Text of the determination
Determination
Case No: 483756 Determination Page 1 of 14
Case number: 483756 18 December 2017
1 Overview
1.1 Dispute
The applicant holds a home insurance policy with the financial services provider
(FSP). The policy covers buildings, but not contents.
The applicant lodged a claim under the policy on 30 March 2017 after her home was
damaged by a cyclone. The FSP accepted the claim and commissioned a scope of
works. The FSP offered to settle the claim by authorising the repairs listed in the
scope of works, or by paying the cost of those repairs.
The applicant says the FSP‟s scope of works is “incomplete”, and the work it allows
for is insufficient to repair all cyclone-related damage to the home.
The applicant also says the FSP‟s response to the claim ha s been negligent, and has
caused her to incur further loss in addition to the damage caused by the cyclone.
The applicant wants the FSP to settle the claim by paying her the entire sum insured
($270,000), plus the cost of demolition (up to $54,000).
1.2 Issues and key findings
Is the FSP’s scope of works sufficient to repair all cyclone-related damage?
The FSP‟s scope of works is not sufficient to repair all cyclone-related damage to the
insured property. Furthermore, the FSP should allow for any additional repairs
required as a result of water entering the house after the cyclone due to the failure of
the tarpaulin installed by the FSP.
The FSP must amend the scope of works to allow for the following works:
rectification of all damage caused by the movement of the sub-floor stumps,
including floor unevenness and window misalignment
removal and replacement of timber flooring throughout the house
mould removal and testing
repair or replacement of the shed roller door.
Is the applicant entitled to compensation for consequential loss?
The evidence indicates that water entered the house after the cyclone due to the
failure of the tarpaulin installed by the FSP. The FSP should indemnify the applicant
for any damage so caused.
Case No: 483756 Determination Page 2 of 14
The available evidence does not otherwise establish that the applicant has suffered a
financial loss as a consequence of the FSP mishandling the claim. Therefore, the
FSP is not required to pay compensation for consequential loss.
Is the applicant entitled to compensation for non-financial loss?
Although the dispute has been extremely stressful for the applicant, the Panel is not
satisfied that the FSP has contributed to the applicant‟s stress by misha ndling the
claim. Therefore, the FSP is not required to pay compensation for non-financial loss.
Is the applicant entitled to reimbursement of expenses?
The FSP is not required to contribute to the applicant‟s legal costs.
The FSP is required to reimburse the applicant for professional costs incurred in
appointing a building consultant.
1.3 Determination
This determination is substantially in favour of the applicant.
Within 14 days of being advised of the applicant‟s acceptance of this determination,
the FSP must obtain an amended scope of works which includes the work allowed
for by the FSP‟s building consultant , plus the following additional work items:
rectification of all damage caused by the movement of the sub-floor stumps,
including floor unevenness and window misalignment
removal and replacement of timber flooring throughout the house
mould removal and testing
repair or replacement of the shed roller door.
Within 14 days of obtaining an updated scope of works, the FSP must estimate the
reasonable cost of repairs and advise the applicant how it intends to settle the claim.
The FSP is required to pay the applicant $985.60 for fees charged by the applicant‟s
building consultant.
Case No: 483756 Determination Page 3 of 14
2 Reasons for determination
2.1 Is the FSP’s scope of works sufficient to repair all cyclone -related
damage?
Policy covers cyclone-related damage to buildings
The policy is a „defined events‟ policy. This means that it only covers damage caused
by the “insured events” listed in the product disclosure statement (PDS). The PDS
also includes optional cover for accidental damage. However, the certificate of
insurance shows that the applicant‟s policy does not include this option.
One of the insured events is “Storm”: page 12 of the PDS says the policy covers
“ damage to the insured property caused by storm ”. There are no relevant exclusions
listed under this insured event.
The applicant‟s property was damaged by a cyclone on 28 March 2017. This damage
is covered under the policy.
FSP commissioned scope of works
During the cyclone, the roof of the applicant‟s home was destroyed. The FSP
undertook make-safe work which included disposing of the roof and covering the
home with a tarpaulin.
