After the FSP's builder botched storm-damage repairs, the applicants asked to be cash settled for the remaining work at $19,998. AFCA accepted that cost, ordered $9,878 more after the $10,120 already paid, and awarded $750 non-financial loss.

The reasonable cost to repair under the policy PDS was established by the only recent quote, and the builder's poor workmanship and delay justified non-financial loss compensation.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 495936 Determination Page 1 of 3 Case number: 495936 27 February 2018 1 Overview 1.1 Dispute The applicants hold a home and contents insurance policy (Policy). The Policy was issued by the financial services provider (FSP) and started on 23 December 2016 and renews annually. On 18 February 2017 a storm damaged the insured property. The applicants lodged a claim for the damage on 19 February 2017. The claim was accepted. The FSP’s builder started the repairs, however due to unsatisfactory works the applicants requested they be cash settled for the remaining work. This dispute is about the cost of the remaining work. The FSP cash settled the applicants for $10,120.00. The applicants say the cost of the remaining repairs is $19,998.00. The applicants are also seeking compensation for non-financial loss. 1.2 Issues and key findings What is the fair and reasonable cost of repair and rectification? Based on the information available I am satisfied that to return the property to the condition it was in before the storm damage occurred the entire patio needs to be rebuilt. This is because the two attempts at rebuild and repair have damaged the structural materials, such as the posts and beams, and they cannot be reused. Further the flashings between the house and the pergola require replacement in order to keep the property watertight. The applicants have provided a quote for these repairs from a licenced builder who is prepared to undertake the work. The cost of the work is $19,998.00. Are the applicants entitled to compensation for non-financial loss? The applicants have experienced an unusual degree of stress and inconvenience as a result of the actions of the FSP’s builders and are entitled to compensation for non - financial loss in the amount of $750. 1.3 Determination This determination is in favour of the applicants. Within 14 days of the applicants’ acceptance of this determination the FSP must pay the applicants:  $9,878 plus $750 compensation for non-financial loss. Case No: 495936 Determination Page 2 of 3 2 Reasons for determination 2.1 What is the fair and reasonable cost of repair and rectification? The scope of work required to restore the property was assessed by FSP The FSP accepted the applicants claim for hail damage. The FSP elected to repair the damage. The applicants were dissatisfied with the quality of work. The FSP’s builder (RB) engaged an inspector (AI) to assess the work and provide a roof report. The FSP has not disputed the report findings and has accepted that the damage noted in the report was caused by the FSP’ s builders. The report says the following repairs are required:  steel joists contain holes caused by misdirected screws and although damage is minor would need replacement to restore to pre -storm condition  roof sheeting falls short of guttering and is not sealed and requires replacing  a section of ridge capping was not completed and other sections require additional fixings  flashing damaged and requires removal and replacement of guttering to bay window  roof sheeting not square and sheeting colour is inconsistent requiring replacement. The FSP must cash settle for the reasonable cost of the repairs The FSP has agreed to cash settle the rest of the claim. The Product Disclosure Statement (PDS) says the FSP may: Pay you the reasonable cost to repair or rebuild your home. The applicants have provided a quote to complete the required repairs from a builder (MCB). The FSP says this quote is higher than the previous quotes obtained. The FSP has not provided a recent quote for the work required based on AI’s report . It did provide MCB’s quote to its builder. The FSP’s builder was unabl e to determine why there was a discrepancy in repair cost from the information provided. In the absence of any other recent quote covering the required repairs or other information establishing that the MCB quote does not represent the reasonable cost of repairs, I accept that the reasonable cost of repairs is $19,998.00. The FSP has already paid the applicant $10,120.00 ($9,920.00 plus a refund of $200 for the additional excess that was deducted in error). The applicants are therefore entitled to an additional $9,878.00. Case No: 495936 Determination Page 3 of 3 2.2 Are the applicants entitled to compensation for non-financial loss? FOS jurisdiction for awarding compensation is limited FOS will only award compensation for non-financial loss where there has been an unusual amount of physical inconvenience, time taken to resolve a situation, or interference with the a pplicant’s expectation of enjoyment or peace of mind. In assessing whether to award compensation for non-financial loss, FOS expects applicants to be moderately robust, bear the normal degree of inconvenience experienced when a problem occurs, and take reasonable steps to minimise the inconvenience suffered. Where an applicant has contributed to their loss arising from the FSP’s conduct, their level of compensation may be reduced ac cordingly. FOS can compensate an applicant for non- financial loss arising from the FSP’s poor management of the claim. When doing so, FOS considers the severity and impact of the F SP’s conduct on the particular applicant. FOS takes a conservative approach to assessing compensation for non-financial loss. The maximum amount FOS can award for non-financial loss is $3,000 per claim. FOS may also decide a non-financial remedy, such as a letter of apology, is appropriate. The actions of the FSP’s builders cau sed stress and inconvenience An award of $750 in compensation for non-financial loss was recommended in the preliminary view. The FSP rejected the preliminary view and said that it had not been notified of the applicants’ claim for non -financial loss. It is not necessary for the applicant to request compensation for their non-financial loss; FOS can award compensation if it considers it appropriate. I consider it fair in all the circumstances that the FSP pay the applicants $750 compensation for stress and inconvenience because:  there has been considerable delay in repairing the damage  the FSP’s builders caused more damage requiring additional repairs to areas that were not damaged by the storm and  the applicants’ had to clean the property as the FSP’s builders failed to remove rubbish from the site.