Home / Financial Firm (Unknown - Insurer) / Determination 490186

Determination 490186

Complainant sought footing upgrade, further building repairs and driveway and parking bay reinstatement after storm claim

FirmFinancial Firm (Unknown - Insurer)
Decided2018-11-08
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$12,144
Non-financial loss$750
Amount claimed$36,746
SourceAFCA PDF

Summary

The complainant disputed the insurer's storm repairs to footings and sought upgrades, further building damage repairs and driveway and parking bay reinstatement. AFCA found most disputed damage was excluded, required repair of the en suite and a chipped pier, cash settlement of $12,144 for driveway and parking bay, and $750 non-financial loss.

The lifetime guarantee requires the insurer to fix defects in its own repairs, but the disputed damage was caused by excluded gradual deterioration and earth movement rather than by the repair works.

Issues

Subjects and remedies

home or building damagepay claimpay non financial lossrepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case number: 490186 31 Oct 2018 1 Determination overview 1.1 Complaint A storm event in October 2013 damaged the complainant ’s property’s foundations. In June 2014, the complainant lodged a claim under his home insurance policy with the financial firm (insurer), for damage to his property caused by the storm. The insurer accepted liability for damage caused by movement of the concrete pier footings which occurred when the sub-floor was inundated during the storm. The insurer authorised works which included the replacement of the affected footings and the repair of internal cracking and movement damage to the property. The complainant says these works were not completed to an adequate standard, which has resulted in further damage to the property. In particular, he says the insurer should have replaced all of the original footings to prevent further movement in the future. The complainant wants the insurer to upgrade all of the pier footings and rectify the additional damage to the property which has occurred since the original repairs were completed. He also seeks cover for damage to the driveway and parking bay, on the basis that this damage was caused by the storm. The complainant is dissatisfied with the manner in which the insurer handled his claim and seeks compensation for losses incurred as a result. 1.2 Issues and key findings Is the insurer liable for the disputed damage to the building? The insurer is not liable for the disputed damage to the building as this damage was not caused by the storm in October 2013 (or the repairs carried out by the insurer ’s contractors). The disputed damage was caused by factors which are exc luded from cover (such as gradual deterioration and naturally occurring earth movement). Is the insurer required to upgrade the original footings? The insurer is not required to upgrade the original, undamaged footings. The partial replacement of the footings did not cause or contribute to any differential movement at the property. The available information does not establish that the pier and footing works were otherwise defective. Determination | Case number: 490186 Page 2 of 20 Is the insurer liable for the damage to the driveway and parking bay? The insurer has accepted liability for damage to localised sections of the driveway. An additional allowance should be made as it is likely that the parking bay also suffered some damage during the storm. However, the insurer is not liable for any subsequent deterioration of the bitumen surfaces. How should this complaint be settled? The insurer is required to repair the damage to the en suite bathroom and the chipped pier, in accordance with the lifetime guarantee provided under the policy. However, it is reasonable in the circumstances that the claim for damage to the driveway and parking bay be cash settled. Is the complainant entitled to any additional amounts? The complainant is entitled to compensation of $750 for non-financial loss due to the insurer ’s handling of his claim. The complainant is not entitled to reimbursement of professional fees. 1.3 Determination This determination is substantially in favour of the insurer. The insurer is required to:  carry out the repairs set out in IM’s scope of works for the repair of the en suite bathroom and the chipped pier  cash settle the complainant ’s claim for damage to the driveway and parking bay for $12,144, and  pay the complainant the amount of $750 for non-financial loss. The insurer is not required to take any other action. Determination | Case number: 490186 Page 3 of 20 2 Reasons for determination 2.1 Is the insurer liable for the disputed damage to the building? Insurer carried out repairs following storm in 2013 The complainant ’s home is a timber framed building with external cladding, which was relocated from another site in 2006. Following its relocation, the building was installed on concrete block piers with pad footings, in accordance with council approved plans. In June 2014, the complainant lodged a claim for cracking and movement damage to the property caused by a storm in October 2013. The complainant advised that, during the storm, large volumes of stormwater run- off diverted from his neighbour’s property had flowed under his house, causing the footings to move. The engineer (MC) appointed by the insurer confirmed that the cracking and movement damage to the complainant ’s