Home / Financial Firm (Unknown - Insurer) / Determination 481863
Determination 481863
Claim for fire and malicious damage to vacant investment property after squatters
Summary
The small business landlord claimed $92,270 for fire and malicious damage to an unoccupied investment property during a second squatter event. AFCA found the 60-day unoccupancy condition did not bar the claim, ordered $33,444 for repair costs plus interest, and rejected the demolition costs.
The 60-consecutive-day unoccupancy condition could not reasonably apply where the vacancy was caused by an earlier accepted claim that was not yet settled, and the policy settles repair costs on the cost basis.
Subjects and remedies
home or building damagepay claimpay interest
Text of the determination
Determination
Case No: 481863 Determination Page 1 of 8
Case number: 481863 3 April 2018
1 Overview
1.1 Dispute
The applicant lodged a claim on its landlord insurance policy for damage caused by
malicious acts and fire to an investment property. This followed a previous claim he
had lodged with the FSP for similar damage that had occurred on or around 25
October 2016 and had yet to be settled.
The FSP denied the claim on the basis:
the building was not lived in for more than 60 days without its prior written
agreement
the building was not maintained in good repair
the applicant failed to take reasonable precautions to prevent further loss
the applicant has not suffered a financial loss from this incident.
The applicant says the FSP should accept the c laim and pay $92,270. This is based
on the amount discussed with the FSP‟s initial assessor and the cost to demolish the
property.
1.1 Issues and key findings
Is the FSP entitled to deny the claim?
The FSP is not entitled to deny the claim because:
the 60 day period does not apply when part of it included the time the property
was uninhabitable due to the previous claim that had yet to be settled
the FSP has not established any other basis to deny the claim.
The FSP is therefore liable to pay the sum of $33,444 , being the cost to repair the
damage caused by the event, plus interest. The FSP is not required to pay for the
costs of demolition as the evidence does not show this was necessary.
1.2 Determination
This determination is partly in favour of the applicant. The FSP is to pay the applicant
$33,444 for the cost to repair the property plus interest. The FSP should do so within
14 days of being notified that the applicant accepts this Determination.
Case No: 481863 Determination Page 2 of 8
2 Reasons for determination
2.1 Is the FSP entitled to deny the claim?
Policy covers damage caused by fire or malicious acts subject to conditions
The applicant‟s policy covers damage caused by fire or malicious acts.
The parties do not dispute the damage was most likely caused by the activities of
unknown persons who were squatting at the property.
The FSP does not dispute that fire caused physical damage to the property.
The FSP‟s second assessor (BV) noted additional damage at his inspection,
particularly fire damage and malicious damage in other areas. BV stated the fire
appeared to have been lit in the fireplace of the lounge room, burnt out of control and
ignited surrounding materials. This spread to the floorboards surrounding it. Another
fire was started in a bedroom.
I am satisfied the information establishes on the balance of probabilities, a claim for
damage caused by fire and malicious acts to the property within the terms of the
policy.
FSP relies upon policy conditions and insurance principles to deny claim
The FSP relied upon the following condition, exclusions (as set out in Section 3.3)
and insurance principles to deny the claim:
the building has not or will not be lived in for any period in excess of 60
consecutive days, unless the applicant has the FSP‟s prior agreement in writing
the applicant failed to maintain the building in good repair
the applicant failed to take reasonable precautions to prevent further loss
the applicant has not suffered a financial loss from this incident.
The information shows the following matters are not in dispute:
The damage resulting from this claim occurred on or around 16 February 2017.
An earlier claim for malicious damage (also caused by squatters) was accepted
and settled for a sum of $50,000 on 7 March 2017.
The property was unoccupied for over 60 consecutive days at the time of the
claimed loss.
The FSP did not agree in writing to cover the property when it was not lived in
for more than 60 consecutive days.
The unoccupancy provision is not engaged in these circumstances
There is no dispute the 60 day timeframe included a period of time the property was
rendered uninhabitable due to the earlier claim. Further, this earlier claim had yet to
be settled by the time this claim arose.
I cannot accept that a businesslike interpretation of this clause would be to include
this period. To do so would lead to unjust and unreasonable outcomes. For instance,
the FSP could rely on this provision to deny claim in these circumstances:
Case No: 481863 Determination Page 3 of 8
a tenanted property suffered loss or damage due to an insured event
this damage renders the property uninhabitable
property damage is yet to be repaired after 60 days
further loss or damage occurs from another insured event that caused
significant damage
FSP denies this additional damage due to the above provision.
