Insurer liability under lifetime repair guarantee for defective storm repairs by its appointed builder
Text of the determination
Determination | Case number: 500222 Page 1 of 20
Determination
Case number: 500222 21 January 2019
1 Determination overview
1.1 Complaint
The complainant held a home insurance policy with the financial firm (insurer). On
8 November 2004, the complainant lodged a claim for damage to the home caused by
stormwater runoff.
The insurer accepted the claim and appointed a builder to repair the damage. The
complainant says the builder’s work was defective and the insurer is liable for
rectification.
The insurer says the complainant appointed the builder to undertake private works in
addition to the insured works authorised by the insurer. The insurer says it accepts
responsibility for the insured works, but not for the private works.
1.2 Issues and key findings
What is the scope of the insurer ’s guarantee ?
There has been a mixture of insured works and private works at the complainant’s
home. The insurer’s guarantee applies only to the insured works.
The insurer is not required to guarantee the private works, even if they were
performed by the insurer’s builder.
Is the insurer liable for rectification?
Although the steel posts supporting the house suffered premature corrosion due to
faulty workmanship by the insurer’s builder, the posts were installed as part of the
private works. Accordingly, the insurer is not liable for rectification of this work.
However, there was also faulty workmanship by the builder with respect to the insured
works, including the pouring of the slab and the laying of in-slab pipework. The insurer
is liable for rectification of this work.
Determination | Case number: 500222 Page 2 of 20
What must the insurer do to fulfil its guarantee?
The insurer must obtain expert evidence to determine the cost of rectification of the
insured works.
The insurer must then settle its liability by paying the complainant an amount
determined in accordance with section 2.3 of this determination.
1.3 Determination
This determination is partly in favour of the complainant.
Within 30 days of the acceptance of this determination, the insurer must give the
complainant a scope of works and quote for all work required to rectify the faulty
performance of the insured works.
Within 30 days of giving the complainant a scope of works and quote, the insurer
must pay the complainant:
the reasonable cost of rectification of the insured works
an additional 15% contingency to allow for unforeseen costs
interest on the above amounts at the rate determined under section 57 of the
Insurance Contracts Act 1984 (Cth) (the Act) from 17 May 2014 until the settlement
date
$9,350 reimbursement for house raising, plus interest from 2 July 2008 until the
settlement date
$4,818 reimbursement for garden clearing, plus interest from 19 May 2008 until the
settlement date
$3,300 in partial reimbursement of professional costs incurred in the course of this
complaint
$3,000 in compensation for non-financial loss.
Determination | Case number: 500222 Page 3 of 20
2 Reasons for determination
2.1 What is the scope of the insurer ’s guarantee ?
Insurer ’s builder perfo rmed insured works and private works
The complainant’s house was damaged by a storm in 2004. The insurer appointed
‘UBS’, builder, to repair damage caused by the storm (the insured works).
While UBS performed the insured works, the complainant arranged for UBS to
perform additional work (the private works) at her expense.
Insurer provides lifetime guarantee on repairs
The product disclosure statement effective in 2004 does not mention a guarantee on
repairs. Nevertheless, the insurer accepts it is responsible for repairs done on its
behalf.
The General Insurance Code of Practice (to which the insurer subscribes) requires an
insurer to guarantee repairs if it ‘selected and directly authorised a repairer’.
On 9 March 2009 the insurer sent the complainant a letter saying it provided a lifetime
guarantee for repairs to claim-related damage. The letter said the guarantee:
applies to work authorised, arranged, and paid for by the insurer
does not apply to repairs authorised by the complainant.
Guarantee does not extend to private works
The complainant says the insurer’s letter of 9 March 2009 guarantees ‘private
works… as well as original insured works’. The panel does not accept this. The letter
clearly states that the guarantee does not apply to repairs authorised only by the
complainant.
The panel is satisfied that the insurer provided a lifetime guarantee only for repair
work it authorised. The insurer is not required to guarantee work arranged and
authorised by the complainant, even if it was performed by the same repairer.
2.2 Is the insurer liable for rectification?
Steel posts
Steel posts part of private works
The exchanged material indicates UBS replaced sub-floor timber posts with steel
posts. The expert reports indicate the posts have suffered severe premature
corrosion.
The insurer says the steel posts were installed as part of the private works.
Determination | Case number: 500222 Page 4 of 20
A 2006 report by ‘NJA’, engineers, says there are problems with the footing system of
the insured property. NJA says there are several factors that could be contributi ng to
the problems, but does not mention damage caused by the insured event (the 2004
storm) as a potential contributing factor.
