Determination 496817

Storm-related slab cracking and movement damage claim denied

FirmFinancial Firm (Unknown - Insurer)
Decided2018-06-20
ProductGeneral Insurance · Landlord
OutcomeFor the complainant in part
Amount awarded$1,320
Non-financial loss$5,500
Amount claimed—
SourceAFCA PDF

Summary

The landlord claimed under her policy for slab cracking damage after a January 2016 storm, and the FSP denied it as pre-existing earth movement. AFCA found the FSP liable for 50% of the repair cost and loss of rent, reimbursement of $1,320 engineer fees, and $5,500 compensation, and found the leaking pipe claim not covered.

Some damage pre-existed the storm, but the storm caused additional damage that the FSP could not exclude, so the FSP must indemnify the storm-caused 50% share.

Issues

Subjects and remedies

pay claimpay compensationpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 496817 Determination Page 1 of 11 Case number: 496817 23 May 2018 1 Overview 1.1 Dispute The applicant lodged a claim under her landlord insurance policy with the financial services provider (FSP) for damage to her property caused by a storm in January 2016. The FSP cash settled the applicant for the cost of repairing damage to the driveway and a ceiling at the property In mid-2017, the applicant contacted the FSP to advise of cracking and movement damage to her property. The applicant says this damage was caused by the effects of rainwater run-off during the storm in January 2016. The FSP denied the applicant’s claim for cracking and movement damage on the basis that this damage was not caused by the storm, but by ongoing earth movement due to the manner in which the property was constructed . The applicant disputes the FSP’s decision and seeks cover for the cost of repairing the damage, together with payment for loss of rent. She also disputes the FSP’s decision to deny cover for a second, unrelated claim relating to a leaking pipe in October 2016. 1.2 Issues and key findings Is the FSP liable for the cracking and movement damage? The available information establishes that there was pre-existing cracking and movement damage to the property, which had occurred over an extended period of time. However, the severe storm in January 2016 also caused additional damage to the concrete slab and surrounding areas. The FSP has not shown that this damage was caused by excluded factors. Accordingly, the FSP is liable for this damage. The estimate provided by the FSP ’s engineer (MC) that the storm caused 50% of the damage is reasonable in the circumstances. On this basis, the FSP is liable for 50% of the cost of repairing the cracking and movement damage to the property. Is the applicant entitled to any other amounts for the storm claim? The applicant is entitled to:  payment for 50% of the loss of rent incurred while the repairs are carried out  compensation of $5,500 for financial and non-financial losses suffered due to the manner in which the FSP handled her claim Case No: 496817 Determination Page 2 of 11  reimbursement of fees paid to her engineer. Is the FSP liable for the claim for the leaking pipe? The available information does not establish that the leak caused any resultant damage to the property. Accordingly, the FSP is not liable for the claim. 1.3 Determination This determination is partly in favour of the applicant. The FSP is required to settle the applicant’s claim for cracking and movement damage to the property by:  engaging an appropriately qualified builder (who is prepared to undertake the work) to provide a quotation for the repair of the damage on the basis outlined in section 2.1 below  cash settling the applicant for 50% of the amount of the quotation, plus 50% of the loss of rent for the period required to complete the repairs, as estimated by the builder (based on a weekly rental of $420). The FSP is required to pay the applicant an additional amount of $6,820 (comprising $1,320 as reimbursement of her engineer’s fees and $5,500 as compensation for financial and non-financial loss). Case No: 496817 Determination Page 3 of 11 2 Reasons for determination 2.1 Is the FSP liable for the cracking and movement damage? Policy provides cover for storm damage subject to exclusions The applicant is required to show that, on the balance of probabilities, she has suffered a loss caused by a risk insured against under the policy. This is known as a prima facie claim. If the applicant is able to establish a prima facie claim, then the onus shifts to the FSP to show that, on the balance of probabilities, it is entitled to rely on an exclusion under the policy or is otherwise entitled to deny the claim. The a pplicant’ s policy provides cover for damage caused by the events listed in the policy, including the insured event of storm. The policy states that an event means a single event or occurrence. The policy does not cover damage caused by a storm where the damage results from subsidence, landslide or any other earth movement. However, there is an exception for damage caused by subsidence or landslide which occurs