Home / Financial Firm (Unknown - Insurer) / Determination 500222

Determination 500222

Insurer liability under lifetime repair guarantee for defective storm repairs by its appointed builder

FirmFinancial Firm (Unknown - Insurer)
Decided2019-01-30
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$17,468
Non-financial loss$3,000
Amount claimed—
SourceAFCA PDF

Summary

After a 2004 storm, the insurer's appointed builder carried out defective repairs, and the complainant also arranged private works. AFCA held the insurer liable for rectifying the insured works, reimbursement of house raising and garden clearing, and $3,000 non-financial loss, but not for the private works, roof or irrigation; the rectification cost is still to be quantified.

The insurer's lifetime guarantee covers only repair work it authorised and arranged, so it covers the defective insured works but not the complainant's private works.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay compensationpay interestpay non financial lossprovide documents

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination | Case number: 500222 Page 1 of 20 Determination Case number: 500222 21 January 2019 1 Determination overview 1.1 Complaint The complainant held a home insurance policy with the financial firm (insurer). On 8 November 2004, the complainant lodged a claim for damage to the home caused by stormwater runoff. The insurer accepted the claim and appointed a builder to repair the damage. The complainant says the builder’s work was defective and the insurer is liable for rectification. The insurer says the complainant appointed the builder to undertake private works in addition to the insured works authorised by the insurer. The insurer says it accepts responsibility for the insured works, but not for the private works. 1.2 Issues and key findings What is the scope of the insurer ’s guarantee ? There has been a mixture of insured works and private works at the complainant’s home. The insurer’s guarantee applies only to the insured works. The insurer is not required to guarantee the private works, even if they were performed by the insurer’s builder. Is the insurer liable for rectification? Although the steel posts supporting the house suffered premature corrosion due to faulty workmanship by the insurer’s builder, the posts were installed as part of the private works. Accordingly, the insurer is not liable for rectification of this work. However, there was also faulty workmanship by the builder with respect to the insured works, including the pouring of the slab and the laying of in-slab pipework. The insurer is liable for rectification of this work. Determination | Case number: 500222 Page 2 of 20 What must the insurer do to fulfil its guarantee? The insurer must obtain expert evidence to determine the cost of rectification of the insured works. The insurer must then settle its liability by paying the complainant an amount determined in accordance with section 2.3 of this determination. 1.3 Determination This determination is partly in favour of the complainant. Within 30 days of the acceptance of this determination, the insurer must give the complainant a scope of works and quote for all work required to rectify the faulty performance of the insured works. Within 30 days of giving the complainant a scope of works and quote, the insurer must pay the complainant:  the reasonable cost of rectification of the insured works  an additional 15% contingency to allow for unforeseen costs  interest on the above amounts at the rate determined under section 57 of the Insurance Contracts Act 1984 (Cth) (the Act) from 17 May 2014 until the settlement date  $9,350 reimbursement for house raising, plus interest from 2 July 2008 until the settlement date  $4,818 reimbursement for garden clearing, plus interest from 19 May 2008 until the settlement date  $3,300 in partial reimbursement of professional costs incurred in the course of this complaint  $3,000 in compensation for non-financial loss. Determination | Case number: 500222 Page 3 of 20 2 Reasons for determination 2.1 What is the scope of the insurer ’s guarantee ? Insurer ’s builder perfo rmed insured works and private works The complainant’s house was damaged by a storm in 2004. The insurer appointed ‘UBS’, builder, to repair damage caused by the storm (the insured works). While UBS performed the insured works, the complainant arranged for UBS to perform additional work (the private works) at her expense. Insurer provides lifetime guarantee on repairs The product disclosure statement effective in 2004 does not mention a guarantee on repairs. Nevertheless, the insurer accepts it is responsible for repairs done on its behalf. The General Insurance Code of Practice (to which the insurer subscribes) requires an insurer to guarantee repairs if it ‘selected and directly authorised a repairer’. On 9 March 2009 the insurer sent the complainant a letter saying it provided a lifetime guarantee for repairs to claim-related damage. The letter said the guarantee:  applies to work authorised, arranged, and paid for by the insurer  does not apply to repairs authorised by the complainant. Guarantee does not extend to private works The complainant says the insurer’s letter of 9 March 2009 guarantees ‘private works… as well as original insured works’. The panel does not accept this. The letter clearly states that the guarantee does not apply to repairs authorised only by the complainant. The panel is satisfied that the insurer provided a lifetime guarantee only for repair work it authorised. The insurer is not required to guarantee work arranged and authorised by the complainant, even if it was performed by the same repairer. 