The complainant signed a contract with UBS (the Major Works Contract) for repairs to
be paid for by the insurer. The contract i ncludes a scope of works which does not
mention timber or steel posts. An addendum to the contract states in part:
[UBS] will provide clear cost delineation between insurer's works and works for
the homeowner to include stumping…
The insurer ’s note dated 8 May 2008 refers to the works in the contract. The note
then states:
[The complainant] has agreed for all re-stumping of the home to be completed in
conjunction.
An invoice dated 31 October 2008 from UBS to the complainant states:
Cost of repairs for non-Insurance work to date.
The invoice includes the following items:
Formatube - surround for timber stumps
Excavation - Preparation of stumps to front of home and rear extension
slab
Project management of re-stumping front section and consultation.
The insurer’s note dated 30 October 2009 says it told the complainant it would not
cover work to ‘concrete stump footings’ because ‘these are private works and
information we have to hand does not indicate stumps were defective’.
Having considered the information provided by both parties, the panel is satisfied that
the steel posts were installed as part of work arranged and authorised by the
complainant. Therefore, the insurer is not required to guarantee this work.
Steel posts not damaged by insurer’s rectification work
The complainant says the insurer authorised rectification work to some of the steel
posts in 2009. The complainant says the insurer’s lifetime guarantee applies to this
work.
The rectification work was aimed at arresting the premature corrosion of the posts.
Expert reports indicate the attempt was unsuccessful. However, there is no evidence
that the rectification work damaged the property (ie. that the rectification work left the
posts in a worse condition than before the work).
Determination | Case number: 500222 Page 5 of 20
The evidence indicates the steel posts require replacement. However, this is due to
the faulty workmanship involved in the installation of the posts (which the insurer did
not authorise), not any defect in the rectification work (which the insurer did
authorise). Therefore, the insurer is not liable for the cost of replacing the steel posts.
Concrete slab and moisture barrier
Concrete slab part of insured works
The scope of works in the Major Works Contract includes the excavation of a
concrete slab and the pouring of a new slab. The complainant says the slab was
poured by an unlicensed concreter, with an inadequate or improperly-installed
moisture barrier.
The insurer acknowledges the insured works included the pouring of a new slab, but
says it is ‘unable to determine’ whether the insured works included the installation of
the moisture barrier. The insurer says the Major Works Contract does not mention a
moisture barrier.
The expert reports indicate that the moisture barrier is meant to be fitted to the slab,
and its purpose is to protect the slab from moisture. However, the evidence does not
indicate that it was part of the Major Works Contract or was authorised by the insurer.
Having considered the information provided by both parties, the panel is satisfied that
the pouring of the slab, but not the installation of the moisture barrier, was part of
work arranged and authorised by the insurer. Therefore, the insurer is required to
guarantee the concrete slab but not the moisture barrier.
Concrete slab requires rectification
The complainant appointed an engineer (AM) who inspected the property on
3 November 2012. The insurer appointed an assessor (BOO) and an engineer (JHA)
who inspected the property on 9 April 2014. According to all three experts,
photographs taken by the complainant during construction show the moisture barrier
installed by UBS was incomplete.
JHA says the incomplete moisture barrier will lead to rising damp.
JHA also notes the following defects in the slab:
neither the slab nor the tiles laid over it had sufficient control joints, so the tiles
cracked when the slab shrunk
the slab is poorly set out, which has led to misaligned walls and flooring, especially
in the laundry.
JHA says:
Determination | Case number: 500222 Page 6 of 20
Due to the grossly defective work involving the concrete floor slab, vapour barrier,
and steel post bases… the entire concrete floor slab will need to be removed…
The complainant appointed an engineer (RB) who inspected the property and
produced a report dated 15 April 2015. RB says:
the moisture barrier was not installed in accordance with the engineering drawings
or the relevant Australian Standard
the incomplete moisture barrier is contributing to efflorescence and mould growth
rectifying the issue will require the removal of the slab.
The insurer appointed an engineer (PBK) who said damage to the foundations was
due to environmental conditions rather than poor workmanship. PBK says:
In general, minor failures of the vapour barrier would not be an issue if significant
moisture was not present.
The evidence indicates significant moisture is present. Nothing in PBK’s reports
contradicts the other engineers’ conclusions regarding the defects in the slab and how
they can be rectified.
Having considered the information provided by both parties, the panel is satisfied that
UBS exhibited faulty workmanship in the pouring of the slab.