within 72 hours of a storm. Such damage is covered, provided it is caused directly by the storm and not by a structural or design fault. The policy also contains general exclusions for naturally occurring earth movement (other than landslide or subsidence which occurs in circumstances which are specifically covered under the policy). FSP’s liability depends on cause of damage The available information confirms that there is a large crack in the concrete slab of the property. The crack is located in the master bedroom at the north east corner of the property and extends up the side dwarf wall. The engineers who inspected the damage confirmed that the slab had dropped significantly in this area, resulting in the crack observed. The engineers also observed associated movement damage to nearby areas, including gaps around the timber window framing. The applicant discovered the damage in mid-2017, when she inspected the property after it was vacated by her tenants. The crack in the slab had previously been covered by carpet. The applicant says the damage was caused by the effects of rainwater run-off during the storm in January 2016. The FSP accepts that the property was affected by a severe storm in 2016. However, the FSP says the cracking damage to the slab pre-existed the storm and was caused by gradual earth movement over time (exacerbated by the manner in which the property was constructed). Case No: 496817 Determination Page 4 of 11 Accordingly, in order to determine the FSP’s liability, it is necessary to identify the proximate cause of the damage. It is well established at law that the proximate cause of a loss is not necessarily the first (or the last) or the sole cause of the loss. It is the effective or dominant or operative cause. In any particular case, the proximate cause of the loss is a question of fact to be determined based on the surrounding circumstances. Where there are several causes operating, each must be examined for the qualities of predominance and efficacy in relation to the resultant damage. Engineers have provided conflicting views about how damage occurred The applicant’s property has been built alongside a reasonably steep hill (or cliff). The property is constructed on a flat plate concrete slab , which has been laid on fill material retained by a stone retaining wall below the front (east) side of the building. Both the applicant’s engineer (CE) and the FSP’s engineer (MC) agree that the crack in the north-east corner of the concrete slab (and the related movement damage) was caused by the settlement (downwards movement) of the slab in this area. However, the engineers disagree about how and when this movement occurred. In his report prepared in November 2017, t he applicant’s engineer (CE) concluded that the damage to the slab occurred due to movement of the northern section of the retaining wall caused by the effects of stormwater run-off. CE noted that this section of the retaining wall was built of small, loose stones laid on top of each other with no bonding mortar in between. He advised that:  during heavy storms, rainwater would fall at high speed from the cliff behind the building, run across a horizontal rock terrace at the rear of the buildi ng and overflow over the retaining wall to discharge on the dirt road at the front of the property  the force produced by the stormwater running down the cliff had moved the small stones making up the retaining wall fro m their original position (and possibly also undermined the corner of the retaining wall at its base). CE advised that the north eastern corner of the retaining wall supported the concrete floor slab. Accordingly, he concluded that the movement of the retaining wall had caused the floor slab to settle, resulting in the cracking damage observed. CE considered that all of the damage to the property in this area was attributable to the storm in January 2016. The FSP disputes CE’s conclusion that all of the damage to the property was caused by the storm in January 2016. The FSP also says that, regardless of the mechanism by which the damage occurred, the proximate cause of the damage was the manner in which the property was constructed. In his initial report dated 16 August 2017, the FSP’s en gineer (MC) advised that a substantial proportion of the cracking and movement damage had occurred before the storm in January 2016. Case No: 496817 Determination Page 5 of 11 MC concluded that the proximate cause of the damage was the manner in which the house was constructed, which made it vulne rable to settlement of the concrete slab over time. In particular, MC noted that the floor slab was not particularly strong or rigid and the retaining wall was prone to losing backfill as stormwater washes through the soil and out of the gaps between the rocks. In his supplementary report prepared in November 2017, MC acknowledged that it was likely that at least some of the cracking and movement damage had occurred during the storm in January 2016 (although he disagreed with CE’s conclusion that the retaining wall itself had