Home / Financial Firm (Unknown - Insurer) / Determination 491174

Determination 491174

Water leak and house cracking claim declined

FirmFinancial Firm (Unknown - Insurer)
Decided2018-05-15
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant claimed for cracking and tile damage attributed to leaking under-slab pipes, and the FSP declined. AFCA accepted the FSP's structural engineering evidence that the damage arose from design, construction and workmanship defects, which is excluded, and ordered nothing.

Exclusions for structural defects, faulty workmanship and earth movement applied on the expert evidence, which the applicant did not rebut with comparable qualified expert evidence.

Issues

Subjects and remedies

no remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 491174 Determination Page 1 of 12 Case number: 491174 11 May 2018 1 Overview 1.1 Dispute On 25 February 2014, the applicant (the i nsured) lodged a claim with the financial services provider (FSP) under his home insurance policy due to water damage. The claim was for cracking through parts of the house caused by leaking pipes in the bathroom under a concrete slab. The claim also includes the detachment of tiles in the bathroom. On or around 3 September 2015, the applicant lodged a second claim for water damage to floorboards. The FSP denied the first claim and settled the claim for damage to floorboards. The applicant seeks settlement of his claim on the basis that the FSP pay the applicant for the cost of fixing the damage to his home caused by the leaking pipes plus compensation for costs incurred. 1.2 Issues and key findings Is the FSP entitled to decline the claim? The FSP is entitled to refuse payment of the claim in accordance with the terms and conditions of the policy. The FSP is not required to pay compensation. 1.3 Determination This Determination is in favour of the FSP. The FSP is entitled to decline the claim. Case No: 491174 Determination Page 2 of 12 2 Reasons for determination There has been an exchange of material between the parties and each party has had the opportunity of addressing the issues that arise from the information exchanged. This determination follows consideration of all of the information exchanged and is based on what is fair in all the circumstances, having regard to the relevant legal principle, terms of the policy, good industry practice including codes of practice and prior determinations where applicable. 2.1 Is the FSP entitled to decline the claim? Applicant must establish a claimable loss The policy in question provides cover for accidental damage to buildings. The cover is set out in the applicant‟s schedule of cover dated from 20 October 2013 to 20 October 2014 (Schedule), the Product Disclosure Statement dated 20 November 2010 (PDS) and the Supplementary Product Disclosure Statement dated 1 April 2009 (SPDS) (see section 3.1 of this determination for the relevant policy terms). The Schedule states the applicant has cover for accidental damage to buildings. The definition of “accidental damage or loss” in the PDS refers to accidental damage to contents and valuable items which does not appear to include buildings. “Accidental damage” to buildings was added into the insurance contract by the SPDS. The SPDS refers to cover for b uildings for “Any accidental loss or damage”. It is noted that the use of the words “accidental loss or damage” in the SPDS is slightly different to the title of the definition “accidental damage or loss” used in the PDS. Based on the sections of the PDS the FSP referred to in its correspondence, it was intended that the applicant be covered for insured events as set out in the PDS as well as “accidental damage or loss” to buildings as set out in the SPDS. The method used by the FSP to set out the policy co ver should have been clearer. The Schedule should have mentioned both “insured events” and “accidental damage”. In order to make sense of the “accidental damage” cover the FSP is providing for buildings, the panel thinks it is reasonable to use the defini tion of “accidental damage or loss” in the PDS and substitute the word “building” for the words “contents and valuable items”. Accidental damage to buildings therefore means damage to a building that is caused by an unintentional act or an unforeseen and uncontrollable event. Although not clearly set out in the Schedule, based on the FSP‟s correspondence and the way the PDS is set out, it appears it was intended that the applicant was also covered for listed insured events. In this case the relevant insured event is „Water or liquid damage‟. To claim damage for a listed insured event the applicant is required to show, on the balance of probabilities, he has suffered a loss caused by an event insured under the policy. This is known as a prima facie or claimable loss. The applicant can also claim accidental damage as set out in the Schedule. For the reasons given above, to claim accidental damage to buildings the applicant is Case No: 491174 Determination Page 3 of 12 required to show, on the balance of probabilities, a loss has been suffered caused by an unintentional act or an unforeseen and uncontrollable event. If this is established, the onus shifts to