The panel is satisfied that rectification of this issue will require the removal and
replacement of the slab.
In-slab pipework
In-slab pipework part of insured works
The insurer says the laying of in- slab water and sewage pipes ‘may’ be part of the
insured works. The work is included in the Major Works Contract. The insurer has not
offered any reason why the work should not be considered part of the insured works.
The panel is satisfied that the laying of in-slab water and sewage pipes was work
arranged and authorised by the insurer. Therefore, the insurer is required to
guarantee this work.
In-slab pipework requires rectification
The complainant says there has been a foul odour emanating from the laundry and
downstairs bathroom. The complainant says this is due to poor workmanship by UBS
in the installation of the in-slab pipes.
The insurer does not accept that the property has an odour problem caused by
incorrectly laid pipes, and says the complainant has not provided an expert report to
establish this.
Determination | Case number: 500222 Page 7 of 20
The insurer appointed ‘INT’, plumber, who inspected the property and produced a
report dated 9 November 2014. INT found accumulations of sludge and bacteria, and
recommended rectification of the pipework.
RB inspected the property in April 2015 and appointed a plumber to inspect the pipes.
RB concluded:
there is a sag and insufficient fall in a sanitary pipe
the insufficient fall means the pipe is not self-cleansing and does not comply with
the relevant Australian Standard
the odour is likely to continue until the insufficient fall is rectified
rectification of the pipework will require demolition of the concrete slab.
PBK’s report of 21 May 2015 says PBK has ‘No objections’ to RB’s conclusions about
the insufficient fall in the pipe and the need to demolish the slab to correct it.
Having considered the information provided by both parties, the panel is satisfied that
UBS exhibited faulty workmanship in the laying of the pipes.
The panel is satisfied that rectification of the pipework will require the removal and
replacement of the slab.
Other issues
Wall sarking
The Major Works Contract includes the installation of wall sarking.
JHA, PBK, and RB all say the sarking is incorrectly positioned. As a result, water is
entering the house above the French doors at the rear of the lower level family room.
Rectification of this issue will require the removal of flashing and wall cladding to
access the sarking.
The panel is satisfied that the insurer is liable for the rectification of the incorrectly
positioned wall sarking, including the repair of any damage caused by water entering
the house as a result of this defect.
Termite barrier
The Major Works Contract includes the installation of a termite barrier around the
lower level of the house.
JHA and RB say the side timber staircase has no termite protection, in violation of the
relevant Australian Standard.
The panel is satisfied that the insurer is liable for the installation of termite protection
for the side timber staircase.
Determination | Case number: 500222 Page 8 of 20
Mould growth
A mould report dated 11 November 2014 says high levels of mould were detected in
some samples taken from the complainant’s property, and says the premises require
mould remediation.
JHA says there is mould growth in a lower level bedroom due to the room’s poor
ventilation. PBK says mould growth in the house is predominantly in dirty, poorly-
ventilated areas with high humidity. RB says mould growth in the lower level is likely
due to a combination of factors, including high humidity, the lack of a moisture barrier,
and the setting of a concrete spoon drain against the slab.
The report produced by NJA in 2006 (before the insured works) says the property has
poor drainage, and water tends to pond at multiple locations (including against the
house) whenever it rains heavily. NJA’s conclusions are not contradicted by
subsequent expert reports.
Based on the available evidence, the panel is not satisfied that there is any mould
growth attributable to poor workmanship in carrying out the insured works.
House raising
The complainant says the insurer made her pay to lift the house, which was required
to allow for the insured works. The complainant provided an invoice dated 28 May
2008 in the sum of $9,350. The complainant says she paid by cheque on 2 July 2008.
The invoice says the house was raised ‘until restumping can be completed’. The
restumping was part of the private works. However, house raising would also have
been required to replace the slab (in which stumps/posts are embedded). This was
part of the insured works, so the insurer was liable for the cost of raising the house.
The panel considers that the insurer should reimburse the complainant $9,350, plus
interest from 2 July 2008 until the settlement date. The insurer is also liable for the
cost of raising the house again to allow for another replacement of the slab.
Timber flooring
The complainant says the raising and lowering of the house resulted in a sagging
floorboard in the kitchen.
The insurer appointed ‘CSO’, engineers, who inspected the timber flooring and
produced a report dated 21 October 2010. CSO’s report says damage to the floor was
not caused by building works, but by a combination of factors including:
repeated sanding over its long life
a lack of control joints or gaps
knots in the wood.
Determination | Case number: 500222 Page 9 of 20
RB’s report says a timber floorboard cracked after the house raising, but does not
give any reason to conclude that the house raising caused the damage.
