Home / Financial Firm (Unknown - Credit) / Determination 485310

Determination 485310

delay

FirmFinancial Firm (Unknown - Credit)
Decided2017-09-19
ProductCredit · Home loan
OutcomeFor the complainant
Amount awarded$5,341
Non-financial loss—
Amount claimed$5,341
SourceAFCA PDF

Summary

The applicants' bridging finance was withdrawn shortly before settlement, causing contractual penalty interest and legal costs. AFCA found the FSP caused the delay by failing to make reasonable inquiries and ordered compensation of $5,341.42.

The FSP should have made reasonable inquiries after its valuer's inspection on 6 April 2017, and the applicants would otherwise have settled on time, so the resulting losses are compensable.

Issues

Subjects and remedies

pay compensation

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Case No: 485310 Determination Page 1 of 6 Case number: 485310 15 September 2017 1 Overview 1.1 Dispute The applicants say the FSP caused the delay of settlement on their purchase of a property by not realising for some weeks that the Contract of Sale contained a clause that was unacceptable to the FSP. This resulted in:  The applicants having to pay contractual penalties of $4,571.42  Additional legal costs of $770  Stress and inconvenience. The FSP say that the applicants provided an incomplete Contract of Sale and did not disclose that the property was partially build when they applied. 1.2 Issues and key findings Did the FSP cause the settlement delay? The FSP caused the settlement delay by not making reasonable inquiries after its valuer inspected the property on 6 April 2017. If so, what loss did the applicant incur as a result? The applicants incurred penalty interest and legal fees totalling $5,341.42. 1.3 Determination This determination is in favour of the applicants. The FSP delayed the settlement of their contract of sale by not taking reasonable steps to identify that they were not able to lend them. If the applicant accepts the determination the FSP should compensate them $5,341.42 by transferring that amount to an account the applicants nominate. Case No: 485310 Determination Page 2 of 6 2 Reasons for determination 2.1 Did the FSP cause the settlement delay? An FSP should act with due diligence Section 27 of the Code of Banking Practice summarises the duty of an FSP when considering lending applications. “ Before we offer, give you or increase an existing, credit facility, we will exercise the care and skill of a diligent and prudent banker in selecting and applying our credit assessment methods and in forming our opinion about your ability to repay the credit facility ”. The National Credit code also says the FSP must, as part of its lending assessment: “ make reasonable inquiries about the consumer ’s requirements and objectives in relation to t he credit contract”. The key events of the dispute I have summarised the key events of the dispute in the table in section 3.1 of the Determination. I have based this summary on the information provided by both parties. For the purpose of my investigation, I offer the following commentary on the key events of the dispute. The applicants applied for finance for a property that was a new development on 16 March 2017. The contract of sale had been signed by them on 27 February 2017 and had a sixty day settlement timeframe, meaning the Expected Settlement Dated was 28 April 2017. The FSP recorded the purpose of the loan application was to “purchase land and construct a new residential property”. The FSP says that after review and discussion it determined that bridging finance was the best option as the applicants had sold their current home on 23 March 2017 for $3,500,000 and were awaiting settlement. The FSP conditionally approved a loan of $2,500,150 on 23 March 2017 that was subject to the following conditions:  Evidence of a car lease commitment not exceeding $667 per month  Evidence that the applicants ’ current property and investment properties were held unencumbered  That the applicants’ current home be sold pri or to the end of the bridging period  Satisfactory Costing Report confirming cost of new construction. After satisfying itself of the other conditions, the FSP ordered a Costing Report for the new property. The FSP received a copy of the Costing Report on 5 April 2017 The valuer then conducted an inspection of the new property on 6 April 2017. This does not appear to have been sent to the credit department until 12 April 2017 because o n 10 April 2017, the FSP noted that “As a Bank valuation has yet to be undertaken {off-the-plan purchase}, the acceptance of the Costing report will remain pending until the completion of the Bank valuation” Case No: 485310 Determination Page 3 of 6 On 12 April 2017, the FSP noted that it could not accept the valuation provided by its valuer because it did not contain t he wording “off the plan purchase” so it would need to be amended. The valuer appears to have amended the valuation The FSP noted on 26 April 2017 that it