Determination 484542
Compliance with earlier determination: excess refund, interest, temporary accommodation extension
Summary
Applicants with a fire-damaged home disputed the FSP's compliance with an earlier determination, including the $300 excess, interest, temporary accommodation and the policy ending after a total loss payment. AFCA decided the FSP largely complied and must refund the excess, pay interest and outstanding temporary accommodation costs, but was not required to extend temporary accommodation beyond 20 March 2018 or pay for a new policy.
The earlier determination set the payment terms, the FSP had not unreasonably delayed settlement, and the policy ends on a total loss payment under its terms.
Issues
- Delay primary · not upheld
“I do not consider the FSP has unreasonably delayed payment of the cash settlement amount. The FSP is entitled to limit temporary accommodation and storage cost to 20 March 2018.”
- Claim amount dispute secondary · upheld
“The FSP must refund the excess paid of $300 and pay interest of $436.16 if it has not already done so.”
- Policy cancellation or underwriting secondary · not upheld
“I am satisfied the FSP is entitled to rely on the terms of the policy to end the policy and not required to issue a refund of the premium.”
Subjects and remedies
home or building damagepay claimpay interestrefund fees or charges
Text of the determination
Supplementary
Determination
Case No: 484542 Supplementary Determination Page 1 of 4
Case number: 484542 9 October 2017
1 Overview
1.1 Dispute
This dispute arises from damage to the applicants’ home. The dispute has been
subject of a FOS determination (433928) that was in favour of the applicants.
The determination required the financial services provider (FSP) to make a number
of payments. This dispute is as to the FSP’s compliance with the determination.
1.2 Issues and key findings
Has the FSP complied with the determination?
There have been delays in the payment of the determination and FSP has now
agreed to refund to the applicants the excess of $300 plus pay interest claimed of
$436.16 as requested by the applicants.
Are applicants entitled to further period for temporary accommodation?
The FSP is required to pay the temporary accommodation and storage cost incurred
to date. In the event such payments remain outstanding the FSP must pay the
outstanding accounts plus interest within 14 days of this determination.
Temporary accommodation and storage cost are payable to 20 March 2018. I do not
consider the delay in payments justifies an extension of this period.
Can the FSP cancel the policy?
As the claim was paid on a total loss basis the policy ends. The FSP is not required
to refund the premium given the benefit is paid in the period of cover. The FSP is not
required to pay the applicants for their new policy with another insurer.
1.3 Supplementary determination
The FSP has largely complied with the determination.
The FSP must refund the excess paid of $300 and pay interest of $436.16 if it has
not already done so. Further, if it has not already done so, the FSP must, within 14
days of receiving this supplementary determination, pay the temporary
accommodation and storage costs incurred to date so in accordance with the
Determination.
Case No: 484542 Supplementary Determination Page 2 of 4
2 Reasons for determination
2.1 Did the FSP comply with the determination?
Determination accepted on 20 March 2017
I have previously issued Determination 433928. The determination, sets out the
reasoning for the decision.
The determination was sent to the parties on 20 February 2017. The applicants
emailed their acceptance of the determination on 17 March 2017.
FOS processed this acceptance on its system on 20 March 2017 (the next business
day). FOS notified the FSP of the applicants’ acceptance on the same day.
The date of effective acceptance of determination is therefore 20 March 2017.
Determination sets out how dispute to be resolved
For the sake of clarity, I have summarised my determination for case number 433928
in the following table:
FSP to pay for Amount Applicants to provide
f urther information
for payment
consideration
Interest payable
Building sum ins ured $358,312 No Yes, from 30 January
2016 to date of
payment
Temporary
accommodation
allowance
$2,607 per mont h from
about January 2016 to
20 February 2017.
No No
Further temporary
accommodation
allowance
$2,607 per mont h from
date of acceptance of
determination, until
repairs /rebuilt are
completed or up to a
maximum of 12
months.
Yes. Applicants to
provide proof for cost
incurred.
No
Storage cost Storage cost invoiced
amount, from date of
acceptance of
determination, until
repairs/rebuilt are
completed or up to a
maximum of 12
months.
Yes. Applicants to
provide proof for cost
incurred.
No
Additional costs of
rebuilding, per policy
terms
If applicants chose to
rebuild property, then
FSP needs to consider
additional amount
claimed in line with the
Yes. Applicants to
provide proof for cost
incurred.