Based on the available evidence, the panel is not satisfied that the timber flooring was
damaged by the insured event or any building work. The insurer is not liable for the
cost of repairing the floor. However, the insurer is liable for the cost of any protective
measures required to protect the floor while raising the house again to allow for
another replacement of the slab.
Fireplace
The complainant says some of the bricks in the fireplace have loosened. PBK’s report
of 14 July 2014 says the house raising probably loosened the bricks, and
recommends loose bricks be removed and re -mortared back into position.
As the house raising would have been required for the insured works, the panel
considers that the insurer is liable for the cost of removing and reinstating loose
bricks.
Garden reinstatement
The Major Works Contract includes the removal of garden plants to allow access for
machinery, and the restoration of the garden to the condition it was in before the
insured event.
The complainant has provided invoices for work to the garden after repairs were
completed. The insurer says some of this work was to improve the garden to a better
condition than it was in before the insured event. The complainant has not refuted this
claim.
The insurer’s let ter of 14 October 2015 says it paid the complainant $31,903 for the
cost of reinstating the garden after repairs were completed. The complainant has not
provided any evidence that this payment was inadequate.
The complainant says that before repairs commenced, the insurer made her remove
plants from the garden at her own expense. The complainant has provided an invoice
dated 19 May 2008 for $2,200 for clearing the gardens. The complainant has also
provided a quote and a bank statement showing payment on 25 January 2008 of
$2,618 for tree lopping.
The panel considers that the insurer should reimburse the complainant $4,818, plus
interest from 19 May 2008 until the settlement date. The insurer is also liable for the
cost of clearing and reinstating the garden again to allow for rectification work.
Determination | Case number: 500222 Page 10 of 20
Roof
The complainant replaced the roof of the building in 2008. The complainant has
provided an invoice for roof replacement dated 5 December 2008 in the sum of
$24,850.
The complainant says the roof split (and needed to be replaced) because of the
lengthy delay between the insured event in 2004 and the commencement of repairs in
2008. This claim is not supported by any of the expert reports.
Based on the available evidence, the panel is not satisfied that the roof needed to be
replaced because of the insured event or any building work. The insurer is not
required to reimburse the complainant for the cost of the roof replacement.
Irrigation system
The complainant has provided a quote dated 8 April 2015 for $10,450 for the
installation of a new irrigation system. The complainant says the irrigation system was
‘ obliterated by all the excavation equipment and debris’ that entered her yard during
the insured works. This claim is not supported by any of the expert reports.
Based on the available evidence, the panel is not satisfied that the irrigation system
needed to be replaced because of the insured event or any building work. The insurer
is not required to pay for the installation of a new irrigation system.
2.3 What must the insurer do to fulfil its guarantee?
Insurer must fulfil guarantee with cash settlement
The engineers’ reports establish that the steel posts supporting the house have
suffered severe premature corrosion, and efforts to rectify the issue have been
unsuccessful. Most of the engineers agree, and the panel is satisfied, that the posts
should be replaced, which requires the removal of the slab.
The replacement of the slab (for which the insurer is liable) should not be undertaken
unless the replacement of the steel posts (for which the insurer is not liable) is
undertaken in conjunction. Therefore, the insurer should not fulfil the guarantee by
authorising rectification work, unless the complainant agrees to coordinate this with
private works to replace the posts.
In the circumstances, the insurer should settle its liability by paying the complainant
the reasonable cost of rectifying the insured works.
Insurer must prepare scope of works
The available evidence is not sufficient to determine what work is required to rectify
the insured works, or the cost of such work.
Determination | Case number: 500222 Page 11 of 20
If the complainant accepts this determination, the insurer must prepare a scope of
works for all work required due to the faulty performance of the insured works. This
scope of works must include:
removal and replacement of the slab
rectification of the in-slab pipework
rectification of wall sarking
repair of any damage caused by water entering the house as a result of the
incorrectly positioned wall sarking
installation of termite protection for the side timber staircase
house raising and lowering
protection of timber floor during house raising and lowering
removal and reinstatement of loose fireplace bricks
clearance and appropriate reasonable reinstatement of garden.
The insurer must then obtain a costing of the scope of works.
The complainant may also obtain scopes of work and/or quotes for rectification of the
insured works. The panel invites the parties to work cooperatively to develop an
agreed scope of works and costing.
Insurer must allow for contingencies
When an insurer pays a cash settlement it avoids the risks of unforeseen costs being
incurred in the repair process, and does not have to provide a lifetime guarantee on
the repairs. These risks are transferred to the insured.
