Home / Financial Firm (Unknown - Insurer) / Determination 479362

Determination 479362

Dispute over calculation of business interruption and stock loss after flood

FirmFinancial Firm (Unknown - Insurer)
Decided2018-06-05
ProductGeneral Insurance · Business / commercial
OutcomeFor the complainant in part
Amount awarded$42,743
Non-financial loss—
Amount claimed$115,244
SourceAFCA PDF

Summary

A bespoke cabinet business claimed under its business policy after a burst pipe flood, and the parties disputed business interruption, stock valuation and claim preparation costs. AFCA ordered the FSP to pay further business interruption loss, stock, accounting and repair amounts, less amounts already paid, in part reducing the amounts claimed.

Business interruption is assessed on general accounting principles using the certified accountant statement, and an absorption cost method was accepted for custom stock where labour could not be reliably allocated by materials.

Issues

Subjects and remedies

business interruptionsmall businesspay claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 479362 Determination Page 1 of 8 Case number: 479362 8 May 2018 1 Overview 1.1 Dispute The applicant held a business insurance policy with the FSP commencing on 5 August 2016. He lodged a claim with the FSP on 18 November 2016 after a burst pipe caused a flood at the premises. The FSP has accepted the applicant’s claim but a dispute has ari sen as to the calcu lation of the applicant’s loss, in particular, relating to business interruption and loss of stock. This dispute has been subject to a recommendation. Both parties have rejected the recommendation. 1.2 Issues and key findings What is the ext ent of the FSP’s liability for business interruption? The FSP is liable to meet the applicant’s claim for business interruption for a period of 12 months from 18 October 2016 to 18 October 2017. The FSP is to pay the applicant $45,656.27 for loss of income for the period 18 October 2016 to 31 July 2017. The FSP is entitled to deduct from this amount any sum already paid by way of loss of income. The FSP must further pay the applicant loss of income for the period 31 July 2017 to 18 October 2017 subject to the provision of a certified statement of loss of income from the applicant’s accountants for that period. What is the extent of the FSP’s liability for the showroom stock? The Panel is satisfied that the FSP is liable to pay an additional $7,174.74 based o n the applicant’s calculation using the absorption cost method. Is the FSP liable for the applicant’s accounting fees? The Panel is satisfied that the FSP is liable to meet the accounting fees of $11,050, such fees being reasonably incurred in relation of the claim preparation costs. Is the FSP liable for the cost of repairing the damaged stock? It is fair in the circumstances that the FSP pay an additional $6,372.56 to cover the cost of repairing the damaged stock. Case No: 479362 Determination Page 2 of 8 1.3 Determination This determination is in favour of the applicant. The FSP is to settle the applicant’s claim in accordance with the terms and conditions of the policy and pay the applicant:  loss of income of $45,656.27 less any amount paid to date for loss of income until 31 July 2017  pay the applicant any further loss of income as confirmed by a certified statement from the applicant’s accountant for the period 31 July 2017 to 18 October 2017  pay the applicant a further $7,174.74 for loss of stock  pay the applicant a total of $11,050 (less any amount already paid) for claims preparation costs  pay the applicant $6,372.56 to cover the cost of repairing damaged stock. Case No: 479362 Determination Page 3 of 8 2 Reasons for determination There has been a full exchange of material between the parties and each party has had the opportunity to address the issues arising from the information exchanged. Following the recommendation, further detailed submissions were made by both parties. All information has been exchanged and both parties have had the opportunity to address the issues raised in the further submissions. Due to the complexities involved in this matter, it has been referred to a Panel for determination. In reaching this determination, the Panel has had access to all information exchanged. The determination is based on what is fair in all the circumstances, having regard to the relevant legal principles, terms of the policy, good industry practice including codes of practice and prior determinations where applicable. 2.1 What is the extent of the FSP’s liability for business interruption loss? Policy provides cover for loss of income due to business interruption for up to 12 months There is no dispute that the applicant’s business suffered insured damage on or about 17 October 2016 when a burst water pipe flooded the premises. There is no dispute that the applicant has a valid claim. The applicant’s policy is a business insurance policy. Included in the policy is cover for business interruption (consequential loss of profits - revenue protection). Cover under this section is limited to the period of insurance indicated in the certificate of insurance. The certificate of insurance indicates the applicant took business interruption cover for a period of 12 months. Cover includes:  loss of income resulting from insured damage during the period of insurance  additional expenditure necessarily incurred for the purpose of reducing loss of income  claims preparation costs. The policy provides that the FSP will accept as proof of loss of income, a certified statement from the insured’s accountants or auditors that shows the financial details requested by the FSP. Applicant has established a claim for business interruption There is no dispute that the applicant’s business was interrupted as a result of the insured damage. The FSP has provided an assessment of business interruption for the period ending 31 July 2017 from FAS, a specialist forensic accounting division of the FSP’s loss adjuster. Case No: 479362 Determination Page 4 of 8 FAS assessed the business interruption at $42,891 (exclusive of GST). The applicant provided an assessment of business interruption for the period to 31 July 2017 from its accountants, SU, totalling $45,656 (exclusive of GST). Both assessments appear to be based on the information prov ided by the applicant’ s