Home / Financial Firm (Unknown - Insurer) / Determination 498237
Determination 498237
Cash settlement of storm-damaged garage despite title encumbrance
Summary
A tree fell on the complainant's garage and the insurer offered a cash settlement without addressing a title encumbrance that restricted repairs. AFCA ordered the insurer to repair the claim-related damage, pay storage costs with interest, and pay $1,000 for non-financial loss.
A policy requiring payment of the cost of repairing damaged property is read as covering the costs needed to restore it to a good condition, including works compelled by an encumbrance.
Issues
- Claim amount dispute primary · upheld
“The insurer's settlement of the claim is not fair in all the circumstances, so the insurer should repair the claim related damage.”
- Poor claim handling secondary · upheld
“I am not satisfied the insurer has given fair consideration to the decision to cash settle the complainant's claim.”
- Product terms interpretation secondary · upheld
“The insurer is liable for the cost of repairs if the encumbrance requires additional works, as the cost of repairing must restore the property to a good condition.”
Subjects and remedies
home or building damagenatural disasterpay compensationpay interestpay non financial lossrepair or rectify
Text of the determination
Case number: 498237 2 November 2018
1 Determination overview
1.1 Complaint
The complainant held a home insurance policy with the financial firm (insurer). The
complainant lodged a claim on 14 July 2016 for storm damage sustained to the
insured property after a tree fell on the garage.
The insurer accepted the claim and has sought to cash settle the claim.
The complainant disputes the insurer ’s assessmen t and its offer. This is because the
assessment failed to consider the requirements of an encumbrance and the effect this
would have on being able to repair the garage.
1.2 Issues and key findings
Is the insurer ’s settlement offer fair and reasonable?
The insurer ’s settlement of the claim is not fair in all the circumstances. This is
because it is not clear that the scope of works would enable the complainant to repair
the claim related damage. Therefore, the insurer should repair the claim related
damage.
Is the insurer liable for ongoing contents storage?
The insurer is liable for ongoing contents storage as set out in section 2.2.
Should the insurer pay non-financial loss?
The insurer should pay $1,000 for non-financial loss due to the stress and
inconvenience caused during the course of the claim.
1.3 Determination
This determination is in favour of the complainant
The insurer is required to:
repair the claim related damage in line with section 2.1
pay storage costs in line with section 2.2
pay $1,000 in compensation for non-financial loss
Determination | Case number: 498237 Page 2 of 8
2 Reasons for determination
2.1 Is the insurer’s settlement offer fair and reasonable?
Policy provides the insurer with the discretion as to how to settle a claim
The policy allows the insurer to settle a claim by:
repairing damage; or
rebuilding; or
paying the complainant the cost to repair or reinstate the building to the condition it
was in just before the loss or damage occurred (cash settlement).
However, the insurer must exercise this discretion fairly, reasonably and co nsistent
with the principles of utmost good faith.
The insurer has chosen to cash settle the repairs. This is based on a scope of works
provided by engineer M and a quotation from contractor AIB.
I note the IB within AIB stands for “Insurance Builders”. I t does not therefore appear
likely AIB are prepared to do the works for the complainant. To this extent, there are
concerns with the cash settlement offered.
Putting this aside, the primary issue in dispute is the potential effect an encumbrance
on the property title has on the ability to repair the garage. The encumbrance belongs
to RA.
The complainant says the effect of the encumbrance is that the repairs cannot be
completed in line with M’s scope of works. This is because RA would not approve it.
The insurer says there is no requirement for it to complete upgrades to comply with
the requirements of the encumbrance.
Property title has an encumbrance
The facts of this complaint are unusual.
The encumbrance was signed on 31 May 1948 and appeared to have been registered
on the title on or around 10 June 1948. The terms of the encumbrance contained a
number of conditions. Relevant to this complaint are the following:
That I will not erect or permit to be erected on the said land any house or building or fence
or gate in accordance with plans and specifications which shall prior to the
commencement of such erection have been submitted to and approved by the said
Company. …
That I will not erect or permit to be erected on the said land any house of which the roof is
made wholly or partially of galvanised iron or any garage or other outbuildings or fence or
gate made wholly or partially of galvanised iron …
Determination | Case number: 498237 Page 3 of 8
That I will observe the building line to be directed by the said Company and in no case
shall the front of the house or any outbuildings erected on the said land be made to extend
nearer to the road or street to which such land fronts than such position on the said land
as indicated by the said building line.
According to RA’s letter to the insurer dated 10 November 2016, the complainant’s
property was built in the 1950s. Regarding the garage:
…the garage was erected illegally as it was not in keeping with the 8 metre setback
required from the front boundary of the property, yet due to the lack of policing in that era,
the owners and developers of the property managed to the have the structure built with no
formal approval, apart from presumably that of Mitcham Council.
