Determination 478620
Request to replace entire 24 sqm concrete courtyard after exploratory works damaged about 1 sqm
Summary
The applicant wanted his entire 24 sqm concrete courtyard replaced ($6,180 quote) after the FSP's exploratory works damaged about one square metre. AFCA held the policy covers only the damaged area, but ordered the FSP to honour its increased $1,000 offer, with further payment only on evidence of the cost to replace three plants.
The exploratory-costs clause covers repairing the area damaged by the exploratory work, not replacing the whole slab.
Subjects and remedies
home or building damagepay claim
Text of the determination
Determination
Case No: 478620 Determination Page 1 of 2
Case number: 478620 24 July 2017
1 Overview
1.1 Dispute
The financial services provider (FSP) accepted a claim made under a Residential
Strata Insurance policy to locate a burst water pipe in the applicant’s courtyard and to
repair the area damaged as a result of the exploratory work.
The applicant says the repair to the damaged area of approximately 1 square metre
is unsightly and he wants his entire concrete courtyard (24 square meters) restored
to its original condition. The FSP has denied his request.
1.2 Issues and key findings
Is the FSP required to replace the concrete courtyard area?
The policy provides for the repair of damage caused by exploratory work to locate a
burst pipe. It does not provide for the replacement of the entire concrete slab.
1.3 Determination
This determination is substantially in favour of the FSP. The FSP is to honour its
increased offer of $1,000 subject to this being sufficient to account for both the
damaged area and the plants.
If the amount is insufficient, the FSP is to pay the amount that is subject to the
applicant providing evidence of the cost to replace the three plants.
Case No: 478620 Determination Page 2 of 2
2 Reasons for determination
2.1 Is the FSP required to replace the concrete courtyard area?
Policy wording provides for the repair of damage caused by exploratory work
The following policy provision is key to the outcome of this dispute:
9 Exploratory costs, replacement of defective parts
We will pay for reasonable exploratory costs You necessarily incur in locating the source of
bursting, leaking, discharging or overflowing of tanks, apparatus or pipes used to hold or carry
liquid of any kind.
We will also pay for reasonable costs incurred in:
a. repairing the area of Your Insured Property damaged by such exploratory work;
The FSP has provided photographs of the damage caused by the works undertaken
to locate a burst water pipe. The affected area of concrete is approximately one
square metre. A quote of $550 to repair this area has been supplied.
The applicant wants 24 square metres of concrete replaced
The applicant has rejected the FSP’s offer to repair the affe cted area of concrete. He
wants his courtyard restored to the state it was in before the water pipe burst. In
particular, he says the repair of the affected area of concrete would result in:
extra joins on the concrete, which was not present before the pipe burst, and
an area of concrete that is unlikely to be colour matched to the concrete in the
remainder of the courtyard.
These would create a negative effect on the appearance of his courtyard.
The applicant provided a quote of $6,180 to replace 24 square metres of concrete.
The policy does not provide for the full replacement of the concrete courtyard
I do not consider the exploratory works undertaken to locate the burst pipe had
damaged the entire courtyard area. The policy limits the FSP’s liabili ty to repair the
damaged area only.
The FSP’s offer to increase the settlement of the claim is appropriate
I do not consider the initial offer of $550 to repair the affected area of concrete was
sufficient as it did not cover the loss of three plants in th e applicant’s courtyard.
The FSP’s increased offer to $1,000 to settle the claim is fair in the circumstances
provided this is sufficient to cover the replacement costs of the applicant’s plants . If it
is not, the FSP is to pay any amount required subject to the applicant producing
evidence of the cost to replace these plants.