Text of the determination
Determination
Case No: 486320 Determination Page 1 of 10
Case number: 486320 10 July 2018
1 Overview
1.1 Dispute
A building on the applicant‟s property was destroyed by fire in February 2015. The
financial services provider (FSP) accepted the claim and made a settlement payment
to the mortgagee for the property.
However, the applicant disputes certain aspects of the claim, saying the FSP
(through its contractor) damaged the ground at the property when it demolished the
fire damaged building. The applicant wants the FSP to pay the costs associated with
repairing the damaged ground and to remove debris left after the demolition.
1.2 Issues and key findings
Should the FSP pay for rectifying the applicant’s site?
The FSP should pay to rectify the applicant‟s site because:
the demolition of the damaged building by AD resulted in damage to the
applicant‟s site
rectification of this damage is not part of the normal cost of site preparation.
Should the FSP contribute to the applicant’s expert report costs?
The FSP is required to pay the applicant the costs of obtaining reports from
engineers HBW and BL. This is because these reports assisted the applicant.
1.3 Determination
This determination is in favour of the applicant.
The FSP is required to pay the applicant $50,600 (plus any GST which might be
payable) for the rectification of the site damage. Interest is payable at the statutory
rate on this amount, calculated from 2 February 2016 (the date upon which J
provided its quotation for the remediation), until date of settlement.
The FSP is also required to pay the costs for obtaining reports from HBW and BL (up
to $3,000 per report) in support of the applicant‟s case. This is subject to the
applicant providing evidence of the costs incurred.
Case No: 486320 Determination Page 2 of 10
2 Reasons for determination
2.1 Should the FSP pay for rectifying the applicant’s site?
Applicant’s estimate allowed for backfilling of holes and compaction of soil
The applicant provided an estimate, dated 16 March 2015, from a contractor of its
choosing for the demolition of the fire damaged building. The amount of this estimate
was $61,750 (plus GST).
Although the estimate was not on letterhead, it nevertheless signalled the applicant‟s
expectations with respect to what would need to take place during the demolition.
FSP’s quotation did not include backfilling or compact ion of pier holes
The FSP‟s contractor (AD) provided a quotation dated 11 March 2015. This was in
the amount of $18,920 (plus GST) and allowed for the demolition of the damaged
building.
When the FSP received the applicant‟s estimate, it emailed the applic ant noting that
it had received another quotation for the demolition which was considerably less than
the applicant‟s estimate.
The email sent by the FSP‟s assessor (BH) on 17 March 2015 also indicated that the
scope of works allowed within both quotes would be closely examined in accordance
with policy requirements, and that the applicant would be advised of the FSP‟s
decision when the review was complete.
The policy provision relating to demolition and removal of debris is as follows:
We will pay the reasonable costs of removal, storage and disposal of debris or the
demolition, dismantling, cleaning up, shoring up, propping, underpinning or other temporary
repairs of property insured by You.
It appears the FSP reviewed the two scopes of works and decided t hat AD‟s
quotation was sufficient to fulfil its policy obligations with respect to the demolition of
the damaged building, and the removal of debris.
The FSP later wrote to the applicant, advising that there appeared to be confusion
between site demolition costs and site preparation costs. In its letter dated 17
December 2015, the FSP explained that the land was not insured, and demolition
work includes the removal of structure, termination of running services and make -
safe of the ground. It also stated that secondary measures such as site remediation,
importation of fill, compaction of fill and site levelling were not included in site
demolition.
The panel accepts that when selecting which quotation to use for the demolition, the
FSP would be seeking to minimise its costs, to the extent it was reasonable to do so.
However, where the applicant‟s estimate clearly included allowances for the filling
and compaction of the holes left by removed pier footing, (and the provision of fill
material), the panel is of the view that in choosing a contractor whose quotation did
not include these items, the FSP should have advised the applicant accordingly.
Case No: 486320 Determination Page 3 of 10
It is not clear whether the FSP advised the applicant of its decision following the
review of the scope of works, as flagged in its email of 17 March 2015.
The panel also notes that the applicant‟s estimate clearly included the costs
associated with removing the concrete pier footings. Therefore, the panel is unable to
accept the applicant‟s alternative argument that the FSP should have left the
undamaged piers in the ground or sought his advice before removing them.
