Storm-damaged shed and vintage boring rods; liability for rust damage denied

FirmFinancial Firm (Unknown - Insurer)
Decided2018-09-27
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$3,000
Non-financial loss$3,000
Amount claimed—
SourceAFCA PDF

Summary

After a storm, repairs to the applicants' shed were delayed and the FSP refused off-site storage for vintage precision tools, which were later damaged by rust. AFCA found the FSP liable for the boring rods, ordered an independent expert assessment and cash settlement, and awarded non-financial loss and professional costs.

The FSP's unreasonable repair delays and repeated refusals of storage caused the damage to the boring rods, so it must meet the claim without monetary limit.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay compensationpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 496510 Determination Page 1 of 11 Case number: 496510 11 September 2018 1 Overview 1.1 Dispute The applicants lodged a claim on their Home, Building and Contents Policy held with the financial services provider (FSP) after the property was damaged during a storm on or about 4 October 2013. The FSP accepted liability however issues arose due to delays in the repair process and the failure to complete repairs to the applicants‟ shed. This resulted in a further claim in October 2014 for damage sustained to 14 boring rods that had been affected by rust used in a vintage automotive line boring machine. The FSP initially offered to cover the cost of restoring the rods but now denies liability and says:  the applicants failed to mitigate their loss  the boring rods are tools of trade not covered under the terms of the policy  the rust or loss was not caused by the FSP‟s conduct  it has been prejudiced by the applicants‟ conduct . 1.2 Issues and key findings Is the FSP liable for the damage to the boring rods? The FSP is liable for the damage sustained to the boring rods as, on the balance of probabilities, the damage arose as a result of the FSP‟s failure to complete the storm damage repairs in a timely manner. Has the FSP been prejudiced by the applicant s’ conduct ? The panel is not satisfied that there is evidence to establish prejudice as a result of the applicants‟ conduct. Are the applicants entitled to compensation for professional costs incurred and non-financial loss? The applicants are entitled to compensation for non-financial loss pursuant to paragraph 9.3 of the Terms of Reference for $3,000 and for professional costs incurred of up to $3,000. Case No: 496510 Determination Page 2 of 11 1.3 Determination This determination is in favour of the applicants. Within 14 days of the applicants‟ acceptance of this determination, the FSP is to appoint an independent expert toolmaker/metallurgist to determine the extent of damage to the boring rods. Within 14 days of receiving the report, the FSP is to cash settle the claim for the cost to repair or replace the boring rods as determined by the independent expert. The FSP is to pay the applicants $3,000 compensation for non-financial loss pursuant to paragraph 9.3 of the Terms of Reference. The FSP is to contribute up to $3,000 towards the professional costs incurred by the applicants in obtaining reports in support of the claim. Case No: 496510 Determination Page 3 of 11 2 Reasons for determination There has been a full exchange of material between the parties and each party has had the opportunity of addressing the issues that arise from the information exchanged. Due to the complexities involved in this determination it has been referred to a panel for decision. This determination is based on what is fair in all the circumstances, having regard to the relevant legal principles, terms of the policy, good industry practice including codes of practice and prior determinations where applicable. 2.1 Is the FSP liable for the damage sustained to the boring rods? FSP accepted liability for storm related damage There is no dispute that the FSP accepted liability for the damage sustained to the applicants‟ property during a storm in October 2013. According to the information exchanged the roof of the applicants‟ shed was significantly damaged when a tree fell during the course of the storm, breaking the applicants‟ fence and hitting the shed. The FSP accepted liability for the storm claim, however the repair process was repeatedly delayed, with the final repairs not being completed until approximately 13 months later, on 14 November 2014. Although these repairs were said to have been completed by 14 November 2014 it is apparent further rectification work was required. The panel is satisfied that the delay in repairs is unreasonable and the FSP‟s failure to complete the repairs in the timely ma nner has led to further inundation of the shed. FSP aware the applicants had precision engineering tools in the shed On 31 October 2013 the FSP‟s repairer AM highlighted to the FSP the shed contained: extremely expensive precision engineering tools that need to be stored at the appropriate humidity to prevent corrosion [because] dehumidifier installed in the shed cannot keep up with extracting the moisture. The FSP decided not to offer any storage. It based this decision (the first storage decision) on the high cost s it anticipated due to the equipment‟s weight and delicacy. The FSP noted it should advise the applicants of its decision. The claim records do not note any