The FSP has provided a number of reports by „C R D‟, building consultant. CRD
inspected the applicant‟s property on 20 April 2017 and produced a report dated
26 April 2017.
Based on the report, CRD produced a scope of works dated 11 May 2017. The FSP
obtained several builders‟ quot es based on this scope of works:
„OSB‟ quote dated 12 June 2017 in the sum of $103,910.40
„AB C ‟ quote dated 15 June 2017 in the sum of $123,623.52
„LB‟ quote dated 15 June 2017 in the sum of $141,760.25 .
The applicant obtained a quote dated 29 June 2017 from „MC‟, builder, based on the
CRD scope of works, in the sum of $189,461.25.
Applicant does not accept FSP’s scope of works
The applicant said the CRD scope of works was “incomplete” and “ highly inaccurate ”.
The applicant has provided a report dated 25 July 2017 from „CC‟, builder, who
inspected the house and compared the damage to the CRD scope of works.
CC ‟s report listed several work items which it said should be added to the CRD
scope of works.
Case No: 483756 Determination Page 4 of 14
FSP obtained second round of quotes
The FSP‟s internal assessor inspected the house on 4 August 2017 and concluded
that some repair work was required in addition to the work allowed for in the CRD
scope of works.
CRD considered CC‟s report and agreed that some of the items mentioned in CC‟s
report should be added to the scope of works. CRD produced a second report which
is (incorrectly) dated 10 April 2017.
After receiving the report from the FSP‟s internal assessor and CRD‟s second report ,
t he FSP obtained a second round of builders‟ quotes:
„OSB‟ quote dated 23 August 2017 in the sum of $114,290
„AB C ‟ quote dated 22 August 2017 in the sum of $125,104.45
„LB‟ quote dated 23 August 201 7 in the sum of $156,897.68.
The FSP has also provided a quote dated 20 September 2017 from „AB‟, the
applicant‟s p referred builder, in the sum of $161,241.29. The FSP says the AB quote
includes items that it has not accepted liability for; omitting these items reduces the
quote to $138,700.23.
The FSP has offered to settle the claim by authorising OSB to complete the repair
works, or by paying the average of the quotes by OSB, ABC, and LB (the FSP has
calculated this average at $133,097.38, but it is actua lly $142,097.38).
The applicant does not accept that either of the FSP‟s offer s would be sufficient to
repair all cyclone-related damage to her home.
Applicant commissioned building consultant’s report
The applicant appointed „CCQ‟, building consultan t, who inspected the house on
9 October 2017 and produced a report dated 18 October 2017. CCQ‟s report
includes a scope of works and 96 photographs.
CCQ‟s report says the house was “ found to be in good condition prior to the
[cyclone]”. The FSP said that unless CCQ inspected the house before the cyclone,
this is mere speculation. In response, in an email dated 9 November 2017, CCQ said
that he‟d been to the house many times because he is a personal friend of the
applicant‟s mo ther, who is the previous owner of the house.
CCQ said that when he visited the house before the cyclone, the building showed no
evidence of general movement or cracking, and the floor was level. CCQ says the
current unevenness of the floor is due to the sinking of the sub-floor stumps, which is
a direct result of the cyclone.
Sub-floor stumps moved due to cyclone
CCQ‟s email of 9 November 2017 says the property “ was subjected to substantial
rainfall events and excessive surface water runoff ” during and imm ediately after the
cyclone. CCQ says this has caused movement of the sub-floor stumps.
CCQ‟s report does not explain how movement of the sub -floor stumps caused by a
cyclone can be differentiated from movement caused by gradual deterioration and
Case No: 483756 Determination Page 5 of 14
earth movement. CCQ appears to base his conclusion on his belief that the floor was
level when he visited the house before the cyclone.
CRD ‟s second report says the floor is uneven due to “ long-term degradation of the
timber stumps below-ground ”, and the cyclone has not caused any changes in the
floor level. The report does not say what evidence there is to support this conclusion.
