Text of the determination
Determination
Case No: 491856 Determination Page 1 of 9
Case number: 491856 23 January 2018
1 Overview
1.1 Dispute
The applicant lodged a claim with the financial services provider (FSP) in 2012 for
damage to several sections of the property due to escape of water from pipes/drains.
In June 2016, this Service determined the applicant’s dispute with settlement of the
claim partially in favour of the applicant.
The parties have requested this Service issue an addendum determination on the
FSP’s claim s ettlement options, scope of work and cash settlement amount, as they
disagree on how the final part of the claim should be settled.
The FSP’s builder (BBG) refused to complete the final repairs to the insured property,
as the applicant refused to construct drainage works pre-repairs, as suggested by the
engineer (HC), appointed by the builder. The applicant disagrees as to the extent of
works required. The applicant remains unhappy with the FSP’s cash settlement offer
and prefers that the FSP’s builder cond uct the repairs to the property. She is also
dissatisfied with the F SP’s claim s handling.
1.2 Issues and key findings
Should the FSP’s builder conduct repairs at the insured property?
The FSP’s builder is not obliged to conduct repairs as the applicant failed to comply
with the drainage requirements set out by the engineer HC. It is reasonable the
applicant complies with the engineer’s requirements if the builder is to extend its
repair warranty to the works authorised and completed by it.
Is the FSP’s offer of settlement fair and reasonable?
The FSP’s offer of settlement is not adequate and needs to be increased. Further,
the settlement should also include an allowance for the applicant to be able to
appoint an external builder to conduct repairs and for additional damage that may
occur during repairs. BBG’s current Scope of Works has also missed an item
included in the initial scope of works.
Should the FSP pay compensation?
The FSP’s handling of the claim could have been better. The applicant also
contributed to some delays by revising the scope of works to meet her personal
needs. However, overall there is evidence the applicant suffered stress and
inconvenience as a result. On the other hand, the FSP paid for staining of French
doors and temporary fencing which are not part of the scope of works.
Case No: 491856 Determination Page 2 of 9
1.3 Determination
This determination is substantially in favour of the FSP.
The FSP is:
entitled to cash settle the applicant for the remaining repairs
required to increase its offer of settlement to $50,000
not required to pay compensation for non-financial loss.
Case No: 491856 Determination Page 3 of 9
2 Reasons for determination
2.1 Should the FSP’s builder conduct repairs at the insured property?
FOS determined the initial dispute partially in favour of the applicant
The previous FOS determination was partially in favour of the applicant. The FSP
was required to indemnify the applicant for the following:
damage to the northern courtyard
paving along the rear east side
garage support pillar
garden shed floor
damage to brick work in northeast corner.
It was determined the FSP was entitled to deny the r emaining parts of the applicant’ s
claim.
FSP is entitled to choose to repair or cash settle the claim
The policy allows the FSP to choose the method of claim settlement:
How we settle your buildings claim
We will choose to settle your claim for loss or damage to your home or 'other cover' in
one of the following ways:
1. Arrange for repairers, builders or suppliers to repair or rebuild your home.
If you agree, we can arrange for our preferred repairers, suppliers or builders to repair or
rebuild your home.
2. Pay you the reasonable cost to repair or rebuild your home.
We can choose to:
- pay you
- pay your nominated repairer, supplier or builder, or
- provide you with store credits from one of our nominated suppliers.
The FOS Panel also determined that if the FSP elected to cash settle the applicant,
the settlement should be based on quotes obtained from builders willing to undertake
and guarantee the works. On the basis that quotes were current, no interest was
awarded on the settlement.
FSP now entitled to cash settle the applicant as builder refuses to extend
warranty
The FSP’s builder BBG , appointed engineer HC to assess the scope of works for the
repairs determined under the previous FOS determination. Further, HC also
recommended new drainage plans in order to arrest the inundation issues.
BBG is willing to complete the repairs and offer repair guarantee only in the event the
applicant installs drainage and pits around the perimeter of the home building, to
prevent water from pooling around the building due to the slope of the insured’s and
neighbouring properties.