2.2 Is the insurer liable for rectification? Steel posts Steel posts part of private works The exchanged material indicates UBS replaced sub-floor timber posts with steel posts. The expert reports indicate the posts have suffered severe premature corrosion. The insurer says the steel posts were installed as part of the private works. Determination | Case number: 500222 Page 4 of 20 A 2006 report by ‘NJA’, engineers, says there are problems with the footing system of the insured property. NJA says there are several factors that could be contributi ng to the problems, but does not mention damage caused by the insured event (the 2004 storm) as a potential contributing factor. The complainant signed a contract with UBS (the Major Works Contract) for repairs to be paid for by the insurer. The contract i ncludes a scope of works which does not mention timber or steel posts. An addendum to the contract states in part: [UBS] will provide clear cost delineation between insurer's works and works for the homeowner to include stumping… The insurer ’s note dated 8 May 2008 refers to the works in the contract. The note then states: [The complainant] has agreed for all re-stumping of the home to be completed in conjunction. An invoice dated 31 October 2008 from UBS to the complainant states: Cost of repairs for non-Insurance work to date. The invoice includes the following items:  Formatube - surround for timber stumps  Excavation - Preparation of stumps to front of home and rear extension slab  Project management of re-stumping front section and consultation. The insurer’s note dated 30 October 2009 says it told the complainant it would not cover work to ‘concrete stump footings’ because ‘these are private works and information we have to hand does not indicate stumps were defective’. Having considered the information provided by both parties, the panel is satisfied that the steel posts were installed as part of work arranged and authorised by the complainant. Therefore, the insurer is not required to guarantee this work. Steel posts not damaged by insurer’s rectification work The complainant says the insurer authorised rectification work to some of the steel posts in 2009. The complainant says the insurer’s lifetime guarantee applies to this work. The rectification work was aimed at arresting the premature corrosion of the posts. Expert reports indicate the attempt was unsuccessful. However, there is no evidence that the rectification work damaged the property (ie. that the rectification work left the posts in a worse condition than before the work). Determination | Case number: 500222 Page 5 of 20 The evidence indicates the steel posts require replacement. However, this is due to the faulty workmanship involved in the installation of the posts (which the insurer did not authorise), not any defect in the rectification work (which the insurer did authorise). Therefore, the insurer is not liable for the cost of replacing the steel posts. Concrete slab and moisture barrier Concrete slab part of insured works The scope of works in the Major Works Contract includes the excavation of a concrete slab and the pouring of a new slab. The complainant says the slab was poured by an unlicensed concreter, with an inadequate or improperly-installed moisture barrier. The insurer acknowledges the insured works included the pouring of a new slab, but says it is ‘unable to determine’ whether the insured works included the installation of the moisture barrier. The insurer says the Major Works Contract does not mention a moisture barrier. The expert reports indicate that the moisture barrier is meant to be fitted to the slab, and its purpose is to protect the slab from moisture. However, the evidence does not indicate that it was part of the Major Works Contract or was authorised by the insurer. Having considered the information provided by both parties, the panel is satisfied that the pouring of the slab, but not the installation of the moisture barrier, was part of work arranged and authorised by the insurer. Therefore, the insurer is required to guarantee the concrete slab but not the moisture barrier. Concrete slab requires rectification The complainant appointed an engineer (AM) who inspected the property on 3 November 2012. The insurer appointed an assessor (BOO) and an engineer (JHA) who inspected the property on 9 April 2014. According to all three experts, photographs taken by the complainant during construction show the moisture barrier installed by UBS was incomplete. JHA says the incomplete moisture barrier will lead to rising damp. JHA also notes the following defects in the slab:  neither the slab nor the tiles laid over it had sufficient control joints, so the tiles cracked when the slab shrunk  the slab is poorly set out, which has led to misaligned walls and flooring, especially in the laundry. JHA says: Determination | Case number: 500222 Page 6 of 20 Due to the grossly defective work involving the concrete floor slab, vapour barrier, and steel post bases… the entire concrete floor slab will need to be removed… The complainant appointed an engineer (RB) who inspected the property and produced a report dated 15 April 2015. RB says:  the moisture barrier was not installed in accordance with the engineering drawings or the relevant Australian Standard  the incomplete