No
Case No: 484542 Supplementary Determination Page 3 of 4
additional benefits
section of the policy.
Non - financial loss
compens ation
$3,000 No No
Professional cost
incurred (RB’s report,
JWB’s quotation, fire
authorities report )
$4,775 No No
The FSP agrees to refund the excess of $300
The FSP paid the applicant the building sum insured of $358,312 plus interest.
The applicants dispute the FSP’s decision to deduct the $300 excess from the
settlement amount. Both parties have referred to the determination as the basis for
their position.
The FSP has now agreed to refund the excess of $300 to the applicants. This
resolves that aspect of this dispute.
FSP agreed to pay $436.16 of interest
The applicants sought $436.16 for penalty interest for FSP’s delay in making
payment.
The FSP has confirmed (in its letters to FOS dated 8 June 2017 and 21 July 2017) it
is prepared to pay for this amount. This resolves this aspect of the dispute .
2.2 Are the applicants entitled to further temporary accommodation or
storage cost beyond 20 March 2018?
The FSP has agreed to consider and accept further temporary accommodation and
storage cost from 20 March 2017 to 20 March 2018.
The applicants say the FSP has delayed the settlement of the claim, therefore the
FSP should be required to pay up until 31 May 2018 (approximately two additional
months than what the FSP has agreed to).
The determination allows for further temporary accommodation and storage costs
from the date of determination acceptance, until the repairs/rebuild is completed
up to a maximum of 12 months. The applicants are required to provide the FSP with
proof of the temporary accommodation and storage costs incurred.
FSP did not unreasonably delay settlement.
After reviewing the exchanged material, I do not consider the FSP was solely
responsible for the delay.
On 24 February 2017, the FSP requested for the applicants to seek a confirmation
letter from their bank (IG) about how the funds from the claim settlement should be
paid. This is a reasonable request given IG bank is an interested party on the policy.
The applicants’ bank (IG) provided this letter to the FSP on 25 May 2017.The FSP
made payment according to the bank’s instruction on 31 May 2017.
Case No: 484542 Supplementary Determination Page 4 of 4
Given the above, I do not consider the FSP has unreasonably delayed payment of
the cash settlement amount. The FSP is entitled to limit the extent of temporary
accommodation and storage cost to 20 March 2018.
FSP required to pay outstanding temporary accommodation or storage costs
The applicants have submitted documentations for:
storage cost invoices (SK) from November 2016 to June 2017
signed rental agreement for a house, starting on 22 February 2017 at $600 per
week
signed rental receipts for the period 22 February 2017 to 25 July 2017.
This information was exchanged with the FSP on 4 July 2017. The FSP has not
responded. It is unclear why it has not done so, given the determination requires the
FSP to consider and pay for temporary accommodation and storage costs incurred.
If it has not already done so, the FSP must pay the outstanding temporary
accommodation and storage costs plus interest within 14 days of receiving this
supplementary determination.
2.3 Can the FSP cancel the policy?
The FSP can cancel the policy
The applicants want the FSP to pay for their new insurance policy taken up with
another insurer. They say they were forced to do so because the FSP cancelled their
policy.
It is not in dispute the FSP has paid the applicants the claim on a total loss basi s.
The terms of the policy states if a total loss claim is paid, then:
the policy comes to an end, and
no refund of premium because the FSP has discharged their obligation under
the policy.
I am satisfied the FSP is entitled to rely on the terms of the policy to end the policy
and not required to issue a refund of the premium. The FSP is not required to pay for
the applicants new policy.
Determination
Case No: 433928 Determination Page 1 of 7
Case number: 433928 20 February 2017
3 Overview
3.1 Dispute
The applicants held a Home Building and Contents Policy with the financial services
provider (FSP) and lodged a claim following a fire at the property on or about
12 March 2015.
The FSP accepted liability for the claim however dispute arose as to the extent of the
damage. On 13 November 2015 the FSP offered the applicants a cash settlement of
$273,488.60 in full and final settlement of the claim.
The FSP later offered to obtain a final scope of works (SOW) utilising an independent
assessor including all rectification work and removal of hazardous material, a repair
quotation with a cash settlement to be issued based on this scope of works.