Furthermore, an insured party arranging private works may have to pay more than an
insurer would for the same work, because they do not have the insurer’s industry
connections or bargaining power.
Given that this matter is to be cash settled, the panel co nsiders it appropriate to make
a further allowance to cover possible contingencies that may arise during the repair
process. The panel consider a reasonable contingency allowance to be 15% of the
cost of repairs.
Insurer must pay interest
Section 57 of the Act provides that the insurer must pay interest on the settlement
sum from the time when it was unreasonable for the insurer to have withheld
payment. In the circumstances, the panel considers this date to be 17 May 2014, one
month after the date of JHA’s report.
Determination | Case number: 500222 Page 12 of 20
Complainant entitled to reimbursement of professional costs
Paragraph 9.4 of the Financial Ombudsman Service (FOS) Terms of Reference
provides that we can require an insurer to contribute to legal, professional, or travel
costs incurred by a complainant in the course of a complaint.
Unless exceptional circumstances apply, we will not require an insurer to contribute
more than $3,300 to a complainant’s costs.
The complainant appointed engineers (AM and RB) and an architect (RK) to inspect
her property and provide expert reports. The panel found the reports to be of
assistance in preparing this determination.
The complainant has provided invoices for the reports. The panel considers it fair in
all the circumstances for the insurer to contribute $3,300 to the cost of the reports.
The reports appear to have been used in administrative court proceedings against the
builder and the panel is not satisfied that they should be the responsibility of the
insurer in full.
Complainant entitled to compensation for non-financial loss
Paragraph 9.3 b) of the FOS Terms of Reference provides that we can award
compensation for non-financial loss where there has been an unusual amount of
physical inconvenience, time taken to resolve a situation, or interference with the
complainant’s expectation of enjoyment or peace of mind.
We expect the complainant to be moderately robust and tolerate a normal degree of
inconvenience when making a claim. We take a conservative approach to assessing
compensation for non-financial loss. The maximum amount we can award for non-
financial loss under the FOS Terms of Reference is $3,000 per claim.
The progression of the complainant’s claim has been subject to extraordinary delays:
it is approximately 14 years since the insured event and nine years since the insured
works, and the property is still in need of extensive rectification. The bulk of the delay
is attributable to the faulty work of the insurer’s builder, which the insurer’s engineer
(JHA) describes as ‘grossly defective’.
Some of th e faulty work by the insurer’s builder was done as part of the private works.
However, this occurred only after the builder was appointed by the insurer. The
insurer’s appointment of the builder, and its arrangement and authorisation of the
insured works, led to the defective performance of the insured works (and the
consequent need for extensive rectification). This would have occurred regardless of
whether the complainant subsequently arranged for the builder to perform private
works.
The panel is satisfied that it is appropriate for the insurer to pay the complainant
compensation for non-financial loss in the sum of $3,000.
Determination | Case number: 500222 Page 13 of 20
3 Supporting information
3.1 The determination is made under FOS Terms of Reference
The Australian Financial Complaints Authority ( AFCA) has commenced managing
complaint s previously lodged with Financial Ombudsman Service (FOS).
This determination is made under FOS Terms of Reference but has adopted the
following terminology for consistency with AFCA. In this determination the AFCA
terms have the same meaning as the FOS terms defined in paragraph 20.1 and
Schedule 1, 2, & 3 of the FOS Terms of Reference.
FOS term AFCA term
applicant complainant
financial services provider financial firm
dispute complaint
3.2 Excerpt from insurer ’s letter of 9 March 2009
Our guarantee on home repairs
We guarantee the quality of materials and workmanship of repairs that we
authorise and arrange for the lifetime of your Home.
This guarantee applies to work to repair, build or rebuild your Home where we:
• authorise
• arrange and.
• pay the builder or repairer directly for this work.
We guarantee the materials used and standard of the workmanship to be free of
defects. If a defect arises in the lifetime of your Home as a result of poor quality
workmanship or incorrect materials, then we will rectify the problem.
This guarantee does not apply:
• to repairs you authorise or make yourself
• to loss, damage or failure of any electrical or mechanical appliances or
machines
• to wear and tear consistent with normal gradual deterioration at your home (e.g.
paint peeling off after its expected life cycle, wood rotting from moisture in the air
or ground, or roofs weathering) or
• where we agree with a repair quote and we give you, or the builder or repairer, a
cheque for the cost of the repairs and you arrange the repairs.
