Summary

The complainants claimed storm and water damage to their home and contents and disputed the insurer's settlement and handling. AFCA ordered a cash settlement of $73,002 for the building and contents claim, reimbursement of the mould expert's report, and $1,500 non-financial loss, and rejected further contents and other claimed costs.

The insurer's settlement of mould remediation was fair, but the building claim is best settled by a cash figure based on the current scope of works plus a 20 per cent allowance for variations.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay compensationpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination | Case number: 496692 Page 1 of 17 Case number: 496692 29 November 2018 1 Determination overview 1.1 Complaint The complainants lodged a claim on 10 June 2017 for both building and contents damage after water inundated their home following a storm. The financial firm (the insurer) accepted the complainants‟ claim. However, the complainants dispute the extent of the insurer‟s obligations and its claims handling. 1.2 Issues and key findings How sho uld the complainants’ building claim be settled? The insurer should pay $73,002 in full and final settlement of this. This takes into account the following:  the allowance for mould remediation already paid  the scope of works and quote provided by the insur er‟s builder (RC)  deducting works that are either not payable or have been settled  allowing a 20% increase. How should the complainants’ contents claim be settled? The insurer is not required to pay any further amount for contents. This is because the information does not show any contents not settled by the insurer were damaged by the claimed event or the insurer‟s conduct. Are the complainants entitled to compensation for other costs? If it has not done so already, the insurer is only required to reimburse the cost of the report from mould expert (MR) report given this assisted the complainants. Should the insurer pay non-financial loss? The insurer should pay the complainants $1,500 for non-financial losses. Determination | Case number: 496692 Page 2 of 17 1.3 Determination This determination is partly in favour of the complainants. Within 21 days of the complainants accepting this determination, the insurer is to settle this complaint by paying the following to the complainants:  $73,002 for the building and contents claim  reimbursing MR‟s report cost if it has not done so already  $1,500 in non-financial loss. Determination | Case number: 496692 Page 3 of 17 2 Reasons for determination 2.1 How should the complainant s’ building claim be settled? Parties dispute the extent of the insurer’s obligations The complainants are required to show that, on the balance of probabilities, they suffered a loss caused by an event they are insured for under the policy. This is known as a prima facie claim. The complainants‟ policy is a home building and contents insurance policy that provides cover for a number of listed eve nts, including storm. There is no dispute the complainants‟ property and contents suffered damage as a result of a listed event and the insurer has accepted the claim for damage. However, the parties dispute the extent of the insurer‟s obligations under t he terms and conditions of the policy. The insurer has paid the following amounts associated with the building claim: Basi s Amount Flooring repairs $11,990 Mould remediation $75,922 Removal of kitchen, transit and storage $17,775 Plumbing works $1,793 Cabinet removal costs and disposables $1,221 Electrical works $3,564 These payments were based on quotes provided by the complainants. Background to the mould remediation The insurer based its settlement on MR‟s quote. MR was engaged by the complainants. The insurer paid this to the complainants on or around 28 November 2017. The insurer accepted an allowance needed to be added for the removal and storage of the kitchen as well as plumbing and electrical works. The insurer paid for the costs to remove the kitchen on 13 December 2017. Quotes for the plumbing, cabinet and electrical were all paid by 7 February 2018. This was after quotes were obtained by the complainants. Determination | Case number: 496692 Page 4 of 17 The complainants have raised concerns that the scope of works for the mould remediation was insufficient. In support they provided a report from WEC dated 6 May 2018. This noted the following:  mould growth has been found higher than the 600mm allowed in MR‟s report for the plasterboard as well as on timber framing  the pattern higher up was consistent with an extended period of high humidity  all of these issues are consistent with a building that was not dried fast enough in the first few weeks  full remediation would require demolition of the bathroom to access hidden mould in the wall cavity. The insurer disputes WEC‟s report. The insurer says that any additional mould remediation required is due to the complainants failing to mitigate their circumstances. The complainants say they did commence remediation once all the settlement monies were received. However, this has yet to be completed given the additional issues found. Further, the issues they have identified were associated with the claim, not any delay in completing the mould remediation. Mould remediation provided is sufficient Having carefully considered the available information, the panel accepts the insurer‟s settlement for the mould remediation is sufficient. The insurer‟s settlement was based on MR‟s report. MR was commissioned by the complainants. MR did not accept there was any requirement to demolish the bathroom. MR allowed for 600mm of plasterboard to be removed as part of the works. The panel is not satisfied the complainants have acted