Failure to warn that building contract was outside lending policy, causing construction delays
Text of the determination
Determination
Case No: 485337 Determination Page 1 of 6
Case number: 485337 13 March 2018
1 Overview
1.1 Dispute
In September 2014, the applicants obtained conditional approval from the financial
services provider (FSP) for a construction loan for $230,000 to build a house. In
January 2015, the applicants obtained council approval to begin construction. The
applicants then approached the FSP for unconditional approval of the construction
loan.
The FSP said the applicants ’ building contract, which had been provided to the FSP
prior to preapproval, was outside their lending policy.
The applicants say:
The FSP had the building contract in September 2014 but made no mention of it
as part of the conditional approval and did not alert the applicants that it was not
acceptable
The FSP’s decision to decline unconditional loan approval caused delays in
construction of approximately five months, for which they incurred direct losses ,
consequential losses , and non - financial losses.
The FSP gave the September 2014 preapproval in breach of ASIC Regulatory
Guide 209 (RG209), in that the preapproval was unsuitable for the purposes of
RG209.16.
The Case Manager provided the parties with a recommendation dated 18 January
2018 on the issues in dispute. The recommendation was in favour of the applicants.
A copy of the recommendation is attached to this determination. The FSP rejected
the recommendation.
1.2 Issues and key findings
Were the findings of the recommendation correct?
Based on all the available information, the findings on merit contained in the
recommendation were correct and are adopted in this determination. However, as
outlined below, I have reduced the compensation payable by $1,800 to reflect delays
for which the FSP was not responsible. Further submissions provided after the
recommendation have been considered.
Do the new submissions from the parties change the outcome?
The warning the FSP says was contained in the preapproval letter was not adequate
in the circumstances as it focussed on building cost differences and did not alert the
Case No: 485337 Determination Page 2 of 6
applicants to the shortcomings of the building contract. The signing date of the
building contact is not relevant to the finding of delay, although the council approval
delay would have contributed to some of the increased costs. The other FSP
submissions on loss do not change the outcome. In the circumstances the FSP is not
liable to pay interest costs stemming from the delay.
FOS does not request further information (as requested by the applicants) in
circumstances where an error has already been established. Nor does FOS award
punitive damages against a member.
1.3 Determination
This determination is substantially in favour of the applicants.
I agree with the case manager’s reasons for the recommendation and the
recommended the approach to the outcome, although I have lowered the total
compensation payable by $1,800.
If the applicants accept this determination, the FSP must pay the applicants
$29,620.40 within seven days by crediting that amount to the construction loan.
Case No: 485337 Determination Page 3 of 6
2 Reasons for determination
2.1 Were the findings in the recommendation correct?
The recommendation was accurate
I have decided this case on its merits, having regard to the relevant law, good
industry practice, codes of practice and previous FOS decisions. I have taken into
account all the material submitted by the parties, both before and after the
recommendation. I am satisfied that the documentation I have relied on has been
provided to both parties. I am satisfied that the case man ager’s recommendation
contains an accurate summary of the dispute, the issues to be determined, any
applicable paragraphs of the Terms of Reference and any relevant law.
The FSP rejected the recommendation. In responding to the recommendation,
neither par ty addressed the Case Manager’s conclusions in section 2.3 of the
recommendation, which related to whether or not the preapproval was given in
breach of RG 209. I agree with the Case Manager’s findings in that regard as it did
not breach the FSP’s responsi ble lending obligations. In the absence of further
submissions from the parties on that matter, the issues raised in section 2.3 will not
be considered further as part of this decision.
The FSP’s and applicants’ further submissions in relation to the Recommendation ’s
findings on the question of delay and loss are addressed below.