moisture barrier is contributing to efflorescence and mould growth  rectifying the issue will require the removal of the slab. The insurer appointed an engineer (PBK) who said damage to the foundations was due to environmental conditions rather than poor workmanship. PBK says: In general, minor failures of the vapour barrier would not be an issue if significant moisture was not present. The evidence indicates significant moisture is present. Nothing in PBK’s reports contradicts the other engineers’ conclusions regarding the defects in the slab and how they can be rectified. Having considered the information provided by both parties, the panel is satisfied that UBS exhibited faulty workmanship in the pouring of the slab. The panel is satisfied that rectification of this issue will require the removal and replacement of the slab. In-slab pipework In-slab pipework part of insured works The insurer says the laying of in- slab water and sewage pipes ‘may’ be part of the insured works. The work is included in the Major Works Contract. The insurer has not offered any reason why the work should not be considered part of the insured works. The panel is satisfied that the laying of in-slab water and sewage pipes was work arranged and authorised by the insurer. Therefore, the insurer is required to guarantee this work. In-slab pipework requires rectification The complainant says there has been a foul odour emanating from the laundry and downstairs bathroom. The complainant says this is due to poor workmanship by UBS in the installation of the in-slab pipes. The insurer does not accept that the property has an odour problem caused by incorrectly laid pipes, and says the complainant has not provided an expert report to establish this. Determination | Case number: 500222 Page 7 of 20 The insurer appointed ‘INT’, plumber, who inspected the property and produced a report dated 9 November 2014. INT found accumulations of sludge and bacteria, and recommended rectification of the pipework. RB inspected the property in April 2015 and appointed a plumber to inspect the pipes. RB concluded:  there is a sag and insufficient fall in a sanitary pipe  the insufficient fall means the pipe is not self-cleansing and does not comply with the relevant Australian Standard  the odour is likely to continue until the insufficient fall is rectified  rectification of the pipework will require demolition of the concrete slab. PBK’s report of 21 May 2015 says PBK has ‘No objections’ to RB’s conclusions about the insufficient fall in the pipe and the need to demolish the slab to correct it. Having considered the information provided by both parties, the panel is satisfied that UBS exhibited faulty workmanship in the laying of the pipes. The panel is satisfied that rectification of the pipework will require the removal and replacement of the slab. Other issues Wall sarking The Major Works Contract includes the installation of wall sarking. JHA, PBK, and RB all say the sarking is incorrectly positioned. As a result, water is entering the house above the French doors at the rear of the lower level family room. Rectification of this issue will require the removal of flashing and wall cladding to access the sarking. The panel is satisfied that the insurer is liable for the rectification of the incorrectly positioned wall sarking, including the repair of any damage caused by water entering the house as a result of this defect. Termite barrier The Major Works Contract includes the installation of a termite barrier around the lower level of the house. JHA and RB say the side timber staircase has no termite protection, in violation of the relevant Australian Standard. The panel is satisfied that the insurer is liable for the installation of termite protection for the side timber staircase. Determination | Case number: 500222 Page 8 of 20 Mould growth A mould report dated 11 November 2014 says high levels of mould were detected in some samples taken from the complainant’s property, and says the premises require mould remediation. JHA says there is mould growth in a lower level bedroom due to the room’s poor ventilation. PBK says mould growth in the house is predominantly in dirty, poorly- ventilated areas with high humidity. RB says mould growth in the lower level is likely due to a combination of factors, including high humidity, the lack of a moisture barrier, and the setting of a concrete spoon drain against the slab. The report produced by NJA in 2006 (before the insured works) says the property has poor drainage, and water tends to pond at multiple locations (including against the house) whenever it rains heavily. NJA’s conclusions are not contradicted by subsequent expert reports. Based on the available evidence, the panel is not satisfied that there is any mould growth attributable to poor workmanship in carrying out the insured works. House raising The complainant says the insurer made her pay to lift the house, which was required to allow for the insured works. The complainant provided an invoice dated 28 May 2008 in the sum of $9,350. The complainant says she paid by cheque on 2 July 2008. The invoice says the house was raised ‘until restumping can be completed’. The restumping was part of the private works. However, house raising would also have been required to replace the slab (in which stumps/posts are embedded). This was part of the insured works, so the insurer was liable for the cost of raising the house. The panel considers that the insurer should reimburse the complainant $9,350, plus interest from 2 July 2008 until the settlement date. The insurer is also liable for the cost of raising the house again to allow for another replacement of the slab. Timber flooring The complainant says the raising and lowering of the house resulted in a sagging floorboard in the kitchen. The insurer appointed ‘CSO’, engineers, who inspected the timber flooring and produced a report dated 21 October 2010. CSO’s report says damage to the floor was not caused by building works, but by a combination of factors including:  repeated sanding over its long life  a lack of control joints or gaps  knots in the wood. Determination | Case number: 500222 Page 9 of 20 RB’s report says a timber floorboard cracked after the house raising, but does not give any reason to conclude that the house raising caused the damage. Based on the available evidence, the panel is not satisfied that the timber flooring was damaged by the insured event or any building work. The insurer is not liable for the cost of repairing the floor. However, the insurer is liable for the cost of any protective measures required to protect the floor while raising the house again to allow for another replacement of the slab. Fireplace The complainant says some of the bricks in the fireplace have loosened. PBK’s report of 14 July 2014 says the house raising probably loosened the bricks, and recommends loose bricks be removed and re -mortared back into position. As the house raising would have been required for the insured works, the panel considers that the insurer is liable for the cost of removing and reinstating loose bricks. Garden reinstatement The Major Works Contract includes the removal of garden plants to allow access for machinery, and the restoration of the garden to the condition it was in before the insured event. The complainant has provided invoices for work to the garden after repairs were completed. The insurer says some of this work was to improve the garden to a better condition than it was in before the insured event. The complainant has not refuted this claim. The insurer’s let ter of 14 October 2015 says it paid the complainant $31,903 for the cost of reinstating the garden after repairs were completed. The complainant has not provided any evidence that this payment was inadequate. The complainant says that before repairs commenced, the insurer made her remove plants from the garden at her own expense. The complainant has provided an invoice dated 19 May 2008 for $2,200 for clearing the gardens. The complainant has also provided a quote and a bank statement showing payment on 25 January 2008 of $2,618 for tree lopping. The panel considers that the insurer should reimburse the complainant $4,818, plus interest from 19 May 2008 until the settlement date. The insurer is also liable for the cost of clearing and reinstating the garden again to allow for rectification work. Determination | Case number: 500222 Page 10 of 20 Roof The complainant replaced the roof of the building in 2008. The complainant has provided an invoice for roof replacement dated 5 December 2008 in the sum of $24,850. The complainant says the roof split (and needed to be replaced) because of the lengthy delay between the insured event in 2004 and the commencement of repairs in 2008. This claim is not supported by any of the expert reports. Based on the available evidence, the panel is not satisfied that the roof needed to be replaced because of the insured event or any building work. The insurer is not required to reimburse the complainant for the cost of the roof replacement. Irrigation system The complainant has provided a quote dated 8 April 2015 for $10,450 for the installation of a new irrigation system. The complainant says the irrigation system was ‘ obliterated by all the excavation equipment and debris’ that entered her yard during the insured works. This claim is not supported by any of the expert reports. Based on the available evidence, the panel is not satisfied that the irrigation system needed to be replaced because of the insured event or any building work. The insurer is not required to pay for the installation of a new irrigation system. 2.3 What must the insurer do to fulfil its guarantee? Insurer must fulfil guarantee with cash settlement The engineers’ reports establish that the steel posts supporting the house have suffered severe premature corrosion, and efforts to rectify the issue have been unsuccessful. Most of the engineers agree, and the panel is satisfied, that the posts should be replaced, which requires the removal of the slab. The replacement of the slab (for which the insurer is liable) should not be undertaken unless the replacement of the steel posts (for which the insurer is not liable) is undertaken in conjunction. Therefore, the insurer should not fulfil the guarantee by authorising rectification work, unless the complainant agrees to coordinate this with private works to replace the posts. In the circumstances, the insurer should settle its liability by paying the complainant the reasonable cost of rectifying the insured works. Insurer must prepare scope of works The available evidence is not sufficient to determine what work is required to rectify the insured works, or the cost of such work. Determination | Case number: 500222 Page 11 of 20 If the complainant accepts this determination, the insurer must prepare a scope of works for all work required due to the faulty performance of the insured works. This scope of works must include:  removal and