reasonably in mitigating their loss. Mould was clearly an issue and a risk to the property. Settlement for this was received on 28 November 2017. MR provided an email dated 26 March 2018 saying they could have proceeded even without the kitchen and cabinet removal. MR said the complainants did not contact them to begin works. Instead, it appears the complainants have used other people to do the mould remediation. It is unclear if the amounts paid for the mould remediation is exhausted. Whilst the complainants say they could not engage anyone to begin the works due to upcoming Christmas and New Year, no evidence was provided of this. Given MR‟s email, it appears works could have begun before Christmas. Therefore, the panel accepts the complainants ought to have been in a position to begin mould remediation shortly after receiving settlement. Further, there is nothing to say they could not commission other contractors to do the other works, particularly given they Determination | Case number: 496692 Page 5 of 17 had received cash settlement for other aspects of the claim that remained unused (e.g. $11,990 for flooring). The panel does not accept WEC‟s opinion that the extent of remediation has increased due to the claim. This is substantively due to the fact the panel does not accept WEC‟s comment that additiona l mould growth would not occur due to any delays in beginning mould remediation. This seems implausible. Mould has remained on the property for a fair period of time. It is difficult to accept this would not spread if left untreated and unmitigated. Particularly given that part of the increased works is due to the plasterboard removal having increased from 600mm to 1,200mm. Therefore, the panel does not accept the insurer is liable for this increased scope of works. Further, for reasons set out later, the panel also does not accept WEC‟s conclusion that the bathroom and toilet need to be completely stripped. Accordingly, after careful consideration of all the available information, the panel accepts the insurer‟s settlement for the mould remediation is fair in all the circumstances. Building repairs The insurer obtained a scope of works from RC. This included all the complainants‟ claimed damages with the provision that mould remediation would be expected to be completed. This scope of works was exchanged with the complainants. The complainants have not objected to the scope of works being incomplete. The complainants instead challenge the insurer‟s submissions that it is not liable for various parts of RC‟s scope of works. Therefore, the panel accepts RC‟s s cope of works represents the extent of the building works being claimed by the complainants. In reviewing the scope of works, the insurer removed numerous items. These included items it believed it had already settled (electrical, carpet, plumbing and kitchen quotes it paid) as well as the following damage it did not accept was caused by the claimed event:  ceiling  bathroom and toilet  tiles in bedroom 3 and 4 The complainants said the tiles in the fourth bedroom are not part of the claim. The complainants also said they ordered new carpets for the bedrooms which was supposed to be laid two weeks after the flood occurred. Determination | Case number: 496692 Page 6 of 17 This is consistent with the fact the complainants‟ quotations did not discuss removing or replacing tiles in the third and fourth bedroom. Therefore, the panel accepts the insurer‟s position to remove these items from the scope of works is reasonable. In terms of the items the insurer says it has already settled, the complainants dispute the electrical ones. The complainants did not comment on the carpet, plumbing or kitchen aspects. The panel therefore accepts the insurer‟s position on those items to be appropriate. Ceiling damage The ceiling damage appears to be due to cracking identified. The complainants provided a report of 1 November 2017 from an engineer (PD). PD confirmed the internal plasterboard and joinery showed some hairline to fine cracks and there were no characteristic signs of building movement externally. PD says the complainants‟ home is prone to the movement related crack ing because of the light footing system with this age and type of building combined with square set ceilings. PD explains such ceilings are less tolerant of movement than when ceiling cornices are adopted. PD considered the evident cracking was inevitably going to occur for these reasons. PD was of the opinion the cracking manifested now simply because of the closeness in time to the recent renovations, as opposed to the water ingress. However, PD advises the recent water issue had the potential to cause cracking. Ultimately, PD concluded there was insufficient evidence to discriminate between the two causes of normal building movement or recent water inundation. PD, who is an appropriately qualified expert, is uncertain whether the water inundation caused the cracking. Given this, the panel has insufficient basis to conclude the ceiling damage was caused by the claimed event. Therefore, the insurer is entitled to remove these items from the scope of works. Bathroom and toilet The complainants say this was affected by mould contaminating the flooring in the hallway. The complainants have maintained from early in the claim that the bathroom was affected by the insur er‟s failure to address the moisture in the floor. MR, who was engaged by the complainants to review the mould issue, did not include in their scope of works anything to do with the bathroom. Determination | Case number: 496692 Page 7 of 17 WEC‟s report found evidence of mould in a bathroom wall cavity. This appears to be adjacent to the hallway. WEC‟s report does not appear to say the whole bathroom needs to be stripped