Determination 491694
Cash settlement amount for fire-destroyed home rebuild
Summary
The applicant's home was destroyed by fire and the FSP cash settled the building claim at $272,726.19, the cheapest of four tenders. AFCA found the tenders and reduced scope unsubstantiated and ordered a further $62,507.96, the midpoint between the tender average and the applicant's rebuild invoice.
A cash settlement must have a reasonable and substantiated basis, and without the tenders the FSP could not show the amount was fair.
Issues
- Claim amount dispute primary · upheld
“The FSP have provided unconfirmed tender amounts as the basis of the cash settlement, and the tenders were based on a reduced scope which the FSP have failed to justify.”
- Poor claim handling secondary · upheld
“The FSP cannot provide the tenders to substantiate on what basis that rebuild cost was calculated.”
Subjects and remedies
home or building damagepay claim
Text of the determination
Determination
Case No: 491694 Determination Page 1 of 5
Case number: 491694 7 May 2018
1 Overview
1.1 Dispute
The applicant lodged a claim for a house fire with the financial services provider
(FSP). This claim was accepted and settled via cash settlement for both the contents
and building.
The applicant disputes the amount of the building settlement, stating that the amount
paid is incorrect. He seeks an increase in the settlement amount based on his rebuild
quote.
1.2 Issue and key finding
Is the F SP’s settlement fair in the circumstances ?
The FSP have provided unconfirmed tender amounts as the basis of the cash
settlement to the applicant. Further, these tenders were based on a reduced scope
which the FSP have failed to justify.
The applicant’s re build invoice is for a home which contains six bedrooms, where the
original home contained five.
Based on the limited evidence provided by both parties, the midpoint between the
average of the tenders and the applicant’s provided rebuild invoice should be
preferred.
1.3 Determination
This determination is substantially in favour of the applicant.
The FSP are required to increase the settlement to the midpoint between the tender
average and the applicant ’ s rebuild invoice.
The FSP are required to pay the applicant an additional amount of $62,507.96 to
finalise its obligations in respect of this claim.
Case No: 491694 Determination Page 2 of 5
2 Reasons for determination
2.1 Is the FSP’s settlement fair in the circumstances?
FSP cash settled on basis of tender
The applicant’s claim for fire damage to their home was accepted by the FSP. The
FSP cash settled the applicant for the loss based on the cheapest of a series of
tenders received by the FSP’s agent , the loss adjuster appointed to the claim.
The FSP says it received four tenders for the rebuild costs as follows:
Builder A: $312,791.11
Builder C: $272,726.19
Builder J: $385,189.19
Builder L: $305,258.71
The FSP settled the applicant on the basis of the cheapest of these tenders.
The FSP cannot provide the tenders to substantiate on what basis that rebuild cost
was calculated, nor does the FSP ever appear to have had this information.
The FSP says that the applicant was cash settled and chose not to proceed with the
builders who tendered and thus the issue of whether the builder would have
proceeded with the rebuild is irrelevant.
The Service does not accept the FSP’s submission in this regard. Whether the
builder would be prepared to action a tender or quote, is a matter relevant to the
question of whether a cash settlement is reasonable.
Further, the basis of and information related to, the tender, is also a matter relevant
to the question of whether a cash settlement is reasonable.
The FSP’s technical loss adjust or has provided an explanation as to the method of
generating these tenders, however, without the tenders to review, the method is
unclear and the FSP have failed to show that the cash settlement amount was fair in
the circumstances, or that it is based on an actionable quote.
Whilst the Service accepts that the FSP is entitled to cash settle in the circumstances
of this dispute, the FSP is to provide a reasonable basis for any cash settlement.
The absence of the tenders creates a significant difficulty for the FSP in establishing
the reasonableness of its cash settlement basis.
Applicant provided quote for six bedroom rebuild
The applicant’s home that was destroyed by fire was , at the time of the original build,
a three bedroom home. The downstairs of this home had been converted to include
two extra bedrooms and an extra living space.
The applicant has provided limited information on the scope for the rebuild of their
property. The information available shows that the new build will have six bedrooms,
Case No: 491694 Determination Page 3 of 5
a kitchen, bathrooms and a living space downstairs. The plans and agreement
provided by the applicant is missing key sections, including the design for the
upstairs to show the number of living areas and bathrooms and the total square
meterage involved in the rebuild agreement.
The building agreement supplied shows that the new home rebuild costs a total of
$351,477. I am not satisfied on the limited information provided that the quote shows
a rebuild in line with the original damaged home, due to the extra bedroom.
FSP contests the applicant ’s quote
The FSP have contested the applicant ’ s rebuild quote on the basis that it does not
show a rebuild on a like for like basis. The FSP’s assessor has outlined that in his
opinion the downstairs area of the original home, while used for two bedrooms and a
living area, was not up to building code due to a number of factors.
The FSP assert that on this basis the rooms downstairs do not need to be included in
the rebuild quote and subsequently brought to code, as the installation of rooms that
meet code would result in betterment to the applicant.
The FSP have referred to elements of the building not meeting relevant codes,
however, have failed to provide evidence to support these statements. The
statements were made by the FSP’s assessor who is also a qualified carpenter. No
photographic evidence showing the issues noted by the FSP, or evidence of the
relevant codes related to these reported issues have been supplied, to show how the
assessor came to this conclusion.
The FSP have cash settled the applicant on the basis of a tender for replacement of
only the upstairs portion of the original home on this basis. As the FSP have failed to
show the downstairs area was not built to code, they have failed to demonstrate the
basis for this reduction.
Original settlement not based on fair quote
The applicant’s provided documents do not show the full scope of the rebuild
proposed and appears to include an extra bedroom. The invoice provided by the
applicant is, however, actionable and represents an actual rebuild cost under the
building sum insured.
The FSP have submitted four tender amounts as the cost of rebuild without any
supporting information beyond a formula for calculation apparently used as a basis
for the tenders. The FSP are unable to provide any further information on these
tenders and have no evidence of an actionable quote. Further the tenders provided
are based on only the upstairs of the home, despite a failure to show the reasons for
this reduction.
On the basis of the above, it is fair in the circumstances that the applicant’s
settlement be increased, although not to the point of the new quote, which is for a
build with an extra bedroom.
The average of the four FSP tenders is a total of $318,991.30. The cost of the
applicant ’ s rebuild invoice is $351,477. It is fair in the circumstances that the FSP
settle the applicant the average of the tenders presented and split the difference
between the applicant’s rebuild cost and the average of the tenders to ensure the
Case No: 491694 Determination Page 4 of 5
applicant is only settled for the five pre-existing bedrooms, rather than six. The
difference between the average and the applicant ’ s rebuild quote is $32,485.70.
The FSP are required to settle the applicant the difference between the prior settled
amount for rebuild ($272,726.19) and the midpoint between the tender average and
the applicant’s quote ($335,234.15) being a total of $62,507.96 above the prior cash
settlement amount. As the applicant ’ s quote is current there is no requirement to pay
interest on this amount.
Case No: 491694 Determination Page 5 of 5
3 Supporting information
3.1 Key references
Record Key points
Home and Contents
PDS
Page 67 & 68
What we pay for your home
Reductions we may apply
We may reduce the amount we pay you to allow for age,
wear, tear and the condition of your home. If we do that, then
the final amount we pay you will reflect the actual value of
your home immediately before the loss or damage happened.
We may reduc e your payment in these cases:
• your home was not in a sound condition or was not well
m aintained when the loss or damage happened
• if you rent the home to tenants and the floor carpets that
were damaged were over 10 years old
• any part of your home did not comply with relevant building
laws when it was originally built.