Text of the determination
Determination
Case No: 490576 Determination Page 1 of 14
Case number: 490576 5 September 2018
1 Overview
1.1 Dispute
The applicant lodged a claim under his home insurance policy with the financial
services provider (FSP) after his home was damaged by Cyclone Debbie in March
2017.
The FSP accepted the applicant’s claim and sought to arrange for the repair of his
property. However, when the parties were unable to agree on a scope of works, the
applicant requested that the FSP cash settle the claim.
The FSP cash settled the claim for $100,369.17, being the estimated cost of
repairing the damage to the property based on a scope of works and a quotation
prepared by its building consultant (SB).
The applicant says the cash settlement paid by the FSP is not sufficient to address
all of the damage to his home caused by the storm. He says the cash settlement
amount should be increased to $185,259.98, based on quotations provided by his
contractors for the repair of the damage.
1.2 Issues and key findings
Should the cash settlement for the building repairs be increased?
The cash settlement should be increased by a total of $35,665.56 to reflect the cost
of fully replacing the roof, as well as additional risks assumed by the applicant as a
result of the building repairs being cash settled.
Based on the available information, the panel is satisfied that there are ongoing
mould and moisture issues at the property caused by water entry during the storm.
These matters have not been adequately addressed by the cash settlement paid to
date.
Accordingly, the FSP is required to arrange for a further assessment to be
undertaken and a scope of works prepared to identify the mould remediation works
required to be undertaken at the property.
Is the applicant entitled to any other amounts?
The applicant is entitled to payments for alternative accommodation costs,
compensation for non-financial loss and reimbursement of fees incurred in obtaining
consultant’s reports.
Case No: 490576 Determination Page 2 of 14
1.3 Determination
This determination is substantially in favour of the applicant.
The FSP is required to pay the applicant:
an additional amount of $35,665.56 for building repairs, plus interest on this
amount at the rate calculated under section 57 of the Insurance Contracts Act
1984 (Cth) from 12 October 2017 until the payment date,
an amount of $24,000 for alternative accommodation costs
an amount of $2,000 as compensation for non-financial loss, and
reimburse the applicant for fees incurred in obtaining the reports referred to in
section 2.2 below, on provision of relevant invoices and subject to a maximum
of $3,000
In addition to the above, the FSP is required to:
engage the applicant’s mould specialist (EB) (or an equivalently qualified
consultant) to undertake an assessment a nd prepare a scope of works for
mould remediation at the property (excluding the localised mould and wood rot
in the immediate vicinity of the bathtub)
obtain a quotation from a mould remediation contractor (and, if required, a
builder) to undertake the steps specified in the scope of works, and
cash settle the application for the amount of the quotation.
Case No: 490576 Determination Page 3 of 14
2 Reasons for determination
2.1 Should the cash settlement for the building repairs be increased ?
FSP accepted applicant’s claim for storm damage
The appli cant’s policy provides cover for damage to his property caused by the
events listed in the policy (including the insured event of storm), subject to the
conditions and exclusions set out in the policy.
The FSP accepts that the applicant’s property was affe cted by Cyclone Debbie,
which caused widespread damage to the local area.
During the storm, the applicant’s roof was impacted by debris from the neighbouring
property and wind driven rain entered through the timber shutters, inundating a
number of rooms in the property.
Policy sets out how claims will be settled
Under the terms of the policy, the FSP may settle a claim for damage to the
applicant’s property by:
repairing the damaged part of the property, or
paying the applicant the amount the FSP determines to be the reasonable cost
of repairing the damaged part of the property.
It is clear from the terms of the policy that the FSP has the discretion to decide which
settlement method to adopt.
In the present case, the FSP appointed its contractors to prepare a scope of works
and quotation for the repair of the property. However, the claim was later cash settled
at the applicant’s request, after the parties were unable to agree on the scope of
works.
Parties disagree about scope of repairs required
During the course of the claim, the parties engaged various contractors to assess the
damage caused by the storm and prepare scopes of work for the necessary repairs.
