Home / Financial Firm (Unknown - Insurer) / Determination 485711

Determination 485711

Cash settlement amount for storm damage to strata unit and restaurant, plus costs and delay

FirmFinancial Firm (Unknown - Insurer)
Decided2018-08-17
ProductGeneral Insurance · Strata
OutcomeFor the complainant in part
Amount awarded$145,371
Non-financial loss$1,000
Amount claimed$242,934
SourceAFCA PDF

Summary

The owners' corporation of a strata scheme disputed the cash settlement for storm damage to a unit and restaurant. AFCA ordered a cash settlement of $66,042.39 with interest, payment of $79,328.34 in costs, and $1,000 non-financial loss, rejecting temporary accommodation costs and reducing an engineer's fee by half.

A cash settlement must allow for transfer of repair risk and contingencies, and the panel preferred the insurer's expert scope while applying a 35% contingency under the policy and Insurance Contracts Act s 57.

Issues

Subjects and remedies

business interruptionhome or building damagenatural disasterpay claimpay compensationpay interestpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 485711 Determination Page 1 of 6 Case number: 485711 17 July 2018 1 Overview 1.1 Dispute This matter involves a claim under the applicant‟s commercial strata insurance policy, held with the financial services provider (FSP), following damage to the applicant‟s unit and restaurant. The FSP accepted the applicant‟s claim but a dispute has arisen as to the extent of the FSP‟s obligations under the terms and conditions of the policy. 1.2 Issues and key findings How should the applican t’s claim be settled? The FSP should pay a cash settlement amount of $66,042.39 (inclusive of GST) to cover the cost of reinstatement of the damage. Interest is payable upon this amount from 22 November 2017 until the date the payment is made in accordance with section 57 of the Insurance Contracts Act 1984 (the Act). Is the applicant entitled to any costs and compensation? The applicant is entitled to $1,000 compensation for non-financial loss due to the time taken by the FSP to implement the recommendation. It is fair and reasonable for the FSP to pay for the applicant‟s costs it accepted to a total of $79,328.34 per its response of 10 November 2017. 1.3 Determination This determination is substantially in favour of the applicant. Within 28 days of the applicant accepting this determination, the FSP is to pay the applicant:  $66,042.39 for the cost of reinstating the damage plus interest from 22 November 2017 to the date the payment is made under section 57 of the Act  $79,328.34 for the costs claimed  $1,000 non-financial loss compensation. The FSP may reduce any of the amounts payable, as well as interest, if the applicant is entitled to an input tax credit. Case No: 485711 Determination Page 2 of 6 2 Reasons for determination 2.1 How should the applicant’s claim be settled? Both parties accepted the FOS recommendation FOS issued a recommendation on 22 March 2017. A copy of the recommendation is attached to this determination. The recommendation dealt with whether the FSP was liable for all the damage and if two excesses should apply. The case manager recommended two excesses applies. The case manager also recommended that the FSP was liable for the damage to the kitchen ceiling above the cupboards, the cupboards, walls, flooring, kickboards, drawer, lower level bathroom and restaurant. Both parties accepted the recommendation. As part of the recommendation, the FSP was to repair or pay the cost to repair the listed damage and assess its liability for the substrate flooring in the kitchen area within 14 days of the parties accepting the recommendation. If the FSP decided to pay the cost to repair the damage, it was to obtain an updated quotation and pay the applicant (less the $20,000 excess). The terms of the recommendation were not completed as the parties dispute how the claim should be settled. Cash settlement to account for transfer of risk, contingencies and variations Both parties agree to resolve the dispute by cash settlement. However, the parties dispute the amount which represents the extent of the FSP‟s obligations under the terms and conditions of the policy. The applicant says the various sums offered by the FSP (during the course of the dispute) were inadequate to allow it to rectify the damage, cover its exposure to liability and any contingency costs. The panel acknowledges the risk associated with the repairs will transfer from the FSP to the applicant. As a result, in calculating an appropriate cash settlement amount, it is necessary to consider all reasonable factors. This includes the nature of the repairs required and whether the cash settlement will ensure the applicant is able to properly complete all repairs and cover all reasonable possibilities. Any cash settlement amount must include an allowance for contingencies and variations. The FSP has made revised offers to the applicant and the applicant has countered with an alternate position. Reports from various experts have been provided to support their respective positions. Case No: 485711 Determination Page 3 of 6 S’s latest scope of works is preferred The FSP provided its final offer of $66,922 (including GST) for the cost of repairs. This was based on a report provided by consultant S dated 8 November 2017. This report included the input of five individuals. Their experience included two building consultants (one senior), two quantity surveyors (one