Home / Financial Firm (Unknown - Insurer) / Determination 493115

Determination 493115

Claim handling delay, waived excess and medical expenses after kitchen water damage

FirmFinancial Firm (Unknown - Insurer)
Decided2018-03-16
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$500
Non-financial loss$1,500
Amount claimed—
SourceAFCA PDF

Summary

The applicant's home insurer accepted a kitchen water damage claim but delayed reimbursing tile costs and did not honour a withdrawn excess waiver. AFCA ordered the $500 excess waived, interest on the tile payment, and $1,500 non-financial loss, and refused the medical expenses.

The FSP's excess waiver offer was not clearly stated as withdrawable, and the policy excludes consequential loss such as medical expenses from mould exposure.

Issues

Subjects and remedies

health or medicalpay claimpay interestpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 493115 Determination Page 1 of 4 Case number: 493115 8 March 2018 1 Overview 1.1 Dispute This dispute arises from a claim for water damage to the applicant’s kitchen. The applicant holds a home insurance policy (Policy) issued by the financial services provider (FSP). The applicant lodged the claim for damage to the kitchen. The claim was accepted. The applicant remains dissatisfied with the way the claim has been handled. 1.2 Issues and key findings Is the applicant entitled to reimbursement of excess and other expenses? The FSP agreed to waive the excess and reimburse the cost of the tiles. Therefore the applicant is entitled to the $500 excess and interest on the payment for the tiles . As the Policy excludes compensation for consequential loss, the FSP is not liable to pay the claimed medical expenses. Is the applicant entitled to compensation for non-financial loss? The FSP unreasonable delayed the claim and caused the applicant an unusual degree of stress and inconvenience. In accordance with FOS’s approach to compensation for non-financial loss the applicant is entitled to $1,500 compensatio n. Does the FSP need to provide the applicant with the claim file? The FSP has complied with FOS’s requests for information and need not provide any further information. 1.3 Determination This determination is partially in favour of the applicant. Within 14 days of the applicant’s acceptance of this determination the FSP must:  waive the excess of $500 (if excess has been paid the FSP must reimburse the applicant)  pay interest on the $110.00 payment for the tiles in accordance with section 57 of the Insurance Contracts Act , and  pay $1,500 compensation for non-financial loss. Case No: 493115 Determination Page 2 of 4 2 Reasons for determination 2.1 Is the applicant entitled to reimbursement of excess and other expenses? The FSP agreed to waive the excess and should honour the offer Based on the information provided I am satisfied that the FSP agreed to waive the $500 excess. On 8 September 2017 the FSP wrote: As per my discussion, I am happy to waive the excess of $500 due to the inconvenience that you have been through and it is your decision whether to accept this offer. The applicant did not accept this offer. Since this offer was made and rejected the FSP has allowed other items. However, I am not satisfied that allowing other items means that the offer to waive the excess should not be honoured. This is because the FSP did not explain the terms and conditions of the offer. For example, the applicant was not told:  the offer would be withdrawn if it was not accepted, or  whether the offer was in full in final settlement of all claims. It is fair in all the circumstances that the offer be reinstated and the $500 excess waived. The FSP unreasonably delayed reimbursing the cost of the tiles Based on the information available the FSP was, or should have been aware, that the builder asked the applicant to pay for the splashback tiles and agreed to reimburse this cost. The applicant requested reimbursement of this cost on several occasions. The FSP unreasonably delayed the payment which was not made until 21 February 2018. The applicant is entitled to interest in accordance with section 57 of the Insurance Contracts Act from the date the applicant purchased the tiles until 21 February 2018. The applicant’s medical expenses are excluded under the Policy There is no dispute that the applicant’s home needed to be treated to eradicate mould that was a result of the water damage. The applicant says that the mould exacerbated an underlying medical condition. He provided a medical report from his General Practitioner dated 18 November 2017 that states: [The applicant’s] asthma is usually well controlled and I believe these exacerbated asthma attacks and acute infection may be related to his immediate environmental exposure to mould and dampness. I accept that the applican t’s symptoms were on balance made worse by the mould. I therefore consider this to be a consequential loss. The Operational Guidelines to the FOS Terms of Reference explains that: Case No: 493115 Determination Page 3 of 4 Direct losses are losses, such as out of pocket expenses or other liabilities, which are caused directly as a result of the FSP’s conduct. Consequential losses are losses which are indirectly caused by the FSP’s conduct. Whether a loss is a direct, or a consequential (indirect), loss will be considered on a case by case basis and will depend on all of the circumstances of the Dispute. The Policy expressly excludes compensation for consequential losses and will not pay for: loss of profit or consequential loss of any kind The FSP can rely on the general exclusion for co nsequential loss and is not liable for the applicant’s medical expenses. 2.2 Is the applicant entitled to compensation for non-financial loss? FOS can award compensation for poor management of a claim FOS’s approach to compensation for non -financial loss was outlined in the preliminary view (PV). An amount of $1500 compensation was recommended in the PV and this recommendation was accepted by the FSP. I agree with the explanation of the approach provided in the preliminary view and add that FOS can compensate an applicant for non- financial loss arising from the FSP’s poor management of the claim. When doing so, FOS considers the severity and impact of the F SP’s conduct on the particular applicant. The applicant remains dissatisfied with the FSP’s handling of the claim. Based on the information available I am satisfied that the applicant co -operated with the FSP and acted reasonably throughout. The FSP has not provided any explanation as to why the repairs were delayed. Based on the information provided, I accept the FSP caused an unusual degree of inconvenience to the applicant. In all of the circumstances, and considering previous awards of compensation, the applicant is entitled to $1,500 in compensation for non- financial loss. 2.3 Does the FSP need to provide the applicant with the claim file? All of the information provided by the parties has been exchanged On 17 October 2017 the FSP provided FOS with a Notice of Response including the information that it based its claim decision on including the claim file notes. On 19 October 2017 the applicant requested that the FSP provide him with all file notes in relation to the claim. He wrote: Please note that we wish to action this, and formally request all documentation pertaining to our claim that you used and relied upon in the assessment of the said claim. FOS’s powers are limited to the Terms of Reference (TOR), which does not allow FOS to subpoena documents or compel an FSP to provide documents if it does not wish to do so. The TOR does however allow FOS to draw adverse inferences against Case No: 493115 Determination Page 4 of 4 an FSP when it chooses not to provide documents in accordance with FOS’s request. I am satisfied that the FSP provided the information FOS requested and complied with paragraph 7.2 of the TOR. This information was exchanged with the applicant. As the requirements for the provision and exchange of information under the TOR have been met, any further request by FOS for information is not reasonable.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.