Case No: 491856 Determination Page 4 of 9
The applicant preferred that the FSP’s builder perform repairs so that the BBG’s
repair guarantee will be extended to the repair works performed. However , she
remains unhappy with the drainage plans suggested by HC and says they are
excessive, extensive, of an industrial type and not suitable for a home and would
impact the aesthetic appearance of the property.
She also says it would not be feasible to have pits dug at the front of property due to
the presence of gum trees adjacent, which would add to blockages in the future.
At the FSP’s request, the applicant provided her own engineer’s drainage plans.
These were further assessed by BBG and they now recommend the applicant
completes both HC’s and her own engineer’s drainage plans, if she wishes for BBG
to complete the repairs.
Considering the extent of previous water damage sustained to the property, the
location of the property and the sources of water entry, the panel is satisfied the
builder is not obliged to complete the repairs and extend warranty, if the applicant is
not willing to comply with the drainage works suggested by HC.
Further, the panel accepts the FSP is not able to compel its builder to provide
warranty on repairs when the builder has sought expert advice before requesting the
applicant complete drainage works.
The applicant herself has said that she has found it difficult to get builders to quote
on the repairs due to the type, structure and location of the property. The FSP’s
builder is therefore entitled to seek expert opinion and rely on HC’s findings before it
commits to repairing the applicant’s property and offering a guarantee on repairs.
Furthermore, the FSP can only suggest and ca nnot compel the applicant to complete
the drainage works. As the applicant is not willing to satisfy the pre-repair drainage
requirements, the FSP is entitled to offer a cash settlement instead of taking the
repair option.
2.2 Is the FSP’s offer of settlement fair and reasonable?
BBG’s initial quote did not include builder’s margin and certain allowances
Based on the initial scope of works prepared by HC, BBG prepared a quote for repair
works as follows:
Carport - 6.00 m x 6.00 m x 2.50 m
Among other works this included ‘ As per engineers scope of works/ Reference
# xxx: Allowance made for plumber to check and attempt to re-align the existing
eave gutter. A supplementary scope of works and estimate/quotation to follow if
additional works are required.
As per engineers scope of works/ Reference # xxx: Carefully demolish, clean
and store for re-use brickwork to south/west brick pier of carport (475mm X
375mm X 2560mm high. Re-use existing footing. A supplementary scope of
works and estimate/quotation to follow if replacement of the footing and/or
bricks are required.
Rear North East Corner of Main Dwelling - 8.50 m x 0.20 m x 2.50m
Case No: 491856 Determination Page 5 of 9
No allowance made for removal or disposal of asbestos material. A
supplementary scope of works and estimate/quotation to follow if necessary.
Paving to Eastern Elevation: rear of main dwelling - 10.70 m x 1.00 m x
0.10 m
Rear Garden Shed - 2.50 m x 3.00 m x 2.20 m
External Stenciled Concrete to Courtyard. - 6.70 m x 3.90 m x 0.10 m
Additional Notes
- No allowance has been made for fees/ permits or works associated with
upgrading. A supplementary scope of works and estimate/quotation to follow if
necessary.
- No allowance has been made for the removal, store or re-positioning of
contents (carport/shed). This will need to be undertaken by the insured prior to
commencing any repairs.
- No allowance has been made for replacement or stabilisation of the footings to
the carport and/or rear brick work (north/east corner). A supplementary scope of
works and estimate/quotation to follow if required.
The total estimate of material and labour was $25,287.63 with GST.
In December 2016, the FSP estimated paver repairs at $8,067.40 on the following
basis:
Rear of dwelling
Lift existing pavers, store on site for re-laying. Prepare substrate, including
supply of new sand base as required. Re-lay existing pavers. Total area
approximately 10.7 m2. ($1,450.00+ GST)
Garden Shed
Lift existing pavers to internal area only, store on site for re-laying. Prepare
substrate, including supply of new sand base as required. Re-lay existing
pavers. Total area approximately 7.5 m2. ($900.00 + GST)
Courtyard
Remove, dispose of, supply and install new stenciled concrete to courtyard,
area approximately 28 m2 x 100mm. Note: Demolition and installation to be
undertaken by hand and wheel barrow. ($4,984.00 + GST)
Total settlement $8,067.40 including GST.