moved). However, MC reiterated his conclusion that the proximate cause of the damage was the manner in which the house was constructed. He advised that, had the property been constructed correctly, the damage would not have occurred. Some of damage pre-existed storm in January 2016 Having carefully reviewed the available information, I am satisfied that some of the cracking and movement damage to the north-east corner of the property pre-existed the storm in January 2016. The repo rt prepared by the FSP’s engineer (MC) includes a close -up, colour photographs which clearly shows paint inside the crack in the stone dwarf wall. On this basis, MC concluded that the damage had commenced before the property was painted prior to it being tenanted in 2013. The applicant has provided photographs of the property at that time, which appear to show it freshly painted. The applicant says that none of the cracking and movement damage was present in 2013. She says paint could have infiltrated the crack in the dwarf wall following the storm in January 2016. However, I do not agree this is the case. In my view, the photograph included in MC’s report clearly establishes that some of the damage occurred prior to the storm. The photographs provided by the applicant do not establish that there was no pre-existing damage in 2013, as the relevant areas are obscured by the soft furnishings. Applicant has established a prima facie claim for additional damage The existence of prior damage tends to support the FSP’s position that at least some of the damage was caused by ongoing issues affecting the property, rather than by the effects of a single storm. However, the FSP’s engineer (MC) acknowledged that additional damage was likely to have occurred during the storm in January 2016. MC estimated the proportion of the total damage caused by the storm at 50%. Where additional damage is caused by an insured event (such as a storm), the FSP will be liable for this damage unless it can show that, on the balance of probabilities, Case No: 496817 Determination Page 6 of 11 an exclusion applies. The fact that there may be pre-existing damage does not preclude the applicant from being entitled to cover in these circumstances. On this basis, I am satisfied that the applicant has established a prima facie claim for the additional damage caused during the storm in January 2016. Accordingly, the FSP is required to show that it is entitled to rely on a policy exclusion to deny cover for this damage. FSP is unable to rely on policy exclusions As outlined above, the FSP’s engineer (MC) says that any additional damage which occurred during the storm was due to the way in which the property was constructed. The policy does not provide cover for settlement damage which occurs during a storm because of a structural or design fault affecting the property. In his report, MC identified certain features of the property which he considered made it particularly vulnerable to settlement damage over time (including the use of fill material and the nature of the slab). The applicant’s engineer (CE) also noted that the property is susceptible to the effects of rainwater run-off due to its location alongside a steep cliff. However, there is no information which establishes that the manner in which the property was constructed failed to comply with the building requirements in force at the time. To the contrary, MC noted that the method of construction was consistent with that commonly used at the time. In these circumstances, I am not satisfied that the FSP has s hown that the property had a ‘structural or design fault’, such as would entitle it to deny cover for the additional damage caused by the storm in January 2016. The FSP also says it is entitled to rely on the policy exclusion for storm damage to retaining walls. However, this exclusion only applies to damage to the retaining wall itself. The applicant’ s current claim relates to damage to the concrete slab and surrounding parts of the property (and not to the retaining wall). Accordingly, the FSP is not entitled to rely on the exclusion for retaining walls to deny cover for the additional damage caused by the storm. FSP is required to cash settle applicant for 50% of repair costs For the reasons outlined above, I am satisfied that there was already some cracking damage to the property prior to the storm in January 2016. The FSP is not liable for the pre-existing damage to the property, which was not caused by the one-off effects of a single storm. T he findings of the applicant’s engi neer (CE) suggests that the property would have been exposed to the gradual effects of rainwater run-off from the cliff and rock terrace on an ongoing basis, during periods of heavy rainfall. The applicant has confirmed that water regularly runs off the cliff during storms. It is not possible to determine with certainty the proportion of the current damage which occurred prior to the storm in January 2016. Case No: 496817 Determination Page 7 of 11 Given the property’s long-term exposure to rainwater run-off, it is