property had been caused by the effects of stormwater run-off. MC advised that, while the majority of the fifty or so concrete piers under the house remained stable, several of the piers had lifted (due to heave caused by the effects of water on the clay foundation soils), while others had sunk (due to supersaturation of the surrounding soils). Based on MC’s report, the insurer accepted liability for the damage to the home and authorised the rectification of the footings and the repair of the internal cracking and movement damage. The initial scope of works prepared by MC provided for the replacement of six to seven unstable piers at the south-eastern corner of the building and the repacking of three piers on the northern side. MC advised that the replacement piers should be ‘upgraded’ - that is, they should be of a greater diameter and fo unding depth than the existing piers. MC’s scope of works also provided for the re -levelling of the floors and the repair of the internal damage. The most extensive works were required to the en suite bathroom, which was located in the area where the piers needed to be replaced. The scope of works was subsequently varied, including to provide for the replacement of several additional piers on the northern side of the house, a ‘complete strip - out’ of the en suite bathroom and the repair of cracking and movement damage to additional rooms. The pier works were completed and the floors re-levelled in December 2014. A ‘settling period’ (to allow for any additional movement) was provided before the internal repairs were commenced in April 2015. Determination | Case number: 490186 Page 4 of 20 The internal repairs were completed in or around May 2015 and a final inspection was undertaken several months later, as a result of which the insurer agreed to cash settle the complainant for the cost of attending to several minor outstanding issues. Complainant says repairs were inadequate and caused further damage In June 2016, the complainant contacted the insurer to express concern that the repairs to the pier footings had not been carried out properly. In his submissions to us, the complainant says that:  the insurer ’s contractors installed hollow piers which were then core filled with slurry (instead of the solid piers provided for in MC’s scope of works)  the house was jacked up so that the core filling could occur, causing further cracking and movement damage to the property, and  the differences between the features of the replacement footings and the original footings has made the property susceptible to ongoing earth movement. The complainant says that the inadequate repairs carried out by the insurer ’s contractors have caused additional damage to the building, including:  damage to the waterproof membrane of the shower in the main bathroom  cracks in the tiles around the en suite windows  movement of the spa bath in the en suite bathroom  cracking to the plasterboard wall linings in areas including the living room  warping of the floorboards and popping of the nails, and  bowing of the window casings and architraves. The complainant wants the insurer to repair the additional damage to the property and upgrade all of the original footings, to prevent any differential movement occurring in the future. Alternatively, he says the house should be demolished and rebuilt. Policy provides a lifetime guarantee of repairs The policy provides a lifetime guarantee for any claim-related repairs authorised by the insurer. The insurer guarantees the quality of the materials used and the standard of workmanship for the lifetime of the building. Accordingly, if the insurer ’s contractors failed to carry out the repairs to an appropr iate standard, then the insurer will be liable for any additional damage which occurs as a result. However, the insurer is not liable for damage to previously repaired areas of the property which occurs as result of the gradual deterioration of the building in the ordinary course (or is caused by factors which are excluded from cover under the policy). Determination | Case number: 490186 Page 5 of 20 Insurer has accepted liability for some of additional damage only After investigating the additional damage, the insurer accepted liability for the movement of the in-built spa bath in the en suite bathroom. The insurer ’s engineer (IM) concluded that the jacking of the house would have caused some movement in the immediate areas where the piers were replaced (including the en suite in the south-east corner). Accordingly, IM considered that the bond between the spa bath and its mortar bedding had loosened during this process. He noted that the wall tiles may also have been affected. In order to reaffix the spa bath, it is necessary to strip out and replace t he tiles and waterproofing in the en suite bathroom. Accordingly, the cracked wall tiles will be replaced as part of this process, which will also address the concerns raised by the complainant about the partial waterproofing undertaken during the original repairs. The insurer has also accepted liability for the cost of repairing chipping damage to one of the existing pier footings, on the basis that this damage may have occurred during the repair process. However, the insurer says it is not liable for the additional damage to the building as this damage was not caused by the storm in October 2013 or the subsequent repairs carried out by the insurer ’s contractors. The insurer says the