Demolition by AD resulted in damage to applicant’s site
The FSP‟s letter of 17 December 2015 indicates that AD employed the usual method
of using available soil to fill the holes left by removal of the footings. It stated that this
had scalloped areas of the site.
The panel does not accept the FSP‟s position that fill material was imported to the
site subsequent to AD‟s departure. The exchanged material i ncludes views from
various parties in support of this position. However, the panel prefers the views
provided by engineers BL and HBW, which show that on the balance of probabilities,
the near-surface soils at the site are natural to the site.
In particular, the panel finds the report from HBW persuasive in this regard. HBW
compared near-surface soil from four boreholes around the site (two from the ground
under where the building had been located, and two from the ground outside the
building envelope). Having reviewed the soil sample results, HBW concluded that the
soils from all four boreholes was very similar. HBW further notes:
the tops of two concrete piers (missed by AD during its demolition works) were
level with the ground, and if material had been imported, they would have been
below ground level
there was still debris from the damaged building present on the ground, and if
soil have been imported, this debris would not have been visible.
Based on the available material, the panel is satisfied that on the balance of
probabilities, the “available soil” (referred to in the FSP‟s letter of 17 December 2015)
included debris and other contaminants.
The panel is of the view that in the circumstances, the use of this contaminated soil
to backfill the holes left after the removal of the piers caused damage to the site.
Rectification of site damage caused not considered site preparation costs
The panel is also of the view that the rectification of this damage to the site, which
was not present prior to the claimed event, does not fall within the costs of site
preparation as the FSP appears to suggest.
The FSP is required to pay the costs associated with removal of the contaminated
soil from the pier holes on the site, and in the circumstances, it should also pay for
the cost to dispose of this material.
The panel also accepts that the cost to remove all the remaining debris from the site,
and the cost to dispose of this material, should be borne by the FSP.
In addition, the FSP should pay for the costs of erecting silt fences to ensure
contaminants do not escape.
Case No: 486320 Determination Page 4 of 10
The applicant has provided a quotation dated 2 February 2016 for site remediation
from contractor J, which includes these items (i.e. items 4 and 7-10).
However, the panel accepts that the cost to import decomposed granite, and the cost
to compact it, is properly regarded as site preparation costs which would form part of
any rebuild undertaken on the site. Accordingly, the FSP is not required to pay costs
associated with these activities. These a re items 6, 11 and 12 of J‟s quote.
The panel is also not satisfied the evidence shows there were agricultural drains
damaged. There is minimal evidence in support. J‟s quotation does not allow for this.
HBW was not aware of any drains at the site or their relative position. HBW‟s report
makes no reference to identifying such damage.
The quotation by J includes several additional items that would appear common to
both rectification and site preparation. These are items 1, 2, 3 and 5. The panel
considers it is fair to allow half of these costs.
Given this, the panel is satisfied that the amount payable by the FSP is $50,600 (ex-
GST), plus interest calculated from 2 February 2016 until settlement.
2.2 Should the FSP contribute to the applicant’s expert report co sts?
Reports from HBW and BL influential in decision
Under its Terms of Reference, FOS may decide that the FSP contribute to the
professional costs incurred by the applicant in the course of the dispute. Unless
exceptional circumstances apply, FOS will no t require the FSP to contribute more
than $3,000 to these costs.
The panel found the reports by HBW and BL, provided by the applicant, to be
persuasive in this matter.
Accordingly, subject to the provision of appropriate evidence by the applicant of the
costs incurred for these reports, the FSP is required to reimburse the applicant up to
a maximum of $3,000 per report.
Case No: 486320 Determination Page 5 of 10
3 Supporting information
3.1 Other matters
The dispute as originally raised with FOS included issues relating to the calculation of
underinsurance. These items were subsequently removed from consideration, and
this determination does not include any other address of these issues.
Later in the dispute resolution process, the applicant raised concerns about the
removal of two gazebos. The FSP subsequently responded to this raising a number
of matters. The applicant disputes the FSP‟s position.