possible that a substantial proportion of the damage had already occurred prior to the storm. However, it is also clear that the storm in January 2016 was severe, as shown by the extent of the damage to the applicant’s driveway caused by rainwater run-off. T he FSP’ s engineer (MC) has advised it is likely that approximately 50% of the existing damage occurred during the single storm in January 2016. Having regard to the factors outlined above, I consider MC’s estimate represents a fair and reasonable assessment of the proportion of the damage caused by the one- off effects of the storm in January 2016. Accordingly, I consider it is fair in the circumstances that the FSP indemnify the applicant for this portion of the damage. Given the FSP is liable for 50% of the damage only, it is appropriate that the claim be cash settled. The FSP’s engineer (MC) prepared a scope of works for the repair of the damage dated 16 August 2017. The scope of works provides for repair by way of traditional underpinning, although MC notes that this approach is not a guara nteed success and may result in additional damage during the repair process. In the circumstances, I consider that the FSP should be required to:  obtain a quotation from an appropriately qualified builder (who is prepared to undertake the work) for the r epair of the damage set out in MC’ s scope of works. The quotation should include appropriate provision for the repair of any additional damage which may occur during the repair process  cash settle the applicant for 50% of the amount of the quotation. 2.2 Is the applicant entitled to any other amounts for the storm claim? Applicant is entitled to payment for loss of rent during repairs The applicant’s policy provides cover for loss of rent where the property is unable to be lived in due to damage caused by an insured event. For the reasons outlined above, I am satisfied that the storm in January 2016 caused additional damage to the property (although this damage was not discovered until May 2017, when the tenants moved out). The applicant’s tenants continued t o live in the property for approximately fourteen months following the storm. Given this, I am not satisfied that the damage caused by the storm made the property unliveable. However, given the nature of the repairs set out in MC’s scope of works, I am satisfied that the property will be unable to be lived in while the repairs are carried out. On this basis, the FSP is required to pay the applicant an amount equal to 50% of the rent for the period while the repairs are completed. This amount is to be deter mined based on:  the current weekly rental of $420 (which reflects the loss suffered by the applicant); Case No: 496817 Determination Page 8 of 11  the estimated repair period (as advised by the builder who provides the quotation referred to in section 2.1 above). Applicant is entitled to compensation FOS may award compensation for non-financial loss (capped at $3,000) where an applicant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind. FOS may also award an additional amount of compensation (capped at $3,300) for consequential financial loss suffered by an applicant in connection with their claim. In the present case, I am satisfied that the applicant has suffered additional stress and inconvenience, as a result of the FSP’s denial of her claim. The FSP denied the claim despite a report from its own engineer (MC) estimating that 50% of the damage had been caused by the storm in January 2016. I also consider that the FSP’s denial of the applicant’s claim (and her resulting lack of funds) has contributed to the delay in the applicant arranging for the property to be re-tenanted. While the property remained habitable, it was reasonable for the applicant to seek to undertake repairs while it was vacant, in order to minimise future disruption to her new tenants. However, I acknowledge that not all of the repairs required to the property were related to the storm in January 2016. In addition to the pre-existing damage, there was also other, unrelated damage (for example, damage caused by termites). Further, the applicant’s loss of rent has to some extent been mitigated by amounts paid by her new insurer under a rental default claim lodged after her tenants vacated the property in May 2017. The available information indicates the new insurer paid loss of rent benefits for at least three months during this period. Having regard to the factors outlined above, I consider it is fair in all the circumstances that the FSP pay the applicant total compensation of $5,500 for financial and non-financial losses caused by the manner in which it handled her claim. The FSP is also required to reimburse the applicant for fees of $1,320. In circumstances where the FSP had denied the claim based on MC’s report, it was reasonable for the applicant to engage her own engineer. 