The contractors engaged by the parties include:
the FSP’s first builder (JL), who prepared an initial report, scope of works and
quotation in April 2017
the FSP’s second builder (QT) who prepared a further report, scope of works
and quotation in May 2017, after the applicant disputed the initial scope of
works prepared by JL
the applicant’s building consultant (CC), who prepared a report and scope of
works in July 2017, after the applicant remained dissatisfied with QT’s scope of
works
the applicant’s roofing plumber (RP), who prepared a report and quotation for
the replacement of the roof in July 2017
the applicant’s builder (AB), who prepared a report and scope of works for the
remainder of the building repairs in July 2017
Case No: 490576 Determination Page 4 of 14
the FSP’s building consultant (SB) who prepared a report, scope of works and
quotation in September 2017, and
the app licant’s mould specialist (BE), who prepared a report regarding mould
remediation in November 2017.
The contractors engaged by the parties have provided conflicting reports about the
extent of the damage caused by the storm and the nature of the repairs required.
The key differences between the views of the various contractors relate to:
whether all or only part of the roof needs to be replaced
the extent of the repairs required to the ceilings and internal walls
the need for mould remediation at the property, and
whether a leaking pipe in the bathroom has contributed to the damage.
The cash settlement amount of $91,538.37 paid by the FSP in October 2017 was
based on a scope of works and a quotation prepared by its building consultant (SB)
in November 2017. The cash settlement amount reflected the amount of SB’s
quotation, plus 5%.
The FSP had previously cash settled the applicant for $8,830.80 in June 2017 for
repairs to the boundary fences. The applicant has not disputed this aspect of the
settlement.
Parties dispute extent of damage to roof
The scope of works prepared by SB provided for the replacement of a 50 square
metre area of the sheet metal roof at the eastern end of the building (together with
the replacement of associated battens, cappings, flashing and insulation).
SB accepted that the roof in this area had been damaged by flying debris during the
storm. However, he considered that the remainder of the roof did not require
replacement. Accordingly, the cash settlement paid to date only allows for the limited
repairs identified by SB.
The applicant disputes SB’s findings and says the FSP should be required to pay for
the cost of replacing the entire roof.
The applicant has provided a report from his roofing plumber (RP) which states that:
the strong winds experienced during the storm lifted the laps of the roofing
sheets and the ridge capping, allowing water to enter
70% of the roofing sheets were scratched and dented by the impact of debris
during the storm, and
the roof needed to be replaced to prevent water entry during future periods of
heavy rainfall.
Both RP and the applicant’s building consultant (CC) have provided a number of
photographs showing roofing sheets with dents and stretched laps, as well as
sections of the roof ridge and hip cappings which appear to have lifted and deformed.
CC advised that these issues are typical of damage caused by high winds.
The FSP’s building consultant (SB) accepted that there was denting and scratching
damage to the eastern section of the roof and minor wind damage to the ridge
Case No: 490576 Determination Page 5 of 14
capping. However, he disagreed with RP and CC that there were any signs of uplift,
deformation or separation of the roof sheets.
FSP is liable for entire roof replacement
Based on the available information, the panel is satisfied that the strong winds
experienced during the storm damaged the roof sheets, ridge and hip cappings. The
photographs provided suggest the roof sheets have stretched and deformed, making
the roof more susceptible to water entry in the future.
The panel notes that the builder (JL) engaged by the FSP to prepare the initial scope
of works allowed for the entire roof to be replaced. However, when the applicant
disputed other aspects of JL’s scope of works, the FSP appointed QT (and then SB),
who reduced the scope of the roof repairs.
Given the severity of the storm and the difference of opinion between the FSP’s
builders, the panel considers the FSP should be required to replace the roof in its
entirety.
The applicant has provided a quotation from his roofing plumber (RP) for $38,860.80
for the replacement of the roof.
As outlined above, the cash settlement amount paid by the FSP provided for the
replacement of a 50 square metre section of the roof, reflecting approximately 20% of
the total roof area.
In these circumstances, the panel considers that that FSP should be liable to pay the
applicant an additional amount of $31,088.64, reflecting 80% of RP’s quotation.
