOS terms defined in paragraph 20.1 and Schedule 1, 2 & 3 of the FOS Terms of Reference. FOS definitions AFCA term  applicant  complainant  financial services provider  financial firm  dispute  complaint  claim  claim 3.2 Our approach to this complaint This complaint was the subject of a recommendation issued on 14 September 2018. The recommendation was rejected by the complainant. This complaint has been determined based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous decisions (which are not binding). There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.