additional damage identified by the complainant has been caused by factors which are excluded from cover under the policy, such as naturally occurring earth movement and gradual deterioration. Disputed damage was not caused by jacking and core filling process As outlined above, the complainant has identified a number of concerns about the manner in which the repairs to the concrete piers were carried out. During the course of this complaint, both parties have provided copies of numerous reports prepared by various consultants appointed to review the footing works and inspect the damage to the property. Many of the views expressed in these reports are conflicting. The panel has carefully considered these reports (and all of the other information provided), in order to determine the cause of the disputed damage. Having done so, the panel is not satisfied that the disputed damage was caused by the works carried out by the insurer ’s contractors. Determination | Case number: 490186 Page 6 of 20 While MC’s scope of works provided for the use of solid block piers, both the insurer ’s engineer (IM) and the complainant ’s engineer (SC) advised that the use of core filled materials was reasonable, given the height of the piers. Further, IM confirmed that core-filled piers perform in the same manner as the solid piers specified in MC’s scope of works. The complainant says that the jacking up of the house in isolated areas to allow the installation and core filling of the replacement piers imposed substantial stress on the building, causing further damage. The claim records confirm that additional cracking damage to the plasterboard wall and ceilings occurred during the initial pier replacement and re -levelling works. However, it is not unusual for additional damage to internal building components to occur during works of this nature. The insurer repaired the damage as part of the internal repairs completed in mid-2015 (after allowing for an appropriate settling period). As noted above, the insurer ’s engineer (IM) concluded that additional damage to the en suite had occurred during the jacking and core filling process, noti ng that the en suite was located in the immediate vicinity of the replaced piers. However, IM considered that the remainder of the damage had not been caused by the jacking process, as it was too remote from the area where the piers were replaced. While one of the engineers (DW) engaged by the insurer concluded that the disputed damage had been caused by the jacking process, DW’s findings were based on inaccurate information about the manner in which the works were carried out. In his report, DW states that the house was lifted by between 70 and 100 mm in isolated areas to allow the hollow block piers to be core filled using a pump hose. DW advised that, in these circumstances, the house should have been lifted uniformly to prevent further damage. However, the insurer ’s builder (RC) has advised that the core filling was carried out using a wheelbarrow and a small plastic container. Accordingly, the house only had to be jacked up by approximately 5 to 10 mm to enable this to occur. The information provided by RC is reflected in a quotation provided by the re-stumper (TK) when the pier works were being carried out. TK’s quotation noted that the house ‘would need to be jacked up slightly’ to allow core filling to occur. The report provided by the complainant ’ s engineer (SC) suggests that even a small degree of jacking may have resulted in additional damage. Determination | Case number: 490186 Page 7 of 20 The complainant says that jacking of the house by even a small amount in isolated areas would have caused damage throughout the house, due to the translation of movement through the braced timber frame. However, when it was first relocated to the site, the building was cut in half and then re-joined using a system of paired timber bearers along the north-south axis, with the joins between the bearers functioning as articulation joints. The panel accepts the findings of IM that, due to the manner of construction, jacking to one corner of the house will not result in a transfer of movement to other areas. The panel notes that this aspect of the construction was not addressed by SC (who did not carry out his own inspection of the property but conducted a desktop review of documentation). The panel also notes the relative absence of damage in rooms close to where the jacking occurred. In these circumstances, the panel considers it unlikely that the jacking of the house in the manner described and core filling process would have caused damage in areas which are remote from the location where the jacking occurred (such as the main bathroom, which is located in the centre of the western wall). Disputed damage was caused by excluded factors Having carefully reviewed the available information, the panel is satisfied that the disputed damage was caused by factors which are excluded from cover under the policy (namely, gradual deterioration and naturally occurring earth movement). The panel considers that the damage to the waterproof membrane in the main bathroom was caused by gradual deterioration over time, as a result of the manner in which the membrane was installed. The available information indicates that the waterproof membrane was installed over ten years before the damage occurred. The membrane was applied directly to the floorboards, following which concrete screed was installed over