Determination | Case number: 500222 Page 14 of 20
3.3 Summary of building contract
Major Works Contract with UBS signed by complainant on 21 August 2007
The contract states it is for insurance repairs and the complainant’s insurer will pay for
the work. The scope of works includes the following items:
• Remove garden plants at rear of carport to allow access for machinery
…
• Restore gardens to pre-event condition on completion of all repairs
• Install termite barrier around perimeter of lower level of house
…
• Break up and remove concrete slab in lower level of house including marble tiles
• Underpin existing piers in accordance with engineers specification
• Excavate slab and footing in accordance with engineers specifications
• Pour new concrete slab using correct mesh etc.
…
• Reinstate gardens to original condition
…
• Supply and lay new marble floor tiles to match original [six rooms]
• Lay all inslab water and sewage services to match original design and Layout
An addendum to the contract states:
[UBS] will provide clear cost delineation between insurer's works and works for
the homeowner to include stumping and laying concrete for exterior paving. The
insured work consists of the removal and replacement of the pavers while the
insured / home owner is responsible for the preparation of the sub grade.
…
Upgrades to insurance work, if any, such as marble, doors, windows, lights,
pavers etc. will be at owner expense offset by the insured allowance for these
items
Marble floors to replace existing are to be laid in accordance with the suppliers
installation specifications. This is included as insurance work and any upgrade will
be paid for by the Home owner.
3.4 Summary of relevant expert findings
Record Key points
MD Plumbing
08 - 05 - 2006
Bad smell coming from laundry floor waste. MD thinks this is
because ‘nothing runs through the trap’ and the water
becomes stagnant
Tree roots fount in original clay pipe. This is a maintenance
issue. This is not related to the bad smell in the laundry.
NJA, engi neers
Appointed by insurer
Undated: circa 2006
NJA observed several locations on the property where
drainage is inadequate and water likely ponds during heavy
rainfall
Determination | Case number: 500222 Page 15 of 20
Record Key points
NJA observed more than 25 stumps which were not in
contact with the supported bearer, o r had packers bet ween
the stump and the bearer. This indicates long - t erm, ongoing
footing system movement causing problems with the stumps
The footing system of the extension does not comply with
current building standards, and would not be expected to
per form on a highly reactive clay site
Given the age of the dwelling, it is unlikely that the footing
system of the original dwelling complies with current building
standards
Footing system movement may be caused by:
o the inadequate drainage at the site
o a hot wat er system which appears to be discharging onto
the ground
o the large trees close to the building
o the pavers around the building, which allow water into
the soil but prevents evaporation
The original building is on timber stumps, but the extension
is on a concrete slab. These different footing systems will
likely perform differently, leading to distress at the interface
‘We have not… attempted to determine whose responsibility
the various items of [rectification] work may fall under.’
RK, architect/build er
RK, architect/builder
13 - 02 - 2009
RK identified ‘ a number of incomplete, defective and non
compliant works ’
RK, architect/builder
Appointed by complainant
13 - 05 - 2009
RK identified 43 items of outstanding building work.
CSO, engineers
Appointed by insurer
In August 2007, UBS raised the building by 1m, replaced
sub - floor timber posts with a steel framing system, and
lowered the building to its original level ( plus 200mm to
prevent future flooding ) . The complainant believes that,
during this work, ti mber floor boards split due to the
movement
In addition to the above work, the complainant had UBS
perform private works:
o conversion of a portion of the sub - floor area to a living
area
o landscaping and drainage installation
Some of the timber splits were be neath the floor finishing,
indicating they had been present for a long time.
AM, engineer
Appointed by complainant
11 - 07 - 2013
Steel posts were not coated externally as required by
Australian Standards
Steel posts were drilled and submerged, allowing water
ingress
The posts were filled with grout (to displace water) and
welded shut. AM is confident that this will prevent further
corrosion
‘Generally ‘slabs on ground’ rely on placement of plastic
under concrete elements to prevent moisture damp from
ri sing to the surface’
NJA’s engineering drawings called for plastic laid under the
slab and continuing up to the slab underside, but the
Determination | Case number: 500222 Page 16 of 20
Record Key points
complainant’s photographs show the plastic does not extend
up the side of the slab, and there is no plastic water barrie r
under the footings
The increase in moisture and mould may be attributable to
the improperly - installed moisture barrier .