RA’s letter then sets out their position regarding these types of breaches:
[RA’s] attitude to such clear breaches of the Encumbrance is that it would be
unreasonable for us to require current property owners to remove illegally built structures;
however, our attitude is, again quite reasonably, that no enhancements, extensions or
related developments can be made to such structures. However, we will allow
refurbishment provided that any non-compliant building materials that have been damaged
must be replaced with modern day materials that are acceptable under the Encumbrance.
For this purpose, galvanised iron and its derivatives, including Colorbond, are prohibited
as are all other metal roofing products with the exception of sheet copper. …”
The letter th en sets out RA’s attitude as to how the repairs should be effected.
The complainant is the Chair of RA. The letter was written by DS as acting Chair.
There is no evidence to suggest the complainant has sought to influence RA’s
position in any way regarding this matter.
Further, it is clear that the property and the garage were already built before ECD
became the sole proprietor of the insured property. ECD is presumably the
complainant’s wife.
Policy covers additional building repair costs
The insurer says it has provided settlement in accordance with the policy terms and
conditions, namely to pay the cost of rebuilding or repairing the buildings to the same
condition as they were when new.
There is provision in the policy for the insurer to pay additional items to comply with
the requirements of a statutory authority or any local or government by-laws. This is
set out as follows:
Additional Items we will pay for when you have insured your buildings
We will pay the costs necessary to meet the requirements of any statutory authority in
connection with rebuilding or repairing the buildings at the situation. We will not pay any
costs which resulted from any notice which a statutory authority served on you before loss
or damage to buildings occurred. The most we will pay in any one period of insurance is
$25,000.
Determination | Case number: 498237 Page 4 of 8
How we pay a claim for your buildings
When loss or damage occurs to your buildings, we will pay the cost of rebuilding your
buildings or repairing the damaged portions to the same condition as when they we re new.
We will also pay any additional costs required for your buildings to comply with
government or local authority bylaws. We will not pay these additional costs if you were
required to comply with these bylaws, and had not done so, before the loss or damage
occurred.
However, the insurer says the nature of the encumbrances and RA’s involvement
does not fall within any of the above categories. To this extent, I agree with the
insurer.
Despite this, I accept the complainant’s submission that if the cost of repairs increase
due to the effect of the encumbrance, the insurer is liable for this. This is due to the
following.
Insurer must comply with encumbrance if it is legally required to do so
An insurance contract is to be constructed objectively by reference to its text, context
and purpose. It should be given a businesslike interpretation. Further, a construction
that avoids capricious, unreasonable, inconvenient or unjust consequences should be
preferred where the terms permit.
The critical issue is how the phrase “we will pay the cost of … repairing the damage
portions” be interpreted. The insurer submits that even if RA, by reference to the
encumbrance, can compel the complainant to undertake additional works beyond the
scope its engineer provided, thi s does not fall within its obligation to “pay the cost of
… repairing the damaged portions”.
This is difficult to accept.
The purpose of the policy to cover the complainant for loss or damage caused by an
insured event. There is no dispute an insured event has occurred which resulted in
both loss and damage.
The term “repair” is defined by the online Macquarie and Oxford dictionaries as
follows:
to restore to a good or sound condition after decay or damage [Macquarie]
restore (something damaged, faulty, or worn) to a good condition [Oxford]
Accordingly, in context of the policy purpose, a businesslike interpretation of the
phrase “cost of repairing” must be what it would cost to restore the property to a good
condition.
The insurer submits there is a policy provision to allow for additional costs to comply
with the requirements of a statutory authority, a government or local bylaw. This
Determination | Case number: 498237 Page 5 of 8
arguably addresses the situation where additional costs are incurred to repair the
property that is otherwise not necessary.
Therefore, the phrase “cost of repairing” in context of this should be limited to what it
would have cost to restore the damaged property to its pre-incident condition.
I do not accept this. The effect of such a construction is that in certain circumstances,
such as the complainant’s situation, the insurer can pay a sum for the “cost of
repairing” that in practical purposes does not enable the insured to restore the
property to a good or sound condition.
Such a construction is substantively contra ry to the policy’s purpose. It also leads to
an unreasonable and unjust consequence. In circumstances when there is an
alternative construction aligned to the policy purpose, that one should be preferred.
In this case, I consider an alternative constructi on of the phrase “cost of repairing” is
to include all the costs necessary to restore the property to a good or sound condition.
This does not include the costs required to comply with the requirements of a
statutory authority, a government or local bylaw given this is specifically catered for
elsewhere in the policy.
Such a construction leads to a reasonable and just consequence. It is consistent with
the policy purpose and the ordinary meaning of repair.
Even if I am wrong about the construction of the policy, I consider it fair in all the
circumstances that it be interpreted in this manner for similar reasons.
Given this, if RA is entitled to compel the complainant to undertake other works to
restore the garage, then the insurer must include this in the “cost of repairing” the
garage.
Insurer should repair the damage
The insurer has sought to cash settle the claim. The submission does not articulate
why it has chosen this action. It is possible this is due to other pre-existing damage
identified near the claim related damage or the fact the parties dispute the effect of
the encumbrance.