CRD‟s first report says: “ At the time of our inspection, the absence of damage
typically caused by structural movement indicated that the dwelling had not
experienced any structural movement in the recent past. ” This is inconsistent with the
conclusion in CRD‟s second report.
The damage caused by building movement includes the misalignment of some
windows. The FSP, and CRD‟s second report, say this is partially due to long-term
differential footing movement. However, this is inconsistent with CRD‟s first report,
which states that the building shows no signs of having experienced structural
movement in the past.
Having considered the available evidence, the Panel is of the view that the
movement of the sub-floor stumps, and the resulting building movement, was most
likely caused by the cyclone. The FSP has not provided sufficient evidence to
establish that this damage wholly or partly pre-dates the cyclone.
Tarpaulin installed by FSP allowed water ingress
After the applicant lodged the claim, the FSP covered the applicant‟ s house with a
tarpaulin. CRD‟s first report states: “ We recommend that reinstatement works …
should commence as soon as possible to mitigate further damage due to water
ingress as the tarpaulin over the roof is only a temporary make-safe and not
completely watertight. ”
The applicant says the tarpaulin was poorly fitted and has frequently allowed
additional water to enter her home ever since the cyclone, causing further damage.
CC‟s report says that a significant amount of water has entered the house since the
cyclone because the tarpaulin did not adequately cover the house. CC says: “A lot of
damage could have been avoided if [t he FSP] had taken more care.”
A report from the FSP‟s internal assessor, who inspected the house on 4 August
2017, confirms that the tarpaulin “has become inadequate” and allowed water
ingress. The assessor concluded that some damage to the house “ can be directly
attributed to further water ingress following the initial storm event ”.
CRD‟s second report says the tarpaulin had a large hole in it, and a second tarpaulin
has been installed over it to rectify the issue.
CCQ ‟s report does not say what internal damage, if any, may be attributable to water
ingress due to the failure of the tarpaulin.
Timber flooring damaged by cyclone and/or failure of tarpaulin
CRD‟s first report does not mention any damage to the timber flooring of the house.
Case No: 483756 Determination Page 6 of 14
CC‟s report says “ sections of floorboards have split, and sections of floor have pulled
apart or dropped ”.
CRD‟s second report says the flooring shows “widespread damages… including but
not necessarily limited to the [damage] identified in the [CC] Report ”. CRD attributes
this partly to wear and tear, because some damaged floorboards “ have been filled
and the fillers have also deteriorated in places ”. However, CRD also says the “ timber
floor coatings have been compromised by the cyclone ”, and by water that has
entered the property after the cyclone. CRD recommends the scope of works include
“ an allowance to prepare and recoat the timber strip flooring ”.
CCQ‟s report contains several photographs of the house‟s timber flooring. CCQ says
the flooring is “ thoroughly damaged throughout the entire interior of the residence,
requiring removal and replacement ”. CCQ says this damage is cyclone -related.
Based on the available evidence, the Panel is satisfied that the floorboards
throughout the house have been damaged, either by the cyclone or by water entering
the house due to the failure of the tarpaulin. The Panel is not satisfied that recoating
the flooring would be sufficient to rectify the damage. The Panel is of the view that
the scope of works should include an allowance for the removal and replacement of
the timber flooring.
Tiling not damaged by cyclone
CRD‟s first report says there are “ no cracks or damage to the floor and wall tiles in
the kitchen, bathroom and laundry ”.
CC‟s report says floor tiles in the bathroom area are misaligned. CRD‟s second
report says there is no evidence of distress or dislocation of the grouting, meaning
the misalignment of the tiles is due to the way they were installed, not cyclone-related
damage or building movement.
CCQ‟s report includes photographs of cracked wall tiles in a bathroom. CCQ says
this is due to cyclone-related damage to the wall. CCQ does not explain how he
determined that the crack was cyclone -related, and the crack is not noted in any of
the previous reports.
Based on the available evidence, the Panel is not satisfied that the floor or wall tiles
have incurred any cyclone-related damage.