senior) and an individual whose title is “Head of Major Loss – Construction”. The applicant has disputed this. He notes not all of these individuals inspected and reviewed the property. He has provided a report from consulting engineer M dated 16 October 2017. M estimated the total cost of repairs to be $130,886.73. Both reports are comprehensive. They set out detailed scopes of works that each believe is sufficient to address the matters set out in the FOS recommendation. Having carefully reviewed both, the panel substantively prefers S‟s report for the following reasons. First, S did make adjustments to its allowances where appropriate following M‟s report. This included increasing the amount for preliminaries, site establishment and timber floor replacement Second, regarding a ccepted construction practices, the panel is satisfied S‟s experience outweighs ME. This is reflected by the five people who encompass a wide range of building experience. It is further supported by the fact S is described as a national specialist firm dedicated to the insurance industry. This involves issuing over 1,000 reports that include scopes of works and quantity surveying cost estimates. Therefore, on those points, the panel prefers S‟s position. This would include their use of unit rates and the appropriate construction program for a job this size. Third, the panel is not persuaded that removal of various items would inevitably result in their damage and subsequent replacement. There is no clear evidence that this should be assumed. Fair in all the circumstances to allow a 35% contingency The panel does not agree that a 5% contingency is sufficient to cater for the risk the applicant will undertake by managing the repairs. This is particularly reflected by the items M says will likely require replacement. If those risks manifest, it will increase the costs by an additional $13,000. This is about 28% of S‟s quote. Therefore, when taking this into consideration as well as the extensive works and the risk being transferred to the applicant, the pa nel considers a contingency of 35% to be appropriate. Accordingly, the panel accepts the amount payable for the repairs should be increased to $86,042.39 (inclusive of GST) before deduction of the two excesses. This is calculated by utilising S‟s “Grand Total Building” figure of $57,941 with an additional contingency fee of 35% ($20,279.35) plus GST ($7,822.04). The FSP is also to pay interest on the net amount payable ($66,042.39) pursuant to section 57 of the Insurance Contracts Act 1984. Interest is payable from 22 Case No: 485711 Determination Page 4 of 6 November 2017, being two weeks after the FSP received S ‟s latest report, until payment is made. If the applicant is entitled to an input tax credit, the FSP can reduce the amount payable to reflect this. 2.2 Is the applicant entitled to any costs and compensation? FSP’s acceptance of $79,328.34 for costs claimed is fair and reasonable The applicant sought the following costs in the course of the dispute:  $27,500 loss of rent (restaurant)  $596.50 leak detection costs  $29,863.68 M‟s fee  $33,720 loss of rent (unit)  $17,787 for temporary accommodation and removal/storage costs  $2,580 carpet. The FSP accepted to pay all costs except the temporary accommodation and M‟s fee (only half) on 10 November 2017. The FSP denied payment for the alternative accommodation because the applicant does not occupy the unit. The panel agrees that such costs are not payable under the terms of the policy. The FSP considered M‟s costs were excessive and agreed to pay half of the fee claimed. The panel considers this is reasonable because:  the FSP did not agree to this fee prior to the applicant incurring such costs  the fee proposal was for $4,620 excluding GST, which was much less  the fee encompasses the cost of reviewing numerous emails, calls with the applicant, preparing aspects of the claim and reviewing the policy at a rate of $280 per hour. Although M‟s report was extensive and comprehensive, it encompassed work beyond that expected or required of a consultant engineer. Much of the work would usually be prepared and conducted by an applicant or a claims management firm. Therefore, it is unfair for the FSP to be responsible for all the fees claimed by M, which FOS would usually award conservatively. As the FSP has agreed to pay half the fees claimed, the panel considers this is fair in all the circumstances. No interest is payable on any of the costs claimed. The applicant did not claim such costs until 17 October 2017, and the FSP agreed to reasonable payment of these costs promptly. FSP contacted applicant more than a month after recommendation accepted Both parties accepted the FOS recommendation by 21 April 2017. On 24 April 2017, FOS notified the FSP to take the necessary steps to comply with the recommendation. Case No: 485711 Determination Page 5 of 6 The applicant contacted FOS and the FSP on 24 May 2017 to seek an update with the FSP‟s implementation of the recommendation. The FSP then responded to the applicant on 29 May 2017. Given this, it appears the FSP made no contact with the applicant for more than a month after the recommendation was accepted. FSP to pay $1,000 in non-financial loss FOS has the discretion to award compensation for non-financial loss if it considers it appropriate and fair in all the circumstances to do so. Compensation for non-financial loss is awarded if there has been an unusual degree or extent of