Home / Financial Firm (Unknown - Insurer) / Determination 485186
Determination 485186
Tree-impact storm repairs alleged defective and further roof, eave and tile damage claimed; delays in repairs
Summary
The applicant alleged that FSP-authorised tree-damage repairs to his roof, eaves and shower tiles were defective and sought rectification. AFCA found the repairs were not shown to be defective and the other damage was not caused by the event, but ordered $1,000 for non-financial loss due to delays.
The applicant did not establish that the repairs were defective or that the claimed damage was caused by the tree or repairs, while unacceptable delay in commencing repairs and responding to complaints warranted compensation under the Terms of Reference.
Issues
- Claim denial primary · not upheld
“The FSP is not liable for the applicant's claim for damage or rectification as the available material does not establish on the balance of probabilities the repair works were defective.”
- Delay secondary · upheld
“The repairs only commenced about a year after the insured event and this is an unacceptable delay.”
- Repairs or contractors secondary · not upheld
“I do not accept the roof is sagging because of the FSP's repairs. I am not satisfied the applicant has established the repair work to the roof was defective.”
Subjects and remedies
pay non financial loss
Text of the determination
Determination
Case No: 485186 Determination Page 1 of 7
Case number: 485186 22 February 2018
1 Overview
1.1 Dispute
The applicant held a home building policy with the financial services provider (FSP).
The applicant says there were a number of issues with repair work authorised by the
FSP, which in turn have resulted in issues with the roof, eaves and tiles in the
shower. He complains about the damage caused by the repairs or the fallen tree.
The FSP se nt a builder to inspect the repairs and the damage. Based on the builder’s
opinion, the FSP denied the claim saying the repairs did not require rectification and
the claimed damage was not caused by any insured event.
The case manager provided the parties with a recommendation on the issues in
dispute. The recommendation was in favour of the FSP.
The FSP accepted the recommendation but it was not accepted by the applicant. In
the circumstances, the dispute has been referred to me for determination.
1.2 Issues and key findings
Is the FSP liable for the applicant’s damage and claim for rectification?
The FSP is not liable for the applicant’s claim for damage or rectification as the
available material does not establish on the balance of probabilities the repair works
were defective or the repairs or the fallen tree caused the claimed damage.
Is the applicant entitled to compensation?
The available information establishes there has been an unusual amount of physical
inconvenience, time taken to resolve a situation and interference with the a pplicant’s
expectation of enjoyment or peace of mind because of delays in commencing repairs
and responding to the applicant’s complaints.
1.3 Determination
This determination is in favour of the FSP.
The FSP is not required to take any further action in relation to the claim or the
dispute.
Should the applicant accept this determination, then within seven days of
acceptance, the FSP is to pay to the applicant $1,000 compensation.
Case No: 485186 Determination Page 2 of 7
2 Reasons for decision
I have decided this case on its merits, having regard to the relevant law, good
industry practice, codes of practice and previous FOS decisions. I have taken into
account all the material submitted by the parties, both before and after the
recommendation. I am satisfied that the docume ntation I have relied on has been
provided to both parties.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, commentary has been restricted to those issues considered
directly relevant to the outcome only.
Applicant provided a plumber’s report after the re commendation
After the recommendation was rejected, the applicant made further submissions and
provided a report from a plumber. Where relevant, this is referred to in the
determination.
2.1 Is the FSP liable for the applicant’s damage and claim for
rectification?
Applicant must show repairs were defective or the fallen tree caused damage
The applicant must establish on the balance of probabilities that he has suffered a
loss caused by an event to which the policy responds. This is known as a prima facie
claim.
The FSP’s policy provides cover for impact damage caused by trees or branches. It
is not in dispute some parts of the applicant’s home were damaged by tree impact.
The FSP’s policy says if it agrees to cover a claim it will pay the cost to repair the part
of the home which was damaged. The FSP can elect for its repairers to repair the
damage or pay the reasonable cost to repair the damage.