the top of the membrane as a bed for the tiles. The insurer ’s consultants have advised that this method does not reflect good industry practice, which requires the use of an underlay or fibre cement sheet between the timber floor boards and the water proof membrane. This was confirmed by the complainant ’s engineer (SC). Photographs taken at various stages during the claim process indicate that the hot water system and air conditioner outlets were discharging moisture directly onto the foundation soils underneath the bathroom. Determination | Case number: 490186 Page 8 of 20 The discharge of moisture into the soil around the footings can result in localised movement damage. This was identified as an issue which may need to be addressed in the pre-purchase reports obtained by the complainant in 2013. The panel acknowledges that the complainant says the leak was not apparent when he installed insulation under the floor boards in February 2014. However, this does not of itself confirm that the waterproof membrane was damaged by the pier replacement process (particularly as the leak was not identified until some time later). The panel considers that the remainder of the disputed cracking and movement damage to the property (including the walls and windows) was caused by naturally occurring earth movement due to variations in the moisture content of the foundation soils. The available information confirms that the property is situated on highly reactive clay foundation soils. The insurer ’s geotechnical engineer (RG) classified the site as Class E (extremely reactive), in accordance with the applicable Australian Standard. RG advised that the site would be susceptible to characteristic surface movement of 60 millimetres (and up to 85 millimetres in the south-east corner, due to a nearby hedge being located within the zone of influence). Consistent with RG’s findings, several of the engineers (MC, DW and IM) noted that the building would be subject to some degree of ongoing differential movement due to the reactive nature of the clay foundation soils. As outlined above, the complainant says that any recent differential movement has been caused by the differences between the original pier footings and t hose which the insurer ’s contractors replaced. The complainant says the insurer should be required to replace all of the existing footings so as to prevent damage to the property caused by ongoing differential movement. 2.2 Is the insurer required to upgrade the original footings? Policy provides for repair of damaged areas only Under the terms of the policy, the insurer is required to repair the damage to the complainant ’s property caused by the storm in October 2013. The policy states that, where the insurer elects to repair the damage (rather than cash settle the claim), it may choose to repair the damage on a ‘new for old’ basis or repair the building to a similar condition to that which it was in before the damage occurred. Determination | Case number: 490186 Page 9 of 20 However, in either case, the insurer is not required to repair the property to a better standard or specification than when it was new. Further, the insurer is only obliged to repair undamaged parts of the property in certain limited circumstances where additional repairs are required to create a uniform appearance. These obligations do not apply in the present case. However, the insurer is subject to an overarching obligation to ensure that any claim- related repairs are completed to an appropriate standard. Accordingly, where the repairs to a damaged part of the property result in an outcome which is unsatisfactory, the insurer may be required to extend the scope of the repairs to undamaged areas. Replacement footings were ‘upgraded’ As outlined above, the plans for the original footings were approved by the local council in 2003, in anticipation of the property being relocated to its current site. The original footing system consisted primarily of 200mm x 200mm concrete block piers, supported by 450mm x 450mm pad footings installed to a depth of 250mm. Larger piers were installed at the corners of the house and along the central line. When the insurer ’s engineer (MC) prepared the scope of works for the initial repairs, he suggested that the footings for the piers should be ‘upgraded’ to provide greater stability (given the height of the piers). Accordingly, the scope of works specified pad footings of 600mm in diameter, installed to a depth of at least 450mm. However, based on subsequent investigations it appears to the footings were installed to a depth of only 410mm. Complainant says upgrade to footings has caused differential movement As outlined above, the complainant says that the combination of the original and the new footings has resulted in the property experiencing differential movement. The complainant has advised he is not disputing that the replacement footings comply with applicable building standards. However, he says that:  the differences between the footings has resulted in non-uniform forces being applied, with the greater mass of the new footings multiplying the effects of any differential movement, and  the insurer should have given greater consideration to the consequences of upgrading some of the footings only (in accordance with guidelines issued by the Australian Building Codes Board). Determination | Case number: 490186 Page 10 of 20 However, having carefully reviewed the available information (including the various engineers’ reports provided), the panel is not satisfied that the differences between the footings has had any material effect on the differential movement at the property. Engineers have provided conflicting opinions The various engineers engaged by the parties have provided conflicting opinions about the adequacy of the original footings and the effect of the partial upgrade. The engineer (OW) who inspected the property on behalf of DK advised that the differential movement to which the property was exposed would be slightly exacerbated by differences in the bearing area of the original and replacement footings. However, OW did not provide any further analysis to support his conclusions. The insurer ’s engineer (IM) advised that the differences between the footings would not result in additional movement at the property. IM noted that the extent of vertical movement would be determined by the reactivity of the clay soils, regardless of the footing mass. The insurer ’s geotechnical engineer (RG) advised that, given the site conditions, the footings should be designed based on an allowable bearing pressure of 100kPa. His investigation of two original and two new footings confirmed that the design satisfied this requirement. Based on the results of RG’s investigations, IM confirmed that both the existing and new footings were suitable for the site (despite the new footings having only been installed to a depth of 410mm). However, the complainant ’s engineer (SC) advised that the original footings did not comply with the relevant Australian Standard for residential slabs and footings in force at the time the building was relocated to the current site. SC considered that the partial replacement of the existing footings created differential movement between the two footing systems. He considered that the use of new, upgraded footings exacerbated the issues arising from the inadequacy of the original footings. The Australian Standard for residential footings (as referred to by SC) states that on reactive clays, concentrated loads from columns should be supported directly on an edge or internal beam or edge footing (rather than a pad footing). The insurer ’s engineer (IM) disputes that the Australian Standard referred to by SC applies to the pad footings at the site. Determination | Case number: 490186 Page 11 of 20 IM says that, because the footings support a relocated timber frame house, they are subject to the Australian Standard for residential timber-framed constructions (with which they are compliant). Having carefully reviewed the available information, the panel is not satisfied that the original pad footings were inadequate. The footings were approved by the council at the time they were installed and geotechnical assessment has found them to be appropriately designed. Further, the complainant has confirmed the footings performed adequately prior to the storm. Upgrade of footings has not caused differential movement Based on the available information, the panel is not satisfied that the partial replacement of the original footings has resulted in differential movement at the property. For the reasons outlined above, the panel is satisfied that the original footings were adequate. In these circumstances, the panel does not consider that the replacement of a relatively small number of the original footings has had any material increase in the extent to which the property is susceptible to differential movement. The panel is not satisfied that the location of the further damage identified by the complainant supports his position that this damage has been caused by relative differences in the mass of the original and replacement footings. All of the engineers engaged by the parties agree that the property is located on reactive clay soils which are subject to differential movement due to changes in the moisture content of the foundation soils. During his initial inspection of the property in August 2014, MC observed that the property appeared to have been re-levelled in the past (as shown by the presence of packers between the tops of the piers and the bearers). This is indicative of prior differential movement. The panel acknowledges that the pre-purchase building report obtai ned by the complainant in June 2013 did not identify any cracking and movement damage at that time. The complainant also says past residents of the property did not observe any such damage. Nevertheless, the nature of the reactive soils at the site mean that the property is inherently susceptible to differential movement. The nature of such movement means that it is subject to seasonal changes and therefore occurs on an irregular basis. Determination | Case number: 490186 Page 12 of 20 Further, the available information indicates that the site has been subject to various alterations which may have affected the levels of moisture in the foundation soils. In particular:  the non-compliant drains installed by the complainant ’s neighbour were removed during the first half of 2014, and  the complainant installed retaining walls and associated drainage pipes at some stage between 2016 and 2018. Insurer is not required to upgrade the original footings As noted above, the policy does not require the insurer to repair or replace any undamaged parts of the property (unless necessary for the effective repair of the claim-related damage). For the reasons outlined above, the panel is not satisfied that