inconvenience, time taken to resolve a situation or interference with the applicant‟s expectations or peace of mind. The FSP did cause an unusual degree of time to be taken to resolve a situation when it failed to action the recommendation in a timely manner. Although the applicant may not be an individual, it is clear the unit and restaurant owner and strata manager involved were affected by this. The panel acknowledges during the dispute that not all delays were borne by the FSP‟s ac tions. There were occasions the applicant also took some time to provide information requested by FOS. Also, the parties disagreed as to which scope of works (the FSP‟s expert (S) or the applicant‟s engineer (M)) should be preferred. And responsibility for M‟s costs also formed part of the issues being considered. All these factors contributed to the delay in finalising the matter. Accordingly, it is the panel‟s view that it is fair in all the circumstances the applicant be awarded $1,000 in compensation for non-financial loss. Case No: 485711 Determination Page 6 of 6 3 Supporting information 3.1 FOS approach The panel has carefully considered all of the material provided both before and after the recommendation, in the preparation of this determination. This determination follows consideration of all of the information exchanged and is based on what is fair in the circumstances, having regard to the relevant legal principles, terms of the policy, good industry practice and where applicable, prior determinations. The applicant is the owners‟ corporati on (OC) of a strata scheme. Any submissions made by the applicant‟s unit and restaurant owner have been treated as having been made by the applicant, for the purposes of this determination. Recommendation Case No: 452172 Recommendation Page 1 of 9 Case number: 452172 22 March 2017 4 Overview 4.1 Dispute The applicant lodged a claim on its commercial strata insurance policy with the financial services provider (FSP), for storm damage to its unit and restaurant. The FSP partially accepted the claim but it says the claim is not payable. It considered two $10,000 excesses applied because there were two insured events leading to the claimed loss. However, the scope of works it obtained fo r the covered damage amounted to $8,098, which is less than one excess. The applicant disputes the FSP‟s decision and seeks for it to cover the majority of the damage under the policy. 4.2 Issues and key findings Has the applicant established a valid claim under the terms of the policy? The parties do not dispute that accidental damage occurred to the unit. Thus, the applicant has established a valid claim under the terms of the policy. However, the parties disagree as to the extent of damage covered under the terms of the policy. Is the FSP liable for all the damage to the unit and restaurant? The FSP is not liable for all the damage observed to the unit and restaurant because gradual deterioration caused the mould staining on the access panel in the kitchen and poor ventilation caused the mould on the ceiling in the top floor bathroom. The FSP is liable for the remaining damage to the kitchen ceiling above the cupboards, the cupboards, walls, flooring, kickboards, drawer, lower level bathroom and restaurant. Is the FSP entitled to apply two excesses to the applicant’s claim? The FSP is entitled to apply two excesses to a total of $20,000 because the policy states an excess applies to each incident. There were two incidents causing damage. 4.3 Recommendation This recommendation is substantially in favour of the applicant. The FSP is to repair or pay the cost to repair the damage and assess its liability for the substrate flooring in the kitchen area. If the FSP decides to pay the cost to repair Case No: 452172 Recommendation Page 2 of 9 the damage, it is to obtain an updated quotation and pay the applicant (less the $20,000 excess) within 14 days of the parties accepting this recommendation. Case No: 452172 Recommendation Page 3 of 9 5 Reasons for recommendation The applicant (the owners of the strata plan) is represented by the owner of the unit and restaurant, which are the subject of this dispute. Any comments or submissions made by the unit and restaurant owner are taken to be made by the applicant. Although the FSP raised preliminary issues relating to whether the unit and restaurant owner had requisite authority to act on behalf of the strata plan, FOS considered that he does. FOS communicated this to the parties on 11 November 2016. I consider it was appropriate for FOS to make this decision. The unit and restaurant owner has a beneficial interest in the outcome of the dispute. The strata manager also nominated him as the authorised party to speak on behalf of the owners of the strata plan. 5.1 Has the applicant established a valid claim under the policy? Policy covers accidental damage subject to conditions and exclusions The applicant bears the onus to establish on the balance of probabilities the claim falls within the terms of the policy. This is called a prima facie claim. Only once the applicant has established such a claim does the onus shift to the FSP to establish the application of an exclusion. The applicant‟s policy is a commercial strata insurance policy that provides accidental loss or damage cover subject to exclusions and conditions. The policy does not define accidental. However, the courts have defined accidental in an insurance context as something that is unintended and unexpected. The