2.2 Do the new submissions from the parties change the outcome?
The warning cited by the FSP was not adequate in the circumstances
The recommendation concluded that the FSP failed to notify the applicants that an
executed building contract was an outstanding condition for unconditional fina nce to
proceed. The recommendation concluded this on the basis of the FSP’s conditional
approval letter to the applicants dated 10 September 2014, which stated only that the
loan would be finalised once “income verification” and a “statement verification of
assets” had been approved by the FSP. Accordingly the FSP did not adequately
warn the applicants that unconditional finance was dependent on a within-policy
building contract being provided to the FSP.
In response to the recommendation, the FSP says adequate warning was provided in
the preapproval letter that the FSP may need to review the loan approval before
unconditional approval was given and it refers to page 2 of the preapproval letter,
which states:
“ We may need to review your loan approval:
If the actual purchase price of the property or building costs on the property is different from the
estimated purchase price or building costs you gave us. ”
When the FSP issued that letter to the applicants, the FSP already had a copy of the
building contract. On page one of the preapproval letter it had not stated that
unconditional approval was dependent on an executed building contract in a different
Case No: 485337 Determination Page 4 of 6
form from that already held by the FSP. In the circumstances, it was reasonable for
the applicants to assume that the FSP had reviewed the building contract and had no
concerns about its contents going forward in the current form. In addition, the
warning on page 2 referred to by the FSP above was not specific to the reasons it
rejected the building contract in January 2015 or effective in disclosing its
shortcomings.
Further, a warning that the FSP “may” need to review loan approval is different from,
and carries less weight than, the assurance on page one of the preapproval letter
that loan finalisation was only dependent on two outstanding factors.
In any event, I agree with the recommendation that good industry practice obliged the
FSP to clearly state in the conditional approval letter that the FSP was yet to accept
the building contract. As it was a fundamental part of the loan application, the FSP
was required to alert the applicants if they needed to take further steps in that regard
before unconditional approval could be obtained. The page two warning cited by the
FSP does not meet this obligation.
Council approval caused some delay in commencing construction
It is not in dispute that it took some time for construction to commence after the
building contract was signed. The building contract was signed in June 2014 and
council approval was not given until December 2014.
The issue in this dispute is whether or not the FSP was responsible for delays once
council approval was obtained because they had not given adequate warning that
building contract was not acceptable for finance to go unconditional in its current
form.
In the circumstances, if an adequate warning in this regard had been give n, there
was time between FSP preapproval and council approval for any issues with the
building contract to be rectified. If unconditional finance was available in January
2015, it is more likely that the timeframe for construction completion in the buildi ng
contract (five months) would have been met.
Having said that, I accept that some of the increased costs of raw materials claimed
as a loss by the applicants are attributable to the fact there were delays between
June 2014 and December 2014. I agree with the FSP that it cannot be held
responsible for those specific increased costings. The recommendation awarded all
of the “delay related costs” totalling $21,800. Given the available information i t is fair
and reasonable for this amount to be reduced to $20,000 to reflect the increased
costs for which the FSP is not responsible.
The signing date of the building contract is not relevant to the finding of delay
The FSP says the applicants were committed to the construction months before they
approached the FSP for finance in 2014. It is unclear what relevance this has to the
finding that the FSP did not adequately warn the applicants that unconditional finance
was dependent on a within-policy building contract being provided to the FSP, and
that this in turn caused construction delays.
Case No: 485337 Determination Page 5 of 6
It is not uncommon for customers to commit to certain contracts, such as purchase or
construction contracts, before finance is finalised. This is particularly the case where
there was no debate around whether the customers could service the finance sought,
and where the applicants had already successfully obtained finance from the FSP for
the purchase of land. The signing date of the building contract does not alter the
finding that the FSP made an error by not including salient conditions in the finance
preapproval letter.
The other FSP submissions on loss do not change the outcome
In response to the recommendation, the FSP also questioned certain costs being
attributed to the delay. I agree with the recommendation that the FSP should be
responsible for the increased costs relating to collapsed footings due to delays
extending construction into winter. The applicants provided sufficient information to
show that these costs were incurred outside the building contract terms, and that
they were paid by the applicants. The applicants also say those costs were not
claimed on insurance. The applicants have provided a sufficient explanation for the
costs relating to the “changes of truss system”, and how they relate to construction
during winter.
