Text of the determination
Determination
Case No: 484004 Determination Page 1 of 12
Case number: 484004 31 May 2018
1 Overview
1.1 Dispute
The applicant lodged a claim under her landlord insurance policy with the financial
services provider (FSP), after she discovered her tenant had vacated her investment
property leaving it in a damaged state.
The FSP accepted the applicant’s claim for damage to the property and appointed its
contractors to prepare a scope of works for the necessary repairs.
Due to concerns about the pre-existing condition of the property, the FSP decided to
cash settle the applicant for the estimated cost of the repairs. The FSP paid the
applicant for a total of $40,018.33, including loss of rent benefits for a period of 33
weeks.
The applicant says the amount paid by the FSP is not sufficient to carry out the
necessary repairs to the property. Further, she considers the FSP should be required
to undertake the repairs.
The applicant also seeks payment for damage to contents at the property, as well as
additional benefits for loss of rent and rent default. She also seeks compensation for
losses suffered due to the FSP’s management of her claim.
1.2 Issues and key findings
Was the FSP entitled to cash settle the claim?
The FSP acted reasonably in deciding to cash settle the claim, given the nature of
the pre-existing issues with the property and the extent of the non-claim-related
damage.
Should the cash settlement for building repairs be increased?
The cash settlement amount for the building repairs should be increased by
$18,291.67 to reflect the reasonable cost of undertaking the repairs (including any
increased costs due to the remote location of the property).
Is the applicant entitled to any other amounts?
The applicant is entitled to:
payment of $9,000 for damage to contents items at the property.
Case No: 484004 Determination Page 2 of 12
loss of rent benefits for an additional period of 20 weeks, as her ability to
complete the repairs and re-tenant the property has been constrained due to
the inadequate cash settlement provided by the FSP
compensation of $1,500 for non-financial loss due to the manner in which the
FSP handled her claim.
1.3 Determination
This determination is partly in favour of the applicant.
The FSP is required to pay the applicant the following amounts in full and final
settlement of her claim (plus interest as set out in sections 2.2 and 2.3 below):
an additional amount of $18,291.67 for the building repairs
an amount of $9,000 for loss or damage to her contents items
an amount of $4,400 representing loss of rent benefits for an additional period
of 20 weeks (plus the additional amount of $440 which the FSP has previously
agreed to pay, if that amount has not already been paid to date).
The FSP is required to pay the applicant an additional amount of $1,500 as
compensation for non-financial loss.
Case No: 484004 Determination Page 3 of 12
2 Reasons for determination
2.1 Is the FSP entitled to cash settle the claim?
Policy provides cover for malicious damage subject to exclusions
The applicant’s policy provides cover for the insured events listed in the policy,
subject to the conditions and exclusions set out in the policy.
The insured events covered under the policy include malicious acts or vandalism by
tenants or their guests. However, there is an exclusion for damage caused by tenant
neglect, lack of cleanli ness or unhygienic habits.
The applicant had also taken out the optional cover available for accidental damage,
being damage that occurs without intent.
The policy contains general exclusions for loss or damage caused by:
the applicant’s failure to keep t he property well maintained and in good
condition
wear, tear and gradual deterioration.
FSP cash settled claim for malicious damage by tenants
The applicant lodged a claim in mid-November 2016 for malicious damage to her
tenanted investment property and various contents items. The applicant had
discovered the damage after her tenants vacated the property.
After carrying out several assessments over a six month period, the FSP accepted
liability for some of the damage, on the basis it had been caused by the tenants
acting maliciously.
However, the FSP denied liability for other items of damage claimed by the applicant,
on the basis this damage was caused by factors which are excluded from cover
under the policy (such as tenant neglect, wear and tear and gradual deterioration).
In mid- 2017, the FSP cash settled the applicant for a total of $32,508.33 for building
repairs. The cash settlement amount reflected the estimated cost of repairing the
damage for which the FSP had accepted liability, based on a scope of works and
quotation prepared by its builder (KB).
The applicant says the FSP should have arranged to undertake the repairs, rather
than cash settling her claim. The applicant says it was impractical for her to supervise
the repair process, as the property was located in a remote area of Western Australia
and she was living interstate during the course of the claim.
Policy outlines how claims will be settled
Under the terms of the policy, the FSP may settle a claim for damage to the
applicant’s property caused by an insured event by:
repairing the damage to the property
paying the applicant the cost (to the FSP) of repairing the property.
