Text of the determination
Determination
Case No: 493976 Determination Page 1 of 10
Case number: 493976 22 March 2018
1 Overview
1.1 Dispute
The applicant held a home building insurance policy with the financial services
provider (FSP). He lodged a claim on 6 April 2017 after discovering a leaking pipe
under his kitchen. The FSP accepted the claim. It conducted mould remediation
works, and after first offering to either repair the house or cash settle, it cash settled.
The applicant raised further concerns about mould, and requested additional
remediation. He wants the FSP to increase the scope and settlement for the work.
The case manager issued a recommendation which the applicant did not accept.
1.2 Issues and key findings
Is the FSP required to increase its claim settlement?
For the reasons outlined in section 2.1 below, it is fair that the FSP obtains a new
actionable quotation for mould remediation work to both the building and contents,
and cash settles 70% of the quoted costs, including GST and margins.
The FSP‟s costings and scope of works were fair with regard to repairs previously
identified; however the cash settlement for repairs should be increased by $8,500 to
cater for possible further damage which might be identified, and to reflect the risk
taken on by the applicant in having to deal with repairs himself. The accommodation
component should be increased by a further 4 weeks to cover a reasonable likely
timeframe for obtaining a quote and completing additional mould remediation.
Is the applicant entitled to compensation?
The applicant and his family have experienced serious upset and inconvenience
during the claim experience. Some of that was due to the FSP‟s (and its agent‟s)
handling of the matter, and so compensation for non-financial loss is payable.
1.3 Determination
This determination is substantially in favour of the applicant. The FSP is required to
promptly obtain an actionable quote from an accredited mould remediation expert
(other than KA) for the necessary mould remediation works to the house and
contents, and cash settle 70% of the total quoted costs. It must also increase the
cash settlement for repairs by $8,500, as well as paying $1,000 compensation for
non-financial loss.
Case No: 493976 Determination Page 2 of 10
2 Reasons for determination
I have decided this case on the basis of what I consider fair in all the circumstances,
having regard to the relevant law, good industry practice, codes of practice and
previous FOS decisions.
I have taken into account all the material submitted by the parties, both before and
after the recommendation. I am satisfied that the documentation I have relied on has
been provided to both parties. For the purposes of this determination, I will deal with
only those points considered relevant.
2.1 Is the FSP required to increase its claim settlement ?
Applicant established a valid claim under the policy
The applicant‟s policy provides cover for loss or damage to the property arising from
certain incidents, including damage caused by an escape of liquid.
In order for the applicant to establish a valid claim, he must demonstrate, on the
balance of probabilities, that liquid escaped from one of the specific items listed in the
policy.
The parties agree the property sustained damage as a result of a leaking fixed pipe.
Accordingly, the applicant has established a valid claim.
FSP accepted and offered to settle claim
The FSP accepted the claim and originally authorised repairs. However, the applicant
raised concerns about the scope of work, as well as mould.
Mould remediation was carried out and certified in July/August 2017. On 1
September 2017, the FSP offered to cash settle the claim in the amount of
$62,465.03 (comprising $57,265.03 for repairs, less the $400 excess; and $5,600 for
temporary accommodation, calculated at $700 per week for 8 weeks).
The cash settlement was offered as an alternative to the FSP conducting repairs
itself. This was because the applicant had not been prepared to accept the FSP‟s
earlier offer to repair, unless a second mould remediation was conducted. It also
appears that the relationship between the applicant and FSP had already become
increasingly strained.
Because the FSP did not hear back from the applicant in response to that offer, it
cash settled for the stated amount, as it had indicated it would (and as it is entitled to
do under the policy), although the applicant did not want a cash settlement.
Parties agree mould was present at the property
The FSP ‟s appointed mould specialist (KA) confirmed mould was present in the
home after the water leak, and obtained samples for independent testing laboratory,
ML, to identify the type and extent. KA then undertook mould remediation work to the
building and contents, providing remediation certificates dated 17 August 2017. KA
Case No: 493976 Determination Page 3 of 10
suggests some staining was left after the mould was removed, but maintained the
mould was dead.
The applicant, however, was not satisfied the mould had been fully removed. He
obtained a report from his expert, IP , following an inspection on 6 October 2017 and
samples being sent to ML for testing. The ML findings confirmed the presence of
mould in the kitchen subfloor area. ML concluded that the property required further
remediation by an accredited expert, using methods in accordance with the relevant
mould remediation standards (IICRC s520), as well as re-testing after the further
remediation to verify the outcome. At its inspection, IP also noted the property had a
peculiar odour, which could not be definitively identified, but which might be
attributable to the mould.
