The applicant's home insurance claim for February 2015 storm water inundation was declined by the FSP under the defective works exclusion. AFCA found defective construction was the proximate cause and ordered nothing.

The proximate cause of a loss is the effective or dominant cause, and the FSP showed on the balance of probabilities that defective works excluded under the policy caused the damage.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 491606 Determination Page 1 of 5 Case number: 491606 28 May 2018 1 Overview 1.1 Dispute The applicant lodged a claim under his home insurance policy with the financial services provider (FSP) after his property was inundated with water following storms in February 2015. The FSP denied the claim on the basis that the damage to the applicant’s property had not been caused by the storm but by factors which are excluded under the policy, such as design and construction defects and water seepage . The applicant has been compensated for some of the damage to his home under a rectification process managed by the Queensland Building and Construction Commission (QBCC). However, the applicant seeks cover from the FSP for the cost of additional repairs and temporary accommodation costs incurred as a result of the damage to his property. 1.2 Issues and key findings Is the FSP liable for the applicant’s claim ? The available information establishes that the proximate cause of the damage to the applicant’s property was defective design and construction, rather than the storm in February 2015 (or any other event insured against under the policy). In addition to the issues identifi ed by the FSP’s engineer (CS), t he QBCC complaint process identified additional defects with the works carried out by the original builder of the applicant’s property. The remediation ordered by QBCC included waterproofing of the concrete slab to prevent further water entry) . The policy excludes cover for damage caused by defective works. Accordingly, the FSP is not liable for the damage to the applicant’s property or any additional costs incurred as a result. 1.3 Determination This determination is in favour of the FSP. The FSP is not liable for the applicant’s claim . Case No: 491606 Determination Page 2 of 5 2 Reasons for determination 2.1 Is the FSP liable for the applicant’s claim? Applicant has established a prima facie claim The applicant is required to show that, on the balance of probabilities, he has suffered a loss caused by a risk insured against under the policy. This is known as a prima facie claim. If the applicant is able to establish a prima facie claim, then the onus shifts to the FSP to show that, on the balance of probabilities, it is entitled to rely on an exclusion under the policy or is otherwise entitled to deny the claim. The a pplicant’ s policy provides cover for damage caused by the events listed in the policy, including the insured event of storm. The policy also provides cover for accidental damage, being damage which happens by chance and is not expected in the ordinary course of events. The applicant lodged a claim after water inundated the lower level of his property, following storms associated with ex-tropical cyclone Marcia in February 2015. Water had previously entered the garage during heavy rainfall in January 2015, but did not cause any damage at that time. Prior to the incident in January 2015, the property had not experienced any water entry issues since the applicant purchased it in September 2013. It appears that the onset of water entry issues coincided with the start of construction on the neighbouring site. Based on the available information, I am satisfied that the applicant has established a prima facie claim under the policy. Even if the damage was not caused by a storm (as the FSP suggests), the applicant would have a prima facie claim for accidental damage. In these circumstances, the FSP is required to show that, on the balance of probabilities, it is entitled to rely on a policy exclusion to deny the applicant’s claim. FSP says damage was caused by faulty design or construction The FSP says it is not liable for the claim because the proximate cause of the water damage to the applicant’s property was not the storm in February 2015, but factors which are excluded under the policy. In particular, the FSP seeks to rely on the general exclusion for damage caused by or defects in design, structure, materials, workmanship or construction. The FSP says the proximate cause of the water entry was defective works carried out by contractors at the applicant’s and his neighbour’s property. The FSP wi ll only be entitled to deny the applicant’s claim if it can show that, on the balance of probabilities, the proximate cause of the loss is defective works. Case No: 491606 Determination Page 3 of 5 It is well established at law that the proximate cause of a loss is not necessarily the first (or the last) or the sole cause of the loss. It is the effective or dominant or operative cause. In any particular case, the proximate cause of the loss is a question of fact to be determined based on the surrounding circumstances. Where there are several causes operating, each must be examined for the qualities of predominance and efficacy in relation to the resultant damage. FSP’s engineer has advised damage was caused by defective works The engineer (CS) appointed by the FSP concluded that the primary cause of the inundation of the applicant’s property was alterations to the sewer main located under the property, in connection with works undertaken at the neighbouring site. In his report, CS advised that:  the existing sewer main was located under the applican t’s garage  the concrete footings of the western garage wall of the applicant’s property had been constructed around the sewer main  the construction of the footings did not comply with local council requirements, as there was an insufficient interface between the footing and the sewer main  building works on the neighbouring property commenced in January 2015, in preparation for the construction of town houses  as part of these works, a new sewer main was constructed by disconnecting the existing sewer main fr om the footing of the applicant’s property by removing the non-compliant concrete  the removal of the concrete exposed the soil under the applicant’s garage to the effects of sub-surface ground water from the neighbouring property which was located uphill  during the storms in January and February 2015, stormwater collected on the neighbouring property, saturating the soil and seeping into the trench backfill material of the newly constructed sewer main  while the construction of the new sewer main was undertaken in accordance with standard design and construction practices, the builder had failed to comply with the requirement under the Building Code to ensure the applicant’s property was protected from the adverse effects of redirected surface water. Accordingly, CS concluded that the primary cause of the inundation was the construction of the new sewer main and the removal of the concrete around the sewer main under the applicant’s property (which did n ot comply with applicable requirements at the time of construction). CS noted that, based on meteorological records, the rainfall experienced in January and February 2015 was not unusual for that time of year. Applicant says claim should be reassessed following QBCC investigation The applicant has not provided any independent information (for example, a report from his own engineer) which directly refutes the findings in CS’s report (including Case No: 491606 Determination Page 4 of 5 CS’s conclusion that the footings of the applicant’s property were not properly constructed around the sewer main). However, the applicant says CS’s report was prepared prior to the investigations undertaken by QBCC in response to his complaint. The applicant says the FSP should reassess the claim based on the findings made by QBCC. Findings made by QBCC do not alter outcome The complaint lodged by the applicant with QBCC concerned the incidents when water entered his property in January and February 2015 (including the inundation which is the subject of the current claim). The materials provided by the applicant indicate that, during the QBCC complaint process:  QBCC identified that the inundation in February 2015 was caused by defective works undertaken by the original builder of the applicant’s property (OP) and issued a direction requiring OP to undertake remediation works  when OP failed to complete these works, QBCC appointed a nother builder (MC) to complete the remediation works, under the home warranty insurance policy administered by QBCC  the remediation works included negative side waterproofing of the garage slab, to prevent future water entry to the lower level of the property, as occurred in February 2015. I do not consider that the issues identified during the QBCC complaint process invalidate the F SP’s findings as to the cause of the water damage to the applicant’s property. To the contrary, the actions taken by QBCC indicate that defective works by the original builder (including inadequate waterproofing) are likely to have contributed to the inun dation of the applicant’s property in February 2015. FSP is not liable for claim Based on the available information, I am satisfied that the proximate cause of the inundation of the applicant’s property was defective design and construction, rather than the storm in February 2015 (or any other event insured against under the policy). The policy excludes cover for damage caused in this manner. Accordingly, the FSP is not liable for the applicant’s claim. Case No: 491606 Determination Page 5 of 5 3 Supporting information 3.1 FOS approach to this dispute This dispute was the subject of a recommendation issued on behalf of the Financial Ombudsman Service (FOS) Australia on 12 January 2018. The recommendation was rejected by the applicant. This dispute has been determined based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions (which are not binding). There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered (whether or not it is expressly referenced in this determination).