The FSP agreed to repair the damage. The dispute relates to the repairs. The
applicant says the roof has not been properly repaired. The applicant claims the roof
sags because the FSP did not replace the battens as specified in the scope of works.
He also claims damage to the tiles in the ensuite shower and damaged eaves.
The applicant says the eaves lining started falling down around the house between
the time of the tree impact and the start of repairs. He says he made these repairs.
He complains about the FSP’s delays.
He says if something was defective outside the scope of works, he should have been
told so he could make repairs. He does not accept the claimed damage was outside
the scope of works or was a pre-existing issue.
The FSP says the roof is properly repaired. It also says the claimed damage to the
tiles and the eaves were not damaged by the repairs or the impact of the tree.
The FSP’s policy provides if the FSP elects to repair damage, then in addition, the
FSP provides a lifetime guarantee. This means it guarantees the workmanship of
Case No: 485186 Determination Page 3 of 7
repairs which it authorised for the lifetime of the home. It also means it will fix any
defect caused by poor workmanship. The policy provides the FSP will decide on what
needs to be done to fix any defect.
The guarantee does not apply to wear and tear that is consistent with normal gradual
deterioration of the home.
The applicant must establish on the balance of probabilities there are now defects
caused by the FSP’s poor workmanship. Once so established, the onus shifts to the
FSP to prove on the balance of probabilities that an exclusion applies if it seeks to
deny or limit its liability for the loss.
Repairs to roof were not defective
The FSP was not required to repair the whole roof. The FSP was only required to
repair the parts of the roof and home damaged by the fallen tree. The damage was
identified by the assessor and builder who examined the damage with the applicant.
A scope of works was prepared. The applicant agreed to the scope of works and the
repairs were carried out in accordance with the agreed scope.
I have considered the available material including photographs. I do not accept the
roof is sagging because of the FSP’s repairs. I accept the scope of works, provided
the FSP’s builder was to remove and replace damaged beams above the ensuite and
master bedroom and this was not done.
However, the available material establishes the beams were not replaced because it
would have affected the cedar lining walls in the ensuite below. After consultation
with an engineer, the existing beams were laminated on both sides. The builder
surveyor approved this work. The available material establishes the works have been
certified as compliant by the relevant authorities.
After the recommendation, the applicant provided a report from a plumber. While the
plumber says the sheets bow, the report does not establish where the sheets bow.
In order to establish the work done by FSP was defective, the applicant must
establish the roof was sagging in the area of repairs over the ensuite and master
bedroom. The available material does not establish this.
On the information provided, I am not satisfied the applicant has established the
repair work to the roof was defective.
Tiles were not damaged by the tree or by the repairs
I accept the tiles are damaged and repair work was done above the ensuite. The
damage was assessed with th e applicant by the FSP’s assessor within weeks of the
impact damage. No impact damage was noted inside the house. The builder
described the internal damage as minimal.
The photographs show no other damage in the bathroom. The cedar timber above
the tiles is not damaged at all. Photographs provided show the grouting is failing but
the house is around 30 years old. The FSP’s builder says the old grout had been
missing for a long time. The applicant provided no material to rebut the opinion of the
FSP’s builde r.
Case No: 485186 Determination Page 4 of 7
In the circumstances, I am not satisfied the available material establishes the claimed
damage to the tiles in the bathroom was caused by the impact damage of the tree or
by the repairs undertaken by the FSP.
Eaves not damaged by the tree and do not require rectification repairs
The applicant also says eaves are coming lose. However, he does not specify which
eaves.
The agreed scope of works shows the FSP was to remove and replace damaged
eave sheets to the veranda (approx. 3 sqm).
The construction manager from FSP’s builder inspected the repairs on 5 June 2017.
He reported to the FSP that there is some rotted fascia but says it is at the other end
of the house to the repairs. He says this is not related to the claim.
The FSP is only obliged to repair the damage caused by the insured event or rectify
repairs undertaken pursuant to an agreed scope of works. The FSP is not obliged to
advise an insured of any other maintenance work which is required. The repair work
is certified as compliant.