Case No: 484004 Determination Page 4 of 12
It is clear from the terms of the policy that the FSP has the discretion to decide which
settlement method to adopt.
The FSP also has the discretion to determine whether the property will be repaired
on a ‘new for old’ basis or to the condition it was in before the damage occurred. An
equivalent discretion applies to cash settlements paid for repairs.
However, FOS expects an insurer to act reasonably in exercising the discretion
provided under the policy, having regard to the circumstances of the claim.
Property is in poor condition and has non-claim-related damage
During the course of the claim, the FSP arranged for the property to be inspected by
its external assessor (CL). CL conducted an initial assessment in January 2017 and
undertook a follow-up inspection one month later, after the applicant advised that a
number of items had been omitted from the scope of works.
Following an extended delay in CL obtaining an itemised quotation, the FSP
appointed its builder (KB) to carry out a further assessment and prepare a scope of
works for the repair of the damage. KB inspected the property in May 2017.
Both CL and KB advised that the property was generally in a poor condition overall,
with pre-existing maintenance issues unrelated to the claim.
Among other things, photographs of the property show that the walls and ceiling in
several rooms had not been painted, leaving the bare gyprock exposed. There were
also signs of wear and tear and gradual deterioration to various parts of the property.
The tenants had left the property in a very messy, dirty and untidy state, with rubbish
and discarded possessions strewn throughout. Under the policy, the FSP is not liable
for this damage as it was caused by tenant neglect and unhygenic living habits.
The FSP’s builder (KB) advised that it would be unable to warrant the claim -related
repairs, due to the poor condition of the property and the non-claim-related damage.
FSP acted reasonably in deciding to cash settle the claim
Having carefully reviewed the available information, the panel is satisfied that the
FSP acted reasonably in deciding to cash settle the claim (rather than undertake
repairs).
The nature of the pre-existing issues with the property and the extent of the non-
claim-related damage meant that it was not feasible for the FSP to repair the damage
for which it was liable, in accordance with its obligations under the policy (including
by providing the lifetime guarantee).
This is particularly so, given the FSP’s obligations under the policy did not extend to
repairing the property to an ‘as new’ condition, but only to the condition it was in at
the time the damage occurred.
The panel recognises that the decision by the FSP to cash settle the claim left the
applicant with the responsibility of arranging the building repairs herself, in somewhat
challenging circumstances.
Case No: 484004 Determination Page 5 of 12
In these circumstances, the FSP was obliged to ensure that the cash settlement
amount paid for building repairs was sufficient to allow the applicant to engage a
builder directly to complete the repairs.
The location of the property in a remote area necessarily increases the cost of
engaging contractors and transporting building materials. Accordingly, these
additional costs need to be factored into the cash settlement amount.
However, the FSP is not liable for any additional costs resulting from the fact that the
applicant herself lived a long way from the property. The applicant is responsible for
any additional costs arising from owning (and self-managing) an investment property
in another State.
2.2 Should the cash settlement for building repairs be increased?
Cash settlement was based on approved scope of works and quotations
The FSP’s loss adjuster (CL) prepare d a scope of works for the repair of the
accepted damage following his initial inspection in January 2017.
After revisiting the property to consider the concerns raised by the applicant, CL
obtained a quotation of $44,400 for the repairs from a local builder (MH). However,
CL does not appear to have prepared an updated scope of works.
The applicant rejected the FSP ’s offer to cash settle the claim for the amount of MH’s
quotation, as she considered this amount was insufficient to carry out the necessar y
repairs.
The FSP then asked CL to obtain an itemised quotation, as the quotation provided by
MH was on an all-inclusive basis. However, after extended delays, the FSP ultimately
appointed another builder (KB) to inspect the property, confirm the scope of works
and provide a quotation.
In May 2017, KB provided an updated scope of works, identifying a number of
additional items which he considered had been caused by malicious damage or
vandalism. KB advised that trespassers had accessed the property and ca used more
damage, since CL prepared the initial scope of works.
KB also prepared a list of additional items of damage (as advised by the applicant)
which he considered had not been caused deliberately or maliciously. The FSP’s
assessor reviewed these items and concluded that they were not covered under the
policy.
The FSP cash settled the applicant for the building repairs based on a quotation of
$30,088.33 provided by KB for the repairs set out in his approved scope of works.
The FSP subsequently paid the applicant an additional amount of $2,750 after
accepting liability for roller shutters removed from the property.