However, it also carried the following warning:
As the soil conditions were unstable, despite the applicant undertaking repairs
to the mains infrastructure, there was ongoing ground moisture affect on the
pavers and paving.
They were unable to relay the pavers by sand re-bedding alone and suggested
an impermeable base particularly concrete paving base instead of the sand
bed.
Further, they also suggested a specialised structural remediation to the rear
corner of the home also required additional removal of paving and repalcement
in the same way.
It appears the above was a recommendation rather than a requirement under any
buidling code. However, the final quote discussed below includes a concrete base.
Case No: 491856 Determination Page 6 of 9
Certain items in scope of works increased by FOS
The applicant requested FOS review the area of scope of works prepared by the
FSP, including BBG’s repair methods suggested.
In February 2017, FOS clarified the following:
Garden shed – The FSP should ensure that all pavers associated with the
garden shed are level right across the area as it is a continuous surface.
Paving adjacent to northern courtyard – This area was blacked out in a map for
the FSP’s easy reference. The FSP wa s to include this area to the current
scope of works and was entitled to cash settle the applicant for this part of the
claim.
Reusing existing footing of carport pillar – The FSP was entitled to reuse the
existing footing if possible. The work was to be completed in accordance with
BBG’s contract.
Fencing – FOS allowed the FSP to assess the applicant’s request for temporary
fencing and the FSP subsequently agreed to include this in its offer of
settlement.
FSP’s current offer of settlement is not adequate
The FSP’s current offer of settlement of total works awarded by FOS amounts to
$31,854.90 . This was based on BBG’s recent quote and also allows $1,400 to test
the soil plus an engineering review of the drainage to be installed by the applicant.
Since the determination, considering the various delays with repairs, the FSP also
agreed to stain the applicant’s French doors and step and make an allowance for
temporary fencing in good faith.
QUOTE 1
Paving
Soil testing and Engineering review of drainage and paving design
(PROVISIONAL SUM $ 1 , 400.00)
Supervision to the works
Garden Shed
Remove and reinstate shed to allow removal of pavers as base plate to
perimeter of garden shed.
Reinstate shed and replace pavers with concrete paving base.
Pathways - North & East
Remove and reinstate pavers to concrete paving base (increase in m2 10.7m2
to 32m2)
QUOTE 1 $10,600.50 (excl builder’s margin and GST)
The panel is not satisfied the above is adequate because:
the FS P’s initial estimate for paving repairs with sand base and not concrete
amounted to over $8,000
Case No: 491856 Determination Page 7 of 9
In February 2017, FOS increased the area of work which would in turn have
increased the area of scope
The external stenciled concrete to courtyard of 6.70 m x 3.90 m x 0.10 (from
initial scope of works in August 16) appears to have disappeared from the
current final scope of works.
Having considered all of these matters, the panel is satisfied that the appropriate
estimated amount for Quote 1, is $16,000.00 (excl margin and GST).
QUOTE 2
Brickwork North East Corner
Structural brick repairs to north east corner of dwelling
Garage Support Pillar
Repairs to garage support pillar
QUOTE 2 $12,262.00
The panel is not satisfied this quote is complete because initially, FOS agreed the
FSP could follow BBG’s scope and attempt to reuse items including existing footings
if possible. The works were to be completed in accordance with the BBG’s contract.
The applicant says she is able to see the footings have already moved. Considering
BBG will not complete the repairs, it is important to allow for any additional works that
may be required under this section.
Having considered all of these matters, the panel is satisfied that the appropriate
estimated amount for Quote 2, is $15,000 (excl margin and GST).
QUOTE 3
French door and step to courtyard
Apply stain to French doors and step to courtyard
QUOTE 3 $1,270.00
The panel notes that the FSP agreed to allow temporary fencing for the duration of
the repairs after considering the applicant’s request in this regard.
The panel is satisfied the following do not need to be included in the scope of works:
Temporary accommodation is not required.