Mould infestation caused by cyclone and/or failure of tarpaulin
CRD‟s first report says: “ Water stains and evidence of mould was observed to some
sections of the ceiling lining that remained intact .”
CC‟s report notes “ water damage to internal wall linings ”, leading to “ possible issues
with mould ”.
The FSP‟s internal assessor recommends mould t reatment of wall cavities during
repairs. CRD‟s second report recommends mould testing of wall cavities during
repairs.
Case No: 483756 Determination Page 7 of 14
CCQ‟s report says the condition of the property “ has become far worse with time
since the initial event … including severe mould to the interior ” . CCQ‟s report includes
several photographs which allegedly show mould damage. CCQ‟s scope of works
allows for the employment of a hygienist and a mould removal specialist.
Based on the available evidence, the Panel is satisfied that the house is infested with
mould due to the cyclone, and to water entering the house due to the failure of the
tarpaulin.
CRD‟s scope of works does not mention mould. CRD‟s scope of works includes an
item stating: “Professionally clean and encapsulate the exposed timber framework
exposed in removing the internal plasterboard wall and ceiling linings.” CRD‟s second
report says this “ may adequately address any potential mould contamination issues ”.
The Panel is not satisfied that this item is sufficient to address the mould issue.
The Panel is of the view that the scope of works should be amended to allow for the
employment of a mould removal specialist.
Asbestos remediation sufficiently accounted for in scope of works
CRD‟s first report notes the presence of asbestos -containing material at the
applicant‟s property.
CRD‟s scope of works includes allowances for the re moval of asbestos from the site
and the employment of a hygienist to provide a clearance certificate after asbestos
removal is complete.
The applicant has not provided evidence establishing that repairing the property
would require any asbestos removal or testing that is not accounted for in CRD‟s
scope of works.
Shed roller door damaged by cyclone
CCQ says there is cyclone-related damage to the door and roof of the shed. One of
the photographs of the shed‟s roller door shows significant deformation; CCQ says
this is cyclone-related damage.
CCQ‟s report includes 14 photographs of the shed roof. CCQ says these photos
show “high winds and deformation” caused by the c yclone. The Panel has reviewed
these photos; while the roof shows some signs of wear and tear, the roof sheets do
not appear deformed.
CRD says they inspected the shed, and found that it had “no significant damage”.
CRD also notes that the applicant‟s builder (CC) “ made no reference to any
significant damage to the garage ”.
CC‟s report notes damage to the shed‟s “gables, eaves, guttering and infills around
door”, but does not mention damage to the roof. CRD‟s second report says there was
no evidence of damage to the gable linings or infill panels, the shed had no eaves
linings, and the guttering was distorted and dislocated due to the vegetation growing
on it.
Case No: 483756 Determination Page 8 of 14
Having reviewed the available evidence, the Panel is satisfied that there is damage
to the shed‟s r oller door, and this damage is most likely cyclone-related. The Panel is
not satisfied that there is cyclone-related damage to any other part of the shed.
FSP’s scope of works not sufficient to repair all building damage
Having considered the information above, the Panel is of the view that CRD‟s scope
of works, on which the FSP has based its settlement offer, is not sufficient to repair
all cyclone-related damage to the insured property. Furthermore, the FSP should
allow for any additional repairs required as a result of water entering the house after
the cyclone due to the failure of the tarpaulin.
The Panel considers that the FSP should allow for the following items that were not
included in CRD‟s scope of works or allow ed for in CRD‟s second report :
rectification of all damage caused by the movement of the sub-floor stumps,
including floor unevenness and window misalignment
removal and replacement of timber flooring throughout the house
mould removal and testing
repair or replacement of the shed roller door.
FSP should amend scope of works and obtain further quotes
The available evidence is not sufficient to determine the fair and reasonable cost of
repairing the applicant‟s home.
The Panel has determined that the FSP should increase its settlement offer to
account for work items that were not included in CRD‟s scope of works or allowed for
in CRD‟s second report. The available evidence is not sufficient to determine the cost
of those additional works.