accountants and on standard accounting methodology used to calculate business interruption. The Panel acknowledges that general accounting principles are applicable when assessing the business interruption under the terms of the policy. There is no dispute about this between the accountants that the rate of gross profit is calculated at 75.28%. The Panel in this instance has preferred the assessment by the applicant’ s accountant, SU. The Panel notes that SU has explained the variation between estimates by explaining that it disagrees with the FSP’s calculation of savings/increase costs of working that are required as part of the overall calculation. The Panel notes the policy provides that the FSP will accept as proof of loss of inc ome a certified statement from the applicant’s accountants. The Panel is satisfied that the applicant has established a loss of gross profit for the period from 18 October 2016 to 31 July 2017 of $45,656.27. The FSP has already paid the applicant for business interruption of at least $27,511. From the information provided to the Service, it is unclear whether the FSP has paid any additional amounts beyond this. The FSP is entitled to deduct those payments made by way of business interruption loss of income from the $45,656.27 payable for the period to 31 July 2017. FSP liable to pay business interruption for period between 31 July 2017 and 18 October 2017 The policy clearly provides cover for business interruption for a period of 12 months. The applicant maintains that his business has continued to suffer as a result of the insured damage and further suffered as a result of the FSP’s delays in completing repairs to the property. The Panel has not been provided calculations to establish the full extent of the applicant’s loss of income due to business interruption for the remaining period from 31 July 2017 to 18 October 2017. The FSP says that as the applicant’s turnover in June 2017 and July 2017 exceeded the expected sales for these months, then there was no further liability for business interruption. The Panel does not accept that this is necessarily the case. The indemnity period is for a period of 12 months. The FSP remains liable for the potential business interruption up till 18 October 2017. The Panel is satisfied that the FSP is liable to pay the applicant for loss of income until 18 October 2017 subject to the applicant providing a certified statement from his accountant SU as proof of loss. The FSP is also liable to meet the cost of SU in providing such a statement. Case No: 479362 Determination Page 5 of 8 2.2 What is the extent of the FSP’s liability of the showroom stock ? The applicant’s policy provides cover for accidental damage including damage to contents and stock. Stock is defined in the policy to include all work in progress and property of others held on consignment. Damaged showroom stock should be assessed using absorption cost method The FSP calculated the value of this showroom stock damage at $32,588. In reaching this figure, the FSP calculated the average correlation between the materials and payroll to determine the rate of payroll expense when compared to the material expenses across the 12 month period. Based on this analysis, the FSP determined that for every $1 spent on materials, 1.2817 was spent on labour. That is the labour cost of production was 128.17% of the cost of production materials. The Panel acknowledges that this is a common method of assessing loss of stock and contents, however the Panel does not accept that it is appropriate to use this method in the current claim. The applicant says that the more appropriate method to assess the loss of the showroom stock was to do so by using the absorption cost method. The absorption cost method looks at the full cost of manufacturing. It calculates the cost of the finished unit including direct materials, direct labour, variable and fix manufacturing overheads and arguably provides a more comprehensive and accurate view of how much an item has actually cost. The applicant’s business is a bespoke cabinet business. The cost of preparing the showroom stock given the nature of the items is different to the cost that might normally be incurred. The applicant has assessed the actual hours and average labour rates for each of the items. The applicant notes each job’s labour requirement is substantially different and to attempt to allocate the labour amount based on a percentage of materials would not give an accurate cost for those items. The Panel accepts that this is not an unreasonable proposition in this case. The applicant maintains the products manufactured were custom products. A more complex job requires a more qualified tradesperson to do the majority of the work. The apprentices would be able to do little work on these jobs. Each job’s labour requirement was substantially different. The applicant says that the labour component of the showroom stock valuation calculation should be calculated by splitting the labour hours between tradespeople, apprentice labour hours and multiplying by the respective average labour rate per hour. Allowing for these calculations, the applicant has assessed the value of the showroom stock damaged at $40,420.50. Salvage of $657.82 is to be deducted from this. Allowing for the deduction of payments received to date for the showroom furniture and salvage, the balance payable is $7,174.74. The Panel accepts that it is fair in the circumstances that the FSP pay the applicant the additional $7,174.74 with respect to the damaged showroom stock. Case No: 479362 Determination Page 6 of 8 2.3 Is the FSP liable for the claims preparation costs? The policy provides cover for claims preparation costs. The applicant has claimed cost of $11,050 (exclusive of GST or x GST). The FSP has offered $8,800 arguing that part of the work performed by SU was normal accounting work required in the running of the business. The Panel notes from the invoice provided that each item claimed by SU is in relation to the preparation and submission of reports to the FSP’s forensic accountant. The invoice also includes meetings with the applicant with respect to the claim. The FSP has not provided any information to dispute SU’s claim that the work related to preparation and submission of reports to the FSP. Whilst the Panel accepts that there are certain fees and