because of this mould found. In their report, they say “mould growth is expected in the wall cavity between bathroom and exterior brick wall”. After this, WEC then say full remediation would require demolition of the bathroom. Given this, it appears WEC says the bathroom should be stripped because of the possibility of mould growing in the wall cavity between the bathroom and exterior bri ck wall. There is no evidence to support this. The only area of mould found was in the cavity adjacent to the hallway. This is on the other side of the bathroom. It is not clear how this could have spread to the other wall yet leave no visible evidence. MR , who attended the property at the complainants‟ request, provides no support for this possibility. Neither does the insurer‟s mould expert (A). RC, who completed the scope of works, found no evidence of water damage to the bathroom. Given this, the panel does not accept there is sufficient basis to say the whole bathroom needs to be stripped out. In the alternative, if the argument is that the bathroom needs to be stripped because of the mould found in the wall cavity, the panel is not persuaded by this for the following. First, it is not clear whether the presence of the mould in the wall cavity cannot be treated. WEC‟s report provides no comment on this factor alone. Second, even if this plasterboard needed to be replaced, it is not clear why the whole bathroom and toilet need to be stripped. This appears excessive. Third, it is not clear if this evidence of mould was due to the insurer‟s failure to remove the moisture in the floor or the delay in arranging mould remediation. The identification of this mould was following a sample taken on 24 April 2018. This would have been about five months after the insurer provided the complainants with the funds to attend to the mould remediation. Electrical works The electrical works paid for by the insurer was based on a quote from EES. This allowed for the disconnection and reconnection of 17 power points, one oven and one cooktop. Determination | Case number: 496692 Page 8 of 17 The complainants say EES‟s quote was for the mould remediation. The power points were removed when the plasterboard was being stripped and then reinstated to ensure there were no live wires. The panel does not accept this. If the power points were disconnected, it is not clear what safety issue was being addressed by reconnecting them after the plasterboard was removed but before building repairs were completed. It appears to be duplicating these works. Given this, the panel does not agree the insurer is required to pay for these power points to be disconnected and reconnected again. The panel does note EES‟s quote makes no reference to light switches. Therefore, these should be included in the insurer‟s quote. How the building claim should be settled The complainants provided four quotes. However, it is clear they are out of date given the following:  they contain works that have been se ttled (e.g. electrical works, mould remediation)  they include works that have not been allowed for (e.g. bathroom) RC‟s quote is the only one available that is based on a current scope of works and has individually priced the relevant items. However, it is not clear if RC are prepared to do the works for the complainants or that the rates and amounts specifically allowed can be matched in the market. Given the history of this complaint and the fact the relationship between the parties have broken down, the panel considers it is fair in all the circumstances to provide a cash settlement figure to resolve this complaint. The panel proposes the insurer should pay $73,002 in settlement of the building claim. This is based on the following:  RC‟s quote, after removing the items that the panel accepts are not covered, totals $60,835  an additional 20% to account for possible variations that may occur during the building process and the fact the complainants may not be able to match RC‟s rates and amounts The panel notes that the amount it allowed for RC is slightly higher than the insurer‟s estimate. This is mainly to do with facilitating an allowance for light switches. The insurer is not required to pay interest on this amount. This is because it is based on an estimate and an extra allowance of 20% has been factored in the final payment. Determination | Case number: 496692 Page 9 of 17 2.2 How should the complainant s’ contents claim be settled? Insurer is not liable for any additional payment The insurer has made part payments throughout the claim for contents. This included numerous furniture items (chester drawers, oak dining table), miscellaneous contents items and electrical items. This totals $18,056. The complainants sought $48,000 for the replacement of mattresses, lounge chairs, linen, clothing and rugs. No evidence has been provided to show these require replacement due to the water inundation or the mould. MR‟s report says that remediation will be attempted on large pieces of furniture. This would not include small contents and clothi ng. MR‟s report makes no reference to finding items non-restorable due to the mould. WEC‟s report simply says “The building & contents require mould cleaning to remove dust & settled spores”. WEC makes no mention of identifying any items that are non - restorable. Given the delay in arranging mould remediation, it will likely be difficult to determine if any items now deemed to be non-restorable was due to the delay in arranging mould remediation or the claimed event. Therefore, the panel does not accept there is sufficient basis to conclude the complainants are entitled to any additional payment for contents 2.3 Are the complainants entitled to compensation for other costs? Complainants seek compensation