the FSP to show that, on the balance of probabilities, it is entitled to rely on an exclusion under the policy to decline the claim. The exclusions set out in the PDS which relate to buildings and contents cover are the same for “insured events” and “accidental damage”. Applicant says the damage was caused by water leaking from pipes The applicant says there is cracking through parts of the house ca used by leaking pipes in the bathroom under a concrete slab. In a letter to the FSP dated 19 May 2016, the applicant says that he thinks the cracks in the house are a result of the concrete slab under the bathroom lifting rather than falling: The above symptoms look very much like a typical heaving problem where water has leaked under the slab, expanded the clay which has lifted the slab causing the wall tiles to be pushed off the wall and in direct alignment we have seen cracks opening up at the ceiling. The diagram provided by the applicant contains several pictures and photos. It depicts two opposite views of the foundation issue. One view shows expanding clay due to moisture pushing the central concrete slab upwards causing cracks at the ceiling. The other view shows the central concrete slab dropping which the applicant says would not cause cracks in the ceiling. The applicant says the cracks in the ceiling are consistent with water from the pipes causing the clay to expand and pushing the concrete sl ab upwards. The applicant‟s view is in direct conflict with the FSP‟s view that the concrete slab is dropping in the middle of the house. In one of the applicant‟s undated letters he says the house was originally designed properly: We know the house was designed by a qualified structural engineer at the time of building and approved by the council to be built in 1989. In a second undated letter the applicant sets out what he believes the initial report from the FSP‟s consulting engineer (SCC) does not adequately confirm. Amongst other comments the applicant says: It confirms there are leaks in the drainage pipes under the slab and confirms the cavity under the slab in the immediate area is caused by water leaking, however it does not appropriately determine what has caused the leaks. It later suggest that improperly compacted soil may have dragged down the plumping causing the cracks, yet that contradicts the above statement and verbally confirmed by our engineer that these cavities can only be explained by water erosion. How can they claim that cavity that was created by water erosion actually caused the leaking pipe. Surely the water erosion must have occurred first. It claims downward pressure on the internal walls where tiles popped. This wall is non-load bearing trussed roof. Confirmed verbally by our engineer and can be clearly seen. They claim faulty workmanship on house and bathroom that has been fine for over 20 years, as proven by the council's initial inspection and approval and the professional Case No: 491174 Determination Page 4 of 12 building inspection conducted when the house was purchased 10 years ago. There is no explanation as to why suddenly all this poor workmanship has occurred at the same time we have a leak under the slab. The report summary appears to ignore all the report details and focus on some handwriting on the council plans of which they are unsure of how the slab was designed and built and they are unsure how the wall was removed, then assuming it was done incorr ectly with no evidence of that in the report.” In a third undated letter the applicant says: The FSP “ continue to refer to the initial engineering report obtained by them claiming that the damage was due to, • Poor compaction during construction over 30 years ago caused the pipes to suddenly leak. A claim made based on the cavity under the slab around the area of the leaking pipes. • Poor adhesion and fixing of the bathroom wall tiles that popped off on a wall, noted in within the report to be under some pressure, after being fine for 30 years. • Poor slab design, that was approved by both engineers and councils during construction over 30 years and has now suddenly started cracking at the same time as [a] the leak under the slab was noticed. • Poor removal of an interior wall some time ago, claiming this may have been load bearing and they could not assess the work as the roof was not accessible. The roof is trussed and over 6 foot high internally so have taken some photos to show the area they could not access. Our engineer has confirmed verbally this is not load bearing. In their summary, all the above items are claimed to be unrelated to the water leaking under the slab, yet they are all in same location and happened at the same time.” The applicant has provided a report from an architect and builder, EEH, in support of his claim. The applicant referred to comments by an engineer in his second and third undated letters, however, he did not provide any written report from an engineer. The key points from EEH‟s report are set out in section 3.2 of this determination. In summary, EEH says:  The internal wall that was removed between the family room and kitchen does not have a structural effect to the walls as it is a non - load bearing wall. The raked roof above does not bear onto the wall that was removed, as the current roof is a truss raked roof structure.  