IP recommended containing, removing and disposing of the entire kitchen area,
including cabinetry and flooring. IP also said that after the demolition, and prior to
reconstruction, additional air monitoring would need to be carried out to determine if
the removal of floor and cabinets had removed the source of the mould and the
potential for „off gassing‟. IP went on to point out that if the problem still existed after
that work, then a specific remediation programme would need to be developed. At
that stage (but subject to the results of the air monitoring), IP did not feel all floors
throughout the property needed to be removed.
In that initial report, IP did not directly comment on the appropriateness or otherwise
of the mould remediation methods undertaken by KA. Subsequently, however, IP did
provide an email to the applicant which specifically said:
„The remediation process completed by the previous contractor [KA] would be considered
inadequate based on the results achieved, especially when referenced to the IICRC
methodology in the S520‟.
FSP scope of works for identified repairs covers IP’s re commendations
The FSP provided a scope of works which was prepared and costed by its builder
(JP), dated 3 August 2017. An excerpt from the JP scope is included in section 3.2
below.
The scope provided for repair/reinstatement works, including proposed carpentry and
cabinet-making in the bedrooms and hallway. The JP scope also included the
removal and replacement of floating and timber flooring, as well as removal and
replacement of cabinetry.
Having considered JP‟s scope of works and the IP recommendation s, I am satisfied
JP‟s scope reasonably covers the necessary basic reinstatement works, including the
mould-related component as identified in the IP report, at that point in time.
However, in an email provided by the applicant, the FSP had given him a general
guideline as to the steps involved in carrying out the initial mould remediation works.
It was indicated that a final inspection by a hygienist would be carried out after the
remediation process to confirm mould had been cleared; as well, it was noted that JP
would conduct a re- inspection to „rescope damages [sic]‟ after the remediation
Case No: 493976 Determination Page 4 of 10
process was completed. It is not clear, on the evidence, that either of these steps
was taken.
In any case, I consider the fact of the inclusion of these steps in the outline of what
might reasonably be expected to occur, itself leaves open the possibility of further
mould remediation being needed, and further damage being identified – as does IP‟s
report.
Fair that FSP ’s settlement for repair be increased
I have seen nothing to suggest JP‟s initial scope or related costing (which includes a
reasonable builder‟s margin) were unreasonable or inappropriate, so I accept that
$57,265.03, including GST, for reinstatement work, is a fair reflection of the cost to
the FSP of the necessary repairs identified at the time.
The FSP also offered and paid the applicant $2,800 for temporary accommodation,
to cover a repair period of eight weeks at $700 per week. The policy provides that the
costs of alternative accommodation are payable if the home is damaged (as a result
of an incident covered under the policy) and the insured is not able to live in it as a
result. On the basis of the works proposed by JP, the applicant would not reasonably
be able to live in the property while reinstatement occurs. I have seen nothing to
indicate the reinstatement works originally identified would reasonably take longer
than that.
However, given that I consider that further mould remediation should be carried out
(as explained below), the settlement for temporary accommodation should be
increased by a further 4 weeks. This is to cater for the time reasonably likely to be
needed to obtain a new quote and complete the mould remediation, including any
additional air monitoring and final inspection/confirmation of its effectiveness.
As well, I consider it fair in the circumstances that the cash settlement component for
the repair work itself should be increased from the $57,265 already paid to the
applicant. That is because, in calculating an appropriate cash settlement amount, it is
necessary to consider all reasonable factors . Those factors would include whether
the cash settlement will adequately ensure the applicant himself is able to properly
complete all repairs, as well as allowing for contingencies such as unidentified
additional damage, or anything further arising from a post- mould remediation „re -
scope‟ (as suggested by the FSP in the email referred to above) . That also takes
account of the fact that, with a cash settlement, the risk associated with the work
passes to the applicant, who no longer has the benefit of the FSP‟s lifetime
guarantee for the repairs. On that basis, I consider the FSP should pay a further
$8,500 in respect of the repair/reinstatement component of the cash settlement.
Parties to contribute to further mould remediation works
KA certified that as at 17 August 2017, the property had undergone successful mould
remediation. However, it is relevant that the area where mould was subsequently
identified by IP (the kitchen subfloor area) is the same area previously treated by KA,
and the mould IP identified is of the same genus as that which KA was said to have
eradicated. It is also not clear that a subsequent inspection was conducted after the
remediation to confirm its effectiveness.
Case No: 493976 Determination Page 5 of 10
The FSP says it offered to conduct repairs on 18 August 2017, and again through its
internal dispute resolution review on 1 September 2017. The FSP says that had
repairs been undertaken by the FSP, or privately by the applicant at that time, the
mould concerns would be a non-issue.