CCQ says the cyclone-related damage to the house could not possibly be repaired
for the building sum insured of $270,000, and estimates that repairs would cost at
least $340,000. However, CCQ‟s report does not explain how he has calculated the
cost of repairs, and the figure of $340,000 appears to be a very rough estimate.
If this determination is accepted by the applicant, the FSP must take the following
steps to settle the claim:
Within 14 days of being advised of the acceptance of this determination, the
FSP must obtain an amended scope of works which includes the work allowed
for in CRD‟s scope of works and CRD‟s second report, plus the additional work
items listed above;
Within 14 days of obtaining an updated scope of works, the FSP must estimate
the reasonable cost of repairs and advise the applicant how it intends to settle
the claim.
The parties are requested to work together to resolve the claim and dispute.
Case No: 483756 Determination Page 9 of 14
2.2 Is the applicant entitled to compensation for consequential loss?
FOS may award compensation for consequential loss
Paragraph 9.3 a) of the FOS Terms of Reference provides that FOS can award
compensation for consequential financial loss. The maximum amount that FOS can
award for consequential financial loss is $3,300 per claim.
Even when the loss is not covered under the policy, FOS may still award
compensation if the loss was caused by poor claims handling by the FSP. The onus
is on the applicant to establish that they have suffered a financial loss as a
consequence of the FSP mishandling the claim.
Policy does not include contents cover
The applicant‟s policy covers damage to buildings, but does not cover loss or
damage to contents.
The applicant says many items in her home have been lost, damaged, or destroyed
as a result of the cyclone.
Although the applicant agrees that the policy does not cover contents, she says the
FSP should still compensate her for loss and damage to her contents. This is
because the applicant says the loss and damage was at least partly caused by the
FSP‟s negligence.
Applicant kept out of property due to possible asbestos contamination
The FSP says it first attended the applicant‟s home on 1 April 2017, two days after
the applicant lodged the claim. The FSP says it was advised by its assessor that the
home was likely contaminated with asbestos.
A “makesafe report” by ABC dated 5 April 2017 says ABC “bagged all loose asbestos
and cleared the yard of asbestos”.
A “makesafe inspection report” by an asbestos expert dated 9 May 2017 confirms
that the home‟s collapsed roof contained asbestos.
A report by an asbestos assessor dated 19 May 2017 concluded that the precautions
taken during the removal of the roof had successfully prevented the house from
being contaminated with asbestos dust.
The applicant says she was told not to enter her home due to the possibility of
asbestos contamination, and as a result, she was not able to recover some of her
property from the home. The applicant has provided a copy of a letter from the FSP
dated 26 April 2017 stating: “ At this point in time we are requesting no access into
the property without prior consent from [the FSP] due to the presence of asbestos. ”
The evidence available at the time indicated that there was a strong possibility that
the home, and any items inside the home, were contaminated with asbestos. In the
circumstances, it was reasonable for the FSP to advise the applicant not to enter the
property.
Case No: 483756 Determination Page 10 of 14
Applicant says she incurred consequential loss due to FSP mishandling claim
The applicant says the FSP mishandled the claim, causing further loss and damage
to her home and contents in addition to the damage caused by the cyclone.
Specifically, the applicant alleges:
the FSP placed a tarpaulin over the home which leaked, causing significant
water damage to parts of the home that were not damaged by the cyclone
the FSP took an unreasonably long time to assess whether the property was
contaminated with asbestos. Had it assessed this within a reasonable period of
time, it would have determined that the contents were not contaminated with
asbestos, and the applicant would have been able to recover the majority of the
contents
the FSP failed to adequately secure the property. As a result, the home was
looted, causing loss and/or damage to the building and contents.
Evidence does not establish applicant incurred loss after cyclone
The Panel accepts that the tarpaulin installed by the FSP allowed water ingress,
which may have contributed to the apparent mould infestation and damage to the
timber flooring. The Panel has considered this in section 2.1 of this dete rmination.