returns such as monthly management accounts, the Panel is satisfied that the amounts charged are reasonable. The Panel accepts the FSP should pay the applicant $11,050 for claim preparation costs, being the amount claimed by SU of $12,155, less applicable GST of $1,105. Other matters The applicant has claimed for the cost to replace a number of blackbutt chairs. The FSP has agreed to pay for the cost of the blackbutt chairs, subject to the provision of relevant invoices. The applicant has now provided those invoices. The applicant has also requested the FSP pay:  $2,136 for the cost to repair a table panel saw, wide belt sander and dovetailer  $2,112.72 for additional timber used for rework jobs  $1,732.71 to remake work benches  $1,523.54 for a new computer. The Panel notes that the FSP has either paid or agreed to pay for these costs. The Panel accepts that these issues are no longer in dispute. The applicant has also claimed the costs of labour and materials and overheads for the rework jobs completed. The applicant claims that the cost of the rework jobs was $10,612.06 as trades staff were used to complete 100% of the rework jobs. The applicant has provided a quotation marked ‘ reworks job work paper ’ and claiming labour rates at $80/hr. It is not a detailed quotation and the Panel is unable to determine from the work paper the reasonableness or otherwise of the amount claimed. The Panel accepts the custom nature of the work performed by the applicant and it is likely a mix of trade skills would be required to complete the work. In the Panel ’ s view, it would be fair in these circumstances to allow the applicant’s claim at an hourly rate similar to that assessed for the replacement of the showroom stock of $20.48 per hour. Calculated on the hours claimed of 178.25 hours at $20.48 per hour, this comes to $3,650.56. Materials claimed total $2,722. In the Panel’s view, it is fair in the circumstances that the FSP pay an additional $6,372.56 to cover the costs of repairing the damaged stock. Case No: 479362 Determination Page 7 of 8 3 Supporting information 3.1 Business interruption key policy terms Policy term Key points Business Interruption – Income: Cover We will pay in accordance with the Basis of Settlement, for Loss of Income that results from an interruption of Your Business caused by any Insured Damage that happens at the Premises. Provided that this Insured Damage happens during the Period of Ins urance shown for this Business Interruption. Basis of Settlement 1. Loss of Income Loss of Income will be calculat ed by subtracting the Income earned during the Indemnity Period from the Income You would have earned during the Indemnity Period had the Damage not occurred. Provided that the Income You would have earned during the Indemnity Period had the Damage not occurred: (a) will be calculate d by reference to the Income for: (i) a period of the same duration as the Indemnity Period that starts a Year prior to the date of the Damage; or (ii) a period of Your normal Business operations that corresponds most closely to the Indemnity Period if Y our Business has operated for less than a Year at the start of the Indemnity Period; and (b) will be adjusted to take into account any: (i) trends of the Business and other influences that would vary the Income; (ii) variation of normal trading whereby Income is maintained during the Indemnity Period from increased sales of low margin goods; (iii) changes to how Stock, materials, finished goods or partially finished goods are used, purchased or sold including sal vage sales of Stock following Insured Damage; and (iv) savings made during the Indemnity Period that reduce the cost of running Your Business. 2. Additional Expenditure We will also pay for additional expenditure necessarily incurred for the sole purpo se of reducing Loss of Income that is covered by this Cover Section and/or resuming and/or maintaining Your normal Business operations or services. Provided that this expenditure is limited to the amount of Income that would otherwise be lost had the addi tional expenditure not been incurred. 4. Auditors and Accountants We will accept as proof of the Loss of Income a certified statement from Your accountants or auditors that shows the financial details requested by Us. Case No: 479362 Determination Page 8 of 8 Indemnity period The period that starts on the dat e of the Damage and ends not later than the number of weeks or months stated in the Schedule after the date of the Damage during which the results of Your Business is affected as a consequence of the Damage Loss of Income Loss or reductio n of Your Income that occurs during the Indemnity Period. Income Income means: 1. … and 2. income from Your Business at the Premises for goods sold, work done, electrical power generated and sold, services rendered or any Government approved incentives, s ubsidies or market development allowances You are entitled to in relation to Your Business, less: (a) working expenses for freight, packing, bad debts, and the purchase of goods, materials, components, or Stock; (b) any other Uninsured Working Expenses sho wn in the Schedule; and (c) payroll if this is shown in the Schedule. 3.2 Contents and stock loss key policy terms Policy term Key points Damage or Damaged means accidental physical damage, destruction or loss. Stock - Basis of Settlement For Damage to Stock We will at Our option:  (i) replace or repair the Damaged Stock with property or mat erials of equal quality, standard and specification unless the Stock has become obsolet e; or  (ii) where the Stock is Obsolete Stock at the time of the Damage, We will pay You its value as Obsolete Stock but no more than its original cost to You; or  (iii) if You request a cash settlement and Reinstatement or repair is not carried out, and the Stock is not Obsolete Stock, We will pay the original cost to You of the Stock that is Damaged beyond repair plus an amount commensurate wit h the cost of repairing Damaged Stock, but not exceeding its Pre - Damaged Value at the time of the loss. Pre - Damage Value means the value of the Property that is Damaged immediately before the Damage has occurred. This value must take account of wear and tear, maintenance, construction, general condition and the anticipated future useful life of the Property.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.