The FSP says the road base costs would have been paid in any event during
construction. The road base costs awarded to the applicants were, again, incurred by
the applicants outside the building contract terms. If they were going to be paid in any
event, they would have formed part of the building contract terms. They would not
have been a cost required to be paid by the applicants in excess of the building
contract budget. Accordingly they have been included in the claimed loss.
FOS does not request further information where an error has already been
established
In response to the recommendation, the applicants said that FOS should require the
FSP to provide further information about their actions in 2015, including their “internal
client notes” f or the period January to April 2015, and a further explanation as to why
the FSP considered the applicants’ building contract to be outside policy.
FOS is satisfied that some losses were caused by the FSP on the basis of the
information already provided and the conclusion set out above. Further information is
not required to determine this issue any further. FOS does not request further
information unnecessarily from parties in circumstances where the question of error
has already been determined.
FOS does not award punitive damages
In response to the recommendation, the applicants requested that FOS consider
whether it is fair in the circumstances for the FSP to charge an early termination fee
on their loan if the applicants decide to move their loan elsewhere.
The decision to switch financial services provider is a decision the applicants are
entitled to make. FOS only awards compensation or costs for losses that flow directly
or indirectly from a financial services provider error. We do not award compensation
Case No: 485337 Determination Page 6 of 6
for costs associated with refinancing when an applicant refinances because of
dissatisfaction with the level of service provided by a financial services provider.
Accordingly if the applicants choose to transfer their lending to another financial
services provider, the ability of the FSP to charge an early termination fee or break
cost will depend entirely on the terms and conditions of the loan.
The FSP is not liable to pay any interest costs
In response to the recommendation, the applicants make a claim for the “ extra
interest ” they had to pay on their construction and land loans because of the five
month delay caused by the FSP. Specifically, the applicants say:
It would be unconscionable for the FSP to retain the interest profit related to the
delay.
The five month delay caused a five month delay in the sale of their old property,
meaning it took five months longer to pay down their loans on the new property.
The five month delay meant they were paying $250 per week interest on their
land loan relating to land that could serve no purpose, because no construction
was taking place on the land at that time.
FOS does not award compensation for the purpose of punishing financial firm or
reducing its profits. The award of compensation is to cover the a pplicant’s loss due to
a financial firm’s error. When assessing loss, FOS will also take into account whether
the applicants have also received a benefit from the error.
When all the circumstances are taken into account, an overall interest loss has not
been identified for the following reasons:
If the construction loan was advanced five months earlier, say in January 2015,
the applicants would have been making repayments and incurring interest on
the new construction loan five months earlier, and so that benefit has to be
taken into account.
If the applicants sold their existing property sooner, it is feasible they would
have achieved a lower sale price. This means the a pplicants’ loans over the
new property would not have been paid down to the same extent as they
eventually were when the applicants ’ existing property was sold.
They have not established that their interest cost outweighs the other factors
mentioned above.
Recommendation
Case No: 485337 Recommendation Page 1 of 7
Case number: 485337 18 January 2018
3 Overview
3.1 Dispute
In September 2014, the applicants obtained conditional approval from the FSP for a
construction loan for $230,000 to build a house. In January 2015, the applicants
obtained council approval to begin construction. The applicants approached the FSP
for unconditional approval. The FSP said the applicants’ buildi ng contract, which had
been provided to the FSP prior to preapproval, was outside their policy. The
applicants say:
The FSP’s decision to decline unconditional approval caused delays in the
construction of approximately five months, for which they incurred direct,
consequential, and non - financial losses.
The FSP gave the September 2014 preapproval in breach of Regulatory Guide
209 (RG209), in that the preapproval was unsuitable for the purposes of
RG209.16.
3.2 Issues and key findings
Did the FSP cause the claimed delays in construction?