The cracking to the walls and movement to the floor slab appears to be related to the leaking toilet pip e and leaking plumbing pipes below the bathroom as when the drain pipes were hydrostatic a lly tested water was found to be weeping between the soil and concrete edge beam and causing soil erosion and water to the base of the buildings.  SCC report says the d rainage pipes below the bathroom and toilet have been damaged and have not been supported. However, this is only an assumption.  Based on the age of the house the plumbing was originally installed and inspected to comply with the current building standards at the time. Case No: 491174 Determination Page 5 of 12  The leaking plumbing below the bathroom has caused variable foundation movement and soil erosion which has caused cracking and movement to the house.  Given the house is approximately 28 years old the damage is not related to poor workmanship. However , this cannot be determined until the slab has been cut and an invasive inspection is undertaken. The FSP does not dispute that there are leaking water pipes The FSP accepts that there are leaking water pipes under the concrete slab in the middle of the applicant‟s house. However, the FSP considers that the house damage and fracture of the bathroom‟s under -slab drainage pipes is due to improper design and construction. In other words, the FSP does not consider that the water leaking from the pipes has caused the cracking damage to the house. The FSP also considers that the tiles in the bathroom have fallen off due to improper workmanship. Evidence on balance shows the damage was caused by improper design and construction The FSP‟s two experts, SCC (an engineer) and IT (a building consultant), each produced three reports which the FSP relies on (see section 3.2 of this Determination). In its first report dated 1 April 2014, SCC attributed the damage to the house interior and fracture of the below-slab waste water drains, to improper design and construction considerations. Further, it concluded based on the available evidence that the house slab does not feature uniform foundation bearing and the escaping water from the fractured pipes had no effect on the south side support of the building. SCC also said in the same report that as presented, the foundation footing drawing is an incoherent mixture of structural engineering advice. Further, that if the foundation footing drawing is the final record submitted to Council records, then nobody knows how the base of this building was finally supported. SCC‟s 2014 report also said the ceramic wall tile detachment in the bathroom is consistent with improper workmanship considerations (poor adhesion/fixing of the wall tiles). In addition, SCC said that during the exposure of the wall lining behind the shower, it was obvious that no waterproofing system was present on the walls of the shower recess, or extending-up from the base of the shower recess. IT produced a report dated 4 April 2014, which was consistent with the reasoning of SCC. In its second report dated 16 October 2017, SCC confirmed its original opinion that the external load caused the pipes to crack and the water to start leaking under the concrete slab. IT in its report dated 15 October 2017, again confirmed its agreement with the reasoning in the 2014 SCC report. In its third report dated 27 October 2017, SCC says in summary:  The claim that water was appearing between the soil and the concrete edge beam when the pipes were pressure tested is simply not true  The bathroom slab shows no sign of movement Case No: 491174 Determination Page 6 of 12  The drains are not known for moving around under their own steam. They are not under pressure. They do not break spontaneously  The temporary buildin g platform was a form of cut - and - fill. The ground outside the bathroom had sunk progressively relative to the slab over time. On the outside of the house, on the south side, the ground has pulled down the storm water downpipe relative to the wall bracket. In its third report dated 26 October 2017, IT says in summary:  The homeowner has failed to provide an engineering report to refute any aspect of the 2014 SCC report.  EEH is not structurally qualified to prepare a report on structural issues .  The EEH report is mute on the subject of the structural design and construction flaws with the house slab , as identified in the 2014 SCC report. The FSP has provided three reports from an expert, SCC, with civil engineering qualifications. The panel is satisfied that SCC is appropriately qualified to provide a report on structural design and construction flaws. The applicant has provided a report from EEH, however, EEH does not have civil engineering qualifications. In the absence of any report from the applicant by an expert with similar or other appropriate qualifications to SCC to refute their reports, on balance the panel is persuaded that the house damage and fracture of the bathroom‟s under - slab drainage pipes was due to improper design and construction . In addition, the panel is also persuaded that the tiles in the bathroom have fallen off