subsequent notification occurred. FSP failed to arrange off site storage for the equipment The FSP says the applicants accepted responsibility for storing the boring rods. The FSP says the applicants:  refused its offers (before and on 15 July 2014) to move the boring rods off-site Case No: 496510 Determination Page 4 of 11  were told (on 15 and 21 July 2014) they were responsible for storing the boring rods. The Panel carefully reviewed the FSP‟s claims records and the FSP‟s reports. On 30 April 2014, the FSP‟s builder (P P) told the FSP the applicants requested it store the shed ‟s equipment off-site. The FSP arranged for a claim assessor and PP to attend the property to assess the storage request. On 13 May 2014, the FSP cancelled the assessment (the second storage decision) meeting based on its decision that:  storage was a claims management (and not assessing or building) decision  the FSP was unable to contact the applicants, so it was unable „to confirm if there are any other issues‟ to justify an assessment meeting. On 18 June 2014 PP again notified the FSP that the applicants had made „several requests‟ for off-site equipment storage. The applicants and FSP then agreed the FSP would provide a sea container at the site, for equipment storage. The FSP requested PP submit a quote for this container. On 1 July 2014, the FSP again requested a quote from PP for a sea container, a req uest it repeated the next day. It also noted to „follow up if insured tools have been stored in shipping container to be provided by [PP]‟. On 2 July 2014, the FSP spoke with the applicants. They agreed to a site assessment with PP and the repair contract or‟s claim assessor (LD) to address the applicants‟ concerns about repairs and storage on 15 July 2014. The FSP reviewed LD‟s report on 18 July 2014. This (third storage decision) noted: Insured is happy if all equipment in repair can moved back to area in shed to allow repairs. PP have allowed to move equipment & partition area items from repair area. Assessor has determined that items don‟t have to be stored outside or in a container. Applicants did not accept responsibility for storing the boring rods Th e panel does not accept the FSP‟s suggestions that the applica nts accepted responsibility for storing the equipment or storing the boring rods. The sequence of events highlights that the FSP received numerous requests for safe storage. The requests were made by its own contractors for the applicants. The FSP was alerted (on 14 October 2013) the damaged shed contained „some quite exotic and expensive tools … which the insured is quite concerned about‟. On at least two different occasions afterwards, the FSP decided it would not provide storage. A third refusal of appropriate storage occurred when its agent decided no sea container storage would be needed during repairs. Whilst the panel acknowledges the applicants‟ agreement with the FSP‟s assessor from 15 July 2014, the panel accepts that such agreement was reached under pressure to have the repairs completed and under the understanding of the build er‟s proposal to „move equipment and partition the area.‟ The panel is satisfied that the FSP is responsible in these circumstances for the arrangements made for the storage of the equipment. Case No: 496510 Determination Page 5 of 11 FSP liable for the damage to the boring rods The applicants say that the FSP‟s failure to complete the repairs to the storm damaged shed, the repeated delays and inadequate claims handling has allowed water to enter the shed. The boring rods had been stored wrapped in cloth in a metal tool box. Access to that box had been blocked resulting in the boring rods rusting. To support this claim the applican ts‟ provided:  machine balancing and calibration expert reports  annotated photographs of the boring rods  detailed submissions on machines, boring rods, restoration and rust  correspondence from the claim and their attempts to seek replacement parts  quotes and products specifications  working solutions for suggested replacement equipment. The FSP has suggested that the bars were already rusted but offered no information to dispute the applicants ‟ expert reports. Photographs support damage likely occurred after storm claim T he FSP relies on a claim assessor‟s (PC‟s) report (29 January 2015). This stated: I could not guarantee the condition when these bars arrived nor the condition when they were damaged. As they were stored out of site, on the concrete floor, and under a cabinet by the external door there is a chance they were damaged prior to the event. [sic] However, the p anel is not persuaded by PC‟s suggestion, which is refuted by a substantial amount of the materials provided. Photographs show vari ous machines and work stations inside the applicants‟ shed. These are taken from numerous different angles and work stations. All equipment is, without exception, very neatly organised and stored. Additionally, the applicants kept the boring rods wrapped in cloth, inside a metal box. As identified by AM, the applicants advised of their concerns that humidity might damage the vintage, precision instruments in October 2013. AM assessed the contents in October 2013 and found four other vintage machines and their parts damaged. AM did not refer to the boring rods being damaged. The applicants intend to continue using the machine with the six undamaged boring rods. PC‟s report confirms „some‟ bars