Home / Financial Firm (Unknown - Insurer) / Determination 479702

Determination 479702

Water leak claim: cause of odour and cash settlement amount

FirmFinancial Firm (Unknown - Insurer)
Decided2018-05-21
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$77,889
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

After a water leak claim, the applicants said an antifungal chemical applied by the FSP's contractor made the house unliveable and wanted demolition and rebuild. AFCA found mould was the likely cause, refused demolition, and ordered a cash settlement of $77,888.59 plus interest.

The cause of the problems was most likely mould contamination, and as the applicants would not allow remediation, a cash settlement equal to remediation cost is fair.

Issues

Subjects and remedies

health or medicalhome or building damagepay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 479702 Determination Page 1 of 8 Case number: 479702 19 April 2018 1 Overview 1.1 Dispute The applicants hold a home insurance policy with the financial services provider (FSP). The applicants lodged a claim in April 2016, for water damage caused by a leak. The FSP accepted the claim and carried out repairs, discovering some mould in the process. The applicants say the house is unliveable because it has a strong, unpleasant smell and spending any time in the house makes them fee l sick. The FSP says the house is contaminated with mould and has offered to arrange or pay for mould remediation. The applicants say the smell in the house is not due to mould contamination, but due to an antifungal chemical applied by the FSP in June 2016. The applicants want the FSP to demolish and rebuild the house. 1.2 Issues and key findings What is the likely cause of the problems in the house? The available evidence does not establish that the odour and health effects associated with the house are due to an antifungal chemical applied by the FSP. It is most likely that the problems are due to mould contamination. How should the claim be settled? The FSP cannot undertake mould remediation because the applicants will not allow it. The matter should be settled by the FSP paying the applicants a cash settlement. 1.3 Determination This determination is substantially in favour of the FSP. The FSP must pay the applicants $77,888.19, to finalise its obligations in respect of the claim. The FSP is required to pay interest on this amount, in accordance with the Insurance Contracts Act 1984 (the Act), from 7 September 2017, until the date the payment is made. Case No: 479702 Determination Page 2 of 8 2 Reasons for determination 2.1 What is the likely cause of the problems in the house? Applicants say the house became unliveable in June 2016 On 4 April 2016, the applicants lodged a claim for water damage to their home. The FSP accepted the claim. The FSP appointed a builder, „RF‟, who appointed a cleaner, „RX‟. The FSP‟s claim notations say that on 20 July 2016, RX advised that the “ last use of any chemical ” was on 23 June 2016. RX advised that a containment area was set up to the area treated, the chemical was heavily diluted and the chemical odour would dissipate within 2-3 days. The applicants say that o n 24 June 2016, their younger daughter „KR‟, saw RX “ mixing chemicals in a dirty bucket ”, smelt “ a horrible, chemical odour ” and heard “ a compressor or hissing sound ”. Their older daughter „NR‟, became “unable to breathe properly”. The female applicant came home over eight hours later and smelt a “ god awful smell ”. The applicants say: “ Eventually every member of our family ended up affected, [female applicant] had chest pains and [KR] was continually coughing, even our dog was rushed to the vet unable to breathe properly …” The applicants say the house became unliveable immediately after the chemical treatment by RX and has remained so ever since. Applicants say the problems are caused by the treatment administered by RX According to „FN‟, a restorer appointe d by the FSP, RX said the solution used to treat the applicants‟ property was „BTA‟ (a proprietary solution containing benzalkonium chloride, a biocide). The FSP has provided a Materials Safety Data Sheet (MSDS) for BTA. According to the MSDS, the product smells like apple, is an irritant to eyes and mucous membranes and is “unlikely to cause anything more than slight discomfort” if inhaled or ingested. The FSP‟s notes say that on 14 July 2016, RX went to the house with a representative of BTA‟s manufacturer. Both reported that “there is a smell in the home but not due to [BTA]”. They suggested the smell may be due to mould. The applicants‟ letter to FOS dated 2 August 2017, says: “ Of course the representatives … are not going to admit that