In the circumstances, I am not satisfied the available material establishes the claimed
damage to the eaves was caused by the impact damage of the tree or requires
rectification.
2.2 Is the applicant entitled to compensation?
Compensation paid in some circumstances
FOS’s Terms of Reference allow the payment of compensation (capped at $3,000)
for non-financial loss. FOS may decide an FSP should compensate an applicant for
such loss only where there has been an unusual amount of physical inconvenience,
time taken to resolve a situation, or interference with the applicant’s expectation of
enjoyment or peace of mind.
The applicant complains about delays and the stress caused by the claim.
I accept issues arose in relation to the i nitial assessment of the claim. However, the
repairs only commenced about a year after the insured event and this is an
unacceptable delay.
Further, when the applicant complained about the repairs in 2017, it took several
months for the FSP’s builder to respond to the applicant’s concerns.
FOS takes a conservative approach to compensation for non-financial loss. In the
circumstances of this dispute, I consider there was an unusual amount of time taken
to resolve the situation both initially and in 2017. I accept the FSP’s conduct has
interfered with the applicant’s expectation of enjoyment or peace of mind.
I am satisfied it is fair in all the circumstances the FSP pay to the applicant $1,000
compensation.
Case No: 485186 Determination Page 5 of 7
3 Supporting information
3.1 FOS Approach
It is an accepted principle of general insurance law that an insured bears the onus to
establish on the balance of probabilities that they have suffered a loss caused by an
event to which the policy responds. This is known as a prima facie claim. Once so
established, the onus shifts to the insurer to prove on the balance of probabilities that
an exclusion applies if it seeks to deny or limit its liability for the loss.
3.2 Expert reports and other material
Expert Key points
Applicant’ s
plumber’s report
20 - 09 - 17
RS inspected the roof repair and photographs .
Batons of the roof have not been rectified before the roof was
reinstalled/repaired.
When walking on the roof the sheets bow down by about 30mm to meet
the baton. The screws would only just be biting the bat on.
Th is results in non - waterproof and non - compliant work .
If the screws are tightened to make a tight seal, the colorbond sheets sag
about 30mm.
FSP’s builder’s
report
06 - 03 - 14
Inspected damage with applicant 28 February 2014.
Tree fell on the home causing a hole through the roof and damage to the
front right hand section of the home.
Noted external damage to about 10 roof sheets, 3 rafters and 2sqm eave
lining to the veranda.
Internal damage is minimal with no damage to plaster. Noted fan in
bedroom 4 making humming sound, fan to ens uite dislodged and will
require reinstatement.
Noted more damage may be found once roof sheeting removed .
Scope of Works
executed
03 - 06 - 14
See below under 3.3.
Variation request
28 - 08 - 14
Variation in quotation $23,387.36. Included:
21. Exhaust fan in ensuite checked and confirmed to be replaced.
21. Arrange engineer to attend site to provide structural plans for the
replacement of the beams.
Truss Replacement
Plans
Approved 18.12.14.
Existing damaged roof trusses above the ensuite hatched area up to be
removed and replaced by new timber trusses.
Email from
structural engineer
to FSP’s builder
04 - 02 - 15
Proposed alternative method of repair to roof truss.
Case No: 485186 Determination Page 6 of 7
FSP’s builder email
20 - 02 - 15
Roof rectified today.
Battens have been fixed done correctly and are compliant.
We have re - screwed every batten on the roof and they meet the current
building standard.
If unevenness to the roof incurs in the future please contact us.
Compliance
Certificate VBA
25 - 02 - 15
Plumbing work completed 23 Feb 2015.
Installation details: remove existing storm damage ro ofing and replace with
new colo rbond corry and sisaltion and matc h existing flashings, guttering,
downpipes, move drainage vent and replace damaged roof sprinkler
system.
Certificate of final
inspection
20 - 04 - 15
Roof truss replacement approved .
FSP ’s builder (GT)
email to FSP
8 - 06 - 2017
Met the applicant on 5 June 2017 with plumber and builder as applicant
says all roof battens should be replaced.