do remain usable. The applicants claim only relates to the 14 damaged rods which they seek to have repaired or replaced. The p anel is satisfied all these factors refute the FSP‟s suggestion the bars were already rusted. Instead, they support the applicants‟ assertion they paid close attention to, and regularly used, their equipment and precision parts. For these reasons the panel is satisfied the applicants have, on balance, established the damage occurred after they lodged the storm claim. The panel is satisfied that the FSP‟s handling of the claim, its failure to complete the repairs in a timely manner and arrange appropriate storage has resulted in the damage to the boring rods. Case No: 496510 Determination Page 6 of 11 2.2 Has the FSP been prejudiced by the applicants ’ conduct? The FSP says it has been prejudiced by the applicants ‟ conduct, in particular:  the applicants delayed the repair process  the applicants acted without its approval in having the boring rods ice blasted  that the applicants have failed to provide the FSP access to the boring rods to properly assess the damage. The applicants did not cause a delay in the repairs The parties give different accounts for why the (first) repairs were completed over 13 months after the claim date. The panel has reviewed the relevant information. The panel is satisfied the FSP ‟s (or its agents ‟ ) inadequate claims handling, or repairs, on repeated occasions delayed the repair process. In particular:  the applicants were correct to seek storage before repairs commenced  make safe works were inadequate and finished repairs required rectification  the FSP erred in its three refusals to provide appropriate storage  regularly, weeks and on repeated occasions months, elapsed before the FSP acted on internal requests, if at all  the applicants were substantially left to progress the claim. On review of the claim actions, the applicants usually returned the FSP‟s contact that day, or within four days. The Panel accepts that on two occasions, the applicants did not respond to the FSP‟s requests for contact. On two further occasions, the FSP contacted the applicants, but they indicated they were busy. The FSP did not clarify whether messages it (and PP) sent to the applicants were by text message (which the applicants advised they could not receive), email, or post. The claim records show:  the applicants advised the FSP their local mobile coverage was very limited  they requested contact by landline instead  there were message facilities on at least one landline  PP appears to have contacted the applicants primarily by mobile  PP used at least one incorrect mobile number, which the FSP later corrected. The panel does not accept the FSP‟s suggestion that it has been prejudiced in any way by the applicants ‟ conduct. The panel is satisfied that the applicants have acted fairly and reasonably. Applicants did not breach policy conditions The FSP says the applicants breached policy conditions by authorising repairs and not cooperating with the FSP‟s claim assessment. It asserts these actions prejudiced the FSP‟s ability to fairly consider the claim. Case No: 496510 Determination Page 7 of 11 The FSP also says due to the applicants‟ restoration works, the bars are now in a different condition to when they were damaged. The panel accepts the applicants refused to give up all of the boring rods for assessment by the FSP and:  had BS, a machine balancing and calibration expert, ice blast the boring rods to clean off the rust to assess the damage  then sought restoration alternatives including heat treatment  authorised heat treatment, which bent one bar. The panel does not consider however, it plausible that further assessments would have concluded any differently to BS. The Panel accepts BS‟s conclusion that bars become irreparable once rusting occurred. The FSP‟s assessor PC viewed the rods . The applicants‟ annotated photograph supports PC‟s report comments that the applicants had „saved some‟ (six), but that others were „pitted with rust‟ (fourteen). It is unlikely the applicants‟ refusal to provide the bars had any effect on the outcome of damage assessments, which the FSP says it would have carried out. Additionally, the applicants had provided one of the damaged bars to the FSP. The FSP had many opportunities to assess damage. The applicants say: As the line-boring bar given to [the FSP] was provided willingly, without restrictions or caveats, they have had every opportunity to collect data about the line-boring bar. They must have information about the exact methodology used b y the „ice - blasting‟ company. [The FSP] had unimpeded access to make measurement of size, concentricity, condition of surface and surface hardness at all times. [The FSP was] never denied access to view, photograph or measure the bearings or design of the line-boring machine. Any requests for access were granted from the time immediately after the flooding and during the subsequent meetings. Access was available, although never requested, until the time of the email communication 19/04/2016 stating “this matter is not one for [FSP] to further address”. On balance, the panel considers the applicants have established:  no other assessment as to the extent of damage was required  the FSP had reasonable assessment opportunities. Further, the panel notes the disputed damage occurred over four years ago. Since then, the FSP has not obtained expert information either confirming or refuting any technical comments made by the applicants (or their experts). 