due to improper workmanship whether it be because they were not fixed to the wall properly, there was no adequate waterproofing, or they came off as a consequence of the structural design and construction flaws. FSP says the loss was excluded by the policy The FSP relies on the building and contents exclusions (see section 3.2 of this Determination). The exclusions in that section apply to building cover regardless of whether th e damage comes with the insured event of “water or liquid damage” or “accidental damage to buildings”. The FSP relies on the following exclusions:  settling, shrinkage or any movement of earth  settling, shrinkage or expansion in buildings, foundations, walls or pavements  a defect in an item, structural defects, faulty or poor workmanship or design. The evidence establishes that the exclusion does apply to the claim For the reasons mentioned above in the SCC report, the available evidence indicates the house damage and fracture of the bathroom‟s under -slab drainage pipes was due to improper design and construction. Also that the tiles in the bathroom have fallen off due to improper workmanship. The FSP has therefore established that the applicant‟s claim is excluded as the damage was caused by structural defects and faulty or poor workmanship or design. Case No: 491174 Determination Page 7 of 12 In addition, the exclusions of settling, shrinkage or any movement of earth or settling, shrinkage in buildings would also apply. Accordingly, the FSP is enti tled to deny the applicant‟s claim. Case No: 491174 Determination Page 8 of 12 3 Supporting information 3.1 Relevant policy terms Page 1 of the SPDS Page 8 of the PDS … Page 13 of the PDS … … Case No: 491174 Determination Page 9 of 12 Page 42 of the PDS … … … Page 60 of the PDS … … Case No: 491174 Determination Page 10 of 12 3.2 Key points from expert material Record Key points FSP’s expert (SCC) Structural Engineers 27 October 2017  The claim that water was appearing between the soil and the concrete edge beam when the pipes were pressure tested is simply not true.  The bathroom slab shows no sign of movement. Remember it is supposed to be a suspended slab and have piers down to rock.  The drains are not known for moving around under their own steam. They are not under pressure. They do not break spontaneously. They have been in place for 25 years.  The temporary building pla tform was a form of cut - and - fill. The ground outside the bathroom had sunk progressively relative to the slab over time. On the outside of the house, on the south side, the ground has pulled down the storm water downpipe relative to the wall bracket.  We un derstand the term „shoring - up‟ as placing some form of temporary or permanent post or strut under or against the side the element to be supported. This is not much of a solution for the plumbing if the ground is expected to settle away from the underside o f the slab after acting as temporary formwork. That is exactly how the drain pipes end up dangling from the underside of the slab, and being dragged down by the settling fill, especially on the south side of the cut - and - fill profile where the fill would be the deepest. FSP’s expert (IT) Building Consultant 26 October 2017  The homeowner‟s failure to provide an engineering report to refut e any aspect of the 2014 SCC report infers that he either did not consult with any engineers or if he did, they were in agreement with the SCC det ermination.  The most remarkable feature of the report by EEH is that the author of the report, Mr E, is not structurally qualified to prepare a report on structural issues .  The EEH report is mute on the subject of the structural design and construction flaws with the house slab as identified in the 2014 SCC report. FSP’s expert (SC C ) Structural Engineers 16 October 2017  T he pipes ruptured first and the leakage occurred secon d.  In the absenc e of any other source of free water under the slab, water cannot escape from a non - pressuriz ed drain in a stable environment until it is broken by some external force arising from an unstable environment.  These loadings are the cause of the drain fractures, and leakage comes after the drains are opened at the fracture locations. The plumber found two such locations, the dropper (or riser/ vertical drain) from the W.C., and the (graded) running drain just before the vanity connection. FSP’s e xpert (IT) Building Consultant 1 5 October 2017  I stand by the opinion I expressed in my earlier 2014 report in which I expressed complet e agreement wit h the 201 4 SCC report. Case No: 491174 Determination Page 11 of 12 FSP’s expert (SC C ) Structural Engineers 1 April 2014  The claim is for damage attributed by the insured to escape/s of water from house drains.  Two existing (water created) holes were enlarged showing a poor quality, loose, foundation filling and cavitation extending under the edge of the base slab . The foundation under the slab was dry even in the previously water - eroded holes in the ground.  Further exploration up and down the south side of the slab edge found similar dry conditions, with loose foundation soil, and cavitation under the slab. This led to the belief that the base slab might be independent of the foundation material for direct support, and that piers to a lower bearing strata may have been used.  