I have ex plained to the insured it is not a renovation it is a rectification. The
area of damaged was repaired as whic h I showed the photos of the work
that had been done and framing inspection that was carried out by the
council with the engineering plan see attached.
Tiles in ensuite have come lose. Wall tiles is missing a lot of its grout
between the tiles and in the corner which is letting water in behind the tiles
which are now coming loos e. Phot attached.
Another issue is there is some rotted fascia at the other end of the house
which the ins ured believe that this should have been replaced as a small
section of eave sheet is starting to b ecome dislodge. Which is not related
to the claim. See photo attached.
Another issue the insured believed that a top plate in the ensuite had not
been replaced. We inspected this in the roof and the top plate has a very
small split where the nail had come out through the side photo attached
(sic).
FSP ’s builder (GT)
email to FSP
26 - 07 - 2017
The reason for the change in the scope was that if the beams had to be
totally replaced it would have affected the cedar lining walls in the ensuite.
The external build er brought this up with our Building Consultant that the
engineer had not taken this into a count the cedar wall lining and the size
of the new beams. The building Consultant contacted anot her engineer
who gave another alternative to laminate on both sides of existing which
the Building Surveyor had approved.
The repair were done on the R/H side of the roof looking from the back
photo attached. The insured was claiming when I went to site on the 5th
June 2017 that the roof was uneven. The uneven part of th e roof is not
where the work were carried out. The repair works that had been carried
out the laminate beams are a lot stronger than the existing ones.
We do not believe that the tree had damaged the shower as none of the
cedar lining boards were dislodged and the tiles in the shower were still
intact. I have spoken to the builder and engineer and they recall that there
was no damage to this area only old grout that had been missing for a long
time. When I viewed this on the 5t h June 2017 I found the same t hing.
Case No: 485186 Determination Page 7 of 7
The insured may of have had a straight roof when the house was 1st built
which was done out of OBHW as we know OBHW does shrink a lot over
time that is why the roof is uneven not by the impact.
Yes the top plate has a very small split in the top edge of the plate where
the rafter was skewed nail the rafter to the top plate unfort unately this can
happen for time to time. I have spoken to the engineer about this and they
have stated this is not a structural problem.
3.3 Original scope of works executed 3 June 2014
The original scope of works executed 3/6/2014 included the following:
2. Check exhaust fan to ensuite and confirm correct operation and reinstate cover. If
damage is found a variation will be required,
3. RHF of home. Remove and replace damaged eave sheets to front verandah to best
match existing approx. 3sqm (variation may be required if any additional sheets are
damage from fascia replacement).
10. 22.5m x 6.8m Carpenter Remove and replace damaged beams to front RHS of home
(above ensuite and master bedroom) approx. 6.8m (Note: Variation will be required if
additional damage is found once roofing sheets are lifted) Approx 4 beams @6.8m.
11. 22.5m x 6.8m Plumbing Remove and replace 10 roofing sheets and flashing to RHS
above ensuite Approx 6.8m x 7.5m (Includes replacement battens to roofing sheets) .
12. 22.5m x 6.8m Electrical Remove and replace 3 damaged solar panels to best match
existing (Variation will be required if solar system inverter does not function correctly) .
13. 22.5m x 6.8m Plumbing Remove and replace gutter to front RHF of home from ensuite
to entry area Approx. 25LM (Includes reinstatement of existing gutter guard) .
14. RHS front of home 22.5m x 6.8m Carpenter Remove and replace fascia to best match
existing approx. 9LM.
15. RHS front of home 22.5m x 6.8m Painting Seal and paint fascia, eave lining and
guttering to the RHS Front of the home approx. 25LM of guttering and fascia eave lining
45sqm.
3.4 Relevant policy sections
The relevant policy extracts are referred to in the recommendation and the FSP’s
Notice of Response dated 5 July 2017. Both the policy document and the Notice
have been exchanged with the applicant.
3.5 Other relevant material considered and relied on
Parties’ submissions, emails, photographs, reports, scopes of work and all
attachments to all submissions both before and after recommendation.
Correspondence between the parties.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.