Declined storm damage claim for floor tiles under defective workmanship exclusion

FirmFinancial Firm (Unknown - Insurer)
Decided2018-06-12
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded—
Non-financial loss$250
Amount claimed—
SourceAFCA PDF

Summary

The FSP declined storm-related floor tile damage under a defective workmanship exclusion and took over three months to reject the claim. AFCA found a valid storm claim, ordered cash settlement of the tile and skirting work, and awarded $250 non-financial loss.

The insurer must show an exclusion applies to the dominant cause of loss, and it could not establish that faulty workmanship rather than the storm caused the damage.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 489277 Determination Page 1 of 6 Case number: 489277 6 June 2018 1 Overview 1.1 Dispute The applicant made a claim for damaged floor tiles under his home and contents insurance policy held with the financial services provider (FSP), following a storm. The FSP declined the claim on the basis that the loose floor tiles were the result of faulty and/or defective workmanship, and so cover was excluded. The applicant did not accept this. He also says there were delays and service issues with the FSP’s handling of the claim. The case analyst issued a recommendation in favour of the applicant, but the FSP did not agree. 1.2 Issues and key findings Is the FSP entitled to decline the claim? There was a severe storm just prior to the damage being identified and the claim being lodged. The applicant said there had been no problem with the tiles before that. The evidence shows, on balance, that he has a valid claim for storm damage to the property. The FSP cannot rely on the general exclusion of defective and/or faulty workmanship to deny the claim, as it has not established, on balance, that is what caused the loss. That means it is liable for the damage to the tiles and skirting (but is not liable for the replacement of the toilet and vanity, which have not been shown to have been damaged). Is the applicant entitled to compensation for non-financial loss? The applicant experienced unnecessary delay and inconvenience as a result of the FSP’s handling of the claim, and it is fair that compensation for non-financial loss be paid. 1.3 Determination This determination is substantially in favour of the applicant. The FSP is required to cash settle the claim for the damaged tiles and associated work to the skirting. It is also required to pay the applicant $250 compensation for non-financial loss. Case No: 489277 Determination Page 2 of 6 2 Reasons for determination I have decided this case on the basis of what I consider fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. I have taken into account all the material submitted by the parties, both before and after the recommendation. I am satisfied that the documentation I have relied on has been provided to both parties. For the purposes of this determination, I will deal with only those points considered relevant. 2.1 Is the FSP entitled to decline the claim? Applicant has established, on balance, a valid claim for insured storm event There is no dispute that the tiles in the downstairs section of the applicant’s property have been damaged. The FSP’s builder (‘A’), who attended at the property within a week of the claim being made, reported ‘the floor appeared to be wet’ and concluded ‘we find the damage is consistent with the claimed event’. After a specific prompt for clarification from the FSP following the recommendation, ‘A’ explained that the wording of their conclusion was not clear , and said instead ‘there has been no event that has resulted in the drummy tiles’. However, if that was the case, then I consider it would have been appropriate for that to have been specifically noted in the original report, and for the report to have clearly identified what was being relayed from the applicant, and what was being presented as A’s professional opinion. As it is, I consider the original report accepts in any case the likelihood of the identified tile damage being from the storm. The FSP’s engineer, SF , did not visit the property until over 2 months later. For that reason, I do not place particular weight on their observation that they had ‘found no eviden ce of elevated floor tile moisture currently or from any event’, since it is more than likely that any moisture from the storm event will have dried out by then. I am satisfied that the applicant has established, on the balance of probabilities, that the tiles sustained damage as a result of the storm event. FSP says that damage is due to defective and/or faulty workmanship As the applicant has established a valid claim, the FSP needs to show that an exclusion applies, or that the claim can otherwise be denied. The FSP says that the damage was caused by defective and/or faulty workmanship, which is a general exclusion under the policy. It points out that its engineer, SF, says there is no evidence that tile defects were caused by any weather event, rising damp or building movements. SF says that the absence of floor tile expansion joints (which makes it non-compliant with AS 3958.1) has caused the tiles to lift and become ‘drummy’. SF also refers to likely poor preparation of the old existing tile surface (suggesting the older tiles had Case No: 489277 Determination Page 3 of 6 ‘possibly’ not been cleared of dust and moisture) and the use of ‘ ina dequate’ tile- over-tile adhesive as a likely contributing factor. However, it is not clear on the available evidence, what version of AS3958.1 applied at the time the property was built and the tiles were laid (either the original tiles or the now damaged tiles which were laid over them); and what differences there might have been between any versions applicable at the relevant times . Nor is there any commentary on how the original layer of tiles beneath had been laid, and what evidence they might have been showing of moisture or movement. ‘ A ’ had also referred in their report to the damage as having been caused ‘as a result of floor tile glue releas ing from the concrete slab ’ . While it was subsequently found that the tiles were not laid directly onto the slab, I consider