for a number of financial expenses The complainants have sought compensation for the following:  $1,595 (electrical services), $1,190 (skip bin hire), $1,860.98 (various furniture)  cost of reports from MR and WEC  alternative accommodation, new utility connections, electricity and phone line rental at their property for the period they are in alternative accommodation  loss of wages, income or leave balances for days taken off to deal with their claim  loss of work due to cancellations for the female complainant‟s cleaning jobs . Electrical services, skip bin hire and various furniture The complainants provided a receipt for electrical services totalling $1,595. It is unclear if the complainants are seeking payment for this. The ABN associated with the receipt matches EES‟s. The insurer already paid $3,564 towards EES‟s Determination | Case number: 496692 Page 10 of 17 quote. No explanation was provided that this receipt represents additional works or part paymen t for EES‟s quote. Therefore, the insurer is not liable for this. The complainants are also seeking $1,190 for a skip bin hire. In a document attached to an email the complainants sent on 20 April 2018, they indicated this was for flooring. MR‟s scope of works allowed $5,500 for a skip. It is unclear why another cost is necessary, particularly when there is no evidence the complainants incurred this cost. The insurer is not liable for this. The complainants sought reimbursement for replaceme nt furniture. The items being replaced did not include items settled by the insurer. As the panel does not accept the insurer is liable for any additional contents, this is not payable. MR and WEC report fees We may require the insurer to contribute to the professional costs incurred by a complainant. This normally occurs when the professional costs assisted the complainant‟s position. MR‟s report substantively assisted the complainants‟ position. Therefore, the insurer should pay for this cost if it has not done so already. The panel does not accept WEC‟s report assisted the complainants‟ position for reasons outlined. The insurer is not liable to reimburse this cost. Temporary accommodation, new services, utilities The insurer has paid $36,120 for alternative accommodation. This was based on a weekly rental of $1,400 for a period of six months. The policy says the following regarding this: When an insured event damages the building to the extent you cannot live there, and we agree, we will pay for your reasonable temporary accommodation costs for the time it will take to repair or rebuild the building to a liveable condition. MR‟s scope of works estimated the works to take about 23 days. The insurer says to complete the remaining building works would take about 8 weeks. The complainants have not provided any information to show the works would exceed six months. Determination | Case number: 496692 Page 11 of 17 Therefore, the insurer‟s allowance for temporary accommodation is fair in all the circumstances. This benefit also says the insurer will pay for the reasonable and necessary costs for mail redirection, utility connection costs and assistance with bond payment if required. The insurer allowed $500 for these costs. This also included power and water use by contractors. There is nothing to suggest this is insufficient. Even if it arguably is, the insurer has allowed six months temporary accommodation. This appears more than necessary to allow the property to be restored to a liveable condition and to account for these other expenses. Therefore, no further payment is required for these items. Lost wages and lost work These appear to be based on the insurer‟s handling of the claim. In summary, some of the main issues raised by the complainants are as follows:  the insurer‟s authorised service providers/cont ractors acting inappropriately and causing further damage  the effects (or lack thereof) of the drying equipment used  the insurer‟s refusal to provide temporary accommodation during the period the restorers used drying equipment  the accuracy of information and descriptions in the insurer‟s reports  health issues experienced due to the mould that occurred. We may compensate complainants for consequential losses that arise from the insurer‟s conduct. No evidence has been provided the cancelled jobs were lost because of the insurer‟s handling of the claim rather than other factors. Therefore, this is not payable. The loss of leave balances claimed by the complainants is also not compensable. This is because the evidence does not show they were caused by the ins urer‟s poor handling of the claim. For instance:  the male complainants‟ annual leave in July was to deal with the insurance claim – this would be a loss caused by the claimed event rather than the insurer‟s poor handling of the claim  no evidence to show the sick leave days was due to the house – the medical certificates do not explain why they were taken. Determination | Case number: 496692 Page 12 of 17 2.4 Should the insurer pay non-financial loss? Compensation is awarded conservatively We may decide the insurer compensate the complainants when the insurer caused them to suffer an unreasonable degree of physical inconvenience, time taken to resolve a situation, interference with their peace of mind or loss of enjoyment of an asset. Compensation is awarded conservatively. Compensation is not awarded for the normal degree of inconvenience a person would expect to suffer when lodging this type of claim or having a problem with the insurer. Compensation can be awarded though if the insurer‟s handling of the claim was unreasonable. Insurer to pay $1,500 in non-financial loss There were aspects of the claim handled poorly. Particularly with the failure to mitigate the presence of