The FSP acknowledges that the final cash settlement amount was lower than its
initial offer of $44,400 (based on MH ’s quotation). However, the FSP says it is
entitled to settle the claim on this basis because KB’s quotation is more detailed and
accurate than that provided by MH.
Case No: 484004 Determination Page 6 of 12
Approved scope of works for building repairs is generally appropriate
Having reviewed the available information, the p anel is satisfied that KB’s approved
scope of works generally provides an accurate assessment of the malicious damage
to the applicant’s property.
The repairs included in KB’s scope of works are generally consistent with the claim -
related damage to the property as identified in the various reports provided (and the
photographs taken) by CL and KB during their attendances at the property.
The applicant has identified a number of items of damage which she says have been
omitted from the scope of works. However, the panel is not satisfied that the bulk of
these items were caused by malicious damage (or by any other event insured
against under the policy).
In relation to some of the specific items identified by the applicant, the panel
considers that:
there is insufficient information to establish that the tenant removed overhead
kitchen cabinets from the property (noting CL’s findings that there is no
evidence these cabinets were ever installed)
the damage to the external chipboard was caused by wear and tear a nd gradual
deterioration, which is excluded from cover under the policy
the FSP is not liable for the cost of obtaining electrical certification for the
property, as there was limited claim-related damage to electrical items and the
property was previously non-compliant
there is insufficient information to establish that the leach drains (which form
part of the septic system) were damaged by an insured event.
Having said that, the panel considers there are there are some additional items which
should be included in the scope of works. Such items include:
the motor for the external evaporative unit, which the applicant advised is
missing. KB did not previously include this item in his scope of works because
he could not access the unit during his inspection
the reverse cycle wall mounted air conditioner, which KB was unable to test due
to the electricity having been disconnected
various items of damage which KB identified as having been caused
accidentally (such as chipping of internal floor tiles and damage to the toilet
walls). It appears the FSP did not consider its liability for these items under the
accidental damage cover provided by the policy.
The panel acknowledges that the cash settlement paid to the applicant mistakenly
included an amount (totalli ng $5,208) for the repair of the lounge room ceiling and the
replacement of the septic tank lid.
This amount should not have been included because the FSP settled the applicant
for the damage to the ceiling under a separate claim for storm damage and paid the
supplier directly for the replacement of the septic tank lid.
Case No: 484004 Determination Page 7 of 12
Applicant says cash settlement amount underestimates cost of repairs
In addition to disputing the scope of works, the applicant says that KB’s quotation (on
which the cash settlement amount was based) is manifestly insufficient to complete
the necessary repairs.
The applicant has provided an updated quotation from the local builder (MH) for the
repair of the property. MH ’s quotation is for a total of $82,500, comprising $43,500 for
the external works and $39,000 for the internal works.
The applicant says MH ’s updated quotation is based on the approved scope of works
approved by the FSP. However, if this is the case, it is not clear why MH’s quotation
would have almost doubled from that provided to the FSP in early 2017.
Further, based on the limited detail provided, it is clear that MH ’s updated quotation
includes items whi ch are not contained in KB’s scope of works (such as general
clean up and removal, a new veranda and new leach drains. MH ’s quotation also
refers to the upgrade of a number of existing items.
The applicant has also provided various quotations for individual elements of the
repairs (such as the kitchen and bathroom). However, the works included in these
quotations also represent an upgrade to the applicant’s property (relative to its pre -
existing condition).
The applicant has also provided various invoices and bank statements, reflecting
costs she has incurred to complete some of the works.
However, the information provided by the applicant contains very little detail (in some
cases, only the name of the supplier and the amount). Accordingly, it is not possible
to confirm whether all of the works were for the repair of claim-related damage.
Cash settlement amount was insufficient to repair the property
For the reasons outlined above, the panel is not satisfied that the quotations and
other information provided by the applicant reasonably reflect the cost of repairing
the claim-related damage.
However, the panel also has concerns about the accuracy of the quotation provided
by the FSP’s builder (KB).
This quotation was provided in circumstances where KB had c learly stated he would
be unable to guarantee the works and therefore cannot be considered to be an
actionable quotation.
Further, it is not clear to what extent KB’s quotation took into account additional costs
arising from the remote location of the property.
The property is located in a small town of around 400 people in a remote area,
approximately 100 kilometres from the nearest population centre (of 37,000 people)
and 450 kilometres from the nearest capital city.