FSP accepts there is accidental damage to the applicant‟s unit and restaurant. However, it disputes that all the damage is a result of the storm over the 4-6 June 2016 weekend on the eastern coast of New South Wales. It accepts the leaking pipe (in the unit‟s lounge area adjacent to the kitchen) in April 2016 caused some of the damage observed. On this basis, I am satisfied the applicant has established a prima facie claim. Accordingly, for the FSP to deny any aspect of the claim, the FSP must establish that an exclusion applies. In the present case, the FSP says the majority of the claimed damage was caused by a lack of maintenance, wear, tear or gradual deterioration. In order to establish an exclusion applies, the FSP must show that the proximate cause of the damage to the applicant‟s property (that is, the effective, dominant or operative cause) was one or more of the excluded factors outlined above . If there are several causes operating contemporaneously, then each must be examined for the qualities of predominance and efficiency as the active, efficient cause that sets a relevant train of events in motion. Case No: 452172 Recommendation Page 4 of 9 5.2 Is the FSP liable for all the damage to the unit and restaurant? Parties’ experts differ in view about cause Courts have said that if one cause would have resulted in the harm in any case and the other would not have done so in the absence of the first, then the first is the proximate cause. The FSP‟s building consultant (S) attributed some damage to an insured event (the leaking pipe), however considered the majority of damage resulted from wear, tear or gradual deterioration occurring over a period of time. The applicant‟s engineer (M) found s ome damage was not covered, but the actual cause of the majority of the damage was due to storm water blockage to the drains in the terrace from the unit above, causing water to surcharge into the building. The water then most likely tracked down the building through the stack near the spa area, which is situated above the various damage points. See M‟s diagram in section 3 for the trail of water entry. M considered the earlier leaking pipe (located in the opposite kitchen wall), amplified the damage to the kitchen floor, lower level bathroom and restaurant. I accept M‟s opinion of the proximate cause, as it is plausible and the most likely explanation for all the damage (except for the top floor bathroom ceiling and kitchen access panel). Both parties have referred to various areas exhibiting damage. Given the issues in dispute, this is a convenient way to consider the dispute to determine those areas that should be covered and those areas that should be denied. Damage to top floor bathroom caused by poor ventilation The FSP‟s building consultant (S) noted the tenants also used the top floor bathroom as a laundry. The ceiling exhibited signs of mould, which S considered was due to poor ventilation when the tenant used the washing machine and dryer. Although t he exhaust fan operated, the applicant advised S its drawing capacity was limited and admitted it did not adequately service the bathroom. The applicant‟s engineer (M) agreed with S‟s assessment that the mould on the top floor bathroom ceiling was not a result of water entry. M considered condensation was the more likely cause. The exchanged information confirms the damage to the ceiling in the top floor bathroom is not a result of the storm but due to a lack of proper ventilation. In fact, it is the applic ant‟s own engineer‟s opinion that the damage is not covered. Accordingly, I consider the FSP is entitled to deny cover for this damage. Part of kitchen ceiling damage caused over time and some due to storm The applicant explained to S how it considered the damage to the property occurred due to the storm water entering through a roof mounted mechanical ventilation outlet. The applicant suggested the water entered the outlet above the top floor bathroom and continued to flow down to the kitchen (second floor), continued to the ground floor bathroom and restaurant directly beneath it. Case No: 452172 Recommendation Page 5 of 9 S observed black mould staining to the plasterboard ceiling in two locations; in a ceiling void access panel and an area of approximately 50 x 100 mm above the wall mounted cupboards. S noted the damage to the access panel was consistent with water exposure over an extended period of time. As to the remaining ceiling above the cupboards, S considered there was evidence of a previous patch repair. In photographs inside the ceiling space above the access panel, S observed water tracks on the surface of water pipes, which extended up the concealed stack pipe leading to the top floor bathroom. S stated the water tracks were located directly above efflorescence staining leading to the c luster of mould staining on the access panel. S concluded the damage resulted from previous water ingress experienced, which occurred over time, rather than a single storm event. M accepted the damage to the plasterboard ceiling, isolated to 500mm x 500mm below the bathroom, was sewer related and unrelated to the storm. M explains the position of this area is away from the cupboards, where the applicant reported the damage. In photographs, M points out this area on what appears to be the ceiling access panel described by S. M disagreed with S that the ceiling above the cupboards had been repaired, but partly painted probably from an earlier sewer