The applicants rejected the FSP’s offer and seek payment of $498,997.12 based on
the building sum insured and allowances for temporary fencing, temporary
accommodation, non-financial loss and other costs related to the claim.
3.2 Issues and key findings
Is the FSP entitled to cash settle the claim?
The Panel is satisfied given the issues in dispute that it is fair in the circumstances
that this claim be cash settled.
Are the applicants entitled to be cash settled for the sum insured?
The Panel is satisfied based on the information exchanged that the applicants are
entitled to be cash settled for the sum insured of $358,312 plus the additional
benefits as set out under section 2.2 of this determination.
Are the applicants entitled to compensation for non-financial loss?
The applicants are entitled to compensation for non-financial loss for the
inconvenience and delay associated with the claim. The panel determines
compensation of $3,000 as applicable.
Are the applicants entitled to compensation for the cost of the reports
obtained?
The applicants are entitled to compensation for the cost of the reports obtained of
$4,775 pursuant to paragraph 9.4 of the Terms of Reference.
Case No: 433928 Determination Page 2 of 7
3.3 Determination
This determination is in favour of the applicants.
The FSP is to pay the applicants the sum of $358,312 plus interest pursuant to
section 57 of the Insurance Contracts Act 1984 (the Act) on the settlement sum from
31 January 2016 to date of payment of the claim.
The FSP is to pay the applicants a temporary accommodation allowance at the rate
of $2,607 per month from the cessation of payments on or about January 2016 to
date.
The FSP is to continue to pay temporary accommodation costs from the date of
acceptance of this determination at the rate of $2607 per month plus any relevant
storage costs until the repairs are completed or the property rebuilt for a maximum
period of 12 months subject to the applicants providing relevant invoices for the costs
incurred.
Should the applicant choose to rebuild then the FSP is to pay the additional costs of
rebuilding as per the additional benefits under the terms of the policy subject to the
applicants providing proof of the costs incurred.
The FSP is to pay the applicants $3,000 pursuant to paragraph 9.3 of the Terms of
Reference as compensation for non-financial loss.
The FSP is to pay the applicants $4,775 being compensation pursuant to paragraph
9.4 of the Terms of Reference for professional costs incurred in obtaining RB’s
report, JWB’s quotation and reports from the fire authorities.
Case No: 433928 Determination Page 3 of 7
4 Reasons for determination
There has been a full exchange of material between the parties and each party has
had the opportunity of addressing the issues that arise from the information
exchanged.
Due to the complexities involved in this dispute, the dispute has been referred to a
Panel for determination.
This determination follows consideration of all of the information exchanged and is
based on what is fair in all the circumstances, having regard to the relevant legal
principles, terms of the policy, good industry practice including codes of practice and
prior determinations where applicable.
4.1 Is the FSP entitled to cash settle the applicants’ claim ?
The FSP is entitled to cash settle the applicants’ claim
The applicants’ policy commenced on 20 August 2014 and provided cover for the
applicants’ home for a sum insured of $358,312 plus contents of $53,045. Cover was
subject to a basic excess of $300 under each item. Additional benefits under part 2 of
the policy include removal of debris and extra costs of rebuilding and temporary
accommodation costs when the home is not fit to live in whilst the home is being
repaired or rebuilt.
The additional benefits are limited under part B of the policy to a maximum sum of
10% of the home sum insured for the removal of debris and extra costs of rebuilding
and a maximum sum of 10% of the home sum insured to cover the temporary
accommodation costs.
The policy provides that where the FSP agrees to pay a claim, it may decide whether
to repair or replace the damaged property or pay the amount it would cost to repair or
replace the property to “as new” condition.
Circumstances of Loss
There is no dispute that on 12 March 2015, the applicants’ home and contents were
significantly damaged in a fire that had occurred that day. The FSP accepted liability
and arranged for temporary accommodation for the applicants and their four children
in a three bedroom apartment.
The panel notes the initial fire report provided to the FSP identifies that the property
was significantly fire damaged. It recommended the appointment of an engineer to
assess the structural damage.
Prior to obtaining an engineer’s report the FSP obtained a SOW from building
consultants S. The FSP obtained an engineering report from FMG in May 2015
approximately two months after the fire. In June 2015, S provided a supplementary
report.