the works undertaken by the insurer ’s contractors (in replacing some of the original footings only) has resulted in further damage to the property. The panel is satisfied that the repairs set out in MC’s scope of works (as subsequently varied) were appropriate to address the damage to the building caused by the storm in October 2013. MC has inspected the completed works to the footing system and has confirmed that they have been carried out to a satisfactory standard and in accordance with his scope of works. Based on the available information, the panel is not satisfied that the works are otherwise deficient (including in relation to the use of crusher dust). Accordingly, the insurer is not required to undertake any rectification works to the footings (either by upgrading the original footings or altering the replacement footings to match the original footings). 2.3 Is the insurer liable for the damage to the driveway and parking bay? Complainant seeks cover for damage to driveway and parking bay The complainant says the driveway and parking bay at the property were damaged by the effects of stormwater run-off during the storm in October 2013. He says the stormwater flows washed away the sub-strate under the bitumen surface, compromising the integrity of the driveway and parking bay. The complainant has provided a quotation from his repairer for $36,745.50 for the full reinstatement of the driveway and the parking bay. Determination | Case number: 490186 Page 13 of 20 Insurer has accepted liability for localised damage to driveway The insurer ’s claim records reflect that, when the complainant lodged his claim, he advised that the brick pier footings had moved and there was internal damage to the property. There is no reference to any damage to the driveway and parking bay. Further, there is no reference to this damage in the reports prepared by the insurer ’s builder (LS) and engineer (MC) following their initial assessments of the property (although MC took photographs of various sections of the driveway). Accordingly, it is unclear to what extent the damage to the driveway and parking bay was assessed at this time. The complainant raised concerns about the omission of the driveway from the initial scope of works prepared by MC in August 2014. However, the insurer declined liability for this damage, based on advice from its builder (RC) that the bitumen used was of poor quality and the deterioration of the driveway was unrelated to the storm. The insurer ’s engineer (IM) initially advised that the damage to the driveway was not caused by the one-off effects of the storm in October 2013. IM considered that an adequately sealed driveway was designed to be exposed to the elements and would have been able to withstand surface run-off. However, IM revised his opinion after the complainant provided photographs of the driveway prior to the storm (which showed it to be in good condition, consistent with the findings in the pre-purchase inspection report). In his supplementary report, IM reiterated his view that the general wear and tear evident to the driveway had occurred over an extended period of time. However, IM also accepted that localised sections of the driveway may have been damaged by the concentrated cross- flow of water from the neighbour’s non -compliant stormwater pipes during the storm. The insurer has accepted liability for the repair of those sections of the driveway identified in IM ’s report. These sections show significantly greater damage than other areas and were in the direct pathway of the storm water flows. The insurer has offered to cash settle the complainant for the cost of repairing these sections of the driveway, based on quotations provided by its contractors. Parking bay may have been damaged by stormwater run-off The complainant has advised that he generally agrees with the views expressed in IM’s supplementary report regarding the localised effects of stormwater flows on the driveway. Determination | Case number: 490186 Page 14 of 20 However, the complainant says that IM failed to consider that the parking bay would have also been affected by the stormwater flows. The complainant notes that the photographs on which IM based his analysis of stormwater flows showed the parking slab, retaining wall and associated drainage installed near the parking bay, which were not in place at the time of the storm. It is difficult to determine with certainty the extent to which the parking bay was affected by the storm in October 2013, given the limited photographic evidence available and the amount of time which has passed since the storm occurred. Nevertheless, the surface of the parking bay (as shown in recent photographs) shows signs of significant deterioration. Further, the location of the parking bay suggests that (absent the retaining wall), it may have been exposed to the water flows from the neighbour’s drainpipes identified in IM’s report. On this basis, the panel considers it is fair in the circumstances that the cash settlement include an appropriate allowance for damage to the parking bay. Insurer is not liable for subsequent deterioration of driveway and parking bay The complainant says that the insurer ’s failure to provide cover for the driveway and parking bay during the initial stages of the claim has caused these areas to deteriorate further, such that they now require complete replacement. The panel accepts that it is likely that the initial damage from the storm in 2013 would have compromised the sub-strate layer, resulting in further damage during rainfall events in subsequent years. However, the panel is not satisfied that the insurer is responsible for the subsequent deterioration of the driveway and parking bay. After raising concerns about this damage in September 2014, it appears the complainant did not pursue the issue again until mid-2017. The panel considers the complainant was responsible for mitigating any additional damage during this period. 