FSP is not liable for separation damage to ceilings
The reports provided by the various consultants confirm that the ceilings in a number
of rooms have ‘popped’ or deflected – that is, they have partially separated from the
timber ceiling battens. However, the consultants disagree about the cause of this
damage.
The applicant’s builder (CC) repo rted that the storm had caused damage to the
ceiling linings, although he did not explain the mechanism by which the damage
occurred. CC considered that all of the ceilings should be replaced.
The applicant’s mould specialist (EB) considered that the ceili ng adhesive and
fasteners had popped due to sudden changes in air pressure experienced during the
storm. However, EB does not appear to be a qualified builder.
The FSP denied cover for the damage to the ceiling linings (other than the cost of
repainting), based on advice from its building consultant (SB) that this damage was
not related to the storm.
SB advised that the deflection of the ceilings had occurred over the life of the
property because:
the roof trusses had been constructed without struts (‘webbing’), which is
required to support the trusses when they are subject to normal loading from
the weight of the roof
Case No: 490576 Determination Page 6 of 14
as a result, the trusses have moved downwards, so that they rested on the top
of the internal walls
where the trusses were not supported by the walls, they continued to move
downwards, and
the uneven movement of the trusses caused the ceiling frame adjacent to the
walls to deflect.
In his report, SB referred to the failure of the original builder to comply with the
relevant requirements of the Australian Standard for trussed roofs in cyclonic areas.
This non-compliance does not constitute a structural or design defect such that the
relevant policy exclusion applies, as the Australian Standard was not published until
June 2010 while the app licant’s house was completed in March 2010.
Nevertheless, the panel is satisfied that, the separation damage to the ceiling was
not caused by the storm, but occurred over time due to the manner in which the roof
trusses were constructed.
SB’s report inclu des a number of photographs taken from inside the roof cavity which
show the trusses bearing down on the roof frame. The panel is satisfied that it is
these forces (rather than any uplift experienced during the storm) which caused the
ceilings to deflect.
Accordingly, the FSP is not liable for the separation damage to the ceilings.
FSP is not liable for localised damage to bathroom
During his inspection in September 2017, the FSP’s building consultant (SB)
identified an ongoing moisture issue in the commo n wall between the bathroom and
the adjacent bedroom.
SB reported that water had been observed running out of the wall to floor junction,
the moisture levels of the external block wall in this area were extremely high and
there was extensive wood rot and mould to the timber bath frame and bath void.
SB advised that the damage to this area was extensive and would require substantial
repairs. He considered that the damage had been caused by a leak in one of the
copper water pipes penetrating the concrete slab.
Based on the available information, the panel is satisfied that the localised damage to
the bathroom and adjacent bedroom was caused by a leaking water pipe (and not by
the storm). The nature and extent of the damage indicates it had been occurring for
an extended period of time.
The applicant lodged a separate claim for damage caused by the leaking pipe in
early 2018. However, the FSP denied cover on the basis that the damage was
caused by a gradual escape of liquid (which is a specific exclusion under the relevant
insured event).
The panel accepts that the wind driven rain which entered the bathroom through the
timber louvres during the storm may have contributed to the moisture issues.
Case No: 490576 Determination Page 7 of 14
However, the panel considers that the bulk of the additional repairs to the bathroom
(as identified by the applicant’s consultants) are required as a result of the leaking
pipe. Accordingly, the FSP is not liable for the cost of these repairs.
Applicant seeks cover for moisture and mould remediation costs
As outlined ab ove, the interior of the applicant’s property was flooded when wind
driven rain entered through the timber louvre windows during the storm.
The applicant says mould developed throughout the property due to the ongoing
effects of moisture following the storm and the FSP’s failure to undertake appropriate
remediation measures.
The applicant has provided a report prepared by his microbiologist (BE) following
testing at the property carried out in November 2017. BE’s tests identified high to
very high levels of viable mould of aberrant ecology, including in the kitchen and
master bedroom.
The FSP’s building consultant (SB) confirmed there was mould growth in the
northern wall cavity of the lounge room, where a section of the wall lining had been
removed by t he applicant’s building consultant.
SB’s scope of works provided for the removal and replacement of the lower wall
sheets in the northern wall of the lounge room and the eastern wall of the adjacent
dining room.