I appreciate that the delays in dealing with repairs after the initial mould remediation
allowed time for the mould to re-appear, and that the applicant did not immediately
attend to repairs when the initial cash settlement was paid to him . However, given the
reported concerns and experience of the applicant and his family that the mould had
not been fully eradicated, I accept it was not unreasonable for the applicant to have
queried and sought confirmation of the effectiveness of the mould remediation, and
for repairs to have been delayed on that basis – particularly since the findings of IP
and ML after the subsequent testing indicate the applicant‟s concerns were justified.
In the circumstances, I consider it fair that the FSP contributes 70% towards the cost
of further mould remediation works at the property (including GST and margins).
Because of the doubt about the effectiveness of KA‟s treatment, and the risk of
possible serious health impacts of any continuing mould, I consider it fair and
reasonable and appropriate that the further remediation should apply to both t he
building and contents.
The FSP is to promptly obtain a quotation for mould remediation works from an
accredited mould remediation expert other than KA, and the applicant will need to
cooperate in allowing appropriate access to the property for this purpose. This expert
must confirm they will undertake the works at the proposed cost privately for the
applicant, and should also clearly indicate the steps involved and the expected
realistic time that will be needed to carry out all aspects of the remediation work
(including any additional air monitoring and final checks).
2.2 Is the applicant entitled to compensation?
FOS may award compensation in certain circumstances
Under paragraph 9.3(b) of the Terms of Reference, FOS may award compensation
(capped at $3,000) for non-financial loss. FOS may decide an FSP should
compensate an applicant for such loss only where there has been an unusual
amount of physical inconvenience, time taken to resolve a situation, or interference
with the applicant‟s expectation of en joyment or peace of mind.
Compensation is not awarded for punitive purposes, but to compensate the applicant
for their particular experience , given the FSP‟s handling of the claim.
Compensation is warranted in this case
I have considered the available material, and am satisfied of the following dates and
key points:
Date Key point
6 - 04 - 17 Clam lodged for leaking pipe
Case No: 493976 Determination Page 6 of 10
21 - 04 - 17 JP estimator attends property
8 - 05 - 17 JP identifies further information required about scope and
measurements
9 - 05 - 17 JP estimator re - attends property
23 - 05 - 17 FSP accepts JP estimate and authorises repairs
29 - 05 - 17 Applicant raises mould concerns with FSP
1 - 06 - 17 Mould testing conducted by another firm
9 - 06 - 17 JP appoints new trades after trades initially appointed request
removal from job
10 - 07 - 17 FSP authorises repairs after receiving revised quote from new trades
18 - 07 - 17 KA attends property to address mould concerns
27 - 07 - 17 KA confirms mould remediation required
17 - 08 - 17 KA issues mould remediation certifica tion
18 - 08 - 17 FSP offers to cash settle claim based on JP scope and quotation
21 - 08 - 17 KA states it is unable to remove dead mould under floor but confirms
spores are dead, and a smell in the building results from being
closed up for months
1 - 09 - 17 FSP offers to repair or cash settle, says it will cash settle if it does
not receive an authority by 18 - 09 - 17
21 - 09 - 17 FSP issues cash settlement via electronic funds transfer
Having carefully considered the material, I accept it was appropriate for the FSP to
obtain a mould specialist report to assist in determining whether mould was at the
property, and the appropriate method of treatment. I accept the FSP was not aware
of the presence of mould until such time as the applicant first alerted the FSP to this
concern.
I am satisfied the time between KA‟s initial attendance (18 July 2017), providing its
report confirming the presence and type of mould (27 July 2017) and attending to
treatment at the property (17 August 2017) is within acceptable industry standard.
I also note the FSP offered to conduct repairs on a number of occasions, and (as it
was entitled to do) ultimately issued cash settlement based on the previously
identified required repairs.
Case No: 493976 Determination Page 7 of 10
However, the applicant‟s queries about the quality and effectiveness of the mould
remediation work carried out by KA appear to have been justified. Notwithstanding
any delay by the applicant in effecting repairs after the cash settlement was made
and the mould issues were first looked at, I consider it fair that the FSP pay $1,000
compensation for the significant upset and inconvenience caused to the applicant,
his understandable concern about the health and well-being of his family, and the
disruption to their living circumstances while this has been addressed.
Case No: 493976 Determination Page 8 of 10
3 Supporting information
3.1 Expert reports
Record Key points
FSP’s expert ( KA )
Report
18 - 07 - 17
„We attended site on the 18/ 07 / 2017 …
The Flooring and frames were soaked. Today the area is dry but clear
evidence of Mould can be found wit h in the home and under the
floor b o ards.
