Home / Financial Firm (Unknown - Insurer) / Determination 499525

Determination 499525

Hail storm claim: cash settlement amount inadequate and claim management

FirmFinancial Firm (Unknown - Insurer)
Decided2018-03-14
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant disputed the FSP's cash settlement for hail damage and its claim management, and sought compensation for her time. AFCA found the settlement reasonable, the claim managed reasonably and no compensation payable.

The FSP's obligation is to repair on a like-for-like basis, so it need not fund upgrades, and FOS does not compensate for time spent managing a claim or minor delays.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 499525 Determination Page 1 of 4 Case number: 499525 14 March 2018 1 Overview 1.1 Dispute The applicant holds a home building and contents policy underwritten by the financial services provider (FSP) covering her home address. On 30 December 2016, a claim was lodged under the policy for damage sustained to the property during a hail storm which occurred on 11 November 2016. The FSP accepted the claim and arranged to settle its liability by way of cash payment. The applicant is dissatisfied with the settlement amount paid by the FSP and its management of the claim. 1.2 Issues and key findings Has the FSP fulfilled its obligations under the policy terms? The FSP has fulfilled its policy obligations because:  the terms of the policy allow it to cash settle its liability  t here is no evidence the FSP’s cash settlement amount did not adequately reflect the works required to undertake the claim related repairs  the FSP is not obliged to cover upgrades or betterment to the property. Is the applicant entitled to compensation? The material shows the FSP managed the claim reasonably overall. An award of compensation it is not appropriate in the circumstances. 1.3 Determination This determination is in favour of the FSP. The FSP has fulfilled its obligations to the applicant and is not required to take any further action. Case No: 499525 Determination Page 2 of 4 2 Reasons for determination 2.1 Has the FSP fulfilled its obligations under the policy terms? Applicant has onus to establish entitlement to further benefits There is no dispute between the parties the applicant suffered a loss from a risk insured against or that the FSP accepted her claim. However, a dispute has arisen between the parties as to the FSP’s settlement and management of the claim. The ap plicant maintains the FSP’s settlement was inadequate to undertake the claim related repairs. She found it difficult to deal with the FSP and seeks compensation for her time. The matter of the excess amount for the building has since been resolved between the parties and will not be addressed further in this determination. FSP’s cash settlement is reasonable The applicant maintains the FSP’s cash settlement was inadequate to properly repair the property. The applicant says the FSP did not settle her to:  replace all veranda roof sheets  replace all solar tubing for the pool  replace skylights with a model that meets current standards. In reviewing the FSP’s settlement amount, I note that this was based off the quotations the applicant herself submitted. The q uotation from pool heating firm “SP” clearly shows that it includes replacement of all solar tubing. Likewise, the quotation from “JP” for the veranda shows it includes the removal and replacement of all polycarbonate sheeting for the veranda roof. The quo tation from “BS” for the skylights shows it is quoted to repair rather than replace the skylights. However, I am satisfied this is the extent of the FSP’s liability. The FSP’s obligation is to repair or replace (if warranted) on a like for like basis to place the policyholder back in the position they enjoyed prior to the loss occurring. It is not obliged to cover improvements or upgrades to a property. As the claim was cash settled, the applicant had the option of upgrading her skylights if she chose. Ac cordingly, I am satisfied the FSP’s settlement is reasonable in the circumstances and fulfils its obligations under the policy terms. 2.2 Is the applicant entitled to compensation for the manner in which the FSP managed her claim? Terms of Reference allow for compensation in limited circumstances The FOS Terms of Reference (the Terms) enable FOS to compensate an applicant for non-financial loss (capped at $3,000). Compensation for non-financial loss is Case No: 499525 Determination Page 3 of 4 limited. FOS may decide an FSP should compensate an applicant for such a loss only where there has been an unusual amount of:  physical inconvenience  time taken to resolve a situation  interference with the a pplicant’s expectation of enjoyment or peace of mind. FOS takes a conservative approach to compensation and expects an applicant to be moderately robust and bear the usual degree of stress and inconvenience when managing an insurance claim. The simple passage of time is not a trigger for compensation. FSP managed claim reasonably overall The applicant maintains it was difficult to deal with the FSP throughout which caused her stress. Whilst this may be the case, that is not a trigger for compensation. FOS accepts any claim will bring with it associated stressors, inconvenience and time to manage it. Review of the material shows that the decision to cash settle the claim was made promptly, once the FSP was made aware by its builder that it could not warrant the work. As the applicant was dissatisfied with the FSP’s builder, she opted to ob tain her own quotations, which were supplied to the FSP on or around 9 March 2017. After reviewing these, the FSP made a settlement offer – which was accepted by the applicant – on 2 May 2017. Final payment was remitted to the applicant upon presentation of her banking details, on or around 17 May 2017 and the claim finalised. This is reasonably timely. FOS does not generally provide compensation for minor delays. There is no evidence presented to show that the applicant was advised at any point she was not able to claim for content items damaged in the event. The material does not show the applicant raised a potential claim for content items at any point earlier than her approach to FOS in October 2017, some five months after her claim had been finalised by the FSP. Costs for time managing a claim are not payable There is no provision in the policy terms for any costs or loss associated with the time spent managing a claim. Such costs would be considered consequential in nature. The policy specifically excludes consequential loss. In addition, FOS does not award compensation for time an applicant spends managing their claim. Award of compensation not appropriate in the circumstances Having considered the material provided by the parties, the evidence shows the FSP managed the claim reasonably overall. Accordingly, it is therefore not appropriate for an award of compensation to be made in these circumstances. Case No: 499525 Determination Page 4 of 4 3 Supporting information 3.1 FOS approach to this dispute A full exchange of the relevant information has taken place between the respective parties. Each party has had the opportunity of addressing any issues raised. All of the provided material has been reviewed and considered. The parties have raised numerous issues in their submissions to the Service. However, commentary in this determination is restricted only to those issues considered relevant to the outcome.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.