This would suggest that the perimeter beams and supported walls are on a non - yielding foundation while the interior of the beam and slab is on a foundation capable of cyclic movements. This is not recommended. So the edges are supported on a rock foundatio n and the interior is free to move up and down depending on foundation moisture cont ent.  As presented, the foundation footing drawing is an incoherent mixture of structural engineering advice. If this is the final rec ord submitted to Council rec ords, then nobody knows how the base of this building was finally supported.  Based on available evidence, inclusive of the background information provided by the rec ords obtained from the local Council, our conclusion is that there is no tangible evidence to link the south side leaking waste drains under the bathroom, and the external escaping storm wat er from the separated downpipe, to the claimed internal house damage, specifically the bathroom, hallway and combined kitchen/family/dining areas.  We have determined t hat the damage to the house int erior and fracture of the below - slab waste water drains are due to improper design and construction considerations .  We believe the house slab does not feature uniform foundation bearing.  The structural drawings suggest the sl ab perimeter was piered to stable foundation, more than likely rock and int ernal piers, if used, were to be taken down to natural clay but without any direction as to location of the piers.  We further believe piering of the slab perimeter had the effect of holding - up the perimeter of the base slab while the poorly compacted filled ground under the south side, in particular, settled away*. This exerted negative friction (perimeter pull - down) on the plumbing pipes descending from the concrete floor of the sou th side bathroom/W.C. into the subsiding (filled) ground.  While the breaching of the drains occurred in two identified locations under the bathroom and adjoining W.C., the escaping water had no effect on the sout h side support of the building which was ind ependent of the (settling) filled ground and resultant edge cavitation.  There is no likely association of the ceiling and wall damage with the distant escape of water under the south side bathroom and W.C. Case No: 491174 Determination Page 12 of 12  As presented, the foundation footing drawing is an incoherent mixture of structural engineering advice. If this is the final rec ord submitted to Council rec ords, then nobody knows how the base of this building was finally supported. The documentation supplied does not refer to the removal of this previous wall. We are no wiser as to the effects of the removal on the roof support wall (if it did support the roof).  Observed ceramic wall tile detachment in the bathroom is consistent with improper workmanship considerations (poor adhesion/ fixing of the wall ti les).  During the exposure of the wall lining behind the shower, it was obvious that no waterproofing system was present on the walls of the shower recess, or extending - up from the base of the shower recess. FSP’s expert (IT) Building Consultant 4 April 2014  I confirm that I have reviewed the SCC report and that I am in complete agreement with the report‟s findings . Applicant’ s expert (EEH) Architectural and b uilding report 19 October 2017  The comment by SCC report in relation to the int ernal wall being removed bet ween the family room and kitchen having a structural effect to the walls and bowing is not correct as this was a non load bearing wall and the raked roof above does not bear onto the wall that was removed, the current roof is a truss raked roof structure that is supported onto the external cavity wall and across the hall and family room walls.  The cracking to the walls and movement to the floor slab appears to be related to the leaking toilet pipe and leaking plumbing pipes below the bathro om as when the drain pipes were hydrostaticity tested water was found to be wheeping between the soil and concrete edge beam and causing soil erosion and water to the base of the buildings will cause continuous movement and cracking which is evident to the structure adjoining.  It has been mentioned in the SCC report that the drainage pipes below the bathroom and toilet have been damaged and have not been supported (The soil not being compacted). This cannot be determined by a visual inspection this is only an assumption. The house based on age has stood the test of time to indicate the plumbing was originally installed and inspected to comply wit h the current building standards at the time.  It is my opinion that the leaking plumbing below the bathroom has ca used variable foundation movement and soil erosion has caused cracking and movement to the house generally foc used around the bathroom, hall way, kitchen area and family room.  Based on the test of time the house is approximately 28 years old. This is not r elated to poor workmanship as this cannot be determined until the slab has been cut and an invasive inspection to be undert aken.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.