[…]
From the evidence of site and the particle counts I believe there is Mould
in the home and certainly on the underside of the floorboards which
requires treatment.‟ [sic]
FSP’s expert ( KA )
Report
27 - 07 - 1 7
„As per [ML] results from samples taken from site, mould is present at
the property. Results show, as per our original report that the mould is
predominately on the underside of the floorboards. The chart below
shows that it mould is elevated in the hall way subfloor.‟ [sic]
FSP’s expert ( KA )
Report
29 - 08 - 17
„We attended site on the 15 – 17th Aug 2017 … to perform Mould
Remediation to the home following our previous visit which established
the presence of, and extent of Mould within and under the Home.
On arrival, we met with [applicant] where we explained the process and
timings of the remediation. [Applicant] did ask us how we could get
Mould out of wood as he believed it was within the wood itself. I
explained the Mould could not live within the wood as he believed it
needed Oxygen to live however, any Mould on the surfaces would be
treated. Further I ex plained we would be running Ozone throughout &
under the property and once we finish they would be able to smell the
remnants for a day or so as the home was and would be shut up. […]
We performed the remediation which included running Ozone with in the
Home, Ozone doesn‟t kill Mould but rather Bacteria etc. which Mould
may be living on. We then crawled under the floor boards and cleaned
off any Mould we c ould see using scrubbers etc. Any Mould missed
would not be an issue as the treatment will kill all Mould any way. Finally,
and most importantly we then treated the underside and then internal
areas of the Home with Fresche. This product adheres to all surf aces
and kills any Moulds & Bacteria‟s as they come into cont act with the
surfaces. The Kill is Mechanical Not Chemical which makes the
treatment Hyper Allergenic. It is an ongoing treatment as well that would
last many more months. Further we left for the ir use a bottle of surface
spray which they could use just once a week on their Bench tops […].
On completion, we performed another Las er Particle Count Test… From
the …res ults… I am confident there are no abnormal levels of Mould
within the property.
Applicant’s expert (IP)
Report
26 - 10 - 17
„[IP] was requested to attend the site following concerns of the home
owner regarding the presence of mould following an Escape of Liquid
(EoL) event. The property had been remediated for mould by another
Case No: 493976 Determination Page 9 of 10
company who certified the property as clear of mould but undertook no
post re - mediation testing.
The home owners are concerned that mould is still present and are
experiencing health impacts which they feel may be from the mould .. .
[ The home owners ] along with the c hildren have since started living in a
caravan at the rear of the property but need to access the house from
time to time to use toilets and bathroom.
[…]
[ IP ] attended the property on the 6t h of October to carry out the
inspection and obtain mould swab sampling for further testing.
[ IP ] sent our samples to [ML] i n Sydney for culturing and analysis. The
report from [ML] alerted us to positive readings in the kitchen, under the
floor and the back side of the floor coverings. Other tests taken from
areas w ithin the hallway indicate that there is … well below minimum
acceptable standards for indoor environmental health standards.
[…]
The type of mould indicated on the results from [ML] are “Penicillium”,
this is a commonly found species of mould and can be pat hogenic when
found in large volumes as indicated by the test results.
Scope of Works
Based upon our investigation and the mould sampling results we
recommend that once appropriate cont ainment be installed and the
entire kitchen area be stripped out this includes flooring and kitchen
cabinetry removed and disposed from site.
… we will als o install HEPA filters to control and assist in removing
airborne particles and reduce the potential for spreading or cross
contamination of mould.
Applicant’s expert ( IP)
Email
30 - 11 - 17
The remediation process completed by the previous contractor [KA]
would be considered inadequate based on the results achieved,
especially when referenced to the IICRC methodology in the S520.
…there is an unknown contaminant in the property which may or may
not relat e to the insured‟s event. the only way for this to be determined is
for an indoor air monitoring program to be established.
3.2 Excerpt JP Scope of Works dated 3 August 2017
TRAD E SUMMARY DESCRIPTION OF WORKS
KITCHEN at 3.7x4.3x2.4 METRES
Carpenter Remove skirting boards and door architraves and dispose of.
Cabinet Maker Remove and replace cabinetry in full, including base cabinets
and associated benchtops, to best matching existing.
Case No: 493976 Determination Page 10 of 10
Materials for above description.
Carpenter Remove and dispose of floating timber flooring at
approximately 16sq metres.
Remove solid timber flooring at approximately 16sq met res.
Inspect and report on condition of subfloor area.
Timber Flooring Supply and install new solid timber flooring (Jarrah) to
subfloor area at approximately 16sq metres to best match
existing (PC Allowance at $90.00 per sq metres – supply
only).
Materials for above description.
Prepare flooring area for new floating timber flooring.
Supply and install new floating timber flooring, including
underlay to best match existing at approximately 16sq
metres.
Materials for above description.
Carpenter Supply and install new door architraves and skirting boards
to best mat ch existing at approximately 20 lineal metres.
Materials for above description.
Painter Prepare and paint new skirting boards, door archit raves and
door jambs to best match existing.
Materials for above description