However, given the uncertain nature as to the extent of repairs. I do not consider the
insurer’s election to cash settle is fair in all the circumstances or consistent wit h the
principles of utmost good faith.
A cash settlement transfers the risk of the repairs to the complainant. It leaves the
complainant in the difficult position of having to deal with RA who have clearly set out
an intention to exercise their rights under the encumbrance regarding the repairs.
This shows the scope of works are far from certain.
Determination | Case number: 498237 Page 6 of 8
Further, the insurer has partly based its position on the fact it does not accept it is
required to comply with RA’s requirements. In such circumstances, it sho uld be
prepared to advocate this position rather than expect the complainant to do so without
any assistance.
In addition, the cash settlement means the complainant loses any warranty of repairs.
I acknowledge the situation is complicated by pre-existing damage. However, I expect
the parties can come to a resolution to what extent, if any, the complainant is required
to contribute to these costs. Particularly given the complainant does not dispute there
are pre-existing issues.
I also note the complainant is Chair of the RA. However, as he has done already, I
expect that he will excuse himself of any involvement RA has on this matter given the
clear conflict of interest.
Therefore, I accept it is fair in all the circumstances the insurer repair the claim related
damage.
2.2 Is the insurer liable for ongoing contents storage?
I nsurer is liable for the complainant’s contents storage
The insurer says they have paid the complainant for the cost of storage up to 7
February 2017 (totalling $3,925). As they cash settled the cost of repairs on 30
January 2017, they have provided an additional 8 days for storage costs in good faith.
The complainant says his contents have remained in storage as the garage has yet to
be repaired and has submitted ongoing storage fees.
The PDS says the insurer will pay the reasonable costs to remove and store your
contents while your situation is being repaired, for up to 12 months.
I have not accepted the insurer’s position was consistent with its obligations under the
policy. Given this, I accept the insurer is liable to pay for the complainant’s storage
contents during the period of time he has disputed this position. This period is not
subject to the policy limit. This is because this cost was incurred due to the insurer’s
failure to comply with its policy obligations rather than the claim itself.
Therefore, the insurer is liable for the complainant’s storage costs until the earlier of
the following times:
7 months have passed since it received notification that the complainant accepted
this Determination – this reflects the remaining period left of the 12 month benefit
since the insurer assessed and attempted to settle the claim
the garage is repaired
Determination | Case number: 498237 Page 7 of 8
Further, the insurer is to pay interest on the amount payable pursuant to section 57 of
the Insurance Contracts Act 1984 . Interest is payable from the date the storage costs
were incurred until payment is made.
2.3 Is the complainant entitled to compensation?
Complainant is entitled to compensation
Under paragraph 9.3 of the FOS Terms of Reference, we may award compensation
for non-financial loss where a complainant has suffered an unusual degree or extent
of physical inconvenience, time taken to resolve the situation or interference with their
expectation of enjoyment or peace of mind.
The maximum amount of compensation for non-financial loss is $3,000.
However, we adopt a conservative approach to the award of compensation for non-
financial loss. This is because we do not award compensation for the usual stress and
inconvenience associated with an insurance claim.
The claim was made in September 2016. A final decision letter was sent 24 January
2017. In view of the cash settlement being paid on 30 January 2017, I am not
satisfied the insurer’s claims handling was unreasonably slow.
However, I am not satisfied the insurer has given fair consideration to the decision to
cash settle the complainant’s claim. Particularly given the potential effect of the
encumbrance.
I accept this caused the complainant to experience an unusual degree of
inconvenience and time taken to resolve this dispute. Also, this would have interfered
with his expectation of enjoyment or peace of mind.
Given this, it is fair in all the circumstances the insurer pay the complainant $1,000 for
compensation for non-financial loss.
Determination | Case number: 498237 Page 8 of 8
3 Supporting information
3.1 The determination is made under FOS Terms of Reference
The Australian Financial Complaints Authority ( AFCA) has commenced managing
disputes previously lodged with F inancial O mbudsman S ervice (FOS) .
This determination is made under FOS Terms of Reference but has adopted the
following terminology for consistency with AFCA. In this determination the AFCA
terms have the same meaning as the FOS terms defined in paragraph 20.1 and
Schedule 1, 2 & 3 of the FOS Terms of Reference.
FOS definitions AFCA term
applicant complainant
financial services provider financial firm
dispute complaint
claim claim
3.2 Approach to the complaint
As advised to the parties, we have considered it appropriate to expedite this dispute
in accordance with the Operational Guidelines to the FOS Terms of Reference, due to
the nature of the complaint. Accordingly, this complaint has not been the subject of a
FOS recommendation and has proceeded directly to determination.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, commentary has been restricted to those issues considered
directly relevant to the outcome only.
3.3 Other relevant material considered and relied on
Parties’ submissions, emails and reports.
Correspondence between the parties.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.