The SOW was reviewed by a second engineer C. C suggested variations to the
SOW. C’s report was prepared on 23 September 2015, six months after the fire. The
Case No: 433928 Determination Page 4 of 7
FSP then arranged for asbestos testing and an environmental assessment report
from B was obtained after mould had developed through the property.
The environmental assessment was provided on 22 September 2015 and noted a
significant amount of mould was air borne viable.
The report recommended amongst other things the removal of all plasterboard wall
panels and the requirement of an independent assessment to perform a post
remediation verification. Only after receipt of a clearance certificate should
containment be taken down and other contractors given access to the site before
rebuilding works.
On 29 October 2015 the FSP advised the applicants via email that relying upon the
information received the best settlement method was for a cash settlement to be
processed for the cost of the building works and mould remediation. The Panel is
concerned that the FSP provided no reasoning why it considered a cash settlement
the best method by which to settle this claim. Given the concerns expressed in the
SOW and mould assessment report by offering to cash settle the claim, the FSP was
transferring much of the risk for additional costs to the applicants without any
appropriate allowance for those risks.
The Panel acknowledges the policy provides the FSP with a discretion as to the
method of settlement of the claim however such discretion must be issued
reasonably and consistent with the principles of utmost good faith. If an FSP is to
seek to cash settle a claim based on quotations that do not cover all possibilities,
then the FSP should make suitable allowance to allow the insured sufficient funds to
complete the required purpose.
Cash settlement offered inadequate
In an email dated 13 November 2015 the FSP offered the applicants $273,488.60
comprising the following:
Building repairs - $226.381.98
Removal of contents debris - $3,000
Temporary accommodation for 120 days - $10,428
Contents storage for 120 days - $1,368
Mould remediation - $32,038.62
Temporary fencing
Total costs less $300 excess - $273,488.60
The FSP had previously offered to continue to pay temporary accommodation costs
for the length of time the repairs would take over and above policy limits. This is not
reflected in the offer on 13 November 2015.
When the applicants’ questioned the adequacy of the offer, the FSP th reatened to
discontinue payment of the temporary accommodation costs. The FSP had taken
over eight months to make an offer to the applicants. The Panel considers such
conduct is not consistent with the principles of fairness or utmost good faith. The
FSP’s conduct was threatening and intimidating to vulnerable applicants.
The FSP later revised the offer and offered:
Case No: 433928 Determination Page 5 of 7
an independent assessor to attend the property for the purpose of submitting a
final statement of works
final statements of works to include an estimated completion date of repairs
Temporary accommodation to be provided until that date regardless of the
policy limit
repair quotation obtained based on the scope of works, cash settlement based
on this quotation
costs incurred for malicious water use to be compensated
non-financial loss of $1,000.
The applicants had informed the FSP that they had obtained an independent
engineer’s report from RB. The FSP said it was not reasonable for the applicants to
obtain an independent report of their own. It argues that the notion of a report
commissioned by the applicants defeats the purpose of an independent report. The
Panel does not agree. It is not unreasonable for an applicant to obtain an
independent report particularly where the issues in dispute are as complex as in the
current matter. A full exchange of information between parties allows for an informed
discussion to occur
The FSP claims that at all times the applicants have made it clear that they want the
house rebuilt. The Panel disagrees. The app licants have relevantly advised the FSP
that they seek to either have the house repaired or rebuilt in accordance with the
terms of the policy.
The Panel accepts given the time that has elapsed and the breakdown of the
relationship between the applicants and the FSP that it is now appropriate to cash
settle the dispute. The Panel however is not satisfied that the FSP’s offer to settle the
claim adequately covers the likely cost to repair or rebuild the property.
4.2 The applicants are entitled to be cash settled for the sum insured.
The applicants engineering report and costings for the repair or rebuild of the house
are unchallenged by the FSP.
S originally provided the FSP with a scope of works and recommended an
engineering report be obtained. FMG provided an engineering report. FMG agreed
that the entire roof and ceiling framing of the property needed to be replaced and
also identified damage to the footings. It is unclear whether FMG agreed that the
water damage was proximately caused by the fire. The Panel accepts that the water
damage to the property was caused by not only during the attempts to put out the fire
but also by rain and subsequent water leaks throughout the property due to the
inadequate make safe repairs.
B recommended remediation work due to mould including removal of all contents,
wiring, ducts, tiles and plasterboard walls. This is not disputed.