BOO, a sse ssor
Appointed by insurer
12 - 04 - 2014
BOO inspected the home with JHA
The major concern with the works by UBS is the steel p osts
installed to support the house
NJA’s engineering drawings called for 5 SHS posts, but the
posts used were only 4 SHS
The posts should have a protective coating to prevent rust,
but don’t
BOO and JHA viewed a lot of phot ographs taken by the
complainant during the work. The photographs show:
o the plastic used in the footing does not extend all the
way into the footing
o concreters drilled into the posts after they were installed
o due to poor site management by UBS, the site had no
drainage and was often floo ded, and water entered the
posts through holes drilled by the concreters
There was an attempt at rectific ation works to some of the
posts, but they are still rusting; the attempted rectification
does not appear to have worked at all
There are other issues with the works by UBS, but the
problems with the steel posts are so serious that the other
issues are irrelevant
JHA said there’s probably no way to rectify the problem
without removing the posts and demolishing and rebuilding
the entire lower level of the home.
JHA, engineers
Appointed by insurer
17 - 04 - 2014
‘ The repair work appears to have taken a number of years to
finally reach completion, however the standard of the repairs
now appears to be p oor, and failing in some areas.’
Steel posts
The most serious problem is the premature corrosion of the
steel posts supporting the house due to poor installation
practices by UBS. Corrosion is happening bec ause:
o the galvanised coating is insufficient on the outside,
and it is not clear whether there is any co ating at all on
the inside
o the posts are embedded in concrete without being
coated in a protective membrane (as recommended by
the manufacturer)
o the posts have water trapped inside them
The steel posts have a wall thickness of 4mm. This is too
thin: given the height of the posts, and the weight they
support, UBS should have installed posts with a wall
thickness of at least 6mm
Some rectific ation work has been attempted to some of the
posts, but it has not stopped the premature corrosion. JHA
does not recomm end further attempts to repair the posts
JHA recommends removin g and replacing all steel posts
Timber stumps are encased in concrete poured into a
cardboard tube. The cardboard was left in plac e, and the
concrete was not given a dome finish to prevent wate r
Determination | Case number: 500222 Page 17 of 20
Record Key points
pooling at the base of the stumps. This standard of finish is
‘less than professional’.
Concrete slab
JHA notes the following issues with the concrete slab:
o photographs taken by the complainant show the
vapour barrier does not provide sufficient coverag e;
this ‘will have a long term effect on the waterproofing
integrity (rising damp) of the concrete floor slab’
o marble tiles have developed stress cracks because
they were installed on a concrete floor slab without any
of the movement or control joints recommended by
Australian Standard 3958.1
o the slab is poorly set out, which has led to misaligned
walls and floo ring, especially in the laundry
‘ Due to the grossly defective work involving the concrete
floor slab, vapour barrier, and steel post bases… the entire
concrete floo r slab will need to be removed…’
Other issue s
A staircase has been re - built during the repair process with
untreated pine with no termite protection, in violation of
Australian Standard 3600.1
Water is entering the ground - floor family room due to
incorrectly - positioned wall sarking
‘The lower level bedroom at the rear of the house has
insufficient cross - flow ventilation and entry of natural
sunlight, due to the design of the room, resulting in
conditions conducive to mould and mildew gr owth.’
PBK, engineers
Appointed by insurer
17 - 06 - 2014
PBK inspected the property on 23 May 2014 with BOO and
JHA
Despite other engineers’ claims of insufficient wall thickness
in the steel posts, PBK says the posts appear to be
adequate to support the weight bearing down on them
‘In general, minor failures of the vapour barrier would not be
an issue if significant moisture was not present.’
Wall sarking appears to have been compromised, allowing
moisture to get into the wall frame
Loose brickwork in the fireplace has probably been
exacerbated by the propping and rebuilding on the lower
floor. Loss bricks should be removed and re - mortared back
into position
The damage to the foundations is likely due to soils being
‘aggressive’ (high acid - s ulfate), reacti ve, and high in
moisture; these factors are due to site conditions, not
incorrect design
‘The majority of issues claimed by [the complainant] are
relating to aesthetics and minor imperfections… None of
these issues are structural, or compromise the integri ty of
the building.’
PBK recommends testing all pipework around the dwelling. If
the soil is reactive, older pipes may be cracked, which could
account for the excessive moisture observed on site
Photographs attached to the report show several problems,
inc luding corrosion and efflorescence.