However, SB was unable to confirm whether there was mould growth in wall cavities
in other areas of the building as he was not authorised to carry out invasive
investigations.
Mould growth at property was caused by storm
Having carefully reviewed the available information, the panel is satisfied that the
effects of the storm contributed to the growth of mould at the applicant’s property.
While there was pre-existing mould and moisture damage to the bathroom (due to
the leaking pipe), this damage was relatively localised.
As outlined above, the FSP ’s building consultant (SB) confirmed there was mould
growth in at least one section of the wall cavity in the lounge room, which is
consistent with the area where water entered during the storm.
SB was unable to express a view as to whether there was mould growth in other
parts of the walls.
The FSP’s mould specialist (BE) also identified aberrant mould ecology in the
kitchen, which was another area where water entered during the storm.
BE advised that the pattern of mould growth he observed in November 2017 was
consistent with the property having been affected by water entry many months earlier
and remaining wet for at least a few months before drying out. BE noted that the
warm and humid conditions would have allowed rapid mould growth.
Case No: 490576 Determination Page 8 of 14
The FSP’s claim notes do not indicate that any measures were put in place to dry the
property and prevent mould growth at any stage during the claim. This was despite
the fact that:
during the initial assessment in April 2017, the applicant advised that water had
entered a number of rooms
after reviewing JL’s scope of works in May 2017, the applicant expressed
concern about potential damage to the internal wall linings, given the moisture
to which they had been exposed, and
in July 2017, the applicant notified the FSP of visible mould on the ceilings and
walls (as confirmed by the applicant’s contractors (CC and AB), following their
inspection of the property).
In these circumstances, the panel is satisfied that the proximate cause of the mould
growth at the property is the storm in March 2016.
FSP is liable for moisture and mould remediation costs
The applicant says the FSP should be liable for the cost of replacing all of the internal
plasterboard ceiling and wall linings throughout the property to address moisture and
mould damage, as well as undertaking any broader mould remediation required (in
accordance with the recommendations contained in EB’s report).
For the reasons outlined above, the panel is satisfied that the proximate cause of the
mould growth was the ongoing effects of water entry during the storm (and the failure
by the FSP’s contractors to take appropriate preventative measures).
Accordingly, the FSP is liable for the costs of undertaking mould remediation.
The applicant has confirmed that, while the property has been made watertight,
internal repairs to the property have not yet been carried out and the mould has not
been addressed.
The applicant advised that he wanted to confirm the outcome of the FOS dispute
before deciding how best to allocate the funds available.
Given the time which has passed since EB’s report, the panel considers that the FSP
should be required to:
engage EB (or an equivalently qualified mould specialist) to undertake an
assessment and prepare a scope of works for mould remediation at the
property (excluding the localised mould and wood rot in the immediate vicinity of
the bathtub)
obtain a quotation from a mould remediation contractor (and, if required, a
builder) to undertake the steps specified in the scope of works, and
cash settle the application for the amount of the quotation.
The scope of works for the mould remediation should include the strip out of all of the
internal wall linings to a height of at least 1.2 metres (or such greater height as is
recommended by the mould specialist).
This approach reflects the results of testing carried out by EB, which found that there
was evidence of moisture remaining in the lower sections of the walls (which were
affected by water inundation during the storm).
Case No: 490576 Determination Page 9 of 14
It is also consistent with the SB’s scope of works which recommended that the wall
linings be stripped out to a height of 1.2 metres in the area of the lounge room where
mould had been confirmed.
SB did not provide for the strip-out of the internal wall linings in other sections of the
property. However, this was because he did not undertake any invasive
investigations to confirm whether mould was also present in other areas.
The scope of works should also include any strip out of the ceilings required to
address mould or moisture concerns (noting that the FSP is not liable for the
deflection of the ceilings, for the reasons outlined above).
However, the scope of works should exclude the strip out of the bathroom, as these
works were required due to the damage caused by the leaking pipe (regardless of
any additional damage to this area caused by the storm).
Cash settlement amount should be increased by further 5%
The panel considers that the bulk of the storm damage to the applicant’s property
which was not provided for under SB’s scope of works is adequately addressed by
the increase in the allowance for the roof replacement and the provision for mould
remediation (as outlined above).