Based on the available evidence, the Panel is not satisfied that the FSP took an
unreasonably long time to assess whether the property was contaminated with
asbestos, or that the FSP failed to adequately secure the property. Furthermore, the
Panel is not satisfied that the available evidence is sufficient to establish that the
applicant suffered any loss due to these alleged deficiencies in claims handling.
The applicant has provided a report by „LM‟, loss managers, calculating the cost of
dam age to the applicant‟s contents. However, this undated report does not establish
when the contents items were damaged, or the nature or cause of the damage.
The FSP says it assessed the contents of the applicant‟s home as “damaged beyond
repair” immediately after the cyclone. The available evidence does not establish that
any of the applicant‟s possessions were salvageable after the cyclone, and could
have been salvaged if the FSP had handled the claim differently.
Applicant not entitled to compensation for consequential loss
Based on the available evidence, the Panel is not satisfied that the applicant has
suffered a financial loss as a consequence of the FSP mishandling the claim.
Therefore, the FSP is not required to pay compensation for consequential loss.
2.3 Is the applicant entitled to compensation for non-financial loss?
FOS may award compensation for non-financial loss
Paragraph 9.3 b) of the FOS Terms of Reference provides that FOS can award
compensation for non-financial loss where there has been an unusual amount of
physical inconvenience, time taken to resolve a situation, or interference with an
a pplicant‟s expectation of enjoyment or peace of mind.
Case No: 483756 Determination Page 11 of 14
FOS expects an applicant to be moderately robust and tolerate a normal degree of
inconvenience when making a claim. FOS takes a conservative approach to
assessing compensation for non-financial loss. The maximum amount FOS can
award for non-financial loss is $3,000 per claim.
Applicant not entitled to compensation for non-financial loss
The applicant says that dealing with the claim has taken an enormous amount of
time, and the stress of dealing with the claim has damaged her health. The applicant
says the FSP‟s claims handling has been negligent , which has exacerbated her
losses and the stress of dealing with the claim.
The FSP says it first attended the applicant‟s home on 1 April 2017, two days after
the applicant lodged the claim. The FSP has appointed many experts to inspect the
applicant‟s p roper ty and perform „make - safe‟ work.
In dealing with the claim and this dispute, the FSP has relied on expert reports.
Although the Panel has not accepted all of the conclusions in the FSP‟s experts‟
reports, it was not unreasonable for the FSP to rely on them.
The FSP has chosen to waive a provision of the policy that allows it to limit its liability
for the building damage to $124,800, instead agreeing to indemnify the applicant for
building damage up to $270,000.
The FSP has provided temporary accommodation (in excess of the temporary
accommodation it accepts as being covered under the policy) to the applicant, whose
home is currently unliveable.
The Panel accepts that the damage to the applicant‟s home, and the subsequent
claim and dispute, has been extremely stressful for the applicant. The Panel accepts
that the applicant has suffered a great deal of inconvenience, loss of enjoyment, and
interference with her peace of mind. However, the Panel is not satisfied that the FSP
has contributed to th e applicant‟s stress by mishandling the claim.
The panel is not satisfied that in the circumstances of this claim, non-financial loss
compensation is appropriate.
2.4 Is the applicant entitled to reimbursement of expenses?
FOS may award reimbursement of appli cant’s costs
Paragraph 9.4 of the FOS Terms of Reference provides that FOS can require an
insurer to contribute to legal, professional, or travel costs incurred by an applicant in
the course of a dispute.
Unless exceptional circumstances apply, FOS will not require an insurer to contribute
more than $3,000 to an applicant‟s costs.
Case No: 483756 Determination Page 12 of 14
Applicant not entitled to reimbursement of legal costs
The applicant appointed lawyers to advise her in relation to this matter. The
applicant‟s submissions to FOS were made by t he applicant personally, not by her
lawyers.
FOS arranged a telephone conciliation conference with a FOS conciliator and a
representative of the FSP. This conciliation conference was attended by a solicitor
and barrister acting for the applicant, as well as the applicant herself.