2.3 FSP is liable to meet the applicants’ claim Boring bars are vintage parts from vintage machine The damaged boring bars were used in the applicants‟ precision engineering machine. The applicants say that the line boring machine was „ used for boring main tunnels on engine cases‟. The applicants obtained a history of the machine, based on information produced by a [state] museum, and an incorporated motor enthusiasts‟ association (for the relevant vehicle manufacturer). Based on this history, the applicants say it: Case No: 496510 Determination Page 8 of 11 is a specialised, vintage machine and … was used in the vehicle manufacturer‟s former factory between 1959 and 1968 … although 1960 vintage has been restored by [them] and [so] is accurate to 0.0002" of an inch over the boring distance with repeatability. The FSP does not dispute the applicants‟ claim the rods and machine are specialist, original, vintage, vehicle manufacturer‟s engineering equipment. Applicants have quantified their loss to the best of their ability The applicants have tried to find replacement parts and machines. They provided three potential solutions to the FSP. In support, the applicants provided their own submissions, and:  manufacturers' contact details and some partial quote estimates  correspondence to and from manufacturers  related advertisements and product specifications  correspondence to the FSP (detailing replacement attempts and options)  BS‟s reports (regarding the bars‟ potential for repairs)  photographs of their line boring machine. The FSP says the applicants have still not furnished verifiable costings for it to give consideration to in order to resolve the matter. The FSP says that regardless, indemnity is limited to the monetary cost of „rust restoration‟ by PP. The FSP says it may on this basis pay the applicants $1,900, being: the restoration of the rust to the maximum value it would have cost the FSP to restore the rods [after the] … applicant[s] refused its restoration offer. The panel is satisfied that the applicants have taken all reasonable steps to source, quote and identify any possible available repairs and replacements. The panel accepts the applicants have done this at their cost, without assistance from the FSP. The FSP has failed to obtain any expert information to either confirm or review the technical comments made by the applicants or their experts. The panel is satisfied that the applicants have sought competitive quotes for replacement machines and have provided detailed explanations about the technical requirements of any replacement boring rods. The applicants have also provided information to indicate that it may be possible to have replacement boring bars manufactured in Europe or in the USA. The FSP has not provided any information about the availability or feasibility of manufacturing replacement boring rods in Europe or the USA. Independent expert toolmaker and metallurgist to be appointed It is difficult to identify the costs to repair or replace the boring rods or to quantify the appli cants‟ claim. In the circumstances the panel considers it fair that an independent expert toolmaker and metallurgist be appointed to determine whether the boring rods can be repaired and if so, the cost to repair the boring rods in accordance with the manufacturing specifications. If the boring rods can be repaired or replaced the FSP is to cash settle Case No: 496510 Determination Page 9 of 11 the claim for the cost to repair or replace the boring rods as assessed by the independent expert. In the event that the boring rods cannot be repaired or replaced then the independent expert is to identify suitable replacement machine and subject to agreement between the parties, the FSP may either purchase the machine for the applicant or cash settle the applicant for the costs of the replacement machine. The panel is further satisfied that as the damage arises from identified deficiencies in the FSP‟s claims handling process, the settlement figure is not subject to any monetary limits. 2.4 Are the applicants entitled to compensation? Applicants are entitled to compensation for non-financial loss Under the Terms of Reference, FOS may require an insurer pay compensation for non-financial loss suffered by the applicants. This may apply in circumstances where FOS considers an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the insured‟s expectation of enjoyment or peace of mind occurred. The panel is satisfied the available materials establish the applicants experienced an unusual degree of stress and inconvenience. The stress experienced by the applicants was exacerbated by:  the FSP‟s continued failures to respond to the applicants‟ request s for storage  the vintage and unique nature of the damaged equipment  the applicants‟ understanding of the damage, and appropriate testing methods  the FSP‟s continued failures to accept the applicants‟ advice in this regard  the FSP‟s erroneous attribution of responsibility for storage decisions, rust damage and delays to the applicants  that these errors occurred despite the applicants ‟ attempts to mitigate losses and replacement costs (taking significant time, expense and expertise). Accordingly, in line with paragraph 9.3(b) of this Service‟s Terms of Reference, the FSP is to pay the