When the FSP preapproved the construction loan, it did not specify that an executed
building contract was an outstanding condition for unconditional finance. Good
industry practice required the FSP to notify the applicants i n September 2014 that
their building contract was outside policy. Had they done so, the 2015 delays in
construction could have been avoided.
If so, what loss has been established by the applicants?
The applicants have established consequential losses totalling $3,300 and non-
financial losses totalling $4,000. The applicants have also established out of pocket
expenses paid to their builder because of the delays totalling $21,800. The applicants
have not established the remainder of their out of pocket expenses, bar costs for
which there is some supporting information, totalling $2,320.40.
Did the FSP provide the preapproval in breach of RG209?
RG209.18(a) says a credit contract will not be deemed unsuitable if a credit provider
has made reasonable enquiries about a customer’s objectives. The credit contract
put forward by the FSP in September 2014 met the applicants’ objective to build a
house, and as such it was not unsuitable for the purposes of RG209.16.
Case No: 485337 Recommendation Page 2 of 7
3.3 Recommendation
This recommendation is substantially in favour of the applicants. If the applicants and
the FSP accept the recommendation, the FSP must pay the applicants $31,420.40
within seven days.
Case No: 485337 Recommendation Page 3 of 7
4 Reasons for recommendation
4.1 Did the FSP cause the claimed delays in construction?
The applicants say t he FSP caused approximately five month’s delay
The applicants signed a building contract on 5 June 2014. The applicants provided a
copy of the building contract to the FSP when they applied for construction finance
from the FSP on or around 5 September 2014. The FSP gave conditional approval
for construction finance on or around 10 September 2014, and sent a letter to the
applicants confirming this.
Once the applicants obtained council approval for their build on 8 January 2015, they
approached the FSP for unconditional finance approval. The FSP told the applicants
that the building contract previously provided was outside their policy, and that
unconditional finance would not be approved until the construction contract was
brought within policy. Unconditional approval was not given until 23 April 2015. The
applicants say the FSP should have notified the applicants at the point of conditional
approval that the building contract (which it had possession of) was outside policy.
Conditional approval excluded the building contract
The FSP has provided a copy of the conditional approval letter sent to the applicants
on or around 10 September 2014. The letter says the loan application has been
approved, subject to two conditions being met:
income verification, and
a statement verification of assets
It is not in dispute that the FSP had a copy of the building contract when it provided
conditional finance. The FSP says it did not review the building contract at the time it
provided conditional finance. At the same time, when the FSP provided conditional
approval, it did not say that unconditional approval was dependent on a within-policy
executed building contract being provided. It was reasonable for the applicants to
assume that the FSP considered that the building contract was acceptable and that
unconditional finance was only dependent on the factors listed in the conditional
approval letter.
Good industry practice would have been to include the building contract
It is important for credit providers to keep credit applicants informed of matters that
are outstanding prior to giving any sort of unconditional or conditional approval. It
would have been good industry practice for the FSP to clearly state in the conditional
approval letter that the FSP was yet to accept the building contract provided amongst
the two other conditions that remained outstanding. The FSP should have advised
the applicants that the provision of a building contract within their lending policy was
a condition of approval.
Case No: 485337 Recommendation Page 4 of 7
If the FSP had done this, delays would most likely have been avoided
If the FSP notified the applicants in September 2014 that the building contract had
yet to be accepted, and that there were issues within the contract that needed to be
addressed before unconditional finance could be approved, it is foreseeable that the
FSP’s issues with the contract could have been resolved between the applicants and
the FSP before council approval in January 2015. Specifically:
The FSP could have explained the outside of policy elements within the building
contract, giving the applicants sufficient time to make adjustments to the
contract as required before council approval.
Alternatively, the FSP may have given unconditional approval outside policy at
the point of council approval as it later did in April 2015, on the basis that the
FSP was committed to the transaction and that the FSP would be exposed to
loss claims if the original intention to provide funding for land and construction
was not approved.
The FSP caused delays of approximately five months
If the FSP had disclosed sooner that finance was conditional on an appropriate
building contract, construction could foreseeably have commenced in January 2015.