leak. M states the water tracks on the wall mounted cupboards observed by S confirms the water entered from above. However, M did not consider the water entered from the roof (which he considered was minor), but penetrated from the terrace in the above unit through the stack. I accept M‟s view in this regard. Considering the information exchanged, I consider the mould staining observed on the access panel is not a result of the storm but due to wear or tear over time, which has since been fixed. Therefore, this damage is not covered. However, the proximate cause of the damage to the ceiling directly above the cupboards is the storm water given the evidence of water tracks and resulting damage and its proximity in time to the storm. Therefore, the FSP is liable to repair or pay the cost to repair this damage. Damage to kitchen wall-mounted cupboards caused by storm water S observed mould and a strong dank odour within a wall mounted cupboard (directly below the damaged ceiling). S stated the mould stained the melamine edge stripping of the cupboard carcass. S noted three water tracks emanating from the top of the cupboard, indicating water ingress occurred from above. However, S considered the damage to the edge stripping was not a result of a single episode of water exposure. S also noted the cupboard doors and two drawer faces immediately below had swollen due to water exposure. S expected there to be additional damage to surrounding drawers and cupboard doors rather than the isolated swelling if the damage was due to water inundation. M noted the unit occupiers saw the water penetrate through the kitchen ceiling, travelled onto the overhead cupboards, down onto the lower cupboards and flooded the kitchen floor. M disagreed with S‟s opinion that damage to surrounding panels would be expected. I agree with M‟s view that the storm water entering through the terrace of t he above unit most likely travelled down the stack and onto the kitchen ceiling and cupboards. Case No: 452172 Recommendation Page 6 of 9 This is because the location of the leaking pipe is below the height of these affected areas, and M‟s explanation is corroborated by the observations of the unit occupiers. Therefore, the FSP is liable to repair or pay the cost to repair the damage to the kitchen ceiling directly above the cupboards and the affected cupboards. Damage to kitchen flooring and adjacent area caused by storm water S observed darkened scuff marks in the tongue and groove strip flooring in the kitchen. S considered this was consistent with exposure to water, despite being in a pattern sustained in the normal use of the kitchen (given it was the likely thoroughfare of foot traffic). S was of the view this resulted from the leaking pipe. There was also water staining to the flooring, particleboard kickboard of the cupboard adjacent to the dishwasher and adjacent cement rendered walls, which S considered was consistent with long-term exposure to water. S concluded the dark staining to this area was a result of water entering the floor-mounted cupboards from the dishwasher (due to its location) and sink over a period of time. M explains the water staining to the flooring and adjacent area was caused by the storm water ingress because of the height and pattern of the efflorescence tide mark. M stated the fact he could view water well into the cupboards is reflective of an event and not damage occurring over time. M also suggested the storm damage overlayed the earlier pipe leak damage to the kitchen floor. I accept M‟s opinion as to the cause of damage, that is, the storm water flowed through the ceiling, down the overhead and lower cupboards then flooded the floor. Although some parts of the flooring and area directly surrounding the dishwasher may have suffered from some moisture issues from everyday use, the damage to the flooring extends to the dining area, which suggests a larger water source. The information provided by the parties shows there was little damage to the flooring at the time B (repairer) attended prior to the storm. This is demonstrated by the scope presented by B in its email of 9 August 2016, which only provided for 16sqm of timber floorboards and three floorboards in the living room to be removed and replaced. M correctly points out the quote obtained by the FSP from B suggested the substrate flooring may require work. This is because B listed it as an exclusion in the quote. Given there is no evidence the substrate is damaged at this time, the FSP is to assess its liability for it upon removal of the floorboards. Damage to lower level bathroom most likely caused by leaking pipe and exacerbated by storm The applicant advised S the southern end of the bathroom detached from the ceiling frame due to the storm, and a small hole was created to locate the leak in the northern end of the ceiling. But both openings had been repaired since S inspected. S observed water tracks emanating from the ceiling down the entry door and from the ceiling adjacent to the wall mounted mirror above the vanity unit. S was of the opinion the damage sustained to the ground floor bathroom ceiling resulted from water exposure from the leaking pipe and not the storm. Case No: 452172 Recommendation Page 7 of 9 S also noted a swollen timber face of a single vanity drawer. S expected there to be additional damage to the surrounding panels if it were a result of water inundation. M disagreed with S‟s view that surrounding panels would also be damaged