The applicant advised that some of the work done by her lawyers was done without
charge. However, the applicant has also provided invoices from her lawyers totalling
$2,306.
The FOS process is intended to be an informal process tha t does not require legal
representation. FOS does not usually require an FSP to reimburse an applicant‟s
legal costs unless the lawyers‟ submissions have assisted FOS in resolving the
dispute.
The Panel did not find submissions from the applicant‟s lawyers to be of any
assistance in preparing this determination. Therefore, the FSP is not required to
contribute to the applicant‟s legal costs.
Applicant entitled to reimbursement of professional costs
The applicant appointed a building consultant, CCQ, to inspect her property and
prepare an expert report. The applicant has provided an invoice from CCQ dated 18
October 2017 in the sum of $985.60.
Having reviewed CCQ‟s report, the Panel is satisfied that the amount invoiced by
CCQ is reasonable.
The Panel found CCQ‟s report to be of assistance in preparing this determination.
The FSP is required to pay the applicant $985.60 for reimbursement of the
applicant‟s professional costs.
Case No: 483756 Determination Page 13 of 14
3 Supporting information
3.1 FOS approach to this dispute
A full exchange of the relevant information has taken place between the parties and
each party has had the opportunity of addressing any issue raised.
All of the provided material has been read and considered. The parties have raised
numerous issues in their submissions. For the purpose of this determination,
commentary is restricted to only those issues considered relevant.
3.2 Relevant policy terms
Insured events page s 11 – 13
6. Storm
(page 12 )
What is covered?
Loss or damage to the insured property caused by storm, lightning, wind,
hail, snow and storm water overflow from roof gutters and their downpipes
or from the area immediately around the premises …
Where you have increased your sum insured on this policy within 72 hours
of a storm occurring, cover will be limited to the sum insu red that was
effective 72 hours prior to the event.
Extra cover page s 14 – 19
The Extra Cover listed below is automatically included in your policy and, where applicable, the
most we will pay for each claim is noted.
3 . Clean Up and
Profe ssional Fees
(page 15 )
What is covered?
The reasonable cost of demolishing and removing debris from the
premises, and related professional fees for an engineer, architect or
surveyor when a claim is accepted under your buildings policy. The most
we will pay is 20% of t he buildings sum insured [$54,000].
What is not covered?
That part of any professional fees that is not directly relat ed to the damage
claimed for.
4. Temporary
Accommodation:
Insured Events
(pages 15 – 16)
What is covered?
Buildings
The actual cost you incur for your reasonably priced temporary
accommodation for a period of up to 12 months while your buildings are
being repaired or rebuilt, if you cannot live at the premises aft er an insured
event for which a claim is accepted under your buildings policy and we
agree that temporary accommodation is required.
The most we will pay for one month‟s accommodation on eac h claim is 1%
of the buildings sum insured plus up to $250 for pet accommodation. The
most we will pay in total for each claim is 12% of the am ount your buildings
are insured for plus up to $2,500 for pet accommodation.
Case No: 483756 Determination Page 14 of 14
Due to circumstances, temporary accommodation may only be available in
surrounding areas where no reasonably priced accommodation is available
in your immediate area.
…
What is no t covered?
The cost of temporary accommodation:
…
incurred by you, after the expiry of a reasonable period estimated by us
to repair or rebuild the buildings;
if there is no intention to repair or rebuild the buildings;
…
5. Temporary
Accommodation:
Emer gency
Evacuation
(page 16)
What is covered?
The actual cost you incur for your reasonably priced temporary
accommodation in relation to an emergency where the relevant local
authority either instructed you to evacuate or prevented you from accessing
the pr emises. We will pay the temporary accommodation costs up to the
day you are allowed to return to the premises; the maximum period we will
pay for is 30 days.
3.3 Applicants represented by lawyers
At times during the course of this dispute, the applicant has been represented by
lawyers. For the purposes of this determination, submissions made by the applicant ‟ s
representatives have been treated as if they had been made by the applicant.