Determination 499036
Cash settlement of storm and flood building claim
Summary
The applicant's storm and flood building claim was partly declined as flood damage was excluded, but the FSP's conduct in authorising repairs and delaying the response prejudiced him. AFCA ordered the FSP to pay a total of $120,000 for the building claim.
The FSP was entitled to exclude flood damage, but its conduct prejudiced the applicant, so it must restore him to the position he would have been in.
Issues
- Claim amount dispute primary · upheld“The FSP is required to increase its cash settlement offer... an additional $120,000 for the building claim”
- Claim denial secondary · not upheld“the FSP was entitled to decline the flood damage and only pay for the damage caused by the storm”
- Poor claim handling secondary · upheld“CF made an error in accepting TBS's quotation in full; FSP authorised repairs it later reversed”
- Delay secondary · upheld“the property was left in situ for over three months after it was affected by water”
Subjects and remedies
home or building damagenatural disasterpay claimpay compensation
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
Determination
Case No: 499036 Determination Page 1 of 9
Case number: 499036 7 June 2018
1 Overview
1.1 Dispute
The applicant held a home and contents policy with the financial services provider
(FSP). His property was damaged by the effect of Cyclone Debbie.
The applicant lodged a claim with the FSP. The FSP assessed the claim and partially
declined it.
A dispute has arisen to the adequacy of the FSP‟s offer to cash settle the claim.
1.2 Issues and key findings
Was the FSP entitled to decline the flood damage?
The available information shows the house was damaged by storm and flood. The
policy provides cover for storm damage, but excludes cover for flood damage. Given
this, the FSP was entitled to decline the flood damage and only pay for the damage
caused by the storm.
Is the FSP required to increase its cash settlement offer?
The FSP is required to increase its cash settlement offer. Whilst the FSP was entitled
to decline the flood damage, its conduct during the claim has prejudiced the
applicant‟s interest. Having regard to the information available, it is fair and
reasonable that the FSP is required to pay an additional $120,000 for the building
claim (this includes the $23,673.87 it already agreed to pay).
1.3 Determination
This determination is substantially in favour of the applicant.
The FSP is required to:
pay the accepted amount $23,673.87 if it has not already done so
pay an additional $96,326.13 for the building claim.
Case No: 499036 Determination Page 2 of 9
2 Reasons for determination
2.1 Was the FSP entitled to decline the flood damage?
Applicant bears initial onus to show damage covered by policy
At law, the applicant bears the initial onus to show, on the balance of probabilities,
the damage claimed was caused by an event covered under the policy.
The applicant‟s policy covers for loss and damage due t o listed events, including
storm, rainwater or run-off.
If this can be established, the onus then passes to the FSP to establish, on the
balance of probabilities, why it may otherwise be entitled to deny the claim.
The policy specifically excludes cover for loss or damage caused by flood.
Section 3.1 of this determination sets out key extracts of the policy.
House was damage by storm and flood
The exchanged material confirms a severe weather event affected Australia and
within the area of the applicant‟s house in the la ter part of March 2017.
Heavy rainfall occurred at or about the applicant‟s house. The nearest weather
station recorded 442.6mm of rainfall over a two day period of 30 & 31 March 2017.
The FSP‟s hydrologist (WRM) prepared a report following an inspection of the area
around the applicant‟s house, together either consideration of relevant Bureau of
Meteorology data and water level information.
WRM concluded:
the initial inundation of the property was caused by storm water runoff. The
storm water runoff reached a depth of 150mm above ground level. This means
any items within 150mm of the ground level could have been affected by storm
water runoff
floodwater then inundated the property, causing further water damage above
150mm
rainwater also leaked through the roof.
The applicant had not provided any expert evidence to refute WMR‟s conclusions.
Policy allows FSP to decline the flood damage
The FSP‟s bui lder (TBS) initially quoted (dated 21 June 2017) it would cost
$64,840.83 to repair flood and stormwater damage.
TBS later sent a variation quotation for repairs, identifying an additional $38,017.19
worth of repairs (dated 22 August 2017).
Based on WRM‟s report, the FSP partially accepted the applicant‟s claim. It accepted
to cover for building damage caused by the storm (including stormwater runoff and
Case No: 499036 Determination Page 3 of 9
stormwater coming through the roof). However it declined to cover the building
damage caused by flood waters.