this statement, in itself, reasonably allows for the likely effect of water on tile adhesive. There is no suggestion that that woul d necessarily mean the adhesive was faulty or defective. FSP must accept the claim I am not satisfied, on the evidence, that the FSP has established the dominant, effective or operative cause of the damage was any faulty or defective workmanship. While the tiles may not have been laid consistent with current guidelines or standards, I am not persuaded the damage would have happened if it were not for the storm (cyclone) event. I also accept, on balance, that the applicant had not experienced prior problems with the tiles in the 12 years or so during which he had lived in the house. In relation to the extent of liability, the applicant has submitted a quote from his builder. I understand that he has now had the repair work completed, in order for his family to be able to fully use the area again. The FSP must accept the claim and pay for the damaged tiles in the affected downstairs area of the home, and that includes covering the related work to remove, replace and paint the skirting. However, it is not liable for replacement of the vanity and toilet (which have been included in the quote), as the applicant has not submitted any evidence to show that these items were damaged as a result of the storm event. The applicant will need to submit specific invoices/receipts for the completed work, so that the FSP can clearly identify those costs for which it is liable. 2.2 Is the applicant entitled to compensation for non-financial loss? FSP unreasonably delayed the processing of the claim and inconvenienced applicant FOS may award compensation for non-financial loss where there has been an unusual degree of upset or inconvenience as a result of the FSP mishandling a claim, for example by unnecessarily and excessively delaying it. The applicant says that the FSP took over three and a half months to reject his claim, and during that time h e constantly had to call the FSP, its assessor and its builders and t hese parties kept changing the deadlines. He also says h e and his family ha d Case No: 489277 Determination Page 4 of 6 been living upstairs the entire time, as they did not want to damage the area any further. I accept that at least some of the delay was unreasonable, and that the applicant and his family will have experienced avoidable upset and inconvenience as a result. Under the circumstances, I am satisfied that an award of $250 compensation is fair. Case No: 489277 Determination Page 5 of 6 3 Supporting information 3.1 Key references Product Disclosure Statement Record Key points Product Disclosure Statement (PDS) 28 - 12 - 2015 Page 26 Storm A storm has very strong winds and may also involve heavy rain, hail or snow. For example, a cyclone. A storm is not just continuous bad weat her on its own. Yes  A storm causes loss or damage to your home or contents. Pages 61 - 62 3. General exclusions What we don’t cover This section outlines the general things we don’t cover under your policy. They are known as general exclusions. Specific exclusions also apply to certain parts of your cover and are shown as crosses (X) where we describe the cover you have under your policy. Those specific exclusions are shown in the section ‘Your cover’ under any relevant event or benefit that is outlined on pages 19 - 60. Also, w e don’t cover certain items as part of your home or contents which are listed on pages 13 and 16. General exclusions These general exclusions apply to all of the cover we provide under your policy. We don’t cover you under your policy for loss or damage to your home or contents or for legal liability which is caused by or arises in connection with any of the following items, events or circumstances: … Defective or faulty workmanship X Any inherent or built - in defect or defective or faulty workmanship, desig n or manufacture. Correspondence from applicant Communication Content Email from applicant to FOS 08 - 09 - 2017 2. Provide a timeline of the delays you experienced. Email Corres pondence:  ‘4th of April, L notifying me that they have received the claim and that someone will be in touch with me.  7th of the April, contacted L notifying them that no one has been in touch with me.  10th of April, L contacts me, thanking me for bringing it to their attention that no one has been in touch with me. Also, to let then know if B does not get in touch with me in the next 24 hours. Case No: 489277 Determination Page 6 of 6  26th of May, [FSP’s rep] sends me confirmation that they ha ve received a quote from a builder relating to the damaged tiles. (this is a independent builder which I had to arrange to come and inspect the property as my insurance provider was taking too long)  8th of June, L notifies me that forensic report has been completed by engineer. (engineer had inspected property 5th of June)  6th of July, L contacts me, letting me know that they are still waiting on [FSP’s rep] for a response to the reports provided.  10th of July, [FSP’s rep] sends me rejection letter for my claim. (That’s 102 days since I put claim in)  22nd of July, [FSP’s rep] emails me relating to complaint I put forward and sends me engineers report. I could only pull up the emails as I used multiple phones to contact both [FSP’s rep] and L. But each email response is due to multiple phone calls, and a constant push for tasks to be completed. As you are already aware, my claim was put forward 30th of March. The builders attended within the first week, however took several weeks to put forward their findings and reports. B submitted report 24th of May, they were at property 13th of April (41 days, Report was supposed to take several days max). The engi neer however came out to the property 5 th of June, that’s 67 days after claim was made. The tiles are internal, house is cleaned regularly, constant attention was placed on tiles to make them safe and clean. After 67 days of sunshine, drying and cleaning t he site there is no way any moisture should be present. I strongly believe if the engineer came out in an appropriat e time frame, his report would be different. [sic]’

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.