It is apparent that there is significant damage to the roof and supports. Parts of the
roof framing have been burnt and lost structural capacity whilst other parts destroyed.
Asbestos has been removed and the property is now unsafe to enter. Kitchen
cabinets and family room walls are damaged.
Case No: 433928 Determination Page 6 of 7
RB has provided the applicants with a detailed report highly critical of the scope of
works provided by the FSP describing that scope of works as “practically useless as
a document that describes how to reconstruct this building”.
His report contains not only detailed observations as to the nature of the damage but
also consideration of the quotations provided by the FSP from the FSP’s builders P
and Q. Drawings were provided of the property as well as photographs.
RB concluded that the remains of the property were not suitable for reconstruction
and the house had been compromised by the lack of protection from the weather
over the past year. RB considered it a simpler and less risky process to completely
demolish the remains of the house.
The applicants obtained a quotation from a builder JWB. The builder provided a
detailed estimate of $369,772.14 for the rectification of the damage in accordance
with S’s SOW, RB’s report and B’s report for the mould remediation.
The FSP has provided no response to the estimation provided by JWB nor has it
provided a response to the findings of RB.
The FSP did obtain a SOW from CRD dated 25 August 2016. CRD was provided the
reports relied upon by the FSP. The FSP did not provide CRD with a copy of RB’s
report. The FSP did not obtain a quotation based on the SOW.
In the Panel’s view, the applicants’ reports are unchallenged. Th e reports are
detailed and well reasoned. They take into account the reports provided by the FSP
(other than CRD’s). For these reasons the Panel considers the reports from RB and
JWB are to be preferred.
If the FSP is to cash settle this dispute, then the FSP must pay the applicants the
sum insured of $358,312 plus interest calculated in accordance with section 57 of the
Act from 31 January 2016 to date of payment of the claim plus the additional
benefits.
Temporary accommodation costs and contents storage
The applicants advised that the FSP ceased paying temporary accommodation costs
from January 2016. After that date, they were required to pay $2,607 per month until
they could no longer afford it. They have recently been living with a relative.
The FSP paid the applicants the sum insured for the contents lost. However, under
the policy the FSP remains liable to pay the applicants costs to store any undamaged
contents during the repair/rebuild process.
The Panel considers the FSP acted unfairly and without utmost good faith in
terminating the temporary accommodation payments. The ongoing delay in the
resolution of this claim lies with the FSP.
The Panel determines the FSP pay the applicants $2,607 per month from January
2016 when temporary accommodation pa yments ceased to the current time and
ongoing temporary accommodation costs at the rate of $2,607 per month plus any
contents storage costs until either the completion of the repairs or the rebuild of the
Case No: 433928 Determination Page 7 of 7
property for a maximum period of 12 months subject to the applicants providing the
relevant invoices for payment.
Removal of debris and extra costs of rebuilding
The policy also provides cover for the removal of debris and extra costs of rebuilding.
The quotation from JWB includes the cost to demolish those areas required to be
demolished and to remove all debris during the repair. The estimate takes into
account the likely additional costs associated with the removal and disposal of the
debris. The FSP is not liable for any further costs with respect to this.
The quotation does not include the potential costs associated rebuilding such as
surveyor, architect or engineer fees or building application fees. The FSP is liable for
these fees should the applicants chose to rebuild the property.
4.3 The applicants are entitled to compensation for non-financial loss.
FOS may award compensation for non-financial loss in circumstances where a
person experiences an unusual degree of physical inconvenience, time taken or
interference with an expectation of enjoyment or peace of mind.
The Panel’s accepts that the applicants have experienced an unusual degree of time
taken and physical inconvenience as a result of the delays in resolving this matter
and determines the FSP pay the applicants $3,000 compensation for non-financial
loss.
4.4 The applicants are entitled to the cost of the reports obtained.
FOS may determine that the FSP contribute to the professional costs incurred by an
applicant in the course of a dispute. FOS will not normally require an FSP to
contribute more than $3,000 to these costs.
The applicants reports from RB and JWB have been relied upon by the Panel in
reaching this determination. Those reports have been critical in establishing the
applicants’ case. The FSP has provided no information to challenge th ose reports.
The Panel accepts that exceptional circumstances do exist and determines the FSP
should pay the applicants $4775 for the reports from RB, JWB and the fire authority.