The FSP‟s IDR letter (dated 17 November 2017) states only $10,232.72 of TBS‟
quotation relates to storm damage repairs. It says the remainder of the quotation
relates to flood repairs.
The FSP‟s NOR letter (dated 28 November 2017) later increased its accepted liability
for the storm damage repairs to $13,274. It also accepted to pay for the mould
removal.
As the policy excludes flood damage, the FSP was entitled limit its liability to the
building damage caused by the stormwater runoff.
2.2 Is the FSP required to increase its cash settlement offer?
FSP incorrectly accepted to repair the flood and storm damage
Despite the FSP ‟s entitlement to decline the claim, it authorised its builder (TBS) to
repair the stormwater and flood water.
The information exchanged shows:
the FSP‟s loss assessor (CF) received two builder‟s quotation (JLG & TBS) by
23 June 2017. CF advised the FSP about this in a progress update email
CF emailed the applicant that TBS‟s quotation was approved on 18 July 2017.
CF says TBS‟s quo tation covers everything effected by the storm water. CF
provided the applicant a copy of TBS‟s quotation
TBS emailed the applicant advising the FSP approved TBS to carry out the
repair to his damaged house. TBS provided the applicant with the scope of
works and a domestic building contract on 19 July 2017
TBS emailed the applicant saying it will now schedule the repair given the
applicant signed the scope of works
TBS commenced repair works on 25 July 2017
On or around the 14 August 2017 TBS stopped the repairs after its contractor
removed the wall lining. It discovered extensive mould damage in the wall
cavities
On 22 August 2017 TBS submitted a quotation variation to CF, so that it could
also remediate further damage identified
On 8 September 2017 the FSP ‟s claim team realised CF made an error in
accepting TBS‟s quotation in full.
Given the FSP appointed CF to act on its behalf for the claim, the FSP is liable for
CF‟s actions. The applicant also says that he contacted the FSP to confirm the scope
of works before the work commenced. This means the FSP had the opportunity to
review the claim at that time and chose not.
Applicant says he was prejudiced by the FSP’s initial acceptance of claim
Applicant say as a result of the FSP‟s initial acceptance and then its later reversal of
its decision, the scope of works required to repair his house has increased.
Case No: 499036 Determination Page 4 of 9
He says had the FSP correctly advised him flood water damage was not covered and
not authorised the repairs, he would have immediately taken action to remediate his
house. It is not in dispute his house is extensively affected by mould.
He also says in reliance of the FSP‟s representation that TBS‟s quotation was
approved, he assumed all the items approved in it were going to be repaired or
replaced. He says in reliance, he allowed TBS to strip out and dispose of a lot of
undamaged items in his house. He says he would not have allowed TBS to dispose
of the undamaged items had he known the FSP was actually not willing to carry out
TBS‟s quotation in full. He is saying he lost the opportunity to savage some
undamaged items from his house, and now would incur cost to replace these items.
Applicant was prejudiced by the FSP’s conduct
Having regard to the available information, I am satisfied the applicant was
pr ejudiced by the FSP‟s conduct. The information available shows:
the applicant lodged a claim on 2 April 2017, a couple of days after the severe
weather event affected the property
the property was left in situ for over three months after it was affected b y water.
the FSP claims consultant noted on 2 April 2017 that an urgent assessment
was required because the property required make-safe repairs. Despite this
TBS builder confirmed in an email to the FSP (dated 8 September 2017) that no
restoration work to dry the property was done until it started repairs on 25 July
2017
given the period of time it was left in situ, I accept this would have caused
further damage. This is supported by the applicant‟s expert (CE, dated 19
October 2017) who stated the poor response time to remediate and dry the
building structure would have likely caused the growth and spread of the mould
throughout the building.
the premises has been left without electricity as the result of the strip out. This
has reduced the applicant‟s abi lity to undertake remedial drying activity
the applicant could have salvaged the kitchen, laundry cupboard, door fittings,
bedroom‟s built in wardrobes, some tiling, some gyprock and electrical fittings .