replacement of the slab  rectification of the in-slab pipework  rectification of wall sarking  repair of any damage caused by water entering the house as a result of the incorrectly positioned wall sarking  installation of termite protection for the side timber staircase  house raising and lowering  protection of timber floor during house raising and lowering  removal and reinstatement of loose fireplace bricks  clearance and appropriate reasonable reinstatement of garden. The insurer must then obtain a costing of the scope of works. The complainant may also obtain scopes of work and/or quotes for rectification of the insured works. The panel invites the parties to work cooperatively to develop an agreed scope of works and costing. Insurer must allow for contingencies When an insurer pays a cash settlement it avoids the risks of unforeseen costs being incurred in the repair process, and does not have to provide a lifetime guarantee on the repairs. These risks are transferred to the insured. Furthermore, an insured party arranging private works may have to pay more than an insurer would for the same work, because they do not have the insurer’s industry connections or bargaining power. Given that this matter is to be cash settled, the panel co nsiders it appropriate to make a further allowance to cover possible contingencies that may arise during the repair process. The panel consider a reasonable contingency allowance to be 15% of the cost of repairs. Insurer must pay interest Section 57 of the Act provides that the insurer must pay interest on the settlement sum from the time when it was unreasonable for the insurer to have withheld payment. In the circumstances, the panel considers this date to be 17 May 2014, one month after the date of JHA’s report. Determination | Case number: 500222 Page 12 of 20 Complainant entitled to reimbursement of professional costs Paragraph 9.4 of the Financial Ombudsman Service (FOS) Terms of Reference provides that we can require an insurer to contribute to legal, professional, or travel costs incurred by a complainant in the course of a complaint. Unless exceptional circumstances apply, we will not require an insurer to contribute more than $3,300 to a complainant’s costs. The complainant appointed engineers (AM and RB) and an architect (RK) to inspect her property and provide expert reports. The panel found the reports to be of assistance in preparing this determination. The complainant has provided invoices for the reports. The panel considers it fair in all the circumstances for the insurer to contribute $3,300 to the cost of the reports. The reports appear to have been used in administrative court proceedings against the builder and the panel is not satisfied that they should be the responsibility of the insurer in full. Complainant entitled to compensation for non-financial loss Paragraph 9.3 b) of the FOS Terms of Reference provides that we can award compensation for non-financial loss where there has been an unusual amount of physical inconvenience, time taken to resolve a situation, or interference with the complainant’s expectation of enjoyment or peace of mind. We expect the complainant to be moderately robust and tolerate a normal degree of inconvenience when making a claim. We take a conservative approach to assessing compensation for non-financial loss. The maximum amount we can award for non- financial loss under the FOS Terms of Reference is $3,000 per claim. The progression of the complainant’s claim has been subject to extraordinary delays: it is approximately 14 years since the insured event and nine years since the insured works, and the property is still in need of extensive rectification. The bulk of the delay is attributable to the faulty work of the insurer’s builder, which the insurer’s engineer (JHA) describes as ‘grossly defective’. Some of th e faulty work by the insurer’s builder was done as part of the private works. However, this occurred only after the builder was appointed by the insurer. The insurer’s appointment of the builder, and its arrangement and authorisation of the insured works, led to the defective performance of the insured works (and the consequent need for extensive rectification). This would have occurred regardless of whether the complainant subsequently arranged for the builder to perform private works. The panel is satisfied that it is appropriate for the insurer to pay the complainant compensation for non-financial loss in the sum of $3,000. Determination | Case number: 500222 Page 13 of 20 3 Supporting information 3.1 The determination is made under FOS Terms of Reference The Australian Financial Complaints Authority ( AFCA) has commenced managing complaint s previously lodged with Financial Ombudsman Service (FOS). This determination is made under FOS Terms of Reference but has adopted the following terminology for consistency with AFCA. In this determination the AFCA terms have the same meaning as the FOS terms defined in paragraph 20.1 and Schedule 1, 2, & 3 of the FOS Terms of Reference. FOS term AFCA term applicant complainant financial services provider financial firm dispute complaint 3.2 Excerpt from insurer ’s letter of 9 March 2009 Our guarantee on home repairs We guarantee the quality of materials and workmanship of repairs that we authorise and arrange for the lifetime of your Home. This guarantee applies to work to repair, build or rebuild your Home where we: • authorise • arrange and. • pay the builder or repairer directly for this work. We