This cannot be consistent with the purpose of the policy. The purpose of the policy is
to indemnify the applicant for losses that are caused by an insured event during the
period of insurance. In this case, the exclusion is being applied by reason of this
purpose being engaged by an active claim that had yet to be settled by the FSP at
the time of the second event.
Therefore, I do not accept a reasonable person in the position of the parties would
interpret this provision in such a manner. Instead, it is my opinion that this 60
consecutive days would include matters that are unrelated to the policy. For instance,
when the property is untenanted and an insured loss occurs for this reason.
If I am wrong about the interpretation, I consider section 54(5) of the Insurance
Contracts Act 1984 (the Act) applies. This is because the evidence shows it was not
reasonably possible for the applicant not to leave the property unoccupied for more
than 60 consecutive days given the status of the previous claim.
Even if I am wrong about both the interpretation and section 54(5) of the Act, I
consider it fair in all the circumstances that the condition does not apply for the same
reasons.
FSP did not establish applicant failed to maintain the building in good repair
The FSP‟ s submission quoted the policy provision for maintaining the property in
good repair. However, this is not applicable because it is more likely the loss arose
due to its condition from the earlier claim.
Applicant did not court danger of potential further damage
The FSP says the applicant failed to take reasonable precautions to prevent further
loss. However, to rely on this, the FSP must show the applicant:
was aware of the risk of his or her actions (in a subjective sense)
deliberately „courted‟ the dang er or showed reckless indifference as to whether
or not the danger eventuated.
The applicant knew the risk of not boarding -up the property had the potential for
further damage. However, the applicant decided not to do this based upon the FSP‟s
assessor‟s DS‟s advice. DS has not provided evidence specifically refuting this.
Further, the applicant said the property was regularly inspected between the first and
second event. This is not disputed.
Given these factors, I do not accept the evidence shows the applicant deliberately
courted the danger or showed any reckless indifference to this.
Case No: 481863 Determination Page 4 of 8
FSP required to indemnify the applicant for its loss
The FSP argues the applicant has not suffered a financial loss from this event. The
FSP says the cash settlement from the earlier claim would have offset the cost of
demolition because the applicant did not intend to repair or reinstate the property.
I do not accept this argument is consistent with the policy.
It is plain the property suffered further damage from the fire . The policy covers the
building for “damage caused by one or more of the insured events”. The applicant‟s
claim therefore engages the insuring provision.
Following from this, the policy then talks about how the FSP will settle “your buildings
claim”. The first part provides the FSP with the discretion to settle the claim in one of
three ways. This is to either repair or rebuild the damage, pay the cost of doing so or
pay the sum insured.
There are other numbered sections that flow from this. However, it is clear this first
section is the primary consideration as to how a claim is to be settled.
The FSP has referred to section 4. This says the FSP can pay the value of the land
and building or apply depreciation. However, this is conditional on the FSP electi ng to
repair or rebuild the damage. There is no evidence showing the FSP elected to repair
or rebuild the damage. Therefore, that section does not apply.
As such, I accept the FSP‟s obligation is to either repair the damage caused by the
second event or pay the cost of doing so.
The property has now been demolished. Given this, I accept the appropriate method
of settling the claim is for the FSP to pay for the cost to repair the damage caused by
the second event.
FSP is to pay $33,444 plus interest
The FSP engaged S to determine the cost to repair the damage resulting from the
second claim and apply depreciation. S calculated the cost of repairs to be $33,444
based upon the loss adjuster‟s scope of works (SOW). S then said the indemnity
value would be $16,117.50 after depreciation.
I accept S is suitably qualified to provide an assessment as the likely cost of repair.
The applicant disputes the SOW covers all the additional damage. In doing so, he
has highlighted matters such as the front and rear security doors and additional
damage to walls that were not included in the previous claim.
I do not accept this. The loss adjuster who provided the SOW was clearly in a
position to ascertain the additional damages caused by the second claim given he
viewed the photographs and quotes from the earlier claim. Further, when the
applicant initially highlighted items he said should be included in SOW, it was
correctly pointed out that these were already allowed for in the previous claim.
Therefore, I am satisfied it is reasonable to rely upon the loss adjuster‟s SOW.
There is no evidence to show S‟s repair cost calculation for this SOW is unfair or
unreasonable. Whilst the applicant has provided a higher quote, it is not clear if this
Case No: 481863 Determination Page 5 of 8
contractor based it on the SOW. Given this, I prefer S‟s estimate for the cost of
repairs.