This issue has not been part of FOS‟s investigation. It is not clear whether the matter
had been raised and reviewed through the FSP‟s internal dispute resolu tion process.
Given this, the panel does not consider it appropriate to determine that issue.
Therefore, it should not be considered as an issue dealt with in this Determination.
3.2 Policy provisions
General definitions
Unless defined differently in individual policy sections, these definitions apply to all policy
sections.
…
Building(s)
The building(s) at the premises.
Building(s) includes:
…
(e) walls, foundations, storage tanks and sheds, awnings, exterior lights, masts, antennae and
aerials, fixed external signs, gates, fencing, pavements, roads and other structural
improvements pertaining to the building(s);
…
Extra covers
When damage to property insured is covered by this policy section, We will pay for the following
costs that are incurred as a res ult of that damage.
…
11. Removal of debris including necessary temporary repairs
We will pay the reasonable costs of removal, storage and disposal of debris or the demolition,
dismantling, cleaning up, shoring up, propping, underpinning or ot her temporary repairs of
property insured by You. We will also pay for Your legal liability for the cost of removal of debris
from adjoining premises, property, services, roadways and waterways as well as on the site.
Case No: 486320 Determination Page 6 of 10
We will pay You up to $100,000 or 20% of the total insured amount on buildings and contents
shown on the policy schedule for the damaged premises whichever is the greater or the amount
for „Removal of debris‟ shown in the policy schedule. If this is insufficient and you have not
exhausted your insured amount on the damaged items requiring demolition and/or removal of
debris, We will pay up to the remaining balanc e of the insured amount.
…
16. Undamaged foundations
If foundations are not destroyed following an occurrence and any Government or Statutory
Authority requires reinstatement of the property insured to be carried out on another site, the
abandoned foundations will be considered as destroyed. If the resale value of the original
building site is increased due to the presence of the abandoned foundat ions, the increase in
resale value will be paid to Us at the time of sale.
3.3 Information considered
Record Key points
FSP’s
demolition
contractor (AD)
Quotation
11 Mar 2015
Provide a Demolition Safety, Environmental and Recycling
Management Plan
Supply supervision, labour and equipment to:
o Demolish remainder of fire damaged structure
o Clean up all fire damaged debris and remove from site
o Demolish and remove existing steel stumps with concret e
footings
o Demolish and remove any concrete hardstand attached to
existing fire damaged house
o All demolition waste to be removed from site
Any council permits and servic e disconnections by client.
No allowance has been made for the removal of any hazardous
material, including asbestos
No allowance has been made for site fencing
This price allows for the value of all salvageable items onsite at the
time of quoting to become the property of AD
TOTAL - $18,920 + GST
Applicant’ s
demolition
contractor
(name not
disclosed)
Estimate for
clean -
up/reinstatement
of site
16 Mar 2015
(9) Cartage concrete stumps and concrete pads to dump including
loading
(10) Estimate total 100 tons of debris @$65.00 dump fees
(11) Stump removal 2 excavators allow to rip around conc rete
Site Reinstatement –
o Fill and compact all post holes using 2 machines including water
truck
o Material to fill and compact holes. 45 cubic metres. And allow
topping for site – 100 tons
o Grader to level site
o Plumber to terminate water pipes to Fire Hose Reels including
installation. Thrust blocks, plumber to terminat e all sewage and
water outlets.
Case No: 486320 Determination Page 7 of 10
FSP’s loss
adjustor (BH)
Email to applicant
17 Mar 2015
Quotation to demolish and remove fire debris received from applicant
Reviewed scope and costs – total $61,750 +GST – referred to FSP‟s
Project Manager for review and comment.
Aware of at least one ot her quot ation already obtained by FSP –
considerably less than quotation from applicant
Scope of Works for both quotes will be closely examined in
accordance with Policy entitlements – applicant will be advis ed of
FSP‟s decision once review complete.
FSP’s
demolition
contractor (AD)
Email / letter
8 Dec 2015
AD did not import any fill whatsoever onto the site – applicant
requested that we do so throughout project, but it was not in our
scope.
Have viewed photos of 3 con crete footings – unsure if these have
come from the onsite building, were imported, or came from another
structure (i t was extremely wet underneath the building due to
stormwat er runoff, and there were a large number of footings needing
rem o val ) - possible but unlikely the operator missed a couple.