the problem came from (a) their company representative or (b) the chemical they manufacture, that is just common sense .” The applicants say they appointed their own expert to inspect the home in or about July 2016, but he did not provide a written report. In respect of this expert, the applicants say: It was a person that we found on Facebook who is a mould remediator who was kind enough to stop by and try and help out for free when he heard of the difficulties we were Case No: 479702 Determination Page 3 of 8 having. He said that he felt chemicals were definitely used and… were causing a gas like pr oblem… His suggestion was to heat the room to test if a chemical was used. He said if it was a chemical that was causing the problem a fog would appear, which it did. The applicants do not accept that BTA is as safe as the MSDS indicates, or that BTA was the chemical used in treating their home. Evidence indicates house is contaminated with mould After June 2016, the FSP appointed at least seven different experts to investigate the cause of the odour at the insured property. Their findings are summarised in the table in section 3.1 of this determination. The expert reports identify the following factors which may be contributing to the odour and health problems associated with the house:  „MT‟, mycologist, says the house is contaminated with mould and strongly recommends mould remediation  „FN‟, restorer and „EO‟, hygiene consultant, say the house is extremely dusty, which could cause health problems, including triggering allergies  „VA‟, environmental monitors, say the first floor has a “lack of ventilation” which is “having an influence on the occupancy conditions”. In a letter to FOS dated 21 October 2017, the applicants say: “ this issue was caused by [RX] fogging our home, with what now is an unknown chemical, which is continuing to off-gas .” If this was the case, the severity of the odour and health effects would be expected to diminish over time as the chemical diffused. This does not appear to have occ urred. The FSP‟s internal assessor attended the property with FN on 12 September 2016 and both smelt an unusual odour and suffered headaches after spending 90 minutes in the house. The applicants say that in July 2017 (more than a year after RX‟s attendan ce), the male applicant entered the house and reported: “[it] had a very strong wooden smell, he ended up with a stuffy no se, headache and sinus pain and… severe chest pains … These effects lasted for several days.” The available evidence indicates that the odour and health effects associated with the house were as severe in July 2017, as they were in June 2016. This is consistent with mould infestation and is unlikely to be the result of a one-time application of a chemical. No evidence has been provided that there is any chemical whose application could cause such effects over a period of more than a year. On the other hand, the experts who attended the property provided conflicting reports regarding the odours and health effects associated with the house. The Panel is satisfied that this is at least partly because reports of odours and health effects are highly subjective. It may also be because the attendances occurred over the course of about nine months and variations in mould ecology occurred over that time. The applicants do not accept that the house has problematic levels of mould because there is no visible mould, other than in the roof. The Panel is satisfied, however, it is possible for mould to have health effects without being visible. Case No: 479702 Determination Page 4 of 8 The FSP has offered to arrange or pay for mould remediation in accordance with MT‟s recommendations. Having considered the available evidence and noting that the cause of the problems with the house has not been precisely determined, the Panel is satisfied that this is the best approach to rectifying the problems. 2.2 How should the claim be settled? Applicants will not allow FSP to undertake remediation The applicants say both of their daughters are immunocompromised and NR has “ Multiple Chemical Sensitivities ” (MCS), a condition that has been exacerbated by the chemical applied by RX. The applicants say that before the FSP does any work on the house, they require a written absolute guarantee that there will be no negative effects on the health of any member of their family. The FSP could not honestly give the guarantee the applicants have requested. The applicants say NR‟s MCS symptoms can be triggered by exposure to many different chemicals and there aren‟t any chemicals they can guarantee she is not sensitive to. Accord ing to the applicants‟ letter to FOS dated 2 August 2017, they “ learn everyday of new triggers