These items were all disposed of when TBS stripped out the house in
anticipation it was going to be replaced. I am satisfied had the FSP not
incorrectly advised TBS‟ quotation was accepted, the applicant could have
salvaged all these items.
the applicant lost the opportunity to determine whether the amount assessed for
storm damage was adequate.
the applicant has not had the opportunity to mitigate his loss , whilst this dispute
has been ongoing, and has made some minor repairs already at his expense.
the applicant had intended to rent the property out but has been delayed in his
ability to do so.
FSP is liable for some of the repair work
Given I am satisfied the applicant was prejudiced the FSP‟s conduct in relation to this
claim, the FSP liable to restore the applicant into a position he was in before the
prejudice took place.
Case No: 499036 Determination Page 5 of 9
In the circumstances, this is a difficult exercise.
The FSP attempted to calculate its liability by having regard to:
it was entitled to deny all the flood related damage, therefore maintains all
repair items listed in TBS‟ quotation which relates to flood damage are declined
it says TBS completed or was in progress to complete $37,981.15 worth of work
before it stopped. Of this amount, $14,301.28 was completed, $8,411.49 of this
work was flood related and $5,889.79 was storm related.
it says it is entitled to limit its liability to $23,673.87, being the difference
between the work in progress and work completed. It says this amount of
money would allow the applicant to put the property back into the condition
before the damage occurred.
I am not satisfied the FSP‟s liability can be limited to $ 23,673.87 given:
it does not take into account building damage caused by water entering through
the roof nor can I see how that can now be determined
it does not take into account the items that the applicant could have sa lvage
had it not been disposed of by TBS builder
it does not take into account its delay in restoring the house caused further
damage, especially in relation to the spread and g rowth of mould damage.
it does not take into account that the strip out has exposed asbestos and the
mould remediation may require further asbestos remedial work
Appropriate resolution
The applicant has provided information to show it would now cost appro ximately
$83,563.42 to repair the house. This includes all flood, storm and mould damage.
He provided information to show:
mould remediation would cost $5,000
kitchen (which was disposed of) would cost approximately $33,495 to replace
laundry cupboard (which was disposed of) would cost approximately $4,188.17
to replace.
The applicant‟s estimate is based on the lowest estimate and he has other quotes
which are in excess of this amount. These estimates were obtained several months
ago.
Given the delay and the fact that he has not been able to use drying equipment
without the availability of electricity it is likely that the cost of mould remediation will
now be increased.
The state the property has been left in by the FSP means it is likely the cost of
restoration will increase.
I am satisfied the applicant is entitled has established a storm claim, and he was
prejudiced by the FSP‟s conduct during this claim. Having regard to all of the above
matters and doing what is fair in all the circumstances, I am satisfied the FSP is
required to pay an additional $96,326.13 for the building claim (this is in addition to
the $23,673.87 it agreed to pay).
Case No: 499036 Determination Page 6 of 9
Any payments already made or due for the strip out or repairs to date are the
responsibility of the FSP.
This further payment of $96,326.13 towards the building repairs finalises the FSP‟s
obligation to the applicant under the terms of the policy and remedies his loss due to
the FSP‟s prejudice.
.
Case No: 499036 Determination Page 7 of 9
3 Supporting information
3.1 Key policy terms
Insured Events we will pay
…
9. Storm, rainwater or run-off
(Applicable whether you have buildings and/or contents cover)
We will pay for loss or damage caused by storm, rainwater or run-off.
“storm” means violent wind (including cyclones and tornadoes), thunderstorms and hail
which may be accompanied by rain or snow.
“rainwater” means rain falling naturally from the sky onto the buildings and/or ground.
“run - off” means rainwater that has collected on or has flowed across normally dry ground or
has overflowed from swimming pools or spas.
We will not pay for loss or damage:
a. caused by:
• flood, or
• flood water combined with run -off and/or rainwater;
“flood” means the inundation of normally dry land by water that has escaped or has been
released from the normal confines of any natural watercourse, lake or lagoon whether or
not altered or modified, or of any reservoir, canal or dam.
