Determination 484189

Reimbursement of rectification works costs under water damage claim

FirmFinancial Firm (Unknown - Insurer)
Decided2017-11-30
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed$8,605
SourceAFCA PDF

Summary

The applicant had rectification works costing $8,605 carried out after the insurer had dropped its requirement for them, and sought reimbursement. AFCA refused the works cost but ordered the insurer to pay for the applicant's consultant report, which the insurer relied on in changing its position; the report amount is not stated.

A claimant who proceeds with works after being told they are not required cannot recover their cost, but an expert report the insurer relied on in reversing its position is reimbursable under the claim.

Issues

Subjects and remedies

pay claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 484189 Determination Page 1 of 3 Case number: 484189 30 November 2017 1 Overview 1.1 Dispute The applicant holds a home building and contents insurance policy (the policy) with the financial services provider (FSP). On 31 October 2016, the applicant lodged a claim for water damage to the insured property. The FSP has accepted the claim under the insured event Escape of Liquid as the water escaped a burst pipe. As part of its assessment of the cause and extent of the damage the FSP initially referred to concerns relating to the construction of the insured building. The FSP on further review and having received a report from consultants ‘B’ elected to authorise repairs under the claim. The applicant chose to authorise the rectification building works initially recommended by the FSP and believes it should be required to reimburse her for these costs. These works were not required and did not resolve the issue of existing elevated moisture levels in the area of the building subject of the claim. 1.2 Issues and key findings Is the applicant entitled to be reimbursed for her costs under the claim? The available information establishes the applicant, despite obtaining a consultant report advising there was no need to undertake the recommended works and the FSP confirming it had reversed its decision, proceeded to authorise the works. Accordingly, the applicant essentially elected to authorise and pay for the previously recommended building works despite being informed she was not required to do so. Therefore, the applicant having proceeded with the works on her own account is not entitled to a reimbursement by the FSP of the costs sought under the claim. 1.3 Determination This determination is in favour of the FSP. The FSP is not obliged to reimburse the applicant for the building works she is seeking cover for under the claim. The FSP is to arrange payment to the applicant of the cost incurred in arranging the building assessment report by consultants B within 14 days of being provided with the relevant evidence of payment (tax invoice) by the applicant. Case No: 484189 Determination Page 2 of 3 2 Reasons for determination 2.1 Is the applicant entitled to a reimbursement for the costs claimed? The building works were not authorised on the instructions of the FSP I have considered the available information and am satisfied on balance it establishes the following:  the applicant lodged a claim for water damage to her home which was accepted by the FSP to be due to an insured event (burst pipe)  the original consultants ‘J’ appointed by the FSP raised concerns with the drainage at the insured property and recommended rectification works  the FSP informed the applicant she would need to arrange this rectification works before it would authorise the repairs accepted under the claim  further investigations by the consultants appointed to the claim including consultants B appointed by the applicant established the concerns raised were not supported by the evidence  the FSP informed the applicant it would authorise the repairs under the claim regardless of whether she wished to action the recommendations by J or not  the applicant despite the evidence from B and clarification from the FSP that it did not require her to arrange for the rectification works initially recommended, proceeded to authorise for them to be completed at a cost of $8,605  the works authorised by the applicant did not address the issue as the moisture levels in the area remaining elevated and the reason for which is yet to be established. The applicant chose to authorise the rectification works on her own accord I acknowledge the available information establishes the first consultants appointed by the FSP erred in their recommendations to the FSP. J’s recommendation that there existed issues relating to defective building and drainage arrangements at the insured property were not accurate. The available information also shows the FSP did originally inform the applicant that she would need to have these building and drainage concerns rectified before it would authorise repairs for the water damage under the claim. The applicant in line with the available information was not satisfied with J’s findings and arranged a building assessment of her own by consultants B. The FSP also authorised further investigations under the claim in the effort to establish the reason for ongoing elevated moisture levels at the insured property. The FSP on considering the report from B as well as advice from its appointed consultants reversed its decision requiring the applicant to arrange the recommended works. The FSP informed the applicant it was prepared to authorise repairs for the water damage to the insured building subject of the claim with no requirement for her to arrange any rectification works. The applicant, despite the more recent information and advice from the FSP, proceeded to authorise the recommended works on the basis she felt the FSP was Case No: 484189 Determination Page 3 of 3 not satisfied with B’s findings. These works failed to address the i ssue of the ongoing elevated moisture levels within the area in question. The applicant reasonably formed the view the works suggested by J were unnecessary and did not address the issue. In saying that, I am not satisfied it would be reasonable to require the FSP to reimburse the applicant for the costs of the works. The FSP, prior to the applicant authorising the works did clearly advise her it no longer required the works do to be done, it would be authorising repairs under the claim in acknowledgement of the more recent expert evidence. The applicant chose to continue with the previously recommended works arising from her own concerns and impressions formed having communicated with the FSP’s representatives. As the applicant has clearly chosen to ignore B’s findings and the FSP’s clarification that it did not require her to arrange the works, I am not satisfied she is entitled to seek reimbursement for the costs incurred. In saying that, I note the FSP was provided with the report from B arranged and paid for by the applicant which formed part of its consideration of the claim. This report was a major part of the FSP’s decision to alter its position and therefore can safely said to have been relied upon by the FSP. Therefore, I recommend the FSP is to reimburse the applicant for the cost incurred in arranging the report from B on being provided proof of the payment (tax invoice) under the claim. I acknowledge the claim has remained on foot for an extended period of time. This however, I accept relates to numerous and ongoing investigations into the cause for the continued elevated moisture levels identified at the insured property. The consultants, including B, appointed to the claim from the information available to me are yet to diagnose the cause for the ongoing elevated moisture levels.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.