that set off her condition ”. The Panel notes that even if the FSP demolished and rebuilt the house, as the applicants have requested, it could not guarantee that no member of the applicants‟ family would experience any negative health effects associated with the new house. The construction of a new house would involve many chemicals. There is no evidence that demolishing and rebuilding the house would be less likely to trigger NR‟s MCS symptoms, than the mould remediation work proposed by the FSP. Furthermore, the Panel is satisfied that the evidence does not support the applicants‟ position that the house requires demolition. Matter should be resolved by cash settlement The FSP is unable to undertake remediation because the applicants will not allow it. Furthermore, the history of the dispute shows that the applicants feel a great deal of animosity towards the FSP and have no trust in the FSP or its contractors. Even if the FSP were to undertake remediation with the applicants‟ consent, it is overwhelmingly likely that the applicants would express dissatisfaction with the work. The Panel is of the view that the most appropriate way to resolve the dispute is by the FSP paying the applicants a cash settlement. The sum of the settlement should be what it would have cost the FSP to undertake mould remediation. FSP offers cash settlement of $64,909.59 The FSP has offered to settle the matter by paying the applicants $64 ,909.59. This includes approximately $32,000 for mould remediation, $5,000 for building repairs, and $15,000 for carpet replacement, plus additional allowance for temporary accommodation and storage fees. In addition, the FSP has offered to reimburse the Case No: 479702 Determination Page 5 of 8 applicants for the cost of power consumed by the machines used to remediate the property. The FSP‟s offer is supported by a scope of works prepared by „AC‟, cleaners and restorers. The scope of works is dated 7 September 2017 and costed at $27,103.19. Offer accounts for cleaning of split systems The FSP‟s offer includes allowances for replacing ducting for the heater and the evaporative cooling unit. The applicants say that if there are mould spores in the ducting, “ the head units of the Split Systems need to be replaced or at the very least cleaned … to ensure they are safe to use .” AC‟s scope of works includes two items (one each for upstairs and downstairs) stating: “ Decontaminate and detail clean split systems inside out .” The Panel is satisfied that the F SP‟s settlement offer adequately accounts for the cleaning of the split systems. Offer accounts for cleaning of the applicants’ contents The applicants say the FSP‟s offer does not account for the replacement of contents, including a fabric couch. AC‟s scope of works includes two items stating: “ Decontaminate/HEPA vacuum loose contents ...” The applicants have not provided any evidence indicating that this work would not be sufficient to ensure the applicants‟ contents are not contaminated with dangerous levels of mould. The Panel is satisfied that the FSP‟s offer sufficiently accounts for the cleaning of the applicants‟ contents. Offer does not account for curtain replacement The applicants say the FSP‟s offer does not account for the replacement of curtains . The FSP‟s Notice of Response says that on 3 November 2016, the FSP‟s internal assessor recommended: “ All carpet and curtains to be removed from the home and disposed of .” The FSP‟s offer includes an allowance for carpet replacement, but not curtain replacement. The FSP has offered to increase its offer by $10,000 to account for curtain replacement. Alternatively, the FSP has offered to obtain a quote for curtain replacement. There is no evidence that challenges the adequacy of the FSP‟s cash offer with regard to curtain replacement. The Panel is satisfied it is appropriate to bring this matter to a conclusion rather than await another quotation for curtain replacement. As such, the FSP is entitled to rely upon its allowance of $10,000 for curtain replacement. Case No: 479702 Determination Page 6 of 8 Offer does not account for post-remediation verification AC‟s scope of works includes an item stating: “Indoor Environmental Professional to attend after 48 hours to complete Post Remediation Verification throughout”. The scope of works includes a disclaimer stating that the estimated cost “ does not include the Indoor Environmental Professionals‟ fees”. The FSP says AC‟s estimate for the cost of post-remediation verification is $1,479. The Panel is of the view that the FSP‟s offer should be increased by $1,479 to account for the cost of post-remediation verification. Reimbursement of cost of power The FSP has agreed to reimburse the