had attached the Costing Report and “as if complete” valuation for the credit department to review. The FSP then noted on 26 April 2017 that the Contract of Sale provided with the Building Contract was between the Seller and the Builder, with the applicants not having entered into a building contract. After discussion with their solicitor the FSP noted that there was a clause in the Contract of S ale originally signed “stating that [the Seller] can allocate building contract to purchaser [applicants] which has been done hence land settlement required on the 28/04” . The credit department made the decision on 26 April 2017 that “as this is a split contract…it is treated as off the plan. Therefore we will need to wait till the dwelling is complete”. The FSP advised the applicants that the bridging loan had been declined on this basis at 2pm on 26 April 2017. The Expected Settlement Date was 28 April 2017 but the applicants were trying to source alternate funding and could not settle. They were provided with bridging finance by another FSP and settled on 5 May 2017 but incurred contractual penalties from the Seller in the amount of $4,571.42 for the delay. They also say they had to pay their solicitors an additional $770 as a consequence of the FSP withdrawing the finance The FSP did not act with due diligence It is my view that the FSP:  Was not required to make further inquiries about the full contract when it first received the application for the bridging loan on 24 March 2017  Should, however, have made further inquiries of the applicants as soon as practically possible after receiving the valuation conducted on 6 April 2017 to determine what the contractual relationship was between them and the builder and seller  By not doing so until 26 April 2017, the FSP caused the settlement of the sale of the property to be delayed. My reasons for this view are: The bulk of the FOS dispute to date has been centered on whether the FSP should have been aware that they had uploaded an incomplete contract of sale on 16 March 2017. The reasoning was that if the FSP had made further inquiries at this time about the “Special Conditions” mentioned on page 5 of the contract of sale they would have discovered the issue with the owner builder clause earlier. I consider that, as the reason the FSP requested the Contract of Sale at that time was to inform the FSP of the purchase price and address of the security property to enable them to conduct a valuation and title searches, the FSP did not act unreasonably by not requesting a full copy of the contract, even if I accept that it should have noticed it was incomplete. Case No: 485310 Determination Page 4 of 6 Based on the information it had available to it at the time, the relationship the applicants had with the vendor and builder were not relevant considerations in whether they would lend to them or not. It is clear from the fact that the FSP was comfortable to provide conditional approval for a loan of $2,500,150 on 23 March 2017 that it was not basing its decision at that time on the nature or cost of construction. There were no “red flags” about the property being partially constructed that would have been evident to the FSP at that time. However, when the FSP’s valuer inspected the property on 6 April 2017 he noted the following:  In preparing the valuation we have relied upon the documents supplied by the [FSP], including annexure of the building contract with the Contract of Sale, a copy of the schedule of finishes and endorsed floor plans and evaluations  The property was sold off the market and we consider the current contract price to be above achievable levels  There was a general risk identified of the purchase being a “house and land package purchase”, with the valuer noting that “on the date of inspection the property was approaching frame stage which is estimated for September 2017”  Attached photos show a partially completed property. I consider that a diligent reading of the valuation would have resulted in the FSP making further inquiries of the applicants to determine what the status of the construction was at that time stage. Up until that point it appeared that the applicants had signed a contract for purchase of land on which they were going to build a residential property and just needed bridging finance until their current home settled. However, once the FSP became aware that the land also had a partially completed property on it already, they should ha ve asked some more questions. They also appear to have received a copy of the Building Contract by this time, or their valuer did at least. It was apparent from the Building Contract who the parties were and this would also have been a “red flag” that the y may not be able to fund the purchase. The FSP later noted on 27 April 2017 that: “We have concerns as to why a developer would get a property to frame stage and then change the building cont ract into the customer’s name. We find this inappropriate and we are not prepared to