applicants $3,000 compensation for non-financial loss. Applicants are entitled to professional costs The applicants have incurred professional costs in providing information fro m their experts to the FSP to assist in the determination of this dispute. Under paragraph 9.4 of the Terms of Reference, FOS can determine that an FSP contribute up to $3,000 towards professional costs incurred in the course of a dispute. The panel is satisfied that the applicant has necessarily incurred the professional costs, given the complexity of the issues involved and genuinely require the expert assistance. In the circumstances the panel is satisfied that the FSP should contribute up to $3,000 towards the professional costs incurred , subject to the applicant providing relevant receipts or invoices. Case No: 496510 Determination Page 10 of 11 3 Supporting information 3.1 Reports Record Key points FSP’s expert (A M ) Restoration cont ractor Assessment of (other) machines damaged in insured event 14 - 11 - 2013  I nsured has provided [AM] quotes for replacement and though this is not the normal process, due to the complex nature of the items, [they] appear to be the nearest equivalent to what the insured has and in our opinion, this is the most economica l method of settlement for these particular contents loss .  I nsured‟s equipment is used to work on machinery, engines and car parts which are no longer manufactured, so a lot of what he provided quotes on are seconds but this is because the second hand part s are all that can be utilized today for him to be able to carry on doing the same work that he does .  [Machine 1:] The quote is actually for a second - hand machine which is all the insured wants as the newer machines will not serve the same purpose that he uses them for. This has reduced costs by approx. $20,000.00.  [Machine 2:] The quote from [an industrial supplier] the nearest equivalent as far as we have been able to ascertain.  [Machine 3:] The current equivalent replac ement only provides output in digit al and the cheapest we were able to find was the US$3,169 +GST + freight + the shops necessary margin. The insured prefers an analogue output and in imperial . measurements based on today‟s current supply. He would have to buy two separate gauges to fulfil this need which the insured is content with.  [Machine 4:] This item requires replacement. The insured has the tools to remake one if he is able to get the materials needed at little or no cost he will not bother claiming for it, however if costs are high he will provide a receipt and request reimburs ement for the materials to recreat e the tightener and not charge for his labour. We believe this is reasonable.  T his report is the only assistance that [AM] can provide on this contents loss. FSP’s expert (PP) Building contractor Assessment report 12 - 10 - 2014  Length of time of repairs are due to multiple issues not wit hin PP control ...PP have only been approved since February in this time we have had to obtain plans/permits, have trades attend measure up, access difficulties due to the insured being away multi ple times, difficulty in contacting the insured, and issues with storage as advis ed by insurer.  After demolition of damaged garage section, the garage had a temporary frame installed to help tarp up to limit exposure to the weat her and elements.  The insu red advised that excessive rain hit the property and run down the tarps onto the concrete slab and flooded the insureds garage.  He spent up to 30 hours trying to limit damage from the water Case No: 496510 Determination Page 11 of 11 ingress. When asked if the insured contacted PP or their insurer during the high rain flood event, they were unsure and believed they had trouble as it was after hours. PP and the insurer have afterhours contact and when we were made first aware (17/08) PP attended that day to res eal and prevent furt her water entry.  Th e shed was repaired and wat ertight 2 days later. Rust to the insureds machinery and products, we believe cannot be directly related to the one flood event . FSP’s expert (PC ) Claim assessor Reins pection report 12 - 02 - 2015 Machine rods:  the machine rods were removed from the stand after the tree impact, wrapped in a towel and put in the bottom cabinet  the cabinet then flooded with water but the insured's machinery was put in front of the cabinet so he was unable to get to the rods  when the work was completed and the machinery moved the insured then discovered the rods were sitting in water and had become damaged  this would make sense as it was described  I originally believed the rods were always stored there and thus could have been damaged outside the claim but I was wrong  there are 14 rods, 3 are not being claimed f or so there are 11 rods damaged  the insured has found a place in America t o fix these but at a huge cost  t he insured is trying to find a way of doing this locally  e ither way, this could cost anywh ere between $6k - $15k depending on the insured's investigations . 3.2 Repairs and replacements Applicants’ summaries – sourcing attempts The applicants provided detailed information of attempts to source the replacement parts through the original vehicle manufacturer through local contacts who may have been able to repair or replace the boring rods, through international enquiries and various recreation attempts.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.