3.2 Key timeline
Date Action
31 - 03 - 2017 Stormwater runoff and floodwater inundated property
02 - 04 - 2017 Applicant lodged claim
FSP notes an urgent assessment was requested because make - safe repairs
required
20 - 04 - 2017 CF requests hydrologist report
3 - 05 - 2017 Hydrologist inspect the site
17 - 05 - 2017 FSP receives the hydrologist report
25 - 05 - 2017 FSP advise applicant of the hydrologist report findings in a call
07 - 07 - 2017 CF sends copies of builders‟ repair quote (TBS and JLG) to applicant
18 - 07 - 2017 CF says to applicant TBS‟s quote is approved, and it covers everything
effected by storm water
Quote totals $64,840.83 (inc GST)
25 - 07 - 2017 TBS receives applicant‟s signed scope of works
14 - 08 - 2017 CF asks applicant to provide quote for „remaining work that cannot be
Case No: 499036 Determination Page 8 of 9
completed by the builder such as matching the paint work for the cabinets. ‟
15 - 08 - 2017 TBS identifies additional mould
17 - 08 - 2017 CF advise the applicant he will recommend payment for the cabinet quot e
23 - 08 - 2017 CF sends TBS‟s variation quot ation to applicant
Variation quote totals $38,017.19 (inc GST)
25 - 08 - 2017 CF updates applicant s tating “ the acceptance of the variation that we have
received [to the FSP] , this includes the work benc h that was damaged during
removal. Also I have advised that this is urgent as the mould will continue to
gr ow the longer this is delayed, I currently awa it their acceptance of the
variation. ”
20 - 09 - 2017 CF and TBS re - inspected the property
21 - 09 - 2017 CF advise FSP to negotiate a cash settlement with the applicant
27 - 09 - 2017 CF advise applicant that FSP will accept responsibility for commenced works
only . CF explained that flood is not covered and that errors were made that
lead to the authorisation .
6 - 10 - 2017 CF offer $20,754.67 to the applicant to resolve the claim .
3.3 Key records
Record Key points
FSP’s hydrologist (WRM)
Report
8 - 05 - 2017
The subject property is a single storey brick hous e constructed on
a concrete slab. The slab is elevated approximately 400 to 500 mm
above the surrounding ground level. The house was inundated to a
maximum depth of about 150 mm above floor level.
The clear water initially observed inundating the property to a
depth of about 150 mm above ground level would have been
stormwat er runoff from the local catchment.
Any items within 150 mm of the surrounding ground level (f or
example, the air - conditioning unit at the granny flat) could have
been affected by stormwater runoff to a depth of 150 mm prior to
inundation by floodwaters
The initial and peak inundation of the house above floor level was
caused by floodwat er overflow ing from Burringbar Creek.
Damage to the ceiling was caused by rainwater leaking through the
roof.
FSP’s loss adjuster ( CF )
Report
25 - 08 - 2017
We refer to our second report in this matter, since this report we
received confirmation that the claim is a part ial denial with the
acceptance of 150mm only.
We received quotations from JLG and TBS and reviewed using our
contractor connection team. TBS was chosen as the most cost
effective and includes works covered for 150mm.
Since then we have had to perform emergency mould remediation
at the property, as mould has begun to spread due to the
stormwat er and delays. It has caused an extensive amount of
Case No: 499036 Determination Page 9 of 9
damage with mould specialists advising most of the bathroom
needs to be repla ced.
Please not e the variation also includes the cost to replace stone
bench top to the kitchen which cracked during removal of the
existing item which was glued in place and could not be removed
without breakage.
We recommend the acceptance of the variat ion which is attached
with the report. Please advise us as soon as possible if we are to
proceed.
FSP’s builder ( TBS )
Email
08 - 09 - 2017
As advised we completed our initial quote based on receiv ed
request to gut the property.
During our attendance we inspected the roof and found storm
related damage to bedding and pointing to hip and ridge tiles lifted
during the 30/3/2017 event whic h had allowed water ingress to
occur to internal ceilings.
Our original quotation was to complete repairs based on 150mm
CAT 3 water ingress only which was to remove and replace joinery
items , doors and linings to 1200mm only.
An inspection was completed to the bat hroom areas and the only
visible damage evident was to the bathroom vanity unit.
Once we had received authority to proc eed with work and wall
lining were removed it was found that mould cont amination had
occurred in the wall cavities above 1200mm requirement for CAT 3
contamination to plaster work and timber framing.
It was also found that once linings had been remo ved from wall to
room adjacent the bathrooms and toilet and found extensive mould
contamination which r equires removal of wall linings .
Please also note no restoration had been completed to expose wall
cavities and dry the structure the property between 30 /3/2017 and
start of works 25/7/2017.