Instead, construction finance was not approved until 23 April 2015, and the loan was
not drawn down until 13 May 2015. The building contract specified that construction
would take five months, so in the normal course of events, construction would have
been finalised in or around the end of May 2015. Because full construction funding
was not available until May 2015, the build continued through 2015, and the last
builder’s invoice was not issued until 8 November 2015. This equates to a delay
period of approximately five months.
4.2 If so, what loss has been established by the applicants?
Some of the losses being claimed due to the delay are consequential losses
FOS can award compensation resulting from financial services provider errors. FOS
can award compensation for direct losses, which are out of pocket expenses or other
liabilities ca used directly by a financial services provider’s conduct. FOS can also
award consequential loss compensation for losses which are indirectly caused by a
financial services provider’s conduct.
In the applicants’ overview of losses, they included:
Income losses related to their business. The applicants had to spend a large
amount of time resolving issues with the FSP and dealing with construction
delays, which detracted from their ability to run a business.
Rental income losses. Because of the delays, the applicants lost the opportunity
to rent out their existing property sooner.
The applicants do not dispute that the income loss is appropriately classified as a
consequential loss, as opposed to a direct loss. The rental income losses being
claimed are also appropriately classified as consequential loss. This is because the
rental income losses are one step removed from the FSP’s error, in that they were
not a direct result of the delay. The rental losses claims are dependent on factors that
Case No: 485337 Recommendation Page 5 of 7
are remote from t he FSP’s conduct, for example the applicants’ ability to secure a
tenant immediately.
The applicants have provided information to show their other property could have
been rented for approximately $380 to $430 a week. The applicants’ income loss
claim is substantial. The maximum FOS can award for the total of consequential
losses stemming from a set of events giving rise to a claim is $3,300. Given FOS is
satisfied that the FSP caused the applicant’s consequential losses, and given those
losses appear to e xceed FOS’s consequential loss compensation cap, it is
appropriate that $3,300 of consequential loss compensation be awarded.
The FSP caused non-financial loss to the applicants
In their submissions, the applicants outlined the stress and inconvenience ca used by
the delays in providing construction finance. I accept that the delay caused by the
FSP would have caused the applicants significant stress and inconvenience,
particularly in circumstances where the applicants would have been under the
impression that construction finance would have been approved once council
approval was given, and that construction would have been finalised by mid-2015.
Instead, the applicants would have spent a great deal of time dealing with the FSP to
ensure finance was provided, and dealing with builders to ensure the cost and
inconvenience of delays was kept to a minimum.
The maximum FOS can award for non-financial losses incurred by an applicant is
$3,000, and we usually only award non-financial loss compensation where an
unusual degree or extent of stress has been caused. In this dispute, it is appropriate
that both the applicants receive $2,000 of non-financial loss compensation in
recognition of the stress and inconvenience they would have incurred.
Some of the direct losses being claimed have been established
The applicants claim a number of direct losses relating to the construction delays.
The total cost of the construction in the building contract was $249,000, but the
applicants say because the construction dragged into winter, the total cost of the
build increased to $286,645. From a list of the overrun costs paid to the builder
totalling $35,345, the applicants have highlighted delay related costs totalling
$21,800, and have provided an explanation for how each cost related to the delay.
The applicants’ loan and transaction account statements show when each of the
progressive building invoice payments was made. The applicants paid the first
instalment of the overrun costs ($15,345) on 26 October 2015. The final builder ’s
invoice incorporating the overrun costs (for $20,308) was issued on 8 November
2015. $5,308 was part paid for this invoice from the applicants’ account number
xx0353 on 9 November 2015. The applicants say the rest of this invoice was paid in
cash in instalments.
I am satisfied on the basis of the information provided by the applicants that:
The delay related costs totalling $21,800 were attributable to the delay, in
particular because of issues that arose during construction in winter.
