Home / Financial Firm (Unknown) / Determination 487704

Determination 487704

Delayed clearance of inter-bank transfer and delayed redraw activation

FirmFinancial Firm (Unknown)
Decided2018-01-25
ProductPayment Systems · Account payment / transfer
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$70,000
SourceAFCA PDF

Summary

A company and its director complained that a large sale-proceeds transfer took four business days to clear and that the FSP delayed redraw activation, claiming a $70,000 capital gains tax loss. AFCA found the FSP's processing was reasonable and the applicants did not establish any loss.

The FSP processed the transfer within acceptable industry timeframes, and the applicants did not show the claimed capital gains tax loss was caused by any delay.

Issues

Subjects and remedies

small businessno remedy

Related

All Financial Firm (Unknown) determinations · Find similar determinations

Text of the determination

Determination Case No: 487704 Determination Page 1 of 3 Case number: 487704 25 January 2018 1 Overview 1.1 Dispute The applicants include Ms P and a company of which she is a sole director (the company). The dispute is about the company‟s transaction account (the account) and Ms P‟s home loan (the loan) held with the financial services provider (FSP). In early 2017, the company sold its business (the business) to three buyers. It was Ms P‟s intention of dividing the sale over the 2016/17 and 2017/18 financial years. On 30 June 2017, settlement occurred for the sale of part of the business. The purchase funds were sent by another financial institution to the account with the FSP (the transaction). The applicants say the FSP unreasonably delayed its processing of the transaction because the funds should have arrived on 30 June 2017 but were not “cleared” in the account until 6 July 2017. Ms P also says the FSP unreasonably delayed setting up redraw and offset facilities for the loan. The case analyst provided the parties with a recommendation dated 8 December 2017 on the issues in dispute. The recommendation was in favour of the FSP. A copy of the recommendation is attached to this determination. 1.2 Issues and key findings Were the findings of the recommendation correct? Based on all the available information, the findings contained in the recommendation were correct and are adopted in this determination. The FSP did not unreasonably delay processing of the transaction and the funds could not have arrived on 30 June 2017. It has not been established that the FSP unreasonably delayed setting up the redraw and offset facilities for the loan. In addition, the applicants have not shown any loss arising from the FSP‟s actions. 1.3 Determination This determination is in favour of the FSP. I agree with the case analyst‟s reasons for the recommendation and the recommended outcome. The FSP is not required to compensate the applicant. Case No: 487704 Determination Page 2 of 3 2 Reasons for determination 2.1 Were the findings in the recommendation correct? The recommendation was accurate I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. I have taken into account all the material submitted by the parties, both before and after the recommendation. I am satisfied that the documentation I have relied on has been provided to both parties. I am satisfied that the case analyst ‟s recommendation contains an accurate s ummary of the dispute, the issues to be determined, any applicable paragraphs of the Terms of Reference and any relevant law. I do not propose to repeat the contents of the recommendation in this decision and adopt its findings. The applicants did not provide reasons for rejecting the recommendation or information showing any loss The applicants rejected the recommendation because they do not consider the recommended outcome was fair and reasonable. However the applicants did not provide any specific response to the issues discussed in the recommendation, nor did they provide any documentary evidence to support their positions or claims for loss. As part of our investigation, FOS asked the applicants to provide certain information to assist with our consideration of the dispute. In particular, FOS asked Ms P to provide information establishing loss in case we found in the applicants‟ favour. For instance, information showing that they will be charged capital gains tax (CGT) from the date the funds cleared into the account, rather than the date of sale. Ms P declined to provide FOS with this information. Where a party does not provide information FOS has requested, we may conclude they have chosen not do so because it does not support their position. In the circumstances of this dispute, without information to show otherwise, the applicants have not established the losses claimed. Accordingly even if I found in the applicants‟ favour (which I have not), it has not been established that the applicants have incurred any loss arising from any delay. The findings in the recommendation were correct Based on all the available information, I agree with the recommendation findings that:  the FSP did not unreasonably delay its processing of the transaction. The sending financial institution chose how to send the funds in the transaction. The funds appeared in the account on the business day following 30 June 2017 (being 3 July 2017) and were cleared by the FSP in line with acceptable industry standards  even if the FSP did unreasonably delay its processing of the transaction, the applicants have not provided any information to show they will be charged CGT Case No: 487704 Determination Page 3 of 3 in the 2017/2018 financial year, when the sale actually occurred in the previous financial year  the FSP activated the redraw within a reasonable period of time and did not make any error in denying Ms P access to an offset account where the loan did not qualify for that feature  Ms P had access to funds prior to the