In these circumstances, the panel is satisfied that the location of the property would
necessarily increase the cost of undertaking the repairs. For example, it is likely that
Case No: 484004 Determination Page 8 of 12
contractors would either need to be relocated for all or part of the repair period or
would need to travel significant distances on a daily basis.
During the dispute process, the FOS case manager specifically asked the FSP to
confirm whether KB’s quotation included an allowance for additional costs arising
from the location of the property. However, the FSP did not provide a response.
In contrast, the local builder (MH) appears to have taken into account these
additional costs in the various quotations he provided during the course of the claim.
This may explain why his initial quotation of $44,400 was considerably higher than
the quotation provided by KB.
In light of the issues outlined above, the panel considers that the quotation provided
by KB (on which the cash settlement was based) underestimates the reasonable cost
of carrying out the claim-related repairs to the property.
In her submissions, the applicant has indicated that the property suffered additional
damage following KB’s inspection in May 2017, as a result of break -ins which
occurred during the extended period it remained unrepaired. She says the FSP
should be liable for the cost of this damage.
The FSP says it should not be liable for the additional damage because it was the
applicant’s responsibility to ensure that the property was secured against further
break-ins, given the FSP had advised her that the claim would be cash settled (and
therefore it would not be undertaking the repairs).
However, the applicant says the property has been targeted by local vandals due to
being unoccupied, despite multiple efforts to secure it.
The applicant has not lodged any additional claims for malicious damage during this
period and therefore this damage has not been separately assessed. Based on the
materials provided, it is difficult to determine the nature and extent of such damage
(including whether it affected areas of the property which already required repair).
In the usual course, any such damage would usually be dealt with as a separate
claim (subject to an additional policy excess).
However, in circumstances where the cash settlement amount paid to the applicant
was insufficient to undertake the repairs, the panel accepts that this has contributed
to the delays in the repairs being undertaken and therefore exposed the property to
further break-ins.
Accordingly, and in the interests of providing finality, the panel considers this damage
should be addressed as part of the current dispute.
Cash settlement for building repairs should be increased to $50,800
For the reasons outlined above, the panel considers the cash settlement amount of
$32,508.33 paid by the FSP for building repairs materially underestimates the cost of
those repairs.
The FSP had previously accepted the quotation it obtained from the local builder
(MH) for $44,400 and had offered to cash settle the applicant for this amount. After
this offer was rejected, the FSP subsequently reduced the cash settlement amount.
Case No: 484004 Determination Page 9 of 12
In these circumstan ces, the panel considers it is reasonable to use MH’s quotation as
the basis for determining an appropriate cash settlement for the building repairs.
However, the panel considers the amount of MH’s quotation should be increased by
15% in order to reflect the following:
additional items of damage which occurred as a result of break-ins at the
property, both following CL’s inspections in January 2017 and during the
extended repair process
any increase in costs since MH’s quotation was provided in February 2 017
(noting the cash settlement was not paid until June 2017)
the additional risk assumed by the applicant due to the absence of the lifetime
guarantee provided under the policy in situations where the FSP undertakes the
repairs.
The panel is satisfied that MH’s quotation included provision for the additional items
of damage which were incorrectly omitted from KB’s scope of works (namely, the
motor in the evaporative unit, the wall mounted air conditioner and the floor tiles).
Accordingly, the FSP is required to increase the cash settlement amount to $50,800
(that is, by an additional amount of $18,291.67).
The FSP is required pay interest on the additional amount at the rate calculated in
accordance with section 57 of the Insurance Contracts Act 1984 (Cth ) (the ‘Act’) from
22 June 2017 (the date the cash settlement was paid) until the payment date.
2.3 Is the applicant entitled to any other amounts?
Applicant is entitled to payment of $9,000 for contents items
The applicant seeks cover for the replacement of contents items (valued at
approximately $13,000) which she says were maliciously damaged by the tenant.
The items for which the applicant seeks cover include curtains and blinds, as well as
furniture and electrical appliances.
The policy schedule confirms the applicant had cover for landlord contents for a
maximum sum insured of $33,100. This is consistent with the applicant’s advice that
she rented the property to the tenant on a partially furnished basis.
The photographs provided by the FSP’s contractors indicate that various items of
furniture were left at the property in a damaged condition, after the tenant vacated.
The applicant included the contents items in the police report lodged after the claim
was lodged. She also provided a list of these items to the FSP during the early
stages of the claim.
The FSP acknowledges that it is likely that some of the applicant’s contents items
were damage or stolen by the tenants. However, the FSP says the applicant has not
provided sufficient proof of ownership and value to support her claim.