mould and attempting to source temporary accommodation in a quick manner at certain times. The panel accepts this caused substantive inconvenience to the complainants. However, the inconveniences have not all been caused by the insurer. The complainants restricted access to the insurer‟s authorised representatives to continue to attend and inspect their property from at least September 2017. This significantly added to the difficulty for the insurer to adequately address the complainants‟ concerns. The insurer also settled aspects of the complainants‟ claim generously. The policy allows the insurer to arrange for experts to assess the damage. The complainants would often not agree to this. Despite this, the insurer agreed to settle amounts based on quotes the complainants provided which the insurer was not able to assess. Further, the information exchanged shows the insurer changed claim managers and appointed new assessors and builders in response to the issues raised by the complainants. The panel considers these factors mitigated the insurer‟s poor handling of the claim. Given this, and taking into account our conservative approach, the pa nel considers it fair in all the circumstances for the insurer to pay $1,500 for non-financial loss. Determination | Case number: 496692 Page 13 of 17 3 Supporting information 3.1 The determination is made under FOS Terms of Reference The Australian Financial Complaints Authority ( AFCA) has commenced managing disputes previously lodged with F inancial O mbudsman S ervice (FOS) . This determination is made under FOS Terms of Reference but has adopted the following terminology for consistency with AFCA. In this determination the AFCA terms have the same meaning as the FOS terms defined in paragraph 20.1 and Schedule 1, 2 & 3 of the FOS Terms of Reference. FOS definitions AFCA term applicant complainant financial services provider financial firm dispute complaint 3.2 FOS approach This dispute has not been the subject of a FOS recommendation. In view of the complexity of the issues in dispute, this matter has been referred to a panel for determination. The panel consists of an Ombudsman and two representatives with consumer and insurance experience. The panel has based this determination on what is fair in all the circumstances having considered all of the information exchanged, the relevant legal principles, terms of the policy, good industry practice, including relevant codes of practice and prior determinations where applicable. There has been a full exchange of material between the parties and each party has had the opportunity of addressing the issues that arise from the information exchanged. The panel has reviewed and considered all of the material provided by the parties. While the parties have raised numerous issues in their submissions, for the purposes of this determination, the panel has restricted its commentary to those issues that it considers directly relevant to the outcome only. Any reference in this determination to the complainants includes reference to both the female and male complainant. Submissions made by the female complainant are taken to have been made on behalf of both the complainants. Determination | Case number: 496692 Page 14 of 17 3.3 Policy terms Section Terms Complete Replacemen t Cover [ Insurer ] Home Building Insurance with the Complete Replacement Cover option covers insured damage or loss to your home building for the total amount it would cost to us repair or rebuild it. When you have selected the Complete Replacement Cover option, we repair or rebuild insured damage or loss to your home or pay the cost of repairing or rebuilding to the same size and standard of your current home. Some exclusions apply. Please read this Product Disclosure Statement for full details. We cover Loss or damage to the building due to an insured event during the period of insurance up to what it costs us to repair or rebuild the damaged parts of the building on a „new for old‟ basis unless provided otherwise in your policy. Limit Up to what it costs us to repair or rebuild the building on a „new for old‟ basis unless provided ot herwise in your policy. We do not cover  any loss, damage, item, cost or expense that is not covered under the insured event for which you are claiming  upgrading undamaged parts of the building to comply with the current home building regulations and laws Insured event s cover We cover the building for loss or damage at the insured address caused by an ins ured event during the period of insurance. We cover loss or damage t o the building caused by a storm. We do not cover …loss or damage caused by erosion, vibration, subsidence, landslip, landslide, mudslide, collapse, shrinkage or any other eart h movement, but we will cover loss or damage to the building caused by a landslid e or subsidence proved to have occurred within 72 hours of, and directly because of, a storm and not because of erosion over time, structural fault or design fault . Additional features If we accept your claim for loss or damage to the building due to an insured event, we will also provide the following additional features. The additional features and their limits are paid in addition to the cover provided under the building insurance. Temporary accommodation When an ins ured event damages the building to t he extent you cannot live there, and we agree, we will pay for your reasonable temporary accommodation costs for the time it will take to repair or rebuild the building to a liveable condition. We will also pay the reasonable and necessary costs for:  redi rection of mail from the insured address for up to 52 weeks; Determination | Case number: 496692 Page 15 of 17 Section Terms  utility connection costs at the temporary accommodation residence;  assistance with bond payment if required, however any amount we pay in bond is recoverable from you by us. We may deduct this am ount from any amount payable to you. [If your] certificate of insurance shows that you have Complete Replacement Cover option we pay the reasonable and necessary costs. General exclusions You are not covered under any section of your policy for damage, lo ss, cost or legal liability that is cau sed by, arises from or involves:  deliberat e actions by you an act or omission by you, your family, anyone living at the building or any owner or part owner of the building, or anyone acting with your consent, which: o is deliberate; o is a deliberate lack of action; o demonstrates a reckless disregard for the consequences of that action or omission.  