The panel acknowledges that the quotation provided by SB was prepared on a desk
top basis only and was not actionable.
Having said that, the FSP remained willing to authorise QT to carry out the necessary
repairs based on SB’s scope of works. QT had previously provided a quotation of
$85,213.70 for works of a broadly similar nature.
The panel has considered the quotation provided by the applicant’s builder (AB).
However, AB’s quotation is based on a scope of works which includes a number of
items for which the FSP is not liable (or which have been dealt with separately).
Such items include the full strip out and replacement of the bathroom, repairs to the
boundary fences and the cost of a roof report, as well as a significant proportion of
the works which will be separately scoped under the mould remediation approach
outlined above.
Further, the panel is not satisfied that all of the additional items included in the
quotations provided by the applicant were damaged by the storm (including all of the
electrical items identified).
Having regard to the factors outlined above , the panel considers that the cash
settlement amount paid by the FSP is generally reasonable (noting that it includes an
additional buffer of 5%).
However, the panel considers that the cash settlement amount of $91,538.37 paid for
the building repairs should be increased by an additional 5% ($4,576.92) to better
reflect:
the potential for further variations to be required during the repair process (for
which the FSP would have been liable had it authorised the repairs), and
Case No: 490576 Determination Page 10 of 14
the additional risk assumed by the applicant due to the absence of the lifetime
guarantee.
2.2 Is the applicant entitled to any other amounts?
Policy provides cover for alternative accommodation costs
The policy provides cover for the reasonable costs of alternative accommodation (for
a per iod of up to 52 weeks) where the damage to the applicant’s property is so
extensive that he and his family are unable to live there.
The reports prepared by the FSP’s contractors suggest that the property remained in
a liveable condition following the stor m. However, the applicant’s mould specialist
(EB) has confirmed that mould subsequently developed at the property, due to the
lack of appropriate moisture remediation measures.
The results of EB’s testing in November 2017 indicated that the mould growth
present could give rise to health issues. EB confirmed that prolonged exposure to the
type of mould present would likely result in symptoms such as those described by the
applicant’s family.
The FSP has not offered to arrange alternative accommodation for the applicant and
his family (either when it was first advised of mould at the property in July 2017 or
following receipt of EB’s report). The cash settlement paid in October 2017 did not
include any allowance for alternative accommodation.
Accordingly, the applicant and his family (including four young children) have
continued to live at the property.
Applicant is entitled to payment of $24,000 for alternative accommodation
Based on EB’s report, the panel accepts that the property is currently unable to be
lived in due to the presence of mould. Accordingly, the applicant and his family are
entitled to alternative accommodation costs while mould remediation works are
carried out.
Given the scope of the building repairs required, the panel considers that the
applicant and his family will also alternative accommodation while the building repairs
are completed.
The scope of works and quotations provided by the FSP’s contractors do not indicate
how long the works are likely to take. The applicant’s building consultant (CC) has
estimated that the works will take approximately two to three months, which the panel
considers is reasonable in the circumstances.
EB’s report indicates that mould remediation measures need to be completed before
the building works can be commenced. In these circumstances, the panel considers
it is appropriate to allow for a repair period of three months.
Based on the cost of serviced apartments in the region, the panel considers the cash
settlement should be increased by $24,000 to allow for alternative accommodation
costs for the applicant and his family while repairs are completed.
Case No: 490576 Determination Page 11 of 14
Applicant is entitled to compensation for non-financial loss
FOS can award compensation (capped at $3,000) for non-financial loss where an
applicant has suffered an unusual degree or extent of physical inconvenience, time
taken to resolve the situation or interference with their expectation of enjoyment or
peace of mind.
The applicant is dissatisfied with the manner in which the FSP handled his claim.
Among other things, the applicant says that the FSP and its contractors:
failed to provide a comprehensive scope of works for the claim -related repairs
attempted to bully him into accepting an incomplete scope of works, and
failed to take appropriate action to address mould and moisture issues at the
property.