Based on the available information, the panel is satisfied that some of the applicant’s
contents items were maliciously damaged or stolen by her tenant. The panel
Case No: 484004 Determination Page 10 of 12
considers it is fair in the circumstances that the FSP pay the applicant the amount of
$9,000 in settlement of her contents claim.
In determining this amount, the panel has had regard to the fact that some of the
items claimed have been considered as part of the settlement for the building repairs.
The FSP is required to pay interest on the contents settlement amount at the rate
calculated in accordance with section 57 of the Act from 22 June until the payment
date.
Applicant is entitled to additional payment for loss of rent
The policy provides cover for loss of rent where the property cannot be lived in due to
damage caused by an insured event. Loss of rent benefits are payable for the
reasonable period required to repair the property until it can be lived in again.
The FSP accepted the applicant’s claim for lo ss of rent and paid her benefits of
$7,260 in June 2017.
The cash settlement amount paid represented loss of rent for a total of 29 weeks to
8 June 2017, plus an additional 4 weeks (being the period required to complete the
repairs, as estimated by KB). Loss of rent benefits were calculated based on a
weekly rental of $220.
In its submissions, the FSP agreed to pay the applicant an additional 2 weeks’ worth
of benefits for loss of rent ($440), as payment of the cash settlement for the building
repairs had been delayed. It is not clear from the information provided whether this
amount has been paid to date.
The applicant says the repairs have not yet been completed and seeks payment of
benefits for the additional period required to complete the repairs.
The panel accepts that the applicant’s ability to compl ete the repairs and re-tenant
the property has been constrained due to the inadequate cash settlement amount
paid by the FSP.
However, the FSP is not responsible for any additional delays in arranging repairs
due to the fact that the applicant lived interstate.
Having carefully considered the available information, the panel considers it is fair in
all the circumstances that the FSP pay the applicant an additional 20 weeks of loss of
rent benefits (totalling $4,400).
The FSP is required to pay interest on this amount at the rate calculated under
section 57 of the Act from the date loss of rent benefits should have been paid from
22 June 2017 onwards (assuming such benefits were payable monthly), until the
payment date.
The FSP’s liability for loss of rent is not subject to the limits imposed under the policy
(a maximum of 52 weeks or 10% of the sum insured). This is because the obligation
to pay loss of rent arises out of the FSP’s actions and not the insu red event itself.
Case No: 484004 Determination Page 11 of 12
The applicant is not entitled to payment for rental default by her tenant, as the
available information does not establish there was a written lease agreement in place
at the time the malicious damage occurred.
Applicant is entitled to compensation of $1,500
Under the Terms of Reference, FOS may award compensation (capped at $3,000)
for non-financial loss where an applicant has suffered an unusual degree or extent of
physical inconvenience, time taken to resolve the situation or interference with their
expectation of enjoyment or peace of mind.
Having reviewed the claim history, the panel considers the FSP and its contractors
unreasonably delayed finalisation of the applicant’s claim.
There were significant delays in obtaining and finalising assessment reports, scopes
of works and quotations (even having regard to the fact the applicant was living
interstate).
As outlined above, CL’s extended delay in obtaining an updated quotation ultimately
led to the FSP appointing another contractor in an effort to expedite the claim.
The FSP also failed to provide the applicant with any settlement for contents
damage, even though it acknowledged that it was likely that her contents items had
suffered malicious damage by her tenant.
The panel is satisfied that the applicant has suffered additional stress and
inconvenience as a result of the manner in which the FSP handled her claim.
In the circumstances, the panel considers the applicant is entitled to compensation of
$1,500 for non-financial loss.
However, the applicant is not entitled to compensation for costs incurred as a result
of her need to relocate from interstate in order to manage the repairs (for example,
flights, accommodation, loss of income etc).
Case No: 484004 Determination Page 12 of 12
3 Supporting information
3.1 FOS approach to this dispute
This dispute has not been the subject of a FOS recommendation. Due to the nature
of the dispute, it has been referred directly to a panel for determination, in line with
the Operational Guidelines to the FOS Terms of Reference. The panel consists of an
Ombudsman and two representatives with consumer and insurance experience.
The panel has decided this case based on what is fair in all the circumstances,
having regard to the relevant law, good industry practice, codes of practice and
previous FOS decisions (which are not binding).
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other.
The panel has reviewed and considered all of the material provided by the parties.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, the panel has restricted its commentary to those issues that it
considers directly relevant to the outcome only.