2.4 How should this complaint be settled? Insurer is required to repair en suite and chipped pier For the reasons outlined above, the panel considers that the insurer ’s liability in respect of the building is limited to repairing the damage to the en suite bathroom and the chipped block pier. Determination | Case number: 490186 Page 15 of 20 The insurer has offered to cash settle the complainant for the cost of these repairs, based on a quotation provided by its builder (DA) in accordance with a scope of works provided by (IM). The complainant has rejected the cash settlement offered by the insurer. He says the insurer should be required to carry out the repairs, so that he can obtain the benefit of the lifetime guarantee provided under the policy. The complainant also says the amount of the cash settlement is insufficient and does not reflect the specifications of the fixtures and fittings in the en suite bathroom. Under the terms of the policy, the insurer can settle a claim by repairing the damage to the complainant ’s property or paying him the cos t of doing so. However, once an insurer makes an election to repair (rather than cash settle), it is generally obliged to complete the repairs in accordance with the terms of the policy. In the present case, the repairs set out in IM’s scope of works are necessary in order to rectify damage resulting from the original repairs. In these circumstances, it is not appropriate that the insurer can elect to cash settle the claim. Accordingly, the insurer is required to carry out the repairs set out in IM’s sco pe of works for the repair of the en suite bathroom and the chipped pier. The quality of the materials used should reflect the existing materials. Insurer is required to cash settle complainant for repairs to driveway and parking bay The cash settlement offered by the insurer includes an amount of $8,096 (including builder’s margin and GST) for the repair of the localised sections of the driveway identified in IM’s supplementary report. The panel considers it is appropriate that this aspect of the repairs be cash settled. This will allow the complainant to appoint his own contractor to reinstate the driveway and parking bay in their entirety (as he has advised is required). As outlined above, the panel considers the amount of the cash settlement should be increased to reflect an allowance for damage to the parking bay caused by the storm (noting the extent of this damage is unclear). The cash settlement amount should also be increased to allow for:  any volume discounts reflected in the quotation provided by the insurer ’s builder, and  the additional risk assumed by the complainant due to the absence of the lifetime guarantee. Determination | Case number: 490186 Page 16 of 20 Having regard to the factors outlined above, the panel considers the cash settlement amount should be increased by 50% (to a total of $12,144). The insurer is not required to pay interest on this amount. Complainant is entitled to compensation of $750 Under the FOS Terms of Reference, we may award compensation for non-financial loss (capped at $3,000) where a complainant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the complainant ’s expectation of enjoyment or peace of mind. However, we adopts a conservative approach to the award of compensation for non- financial loss. The complainant is dissatisfied with the manner in which the insurer managed his claim. Among other things, the complainant says that the insurer:  unreasonably delayed the resolution of the claim  tried to settle the claim based on incomplete scopes of work and quotations, and  failed to respond to his concerns about the adequacy of the initial repairs. For the reasons outlined above, the panel considers that the insurer is not liable for the bulk of the additional damage to the property which has occurred since the initial repairs were completed. However, during the course of the complaint process, the insurer has accepted liability for some of the additional damage. The complainant raised concerns about these aspects of the damage relatively early in the process. In the circumstances, the panel considers the insurer should be required to pay the complainant the amount of $750 as compensation for non-financial loss. Complainant is not entitled to reimbursement of professional fees Under the FOS Terms of Reference, we may decide that the insurer contribute to professional costs incurred by the complainant in the course of the complaint. The complainant incurred fees in obtaining a report from his engineer (SC). However, the panel does not consider that SC’s report altered the outcome of the complaint. Accordingly, the insurer is not required to contribute to the costs incurred by the complainant in obtaining SC’s report. Determination | Case number: 490186 Page 17 of 20 3 Supporting information 3.1 The determination is made under FOS Terms of Reference The Australian Financial Complaints