However with site conditions and demolition tolerance this would not
normally be seen as an issue.
FSP
Letter to applicant
17 Dec 2015
FSP‟s assessor (BH) reports that 3 (out of 180) concrete stump
footings we re overlooked by AD – agreed these should have been
removed – quote for their removal $250 incl GST
AD also did not quot e to cap servic e pipes – FSP agrees this should
have been done – quote for this work $1,620 incl GST
Payment of these amounts (net of GS T) to be made
FSP submits that site demolition is being confused wit h site
preparation.
Land not insured - demolition includes removal of structure,
termination of services, “make safe” of ground - phot os from AD show
this has been done
Secondary meas ures such as site remediation, importation of fill,
compaction of fill and site leveling are not included (in demolition)
AD employed usual method of using available soil to fill the holes left
by removal of footings – this has scalloped area of the site
Fill has subsequently been imported to level the site (AD deny any
importation of fill)
Applicant’s
engineer (BL)
Report of site
restoration
4 Jan 2016
Site inspected 22 Dec 2015 – to see if it has been restored to allow
reconstruction of the building
Not all debris taken away during building removal process – about 1.5
cubic metres is stockpiled on site
At least 4 concrete piers were not removed by FSP‟s contractor – 2
have since been removed by applicant, 2 remain in the ground
No evidence of fill soils bein g brought to the site (as part of restoration
process or since). Different colours are of soil from different depths –
natural surface soil (grey silty sand); soil from depth of pier excavation
(yellow granite); charcoal from the fire
Possible debris left is present in back - filled pier holes, which would
inhibit re - compaction of back - filled soil
For correct site restoration, piers holes need to be filled with local or
imported soil, and compacted mec hanically in 200mm lay ers. Loose
Case No: 486320 Determination Page 8 of 10
soil/debris scraped into pier holes will have to be removed and
replaced with clean, compacted, decomposed granite.
Removal of piers will also have loosened local soil surrounding the
piers – excavation & re - compacting each pier will be inefficient.
Better to dig out building foo tprint to 500mm, stockpile soil on site and
remove significant debris, compact exposed surface, then backfill from
stockpile in 20mm layers & compact each lay er.
Applicant’s
demolition
contractor (J)
Email and quote
for site
remediation
2 Feb 2016
Time/effort/cost of returning site to original state includes the need to
remove large quantity of contaminated fill, large number of stump
holes, and nature of excavating and backfilling them to acceptable
standard – this could have been avoided if superi or work methodology
was employed from the start.
Safe work methodology outlined, as well as notes about previous
(unsatisfactory) work carried out:
(3) Environmental compliance – erect silt fences and water run - off
drains / sediment pond ($4,000 ex GST):
o Si lt fence was not installed and cont aminants have been escaping
off - site after heavy rain
(4) Strip site of all unwanted contaminants (to 100mm) to be
transported to landfill, to leave site clean and free of cross -
contaminants - ($4, 000, plus $8,400 dump fe es, ex - GST):
o Site was not stripped of unwanted cont aminants and rubbish, and
immediat e sub - grade has been cross - cont aminat ed with nails,
ask, steel, glass and other debris (rendering site unsafe)
(5) Excavate contaminated fill (1m 3 ) from stump holes - ($20 , 000, plus
$11,200 dump fees, ex - GST) :
o Stump holes filled with contaminated rubbish from on - site –
unsuitable sub - grade material & cannot be compacted.
o Rubbish also allows water to penet rate surfac e of building pad,
destabilizing area
(6) Fill excavated s tump - holes with (brought - in) gravel – compacted at
150mm layers – ($18,150 ex - GST)
(7) After excavation and backfill of stump holes, a capping layer of
100mm to be placed on top of site & compacted to dry density rate of
85% - forming a layer which rain/ru n - off will not penetrate, preventing
destabilization – ($3,700 ex - GST)
o Site was left in such a state that water falling on the site gets
contaminated, runs off downstream int o watercourse and ont o
nearby properties – not an acceptable way to leave job site , and
would not comply with environmental laws or safe work
practices.