BBG confirms disconnection of the hot water service is not required as the
service is always installed prior to landscaping and concreting works.
Considering all of the above, the panel is not satisfied the FSP’s current offer of
settlement is reasonable. In addition to the issues and concerns noted above, it is
accepted that by cash settling the applicant for the loss, the FSP would also be
transferring its risk associated with offering warranty on repairs to the applicant.
Further, the applicant would need to find an independent builder and that repair
quote may be more than BBG’s estimate.
Case No: 491856 Determination Page 8 of 9
The panel is therefore of the view that it would be fair in all the circumstances for
the FSP’s payment to the applicant to be a total amount of $50,000 (all inclusive of
builder’s mar gin, GST and an allowance for the risk transfer).
The FSP is entitled to deduct any previous payment made to the applicant, in respect
of the above mentioned works.
2.3 Should the FSP pay compensation?
FOS may award compensation for non-financial loss
Under the Terms of Reference, FOS may award compensation (capped at $3,000)
for non-financial loss where an applicant has suffered an unusual degree or extent of
physical inconvenience, time taken to resolve the situation or interference with their
expectation of enjoyment or peace of mind.
However, FOS adopts a conservative approach to the award of compensation for
non-financial loss. FOS expects applicants to be moderately robust and bear the
usual stress and inconvenience associated with an insurance claim.
Upon reviewing the progress of this claim since the FOS determination was issued,
the panel notes that both the applicant and the FSP have delayed the settlement
process.
There were initial delays in the FSP assessing the property and also providing the
applicant with the scope of works prepared by HC and BBG.
On the other hand, the applicant also requested changes to the scope of work,
corresponding directly with the builder and at times without the FSP’s involvement.
As the parties could not resolve the dispute in complying with the previous
determination, the matter was referred to FOS.
Further, the FSP encouraged the applicant to submit her own engineer’s report and
when she did, it wrote to FOS stating the matter should be considered outside of its
Terms of Reference.
Having regard to the time taken to finalise this claim, the panel is satisfied the
applicant would have suffered stress and inconvenience, especially the missed
communication from the builder, FSP and their representatives, change of contact,
etc.
However, in recognising these issues, the FSP agreed to include the staining of the
French door and step and also allow temporary fencing in its scope. Further, the FSP
did attempt to work with the applicant and have its builder complete repairs provided
the applicant installed the drainage as recommended by HC.
The panel is therefore not satisfied the applicant is entitled to a further award of
compensation for non-financial loss.
Case No: 491856 Determination Page 9 of 9
3 Supporting information
FOS approach to this dispute
This dispute has not been the subject of a FOS Recommendation. Due to the nature
of the dispute, it has been referred directly to a Panel for an Addendum
Determination, in line with the Operational Guidelines to the FOS Terms of
Reference. The Panel consists of an Ombudsman and two representatives with
consumer and insurance experience.
The Panel has decided this case on its merits, having regard to the relevant law,
good industry practice, codes of practice and previous Financial Ombudsman
Service (FOS) decisions.
There has been a full exchange of all material information relied on for the purposes
of this Determination and each party has had the opportunity to address any issues
raised by the other.
The Panel has reviewed and considered all of the material provided by the parties.
While the parties have raised numerous issues in their submissions, for the purposes
of this Determination, the Panel has restricted its commentary to those issues that it
considers directly relevant to the outcome only.
3.1 Product Disclosure Statement
How we settle your buildings claim
We will choose to settle your claim for loss or damage to your home or 'other cover' in
one of the following ways:
1. Arrange for repairers, builders or suppliers to repair or rebuild your home.
If you agree, we can arrange for our preferred repairers, suppliers or builders to repair or
rebuild your home.
2. Pay you the reasonable cost to repair or rebuild your home.
We can choose to:
pay you
pay your nominated repairer, supplier or builder, or
provide you with store credits from one of our nominated suppliers.
For example, we may pay you directly when:
you decide not to repair or rebuild your home, or
you don’t start repairing or rebuilding your home within 6 months from when the
damage takes place, or within any longer period we agreed to in writing.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.