2.3 Is the FSP liable for the claim for the leaking pipe? Policy provides limited cover for escape of water The applicant’s policy provides cover for damage to the property caused by liquid leaking, overflowing or bursting from a fixed pipe or a water supply pipe. The policy states that the FSP will also pay the reasonable cost of locating the source of the leak and repairing any damage caused by the exploratory works. Case No: 496817 Determination Page 9 of 11 However, exploratory costs are only covered where the FSP has accepted a claim for damage caused by the leak. The policy does not provide cover for the costs of repairing the item from which the liquid escaped. FSP says leak did not cause any resultant damage In October 2016, the applicant lodged a claim for the escape of water from a pipe leading to the hot water service in the laundry of the property. The applicant advised she had arranged for her plumber to repair the pipe. The FSP’s assessor (DG) attended the property in mid -December 2016. DG reported that the pipe was located inside a concrete wall at the property, which the plumber had cut into in order to repair the pipe. DG’s report states that the applicant confirmed that:  the leaking water had not caused any damage to the property because the laundry floor was tiled and the walls were concrete  the only damage she was claiming for was the damage caused by the plumber in locating the source of the leak. Based on DG’s report, the FSP denied the applicant’s claim, on the basis that the policy does not provide cover for exploratory costs where the leak has not caused any resultant damage to the property. FSP is not liable for claim The applicant says the leaking water caused a black mark on the concrete wall behind the laundry tub. She has provided a photograph of the wall in this area. The FSP says that any marks visible on the wall were caused by temporary water staining, which would have disappeared as the water dried. The report prepared by the FSP’s assessor following her inspection in mid -December 2016 did not identify any damage to the wall. Further, the FSP’s claim notes indicate that, during a telephone call on 20 D ecember 2016, the applicant declined the FSP’s offer to arrange a further assessment on the basis that the water had already dried out and therefore there was no damage to see. I have carefully reviewed the photograph of the concrete wall provided by the applicant. However, I am not satisfied it establishes that there is any permanent damage to the wall caused by the water leak. On this basis, the FSP is not liable for the applicant’s claim. Case No: 496817 Determination Page 10 of 11 3 Supporting information 3.1 FOS approach to this dispute This dispute has not been the subject of a FOS recommendation. Due to the nature of the dispute, it has been referred directly to a panel for determination, in line with the Operational Guidelines to the FOS Terms of Reference. The panel consists of an Ombudsman and two representatives with consumer and insurance experience. The panel has decided this case based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions (which are not binding). There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. The panel has reviewed and considered all of the material provided by the parties. While the parties have raised numerous issues in their submissions, for the purposes of this determination, the panel has restricted its commentary to those issues that it considers directly relevant to the outcome only. 3.2 Terms of policy Subject Terms Cover for insured events If you have a home insurance policy, we cover your home for loss or damage at the insured address caused by an insured event during the period of insurance … Event means a single event, accident or occurrence which you did not intend or expect to happen. Insured event - storm We cover Loss or damage caused by a storm … We do not cover …  loss or damage caus ed by erosion, vibration, subsidence, landslide, mudslide, collapse, shrinkage or any other earth movement, but we will cover loss or damage caus ed by a landslide or subsidence that occurs within 72 hours of, and directly because of, a s torm and not because of erosion over time, structural fault or design fault …  loss or damage to retaining walls, sea walls, garden borders and free standing outdoor walls … General exclusions You are not covered under any section of this policy for damage, loss, cost or legal liability that is caused by, arises or involves: … Ground movement  erosion, vibration, subsidence, landslide, mudslide, collapse, shrinkage or any other eart h movement, but we will cover landslide or subsidence that is specifically covered under the following ins ured events: - ‘Storm’ … Case No: 496817 Determination Page 11 of 11 Subject Terms Loss of rent If we accept your claim for loss of damage to your home and we agree it cannot be lived in, we will pay the weekly rental amount for the reas o nable amount of time we decide it should take to repair or rebuild your home so it can be lived in again. The most we will pay for any one event is 52 weeks or 20% of your home sum insured, whichever is less. We do not cover … Loss of rent:  if your tenant still has an obligation to pay the rent …