FSP’s
geotechnical
engineer (G)
Opinion Report
March 2016
After the damaged building was demolished, applicant raised issue re:
removal of demolished mat erial - there was a question of whether near
surface material currently present was placed by others sometime
after contractor complet ed works – FSP commissioned G to report on
this issue.
Observed occasional isolated building debris on site perimet er (incl 2
broken PVC pipes and 2 burnt timber joints)
Small stockpile of material in central part of site (incl 2 concrete pier
footings, mixed soils, pieces of burnt timber, rusted metal and
Case No: 486320 Determination Page 9 of 10
occasional pieces of concrete)
2 piers observed embedded in ground (1 on west side and 1 on east
side of building footprint)
Soil erosion channels notes on central western part of site – likely from
overland flows.
Dynamic cone pe netrometer test in central part of site, and 200mm
auger hole dug adjacent
From review of the information made available, site observations and
a shallow auger investigation in the central part of the site, I can draw
the following conclusions on the ques tion of the near - s urface mat erial
covering the site:
o March/ April 2015 photographs by Abyss show the site was
excavated to form a clean s urface that was dish - shaped and free
from charcoal and building debris.
o S urface shown in AD photographs is consistent w ith natural
granitic soil encountered at 220 - 330 mm depth in the March 2016
auger investigation.
o Sometime after AD photographs, site was filled and levelled to
form c urrent surface.
o Fill material comprises light grey and dark grey silty soils that are
not of granitic origin.
o Fill material is generally present within the cross - shaped building
footprint, and is consistent with filling of the dish - shaped
excavation shown in the Abyss phot ographs.
o It is likely that the light grey and dark grey silty soils were imported
or won locally from another area.
o Similarly, it is likely that the scattered charcoal and building debris
currently on the site surface was placed on site around the same
time or sometime after the grey silty soil was placed.
From review of the in formation, I am of the firm opinion that the near -
surface material currently covering the building footprint was placed
sometime after the AD photographs were taken.
Applicant’s
engineer
(HBW)
Report
22 May 2017
PW from HBW office visually inspected area where building once
stood on 3 May 2017
Photos taken of ground surface beneath where building was, plus
areas outside building envelope, plus other areas of interest on site
4 boreholes taken (100mm hand augur) – 2 within & 2 outside original
building env elope. Soil samples taken from each borehole
Report from G reviewed.
Observed:
o a plethora of charcoal fragments across ground surface
o fragments of broken tiles (pres umably floor and wall tiles exposed
on surface)
o Fragment of what appeared to be a toilet p an partially embedded
in ground
o Fragments of thicker dark material partially exposed in ground
(applicant says this was bench top)
o Fragments of burned timber on / partially buried in ground
o Small section of black pipe protruding from ground at sout hern
end (appeared to be 100mm Ag pipe)
Case No: 486320 Determination Page 10 of 10
o 1 concrete bored pier footing remaining in ground – steel post
broken out of its side
o Another pier footing on western side of envelope – steel post
broken off top of pier
o Area of noticeable ground disturbance east - west across site –
applicant says this was where underground electrical service was
installed after AD left site.
o Pile of soil and debris at northern end of envelope (incl tile
bedding, conc rete fragments, partially burned timber, met al
fragments and 2 concrete piers) formed aft er applicant raked
ground
o Light coloured decomposed granite (deco) around much of
perimeter – applicant says this was from original construction for
roadway & carparks. Applicant also says several cubic metres of
deco also recently impo rted to cover excavation for electrical
trench in eastern driveway
Soils from all 4 boreholes examined – in opinion of HBW, near surface
soils from boreholes taken from inside building envelope are very
similar to soils from those taken outside envelope.
A part from charcoal found just below surface in BH3, upper layer of
soils (200mm) is similar in all 4 boreholes
Top 200mm of BH2 & 3 (inside envelope) is not imported soil – rather
it is material natural to site prior to fire
Conclusion – no bulk filling of the site has occurred since AD left site in
2015 (if 200mm of fill material were added to site, the tops of the 2
remaining piers would be buried 200mm beneath surface, rather than
flush with ground as they were observed to be).