guarantee the materials used and standard of the workmanship to be free of defects. If a defect arises in the lifetime of your Home as a result of poor quality workmanship or incorrect materials, then we will rectify the problem. This guarantee does not apply: • to repairs you authorise or make yourself • to loss, damage or failure of any electrical or mechanical appliances or machines • to wear and tear consistent with normal gradual deterioration at your home (e.g. paint peeling off after its expected life cycle, wood rotting from moisture in the air or ground, or roofs weathering) or • where we agree with a repair quote and we give you, or the builder or repairer, a cheque for the cost of the repairs and you arrange the repairs. Determination | Case number: 500222 Page 14 of 20 3.3 Summary of building contract Major Works Contract with UBS signed by complainant on 21 August 2007 The contract states it is for insurance repairs and the complainant’s insurer will pay for the work. The scope of works includes the following items: • Remove garden plants at rear of carport to allow access for machinery … • Restore gardens to pre-event condition on completion of all repairs • Install termite barrier around perimeter of lower level of house … • Break up and remove concrete slab in lower level of house including marble tiles • Underpin existing piers in accordance with engineers specification • Excavate slab and footing in accordance with engineers specifications • Pour new concrete slab using correct mesh etc. … • Reinstate gardens to original condition … • Supply and lay new marble floor tiles to match original [six rooms] • Lay all inslab water and sewage services to match original design and Layout An addendum to the contract states: [UBS] will provide clear cost delineation between insurer's works and works for the homeowner to include stumping and laying concrete for exterior paving. The insured work consists of the removal and replacement of the pavers while the insured / home owner is responsible for the preparation of the sub grade. … Upgrades to insurance work, if any, such as marble, doors, windows, lights, pavers etc. will be at owner expense offset by the insured allowance for these items Marble floors to replace existing are to be laid in accordance with the suppliers installation specifications. This is included as insurance work and any upgrade will be paid for by the Home owner. 3.4 Summary of relevant expert findings Record Key points MD Plumbing 08 - 05 - 2006  Bad smell coming from laundry floor waste. MD thinks this is because ‘nothing runs through the trap’ and the water becomes stagnant  Tree roots fount in original clay pipe. This is a maintenance issue. This is not related to the bad smell in the laundry. NJA, engi neers Appointed by insurer Undated: circa 2006  NJA observed several locations on the property where drainage is inadequate and water likely ponds during heavy rainfall Determination | Case number: 500222 Page 15 of 20 Record Key points  NJA observed more than 25 stumps which were not in contact with the supported bearer, o r had packers bet ween the stump and the bearer. This indicates long - t erm, ongoing footing system movement causing problems with the stumps  The footing system of the extension does not comply with current building standards, and would not be expected to per form on a highly reactive clay site  Given the age of the dwelling, it is unlikely that the footing system of the original dwelling complies with current building standards  Footing system movement may be caused by: o the inadequate drainage at the site o a hot wat er system which appears to be discharging onto the ground o the large trees close to the building o the pavers around the building, which allow water into the soil but prevents evaporation  The original building is on timber stumps, but the extension is on a concrete slab. These different footing systems will likely perform differently, leading to distress at the interface  ‘We have not… attempted to determine whose responsibility the various items of [rectification] work may fall under.’ RK, architect/build er RK, architect/builder 13 - 02 - 2009  RK identified ‘ a number of incomplete, defective and non compliant works ’ RK, architect/builder Appointed by complainant 13 - 05 - 2009  RK identified 43 items of outstanding building work. CSO, engineers Appointed by insurer  In August 2007, UBS raised the building by 1m, replaced sub - floor timber posts with a steel framing system, and lowered the building to its original level ( plus 200mm to prevent future flooding ) . The complainant believes that, during this work, ti mber floor boards split due to the movement  In addition to the above work, the complainant had UBS perform private works: o conversion of a portion of the sub - floor area to a living area o landscaping and drainage installation  Some of the timber splits were be neath the floor finishing, indicating they had been present for a long time. AM, engineer Appointed by complainant 11 - 07 - 2013  Steel posts were not coated externally as required by Australian Standards  Steel posts were drilled and submerged, allowing water ingress  The posts were filled with grout (to displace water) and welded shut. AM is confident that this will prevent further corrosion  ‘Generally ‘slabs on ground’ rely on placement of plastic under concrete elements to prevent moisture damp from ri sing to the surface’  NJA’s engineering drawings called for plastic laid under the slab