provide lending for this particular security outside of on completion. The developer needs to complete the construction and then when we have occupancy certificate/ council approval that the dwelling meets the required building standar ds, we will fund.” I see no reason why they would not have been aware of this risk on or about 6 April 2017 once the valuation was provided. Instead, what they appeared to do was ask the valuer to amend the valuation to clarify that it was “off the plan” p urchase and then eventually decline to finance it on the basis that it was “a split loan, therefore considered off the plan” in which case they would not fund any loan securing it until construction was completed. Case No: 485310 Determination Page 5 of 6 The FSP caused the settlement delay I am satisfied that the FSP could and should have made further inquiries about the property and the building contract on or about 6 April 2017. They were aware of the pending settlement date and contractual penalties that the applicants would incur and they should have taken some steps to clarify the position. The FSP’s notes indicate that the valuation was not correctly imaged into their system until 12 April 2017 and then had to be reindexed on 19 April 2017. So it is possible that the credit department didn’t actually see the amended valuation until after 19 April 2017. However these delays were caused by the FSP and not the applicants and the applicants had no control over these delays. 2.2 If so, what loss did the applicant s incur as a result? The available information shows that the applicants were advised that the bridging loan was declined on Wednesday 26 April 2017. They were able to quickly seek lending from another FSP and settle on Friday 5 May 2017, being seven working days after they were declined by the FSP. I am satisfied that if the applicants had been advised on or about 6 April 2017, after the FSP’s valuer inspected the property, that the FSP had concerns with the Contract of Sale, they would have been able to seek alternate funding in the same timeframe and have settled the sale of the property on the Expected Settlement Date of 28 April 2017. I therefore consider that the FSP should compensate the applicants the $4,571.42 he was required to pay in penalty interest for the settlement delay. The FSP should also compensate the applicants for the additional legal costs of $770 they incurred for having to seek representation for:  Consequences of withdrawal of finance offer by [the FSP]  Consequences of breach of Contract (with the seller)  Other possible avenues to obtain finance. I am satisfied that the applicant would not have incurred these costs but for the FSP’s delay. The FSP should therefore compensate the applicants $5,341.42 by transferring those funds into an account the applicants nominate. Case No: 485310 Determination Page 6 of 6 3 Supporting information 3.1 The key events of the dispute Date Event 15 March 2017 The applicant submit ted the loan application at an FSP branch. He says he provided a full copy of the contract of sale. 20 March 2017 The FSP says that its credit department received the required documentation . They later said they had only received 21 of 37 pages of the contract of sale 23 March 2017 The FSP provided a conditional approval for a loan of $2,500,150 subject to valuations and costings report 6 April 2017 The valuer completed an inspection and valuation on an “on complet e basis”. The valuer noted that the property was approaching Frame Stage and estimated a September 2017 completion. 12 April 2017 The FSP sent the costing report and valuation to the credit department. The credit department responded by saying the valua tion was not attached correctly. They a lso note that the valuation did not provide the wording of “ off the plan purc hase ” so they would need to get the valuer to amend it 19 Apr il 2017 The FSP reindex ed the costing report and valuation for the credit department to review 24 April 2017 The credit department says it received the costing report at which time they discovered there was an unacceptable clause in the cont ract that they were unaware of and that changed the nature of the request from an “off the p lan ” purchase to an owner builder scenario which is outside its policy. 26 April 2017 The FSP advised the applicants that the loan application had been declined 28 April 2017 The property sale was expected to settle (Expected Settlement Day) 5 May 2017 The property settled (Actual Settlement Day) 17 May 2017 The applicants lodged a complaint with the FSP about the delay and requesting compens ation for the penalty interest the y had incurred 5 June 2017 The FSP responded and said it had made every effort to have the application assessed in a timely manner 15 June 2017 The applicants lodged the FOS dispute 5 July 2017 The FSP made an offer of $2,500 to resolve the disput e that was open t o the applicants to accept until 7 August 2017

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.