Case No: 485337 Recommendation Page 6 of 7
The applicants paid these costs to the builder, being $15,345 on 26 October
2015, $5,308 on 9 November 2015, and the remaining portion of the delay
costs ($1,147) by cash on 25 August 2016.
The delay related costs ($21,800) that were paid to the builder as part of the
increased build price should be refunded to the applicants.
Some of the direct expenses being claimed have not been established
In addition to direct losses incurred as a result of overrun costs paid directly to the
builder, the applicants also claim out of pocket costs incurred as a direct result of the
delay. These costs include:
rental of earthmoving equipment for various duties in bogged conditions during
winter: $1,350
purchase of landscaping materials, including rubble, to ensure the safety of a
bogged, muddy work site: $2,089
hire of a bobcat to assist with spread of landscaping materials: $2,900
the cost of a temporary stormwater drain to drain water away from the build site:
$1,600
manual excavation using jackhammers that took longer than usual because of
wet conditions: $2,200
cost of products purchased directly from Bunnings, Mitre 10, and Stratco by the
applicants: $666
The applicants acknowledge that some of these costs were paid in cash and that
they also only retain invoices or receipts for some of these costs. The applicants
have provided FOS with all the invoices available at this stage in relation to these
costs. These include:
invoices totalling $810 for excavator hire on 22 June 2015 and 24 June 2015,
and
five separate invoices for the purchase of landscaping material in May, July,
and August 2015, totaling $1,510.40.
It is reasonable that these costs be paid to the applicants. The invoices provided and
the applicants’ explanation for each cost is sufficient to indicate that they were out of
pocket expenses related to the delay.
FOS requires applicants to provide information to support claims for losses. At this
stage, the available information does not support the applicants’ remaining claims in
relation to other out of pocket expenses listed above. In the absence of any invoices
or other documents to show that the other out of pocket expenses were incurred by
the applicants, FOS cannot award compensation for those losses. Although the
Bunnings, Mitre 10, and Stratco costs are shown on the applic ants’ account
statements, it has not been established that these purchases related to construction
delays.
Case No: 485337 Recommendation Page 7 of 7
4.3 Did the FSP provide the preapproval in breach of RG209?
The applicants say the FSP preapproval was unsuitable
The applicants also say the preapproval given in 2014 was given in breach of
Regulatory Guide 209 (RG209). Specifically, the applicants claim that the FSP
breached RG 209.16, which obliges a financial services provider not to enter into,
suggest, or assist a customer to apply for a finance product or credit contract that is
unsuitable for the customer.
The applicants say the preapproval was unsuitable because it was at risk of being
overturned on the basis of factors that the FSP had not disclosed to the applicants.
RG209.18 gives guidance on unsuitability
RG 209.18 goes on to explain the steps that credit providers are required to follow to
ensure credit contracts are not unsuitable, that is, to ensure RG209.16 is not
breached. There are three requirements, outlined at RG 209.18(a), (b), and (c).
Requirements (b) and (c) are not entirely relevant in this dispute, because they go to
the question of whether or not the FSP assessed the applicants’ financial position
and ability to service the loan. It is not claimed that the loan was unsuitable because
the FSP did not properly assess whether it was serviceable by the applicants.
The credit contract that was offered was not unsuitable for the purpose of
RG209.18
It cannot be reasonably said that the FSP failed to abide by step (a) on unsuitability
when it gave the preapproval in 2014. Step (a) obliges credit providers to ensure a
credit contract is not unsuitable by making reasonable inquiries about a consumer’s
requirements and objectives in relation to the credit contract.
The FSP made reasonable enquiries about the applicants’ requirements in
accordance with requirement (a) – it understood that the applicants required a loan
for $230,000 to construct a new property, and it preapproved a loan for $230,000 to
construct a new property.
As such, the credit contract being conditionally offered by the FSP was not unsuitable
for the purpose of RG209.18(a). The credit contract in and of itself met the
applicants’ requirements, even if the conditions of the credit contract going
unconditional were not ful ly explained as part of the FSP’s offer.