and continuing up to the slab underside, but the Determination | Case number: 500222 Page 16 of 20 Record Key points complainant’s photographs show the plastic does not extend up the side of the slab, and there is no plastic water barrie r under the footings  The increase in moisture and mould may be attributable to the improperly - installed moisture barrier . BOO, a sse ssor Appointed by insurer 12 - 04 - 2014  BOO inspected the home with JHA  The major concern with the works by UBS is the steel p osts installed to support the house  NJA’s engineering drawings called for 5 SHS posts, but the posts used were only 4 SHS  The posts should have a protective coating to prevent rust, but don’t  BOO and JHA viewed a lot of phot ographs taken by the complainant during the work. The photographs show: o the plastic used in the footing does not extend all the way into the footing o concreters drilled into the posts after they were installed o due to poor site management by UBS, the site had no drainage and was often floo ded, and water entered the posts through holes drilled by the concreters  There was an attempt at rectific ation works to some of the posts, but they are still rusting; the attempted rectification does not appear to have worked at all  There are other issues with the works by UBS, but the problems with the steel posts are so serious that the other issues are irrelevant  JHA said there’s probably no way to rectify the problem without removing the posts and demolishing and rebuilding the entire lower level of the home. JHA, engineers Appointed by insurer 17 - 04 - 2014  ‘ The repair work appears to have taken a number of years to finally reach completion, however the standard of the repairs now appears to be p oor, and failing in some areas.’ Steel posts  The most serious problem is the premature corrosion of the steel posts supporting the house due to poor installation practices by UBS. Corrosion is happening bec ause: o the galvanised coating is insufficient on the outside, and it is not clear whether there is any co ating at all on the inside o the posts are embedded in concrete without being coated in a protective membrane (as recommended by the manufacturer) o the posts have water trapped inside them  The steel posts have a wall thickness of 4mm. This is too thin: given the height of the posts, and the weight they support, UBS should have installed posts with a wall thickness of at least 6mm  Some rectific ation work has been attempted to some of the posts, but it has not stopped the premature corrosion. JHA does not recomm end further attempts to repair the posts  JHA recommends removin g and replacing all steel posts  Timber stumps are encased in concrete poured into a cardboard tube. The cardboard was left in plac e, and the concrete was not given a dome finish to prevent wate r Determination | Case number: 500222 Page 17 of 20 Record Key points pooling at the base of the stumps. This standard of finish is ‘less than professional’. Concrete slab  JHA notes the following issues with the concrete slab: o photographs taken by the complainant show the vapour barrier does not provide sufficient coverag e; this ‘will have a long term effect on the waterproofing integrity (rising damp) of the concrete floor slab’ o marble tiles have developed stress cracks because they were installed on a concrete floor slab without any of the movement or control joints recommended by Australian Standard 3958.1 o the slab is poorly set out, which has led to misaligned walls and floo ring, especially in the laundry  ‘ Due to the grossly defective work involving the concrete floor slab, vapour barrier, and steel post bases… the entire concrete floo r slab will need to be removed…’ Other issue s  A staircase has been re - built during the repair process with untreated pine with no termite protection, in violation of Australian Standard 3600.1  Water is entering the ground - floor family room due to incorrectly - positioned wall sarking  ‘The lower level bedroom at the rear of the house has insufficient cross - flow ventilation and entry of natural sunlight, due to the design of the room, resulting in conditions conducive to mould and mildew gr owth.’ PBK, engineers Appointed by insurer 17 - 06 - 2014  PBK inspected the property on 23 May 2014 with BOO and JHA  Despite other engineers’ claims of insufficient wall thickness in the steel posts, PBK says the posts appear to be adequate to support the weight bearing down on them  ‘In general, minor failures of the vapour barrier would not be an issue if significant moisture was not present.’  Wall sarking appears to have been compromised, allowing moisture to get into the wall frame  Loose brickwork in the fireplace has probably been exacerbated by the propping and rebuilding on the lower floor. Loss bricks should be removed and re - mortared back into position  The damage to the foundations is likely due to soils being ‘aggressive’ (high acid - s ulfate), reacti ve, and high in moisture; these factors are due to site conditions, not incorrect design  ‘The majority of issues claimed by [the complainant] are relating to aesthetics and minor imperfections… None of these issues are structural, or compromise the integri ty of the building.’  