redraw being activated and  the applicants have not provided sufficient information to show any losses incurred as a result of the FSP‟s actions . Each of the above issues was addressed adequately and correctly in the recommendation. Therefore, I need not repeat the analysis in this determination. The applicants have not provided any information to warrant a departure from the recommendation findings. Recommendation Case No: 487704 Recommendation Page 1 of 5 Case number: 487704 8 December 2017 3 Overview 3.1 Dispute The applicants are a company (the company) and Ms P in her capacity as an individual borrower. Ms P is also the sole director of the company. The dispute is about the company‟s transaction account (the account) and Ms P‟s home loan (the loan) held with the financial services provider (FSP). In early 2017, Ms P sold the company‟s business (the business) to three buyers with the intention of dividing the sale over the 2016/17 and 2017/18 financial years. On 30 June 2017, settlement occurred for Company A‟s purchase of its share of the business and the purchase funds (funds) were sent to the company account (the transaction). The applicants say the FSP unreasonably delayed its processing of the transaction because the funds were not “cleared” until 6 July 201 7. Ms P also says the FSP unreasonably delayed setting up redraw and offset facilities for the loan. 3.2 Issues and key findings Did the FSP unreasonably delay its processing of the payment? The FSP did not unreasonably delay its processing of the transaction into the account. The funds appeared in the account within one business day of the transaction being made and were cleared within four business days. This is a reasonable period of time and within acceptable industry practice. Did the FSP unreasonably delay setting up the redraw and offset facilities? The FSP activated the redraw within two and a half weeks of Ms P‟s initial request. This was not an unreasonable period of time. Further, the FSP does not offer offset facilities for the type of home loan product Ms P holds. The FSP did not make any error in setting up the redraw facility or denying Ms P access to an offset account. 3.3 Recommendation This recommendation is in favour of the FSP. The FSP should not be required to compensate the applicants. Case No: 487704 Recommendation Page 2 of 5 4 Reasons for recommendation 4.1 Did the FSP unreasonably delay its processing of the transaction? The FSP processed the transaction within a reasonable period of time The FSP did not unreasonably delay its processing of the transaction into the account. The available information shows the transaction, totalling $1,265,312.40, was made by a paper credit transfer voucher on 30 June 2017 and was entered into the FSP‟s system at 10PM on the same da y. The account statements show the transaction funds appeared in the account as:  „uncleared‟ on 3 July 2017, which was the following business day, and  „cleared‟ within four business days of the transaction date. It is not uncommon for an inter-bank transfer to take two to five business days for a payment to be processed and received as cleared funds. This is because it allows the financial services provider time to complete any necessary checks to ensure a payment has been made and received in line with the relevant instructions. As it took one business day for the transaction to appear in the account and four business days from the date the transaction was made to the date the funds cleared, the FSP processed the transaction within a reasonable period of time and in line with acceptable industry practice. Ms P did not ask the FSP to provide her with special clearance beforehand Ms P says it was reasonable for her to expect the funds would clear on the same day as settlement because she had received payments from Company A instantaneously over the past 15 years. She says it was reasonable to expect the transaction would be no different after 15 years of established conduct. It is not disputed Ms P received funds from Company A on a monthly basis for commissions and profits. However, in this case, the transaction was made for a significantly larger amount and for a different purpose. Namely, the purchase (or buy- back) of the business. Ms P has confirmed she did not put the FSP on notice that she would be receiving the transaction. Nor did she attempt to make any special arrangements with the FSP to ensure the funds could be immediately received as cleared funds. It is not reasonable to expect the FSP would be aware Ms P needed the funds to clear immediately without having first been put on notice of this fact. For this reason, the FSP cannot be held accountable for Ms P‟s assumptions about when the funds would clear. The emails from Company A do not lead to a conclusion the FSP made an error Ms P has provided a number of emails between her and the staff member responsible for completing the transaction on behalf of Company A (Mr M). In these emails, Mr M advised Ms P she could expect to receive the funds on 30 June or 1 Case No: 487704 Recommendation Page 3 of 5 July 2017 depending on processing. Ms P relies on this email correspondence to show the FSP intentionally delayed its processing of the transaction. Whilst this email exchange may have caused Ms P to expect she would receive the funds by 1 July 2017 at the latest, it does not mean that the info rmation Mr M gave her was correct. Nor does it prove the FSP unreasonably or intentionally delayed its processing of the funds. It does, however, show she was on notice that:  the transaction would need to be processed, and  there was a possibility she would not receive the funds on the same date as settlement. As Mr M is not the FSP‟s representative, the FSP is not responsible for the information Mr M provided her about how long it would take to process the transaction. Ms P did not otherwise reasonable steps to mitigate her loss Ms