Authority ( AFCA) has commenced managing disputes previously lodged with F inancial O mbudsman S ervice (FOS) . This determination is made under FOS Terms of Reference but has adopted the following terminology for consistency with AFCA. In this determination the AFCA terms have the same meaning as the FOS terms defined in paragraph 20.1 and Schedule 1, 2 & 3 of the FOS Terms of Reference. FOS definitions AFCA term  applicant  complainant  financial services provider  financial firm  dispute  complaint  claim  claim 3.2 Our approach to this complaint This complaint has not been the subject of a recommendation. Due to the nature of the complaint, it has been referred directly to a panel for determination, in line with the Operational Guidelines to the FOS Terms of Reference. The panel consists of an Ombudsman and two representatives with consumer and insurance experience. The panel has decided this case based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and our previous decisions (which are not binding). There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. The panel has reviewed and considered all of the material provided by the parties. While the parties have raised numerous issues in their submissions, for the purposes of this determination the panel has restricted its commentary to those issues that it considers directly relevant to the outcome only. 3.3 Key policy terms Subject Terms Determination | Case number: 490186 Page 18 of 20 Subject Terms Cover for building What we cover – the building The building that you own or are responsible for and use primarily for domestic purpos es … including the following at the insured address: …  driveways or sealed roads … Insured event – storm We cover Loss or damage to the building caused by a storm. We do not cover …  loss or damage caus ed by erosion, vibration, subsidence, landslip, landslide, mudslide, collapse, shrinkage or any other earth movement, but we will cover loss or damage to the building caused by a landslide or subsidence that occurs within 72 hou rs of, and directly because of, a storm and not because of erosion over time, structural fault or design fault …  resultant cracking to paths, driveways, any outdoor surfaces, but we will cover them if they are washed away by the storm … General exclusions You are not covered under any section of your policy for damage, loss, cost or legal liability that is caused by, arises from or involves: … Ground movement  erosion, vibration, subsidence, landslip, landslide, mudslide, collapse, shrinkage or any other earth movement, but we will cover landslide or subsidence that is specifically covered under the following insured events: > ‘Storm’ … Wear, tear and gradual deterioration Wear, tear, ... or gradual deterioration … Settlement of claims If we agree to pay a claim for loss, theft or damage to the building, we will decide if we will:  repair damage to the building;  rebuild the building;  pay you what it would cost us to repair or rebuild the building … If we repair (or pay you what it would cost us to repair), we will at our option repair on a `new for old’ basis or repair to a similar condition to what the building was in before the loss or damage occurred. We will not:  pay extra to repair or rebuild the building to a better standard, Determination | Case number: 490186 Page 19 of 20 Subject Terms specification or quality t han it was before the loss or damage occurred except as stated in the following meaning of ‘new for old’;  fix a fault that existed before the loss or damage occurred … ‘New for old’ means:  New materials, new items we rebuild or repair with new items or ne w materials that are available at the time of replacement or repair from Australian suppliers  New for old, regardless of age we rebuild or repair regardless of age, with no allowance for depreciation  Same type, standard and specification a s when new We re place or repair to the same type, standard and specification as when new. If the same is not available, it means of a similar type, standard and specification when new. It can be a different brand. ‘New for old’ does not …  mean of a better standard, specif ication or quality than when new … When we will repair or rebuild undamaged parts If we cannot match the mat erials with the undamaged parts, we will pay extra to create a uniform appearance when:  wall tiles are damaged …  other wall coverings are damaged …  floor coverings are damaged …  kitchen cabinets, cupboards or benchtops are damaged … Lifetime guarantee of repairs Lifetime guarantee on building repairs When we repair or rebuild the building, we guarant ee the quality of materials and workmanship of that work for the lifetime of the building if we … authorise, … arrange … and pay the building or repairer directly for this work. What we guarantee We guarantee the material used and the standard of the workmanship to be free of defects. If a defect arise s in the lifetime of the building as a result of poor quality workmanship or use of incorrect materials, then we will rectify the problem. This guarantee does not apply: …  to wear and tear consistent with normal gradual deterioration of Determination | Case number: 490186 Page 20 of 20 Subject Terms the building (e.g. paint peeling off after its expected life cycle, wood rotting from moisture in the air or ground, roofs weathering or a hot water tank leaking after its guaranteed life) …

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.