PBK recommends testing all pipework around the dwelling. If the soil is reactive, older pipes may be cracked, which could account for the excessive moisture observed on site  Photographs attached to the report show several problems, inc luding corrosion and efflorescence. Determination | Case number: 500222 Page 18 of 20 Record Key points PBK, engineers Appointed by insurer 15 - 12 - 2014  High levels of moisture and soil sulfides have increased the propensity for steel corrosion and conc rete carbonation  PBK assumes: o protective coatings removed for testing have been reapplied o corrosion in the built - in posts has been inhibited as much as possible o the built - in posts closest to the external wall have been treated with a coating that is at least as good as the relevant code recommends PBK does not give any reaso ns for making these assumptions  ‘[PBK’s] recommendation is for the steelwork columns under the subfloor to be replac ed with new base plates fixed to new concrete pad footings.’ INT, plumber Appointed by insurer 15 - 12 - 2014  Inspection of pipework around the dwelling revealed no cracking  Floor waste risers in the laundry and bathroom show a build - up of bacteria that could be causing the unpleasant smells reported by the complainant  There is a large build - up of sludge throughout the pipework under the slab  ‘Elevated sanitary pipe work at front underside of hous e running at minimum allowable grade but sagging at downstream end. Recommended rectification of works in case any issues arise in the future.’ RB, engineers Appointed by complainant 15 - 04 - 2015  This is a 50 - page report completed after reviewing documents provided by the complainant and the insurer  RB said poor workmanship by UBS is the major cause of the issues affecting the property Steel posts  Steel posts have corroded primarily because of: o UBS’s f ailure to apply sufficient coating to the steel posts o poor site management during construction, allowing the slab to sit in deep water for extended periods  As stated by PBK, high levels of moisture and soil sulfides have contributed to corrosion. However, soil conditions would not have had this effect if it weren’t for poor workmanship. If not for UBS’s poor workmanship, RB estimates the steel could have lasted 15 - 18 years before requiring major maintenance. Due to the lack of sufficient coating, the corros ion protection system did not last more than one year  RB agrees with PBK that the steel posts are structurally adequate to support their loads, provided there is no further corrosion Concrete slab  UBS did not properly install the moisture barrier  The pour ing of the conc rete slab was discontinuous. This would have led to differential shrinkage and cracking. The cracks would allow moisture to seep through  The defects in the slab will lead to rising damp, efflorescence, and mould growth Determination | Case number: 500222 Page 19 of 20 Record Key points  Marble floor tiles ins talled over the slab have cracked because of insufficient control joints, differential shrinkage, and excessive moisture  Rectifying the slab defects will require demolition of the slab Other issue s  RB appointed a plumber to inspect the pipes. After reviewing the plumber’s report, and inspecting the pipes themselves, RB concluded: o there is a sag and insufficient fall in the sanitary pipe leading from these areas o the insufficient fall means the pipe is not self - cleansing and does not comply wit h the re levant Australian Standard o the insufficient fall is the responsibility of UBS o the odour is likely to continue until the insufficient fall is rectified o rectification of the pipework will require the demolition of the concrete slab  UBS failed to correctly in stall wall sarking, leading to water penetration at the rear French doors  The eastern side staircase is built with untreated pine with no termite protection, in violation of Australian Standard 3660.1  Bricks from the chimney were released after the raising and lowering of the house. Loos e bricks should be pointed and re - mortared  The level of mould is unhealthy, likely due to a combination of factors including: o high humidity o the lack of a moisture barrier o UBS setting a concrete spoon drain against the slab, which conveys moisture to the slab  RB recommends a full demolition and reconstruction. Measures short of demolition could be taken, but they would require an unreasonably onerous and costly maintenance regime, with no guarantee it would prevent premature f ailure of the structure. PBK, engineers Appointed by insurer 21 - 05 - 2015  Corrosion has reduc ed the expected life of the steel posts. However, the corrosion rate is only slightly elevat ed: RB said corrosion was ‘substantial’, but PBK thinks this is excessive. Tests indicate there is only a slight loss of thickness of section, and remediation efforts have retarded furt her corrosion  PBK agrees with the replacement of sub - floor steel posts  PBK agrees that the design life of the structure is ‘less than r equired’, but thinks this can be remedied by ‘protective treatment methods’  RB said the slab needs to be demolished to rectify the insufficient fall in the sanitary pipe. PBK’s response: ‘No objections to the correction in the fall.’  RB said measures short of demolition would require an unreasonably onerous and costly maintenance regime, with no guarantee it would prevent premature failure of the structure. PBK’s response: ‘If rectification can provide a comparable design life for the structure as has been demonstrated by the current steelwork repairs, it is Determination | Case number: 500222 Page 20 of 20 Record Key points considered an appropriate and practicable engineering solution.’

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.