P says she could have scheduled settlement for 20 June 2017. This would have provided her with a 10 day period within which to receive the funds before the end of the 2016/2017 financial year. It would also have given her ample time to make the relevant payments she had negotiated to pay on 30 June 2017. Instead, Ms P says she decided to proceed with settlement on 30 June 2017 despite having the option to settle earlier. She has not provided any information to explain why she selected the latter date. As the party who needed the funds to arrive in the account on 30 June 2017, Ms P was in a position to mitigate her loss and take steps to ensure the funds would arrive in the account on time. This includes taking steps to:  schedule settlement a few days before she needed the funds to arrive in the account, or  discuss her concerns with the relevant parties (eg Company A, the FSP, etc) to ensure a more immediate method of payment would be used. It is undeniable how important it was to Ms P that she received the funds on 30 June 2017 because she had told a number of parties she would pay them by that date. However, in these circumstances, it was incumbent on her to take the necessary precautions to ensure the funds were received on time, rather than assume it would all work out. Ms P has not shown she will be charged additional capital gains tax According to the Australian Taxation Office (ATO) website, capital gains tax is typically calculated at the time of sale rather than the date of settlement or when cleared funds are received into the vendor‟s account. Ms P has not provided any information to show this explanation does not apply to her circumstances. Nor has she shown she will be charged an additional $70,000 in capital gains ta x in the 2017/2018 financial year because the funds did not clear on 30 June 2017. Without any information to show the ATO will charge capital gains tax for the sale to Company A in the 2017/2018 financial year, Ms P has not shown she has incurred this loss. On the weight of information, it is more likely than not the applicable capital Case No: 487704 Recommendation Page 4 of 5 gains tax will be calculated from the date of sale rather than the date the cleared funds were received. 4.2 Did the FSP unreasonably delay access to the redraw and offset? The FSP did not unreasonably delay access to the redraw The FSP has provided a copy of its contact and collection notes outlining its dealings with Ms P. This information shows:  on 7 July 2017, Ms P contacted the FSP to activate the redraw linked to the home loan  the FSP needed to remove a „post credits only‟ limitation from the home loan, which is a stop preventing any drawings being made from the home loan  on 26 July 2017, the „post credits only‟ limitation was removed from the home loan and the redraw was activated. Ms P has not provided any information to show she contacted the FSP earlier than 7 July 2017 to ask for the redraw to be activated. The FSP activated the redraw within two and half weeks of Ms P‟s initial request. Given the FSP needed to remo ve the „post credits only‟ limitation from the home loan before it could activate the redraw, this period of time was not unreasonable. Further, the account statements show Ms P did not deposit any of the sale proceeds into the home loan until 4 August 2017, some nine days after the redraw was activated. This shows Ms P still had access to these funds while she waited for the redraw to be activated. As Ms P had access to the funds during this period, and the FSP‟s delay in activating the redraw was not unr easonable, the FSP should not be required to compensate Ms P for this aspect of her claim. The home loan does not provide an offset option The FSP did not make any error in failing to provide Ms P with an offset account linked to the home loan. This is because the FSP says the particular home loan product Ms P holds does not include an offset option. As such, the FSP did not make any error or breach any obligation owed to Ms P by denying her access to an offset account. Case No: 487704 Recommendation Page 5 of 5 5 Supporting information 5.1 Timeline of events Date Details 30 June 2017  Settlement for the sale of the business occurred  The transaction was entered int o the FSP‟s system at 10PM 3 July 2017  The transaction was processed  The funds were received as “uncleared” funds into the account 6 July 2017  The funds were cleared and available to access from the account. 7 July 2017  Ms P contacted the FSP to request the redraw be activated 12 July 2017  The FSP‟s collection/contact notes say it was unable to load the redraw because code preventing dra wings from the home loan was active 19 July 2017  The FSP internally requested post credits only limitation to be removed from the home loan 26 July 2017  Post credits only limitation removed from the home loan and redraw made active. 5.2 Information about CGT from ATO website Capital gains tax The point at which you make a capital gain or loss is usually when you enter into the contract for disposal, not when you settle. So if you sign a contract to sell an investment property in June 2017, and settle in August 2017, you need to report the capital gain or loss in your 2016 – 17 tax return. If you‟re an Australian resident, CGT applies to your assets anywhere in the world. For Norfolk Island residents, CGT applies to assets acquired from 23 October 2015. Foreign residents make a capital gain or loss if a CGT event happens to an asset that is 'taxable Australian property'. Source: https://www.ato.gov.au/general/capital-gains-tax/ 5.3 Key documents  Account statements for the account and the home loan  Terms and conditions for the account and the home loan  Deposit/credit transfer voucher dated 30 June 2017  The applicants‟ submissions to FOS  The FSP‟s submissions to FOS  FSP‟s contact/coll ection notes

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.