applicants for the cost of power, calculated by “The Kilowatt Hour usage of machines (provided by AC), multipli ed by the customers cost per kilowatt hour on their power bill for the period.” Doing the best it can for the purposes of a cash settlement, the Panel is satisfied it is fair to allow $1,500 for reimbursement of cost of power. FSP’s offer is otherwise adeq uate The applicants remain “adamant” that the odours and health effects associated with the house are being caused by a chemical applied by RX and have nothing to do with mould. The applicants are not satisfied with the FSP‟s offer, because they say the only way to solve the problem is to demolish the house and build a new one. However, the panel is satisfied that the problems with the house are related to mould and not the consequences of chemical remediation. Having taken all available evidence into account, the Panel is satisfied that it is fair and reasonable in all the circumstances that the matter be settled by way of a cash settlement. The sum of the cash settlement should be calculated as follows: Item Amount FSP‟s settlement offer $64,909.59 Allow ance for curtain replacement $10,000 Allowance for post - remediation verification $1,479 Allowance for cost of power $1,500 TOTAL $77,888.59 The FSP must pay the applicants $77,888.59 to finalise its obligations under the claim. The FSP is required to pay interest upon this amount, from 7 September 2017, until the date payment is made. Case No: 479702 Determination Page 7 of 8 3 Supporting information 3.1 Extracts from relevant expert reports The FSP appointed several experts to investigate the cause of the odour at the insured property. Their findings are summarised in the following table: Expert Report date Findings „FN‟, restorer 12 July 2016 No unusual odour detected. Hous e is very dusty, which could trigger allergies. “It is our opinion that, aft er 2 weeks, nothing can be done to further dilute the chemicals used and it has naturally neutralised.” „ML‟, mycologist 19 July 2016 Report attached to FN report dated 26 July 2016. FN says ML‟s report shows very high levels of mould “which is associated with asthma sufferers a nd is an allergenic”. „VA‟, environmental monitors 28 July 2016, based on observations and samples collected on 19 July 2016 Ground floor has “a minor mould issue”. First floor has a “lack of ventilation” which is “having an influence on the occupancy con ditions ”. First floor shows elevated levels of carbon dioxide, a sign of inadequate airflow). First floor shows elevated levels of volatile organic compounds, and the site analyst reported a eucalypt us smell. „RL‟, FSP internal assessor 12 September 2016 There is “a strong unknown odour to the lower lounge room and upper storey bedroom”. RL and FN spent 90 minutes in the house, and both “suffered headaches from being in the home”. FN 16 September 2016, bas ed on attendanc e on 12 September 2016 There is a “ chemical odour… evident in all rooms ” that was not there when FN attended on 7 July 2016. FN Re - attendanc e of property on 3 October 2016 FN says odour was “very much reduced” after test cleaning, and the applicants‟ reaction was “very positive”. The appli cants dispute this, saying: “We did note that the smell was slightly reduced however… [we still] had health issues from being in the home…” „EO‟, hygiene consultant 24 November 2016 No signs of mould. “[The] excessive amount of household Case No: 479702 Determination Page 8 of 8 dust… poses the g reatest potential health risk to any occupants of this house.” „MS‟, engineer 7 December 2016, based on site inspection on 30 November 2016 There is “a strong peculiar and unidentified chemical odour… within the Lounge room [and] throughout the home to a lesser degree.” There are some drainage issues at the property, but these issues are not the caus e of the odour. Recommendation: “that the source of the odour be further investigated to determine the cause”. „MT‟, mycologist 3 February 2017, based on site inspection and samples taken 5 January 2017 There is a “mild odour… consistent with a building that has been closed up for a considerable time.” “High to extremely high fungal levels” in the downstairs area and roof void, but “no significant mould prolife ration” in the upstairs area. Mould remediation “strongly recommended”. MT 2 May 2017, based on samples taken from contents items on 30 March 2017 Cont ents show high levels of dust, debris, and dust mites, but low levels of mould. MT 2 May 2017, based on samples taken from the roof void on 30 March 2017 Results suggest roof void has been cross contaminated. “Mould remediation of the roof void is strongly recommended.”

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.