Accordingly, the FSP is required to pay the applicant $33,444 to cover the cost to
repair the additional damage resulting from this claim. The FSP should also pay
interest on this amount from 30 March 2017 to the date of payment, in accordance
with section 57 of the Insurance Contracts Act 1984 (the Act) .
FSP should pay demolition costs incurred
The applicant is also claiming for demolition costs.
The policy provides an additional benefit for the necessary and reasonable costs of
demolition when an insured event is covered.
The applicant says the Council had sought his intentions and were likely going to
order him to demolish the property given its state. However, there is no evidence
demonstrating this.
Further, there is no evidence to say that this event alone would have required the
property to be demolished.
Given this, I am not satisfied the FSP is liable to reimburse the applicant for these
costs.
Case No: 481863 Determination Page 6 of 8
3 Supporting information
The applicant is a small business represented by its property manager in this dispute.
Any submissions made by the applicant‟s property manager or sole director are
treated as having been made by the applicant, for the purposes of this determination.
3.1 Relevant policy terms
Section Terms
Cover - building We will cover your buildings against loss or damage caus ed by
one or more of the insured events occurring during the period of
insurance. We will also cover you for the other benefits listed
below. Details of the terms, conditions and exclusions which
specifically relat e to each insured event and other bene fits are
detailed on the pages indicated.
…
We will pay for loss or damage caused by fire or smoke.
We will pay for loss or damage caused by malicious acts…
How we settle your
buildings claim
1. At our option, we will:
a. repair or rebuild the damaged part of your building to the
same condition as when it was new; or
b. pay you the reasonable cost of repairing or rebuilding any
damaged part of your building to the same condition as
when it was new.
c. pay you up to the amount of the sum insured shown in
the current s chedule for your relevant buildings.
If we pay you the reasonable cost of repairing or rebuilding, this
means the cost of repairing or rebuilding less any discounts
available to us were we to repair or rebuild.
…
4. If we have chosen to repair or rebuild your damaged building
and you do not wish to repair or rebuild then, we will at our
option:
a. pay you the reasonable cost to repair or rebuild your
damaged buildings less an amount for depreciation
based on the age and condition of the buildings; or
b. pay you the value of the land and buildings at the risk
address immediately prior to the occurrenc e of the loss
or damage less the value of the land and buildings
immediat ely after the loss or damage occurred .
Other benefits -
Removal of debris,
professional rebuildi ng
fees and extra costs of
complying with building
a. When the buildings have been destroyed or damaged by
any of the insured events covered by your policy and
we have agreed to pay your claim, we will also pay the
reasonable and necessary costs o f:
Case No: 481863 Determination Page 7 of 8
Section Terms
regulations demolition and removing your buildings debris
from the risk address
architects‟, engineers‟, surveyors‟ and solicitors‟
fees
complying with the requirements of any statutory
authority.
We will only pay these costs if they relate directly to the
removal of debris from or repair or replacement to that
part or parts of the building whic h have been destroyed or
damaged and we have agreed to do so before they are
incurred.
The maximum combined total amount we will pay under
this benefit is 10% of the sum ins ured on your buildings.
However, for a claim under this benefit we will first pay up
to the balance of any buildings sum insured remaining
after payment of your claim for loss or damage to your
buildings, and any such payment will not be taken into
account in calculating the above maximum combined total
amount.
Conditions of cover Buildings not lived in for more than 60 days
If the buildings have not or will not be lived in for any period in
excess of 60 consecutive days, we will not pay for loss or
dama ge caus ed by any of the following insured events unless
you have our prior agreement in writing:
Insured events page number
Accidental breakage of glass 24
Accidental loss or damage 25
Explosion 25
Fire or smoke 25
Malicious acts 26
Theft, burglary or housebreaking 28
Water or other liquid damage 29
Taking precautions
We will not pay for loss, liability, injury or damage if you do not:
a. take all reasonable precautions to prevent the loss, liability,
injury or d amage
b. maintain your buildings in good repair
If thi s insurance has
been issued through an
insurance intermediary
If your policy has been issued through our agent, or a broker
who is acting under a binder arrangement with us, then they are
acting as our agent and not as your agent.
Case No: 481863 Determination Page 8 of 8
Section Terms
If your policy has been issued by a broker, other than a broker
acting under a binder arrangement with us, then the broker is
acting as your agent.
When this policy has been arranged through an int ermediary, a
commission is payable by us to them for arranging the
insurance.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.