failing to take care of the building or contents your failure to: o take reasonable care of the building and contents; o keep the buildings and contents well maintained and in good condition o fix faults and defects as soon as you become aware of them.  wear, tear and gradual deterioration wear, tear, rust, fading, rising damp, mould, mildew, corrosion, rot, action of light, atmospheric or climatic conditions or gradual deterioration such as, but not limited to: o tiles and their adhesive or grouting breaking down; o weat hering of roof tiles or roof ridge capping; o gradual weathering and breakdown of bricks, mortar or concrete.  consequential loss (financial and non - financial loss) or extra costs following an incident covered by your policy, such as: o loss of income or wages; o loss or costs, including the cost of your time (e.g. inconvenience), to prove your loss or to help us with your claim (e. g. telephone calls, postage); o professional, expert, legal, consulting or valuation costs unless you obtained our prior written authority to incur these costs; o cleaning costs; o any costs related to stress or anxiety; o any costs not covered by your policy. Determination | Case number: 496692 Page 16 of 17 Section Terms Claims proce ss What you must do Try to prevent further loss or damage. If possible take reasonable steps to prevent further loss, damage or liability (e.g. if there is a hole in the roof, arrange for it to be covered to prevent further water damage from t he rain). To proce ss the claim, you must  allow us to inspect the damaged building;  allow us to arrange for experts to assess the damaged building and to quote on repair or replacement;  provide us with a quote for repair or replacement if we ask for thi s. If you choose to use our recommended repairers (when available), there is no need to obtain your own quotes;  when requested, provide us with all proofs of ownership and value, information, co - operation and assistance in relation to a claim (including a ttending an interview or giving evidence in court if required) as we may reasonably require;  allow us, or a person nominated by us, to recover, salvage or take possession of the building. When we ask, you must send any items to us, or cooperate in our col lection or retrieval of such items;  consult an expert if we ask for this. If you do not comply If you do not comply with „What you must do‟ and „What you must not do‟ we can reduce or refuse your claim and/or recover from you any costs and/or any monies we have paid and/or cancel your policy. Describe your loss or damage You must also give us accurate and full details of what was lost, stolen or damaged and give us proof of value and ownership for items claimed if we request it. When the building is damaged Allowing us, a repairer or an expert appointed by us, to look at what is damaged is usually all that is needed to prove your loss. Sometimes though we might ask you to produce a copy of the most recent plans and drawings for the building, photograp hs of the building or other evidence that supports the extent of the loss you have suffered. If we decide that you are unable to reasonably substantiat e your claim, we might reduce or refuse your claim. Salvaged building items If we replace or compensat e y ou for an item, we then own the damaged or recovered item. If we agree you can keep an item we will determine the salvage value and we can deduct this amount from any payment we make to you. Determination | Case number: 496692 Page 17 of 17 Section Terms How claims are settled Depending on the circumstances we will de cide to repair, rebuild or pay you what it would cost us to repair or rebuild. We will not pay extra to repair or rebuild the building to a better standard, specification or quality than it was before the loss or damage occurred except as stated in the meaning of „new for old‟. ‘New for old’ means:  New materials , new items we rebuild or repair with new items or new materials that are available at the time of replac ement or repair from Australian suppliers.  New for old, regardless of age we rebuild or rep air regardless of age, with no allowance for depreciation.  Same type, standard and specification as when new we replac e or repair to the same type, standard and specification (but not brand) as when new. If the same is not available, it means of a similar type, standard and specification (but not brand) when new. We can replace with a different brand. „New for old‟ does not mean of a better standard, specification or quality than when new. Repairing or rebuilding damaged parts We will only repair or rebuild the parts that are damaged in the incident covered by your policy. You cannot claim to replace undamaged parts of the building to create a uniform appearance. Definitions Loss or damage means physical loss or physical damage. Storm means a storm, cyclon e or severe atmospheric disturbance. It can be accompanied by strong winds, rain, lightning, hail, snow or dust.