Determination | Case number: 500222 Page 18 of 20
Record Key points
PBK, engineers
Appointed by insurer
15 - 12 - 2014
High levels of moisture and soil sulfides have increased the
propensity for steel corrosion and conc rete carbonation
PBK assumes:
o protective coatings removed for testing have been
reapplied
o corrosion in the built - in posts has been inhibited as much
as possible
o the built - in posts closest to the external wall have been
treated with a coating that is at least as good as the
relevant code recommends
PBK does not give any reaso ns for making these
assumptions
‘[PBK’s] recommendation is for the steelwork columns under
the subfloor to be replac ed with new base plates fixed to new
concrete pad footings.’
INT, plumber
Appointed by insurer
15 - 12 - 2014
Inspection of pipework around the dwelling revealed no
cracking
Floor waste risers in the laundry and bathroom show a build -
up of bacteria that could be causing the unpleasant smells
reported by the complainant
There is a large build - up of sludge throughout the pipework
under the slab
‘Elevated sanitary pipe work at front underside of hous e
running at minimum allowable grade but sagging at
downstream end. Recommended rectification of works in
case any issues arise in the future.’
RB, engineers
Appointed by complainant
15 - 04 - 2015
This is a 50 - page report completed after reviewing
documents provided by the complainant and the insurer
RB said poor workmanship by UBS is the major cause of the
issues affecting the property
Steel posts
Steel posts have corroded primarily because of:
o UBS’s f ailure to apply sufficient coating to the steel posts
o poor site management during construction, allowing the
slab to sit in deep water for extended periods
As stated by PBK, high levels of moisture and soil sulfides
have contributed to corrosion. However, soil conditions
would not have had this effect if it weren’t for poor
workmanship. If not for UBS’s poor workmanship, RB
estimates the steel could have lasted 15 - 18 years before
requiring major maintenance. Due to the lack of sufficient
coating, the corros ion protection system did not last more
than one year
RB agrees with PBK that the steel posts are structurally
adequate to support their loads, provided there is no further
corrosion
Concrete slab
UBS did not properly install the moisture barrier
The pour ing of the conc rete slab was discontinuous. This
would have led to differential shrinkage and cracking. The
cracks would allow moisture to seep through
The defects in the slab will lead to rising damp,
efflorescence, and mould growth
Determination | Case number: 500222 Page 19 of 20
Record Key points
Marble floor tiles ins talled over the slab have cracked
because of insufficient control joints, differential shrinkage,
and excessive moisture
Rectifying the slab defects will require demolition of the slab
Other issue s
RB appointed a plumber to inspect the pipes. After reviewing
the plumber’s report, and inspecting the pipes themselves,
RB concluded:
o there is a sag and insufficient fall in the sanitary pipe
leading from these areas
o the insufficient fall means the pipe is not self - cleansing
and does not comply wit h the re levant Australian
Standard
o the insufficient fall is the responsibility of UBS
o the odour is likely to continue until the insufficient fall is
rectified
o rectification of the pipework will require the demolition of
the concrete slab
UBS failed to correctly in stall wall sarking, leading to water
penetration at the rear French doors
The eastern side staircase is built with untreated pine with no
termite protection, in violation of Australian Standard 3660.1
Bricks from the chimney were released after the raising and
lowering of the house. Loos e bricks should be pointed and
re - mortared
The level of mould is unhealthy, likely due to a combination
of factors including:
o high humidity
o the lack of a moisture barrier
o UBS setting a concrete spoon drain against the slab,
which conveys moisture to the slab
RB recommends a full demolition and reconstruction.
Measures short of demolition could be taken, but they would
require an unreasonably onerous and costly maintenance
regime, with no guarantee it would prevent premature f ailure
of the structure.
PBK, engineers
Appointed by insurer
21 - 05 - 2015
Corrosion has reduc ed the expected life of the steel posts.
However, the corrosion rate is only slightly elevat ed: RB said
corrosion was ‘substantial’, but PBK thinks this is excessive.
Tests indicate there is only a slight loss of thickness of
section, and remediation efforts have retarded furt her
corrosion
PBK agrees with the replacement of sub - floor steel posts
PBK agrees that the design life of the structure is ‘less than
r equired’, but thinks this can be remedied by ‘protective
treatment methods’
RB said the slab needs to be demolished to rectify the
insufficient fall in the sanitary pipe. PBK’s response: ‘No
objections to the correction in the fall.’
RB said measures short of demolition would require an
unreasonably onerous and costly maintenance regime, with
no guarantee it would prevent premature failure of the
structure. PBK’s response: ‘If rectification can provide a
comparable design life for the structure as has been
demonstrated by the current steelwork repairs, it is
Determination | Case number: 500222 Page 20 of 20
Record Key points
considered an appropriate and practicable engineering
solution.’