but provided no basis for this view. M considered the storm water ingress resulted in the ceiling collapse and replacement. M relied on the fact B noted damage to the fabric due to the leaking pipe, but further damage occurred subsequently (from the storm) resulting in extensive other damage to the restaurant. M‟s argument has merit. B‟s email of 9 August 2016 outlining works required because of the leaking pipe differs to the quote provided on 10 August 2016. It is unclear why there is such a disparity between the scope and quote, which B provided a day apart . However, this supports M‟s position that the storm caused additional damage to the lower level bathroom, which the leaking pipe already damaged. The information does not clearly outline how much each event contributed to the damage. However, the extent of damage reported accords with the two events. Therefore, the FSP is liable for all the reported damage and cost of repairing the lower level bathroom upon the provision of tax invoices for repairs from the applicant. Damage to restaurant caused by leaking pipe and exacerbated by storm S observed water marks from cracks in the exposed concrete soffit above both sides of a bulkhead in the northern area of the restaurant. S also noted water staining to the timber pelmet, supporting the fabric material decora ting the timber tables. The fabric and wallpaper covering the bulkhead was also water stained. S considered the amount of water required to come through four levels of the building could not have caused the water to seep through the cracking in the concrete soffit down to the restaurant. S was of the view the damage resulted from the leaking pipe and was not storm related. M noted there was only minor damage to the restaurant initially reported in B‟s scope, which suggested the pipe leak caused minor damage (to the cloth fabric) and considerably greater damage occurred from the storm (to air-conditioning, ceilings and floors). Based on the information exchanged, the storm caused the majority of the damage to the restaurant and some minor damage occurred from the leaking pipe. Regardless, as both are considered accidental damage, the FSP is liable for the reported damage to the restaurant. 5.3 Is the FSP entitled to apply two excesses to the applicant’s claim? Policy applies an excess for each incident The applicant accepts that two excesses may apply. The policy states an excess will be applied for each incident where a claim is made. The information exchanged confirms there were two separate events causing damage; the leaking pipe around 20 April 2016 and the storm on 4-6 June 2016. As it will be difficult to separate the cost of repairs caused by each event, the FSP is entitled to apply two excesses of $10,000 on the accidental damage caused by water. Case No: 452172 Recommendation Page 8 of 9 6 Supporting information 6.1 Diagram by a pplicant’s engineer (M) 6.2 Relevant policy sections Section Provi sion Cover This Policy covers accidental loss or damage to your insured property (building and common area contents) that occurs during the period of insurance. Policy 1 is a „broad form‟ accidental loss and damage in s urance contract in terms of the Insurance Contracts Act, 1984 . What we insure We insure You up to the Sum Insured shown for Policy 1 on the Schedule, against accidental loss or damage to Your Insured Property which occurs during the Period of Insurance. Definitions The words listed below have been given a specifi c meaning i n this Policy and these specifi c meanings apply when the words begin wit h a capital letter. … Event, Events means a happening or an incident not intended to happen which Case No: 452172 Recommendation Page 9 of 9 Section Provi sion occurs during a particular interval of time and causes or results in loss or damage, or series of loss or damage happening from that one Event, that is claimable under this Policy. Exce ss means the amount You must p ay towards a claim. You will fi nd the amount of any exce ss shown on the Schedule or within the Policy. Wear, Tear means damage or a reduction in value through age, ordinary use or lack of maintenance. Exclusions We will not pay for loss or damage … caused by lack of maintenance, rust, oxidation, corrosion, Wear, Tear, fading, gradual corrosion or gradual deterioration, concrete or brick cancer, developing fl aws, wet or dry rot, or failure to maintain Your Insured Property in a reasonably good state of repair. Exce ss Excesses may also apply to any claim unde r this insurance. An excess is an amount you have to pay each time you make a claim. The excesses that are applicable are shown on the Schedule, and/or under the clauses titled „Excesses‟ in Policy 1 and „Excess‟ in Part xx of Policy x . An excess will be a pplied for each incident where a claim is made. We will tell you the amount of any excess when you apply for cover. They may vary according to a number of factors, such as your risk location and your insurance history. You must pay or contribute the amou nt of any Excess shown in this Policy or on the Schedule for eac h claim made. Payment of the Excess may be requested when the claim is lodged, or may be deducted from Our payment. With the exception of the Earthquake Excess of Policy 1, should more than one Excess be payable for any claim arising from the one Event, such excesses will not be aggregated and the highest single level of Excess only will apply.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.