The panel recognises that the process of scoping repairs can be drawn out and often
requires multiple inspections, particularly where the repairs required are extensive
(as in the present case).
The panel also accepts that it is not always possible to fully scope the extent of
repairs required at the outset, in which case it may be appropriate to address
additional repairs as variations (as the FSP sought to do).
Nevertheless, for the reasons outli ned above, the panel considers that the scope of
works prepared by the FSP was insufficient to address all of the damage caused by
the storm.
In particular, the scope of works failed to address the applicant’s key concerns about
the moisture and mould aff ected wall linings (even after the FSP’s building consultant
(SB) had personally confirmed the presence of mould in the lounge room wall cavity.
The available information suggests that the development of mould could have been
avoided, had adequate measures to remediate moisture been undertaken at the
outset. The panel considers that the FSP also failed to respond appropriately when
the applicant raised concerns about mould growth during the claim process.
The panel is satisfied that the FSP’s management of these aspects of the claim has
caused significant additional stress for the applicant and his family. In the
circumstances, the panel considers the applicant is entitled to compensation of
$2,000 for non-financial loss.
Applicant is entitled to reimbursement of fees
Under the Terms of Reference, FOS may require a financial services provider to
contribute to professional costs incurred by an applicant in the course of their
dispute. However, a financial services provider will not be required to contribute more
than $3,000, other than in exceptional circumstances.
The panel accepts that it was reasonable for the applicant to obtain scopes of works
and quotations from his own consultants, in circumstances where the scopes of work
provided by the FSP’s contracto rs were inconsistent and the applicant was
concerned that not all of the storm-related damage had been addressed.
Case No: 490576 Determination Page 12 of 14
On this basis, the FSP is required to reimburse the applicant for professional fees
paid for the purposes of obtaining the following reports, on provision of relevant
invoices and subject to a maximum of $3,000:
report provided by the building consultant (CC) in July 2017
report provided by the roofing plumber (RP) in July 2017
report provided by the builder (AB) in July 2017, and
report provided by the mould specialist (BE) in November 2017.
Case No: 490576 Determination Page 13 of 14
3 Supporting information
3.1 FOS approach to this dispute
This dispute has not been the subject of a FOS recommendation. Due to the nature
of the dispute, it has been referred directly to a panel for determination, in line with
the Operational Guidelines to the FOS Terms of Reference. The panel consists of an
Ombudsman and two representatives with consumer and insurance experience.
The panel has decided this case based on what is fair in all the circumstances,
having regard to the relevant law, good industry practice, codes of practice and
previous FOS decisions (which are not binding).
There has been a full exchange of all material information relied on for the purposes
of this Determination and each party has had the opportunity to address any issues
raised by the other.
The panel has reviewed and considered a ll of the material provided by the parties.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination the panel has restricted its commentary to those issues that it
considers directly relevant to the outcome only.
During the course of this dispute, the applicant has bee n represented by a claims
adjuster. For the purposes of this determination, submissions made by the
applicant’s representative have been treated as if they had been made by the
applicant himself.
3.2 Terms of policy
Subject Terms
Cover for
insured
events
We will provide cover for the following Insured Events if they occur during the
Period of Insurance and are not subject to a:
General Exclusion (please refer to pages [xx] to [xx]); or
specific exclusion described under the Insured Event ...
Insured event
– storm
What is covered
Your building and/or contents are covered for loss or damage caused by storm.
General
exclusions
Under this policy there is no cover provided for any loss, damage or liability
caused directly or indirectly by or in any way connected with: …
d efects, structural or design fault, faulty workmanship or faulty design …
wear and tear and lack of maint enance , including rust, corrosion and
deterioration …
mould, toxic mould, mildew, wet or dry rot, rising damp or dampness …
We will also not cover: …
gradual loss or damage of any kind …
Settlement of
claims
Building claims
If we agree to pay your claim, we will decide whet her to:
Case No: 490576 Determination Page 14 of 14
Subject Terms
repair or rebuild the lost or damaged part of your building; … or …
pay you the amount we det ermine to be the reasonable cost of repairing or
rebuilding the lost or damaged part of your building up to the sum insured
stated on your Certificate of Insurance.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.