Home / Financial Firm (Unknown - Insurer) / Determination 478235

Determination 478235

Quality and method of water damage repairs to flooring

FirmFinancial Firm (Unknown - Insurer)
Decided2017-10-27
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded—
Non-financial loss$2,500
Amount claimed$97,320
SourceAFCA PDF

Summary

After a burst pipe, the applicants disputed the flooring and other repairs done by the FSP's contractor, which did not follow manufacturer standards. AFCA found the FSP must re-attend the work or cash settle at the applicants' discretion, pay related items, and pay $2,500 for non-financial loss.

The policy requires reinstatement to the condition before the loss, and the chosen repair method did not meet manufacturer standards, so the work must be redone or cash settled.

Issues

Subjects and remedies

home or building damagepay claimpay interestpay non financial lossrepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 478235 Determination Page 1 of 9 Case number: 478235 24 October 2017 1 Overview 1.1 Dispute The applicants lodged a claim for water damage to their home after the discovery of a burst water pipe. The financial services provider (FSP) accepted the claim and arranged for the affected areas in and around the kitchen and other areas to be repaired. A dispute later emerged as to the quality of these repairs, particularly in relation to the flooring and the paintwork. The method of ho w the flooring was installed concerned the applicants. Whilst the FSP accepts there are some issues to rectify, it does not accept the floor installation is defective to the extent claimed. 1.2 Issues and key findings What is the extent of remedial work to be done to the flooring? The FSP‟s policy provides replacement “to the same condition”, which the FSP has not carried out in this instance. The applicants‟ floors should be replaced in accordance with the manufacturer‟s instructions. Is any additional settlement required? The FSP must attend to the additional rectification and other work as stipulated in the body of this determination. It must also pay compensation to the applicants of $2,500 for non-financial loss. 1.3 Determination This determination is in favour of the applicants. The FSP, at the applicants‟ discretion, must either replace the flooring and attend to the other work, or pay the costs for the replacement and work. If a cash settlement is requested, the FSP must pay interest on this settlement at the statutory rate from 16 November 2016 until the date of payment. The FSP must pay the applicants non-financial loss compensation of $2,500. Case No: 478235 Determination Page 2 of 9 Case No: 478235 Determination Page 3 of 9 2 Reasons for determination 2.1 What is the extent of remedial work to be done to the flooring? Primary concern for the applicants with the floor work The applicants lodged a claim for resultant damage arising from a burst pipe under the kitchen cabinetry. There is no dispute the damage sustained to the home is covered under the terms of the policy. Further, there is no dispute the FSP attended to repairing the affected areas. Essentially, this dispute rests on the quality of that work and the method of repair used by the FSP‟s agents. It is not in dispute the FSP‟s chosen contractor (“SK”) did not follow the manufact urer‟s standards when attending to the relevant repairs of the floor. The applicants consider the installed flooring is defective and should be replaced. The FSP acknowledges the installation is not perfect but says it is not necessary or practical to foll ow the manufacturer‟s standards exactly and the imperfect work can be rectified. Common ground there are issues with the floor installation It is the applicants‟ contention the repairs to the flooring were defective. Specifically, in submissions made to the Service, the applicants note: „… the sub - floor membrane is not installed as to manufacturer‟s recommendation thus voidi ng flooring product warranties.‟ The applicants obtained quotes to rectify the flooring and to install the flooring correctly. This valued the work at $60,793.58 + GST. Whilst accepting there is some work requiring rectification, the FSP only offered to cash settle the applicants for $40,000. The FSP further believes the value of this work is less than this amount. Applicants consider the FSP has an onus to repair the floor appropriately In simple terms, the applicants say the original laying of the floorboards complied with the manufacturer‟s standards and the repairs conducted on behalf of the FSP do not. They suggest it is unfair they should have to accept such a situation as they have not been returned to the position they were in prior to the loss. The applicants say the floor was not re-done as per its original installation and they want and should be entitled to a like for like replacement. It is their contention the subfloor membrane was not installed to the flooring manufacturer‟s recommendations. The applicants‟ concern extends to the possible long term consequences of work which does not follow the manufacturer‟s standards. Speci fically, they worry that Case No: 478235 Determination Page 4 of 9 moisture may penetrate the concrete slab and affect the floorboards over time, the way they are laid now. This potentially presents as a long term damage issue, which is avoided if the floorboards are laid in accordance with the ma nufacturer‟s specifications. Expert evidence as to the work conducted Several experts were engaged to comment on the quality of the work conducted. On 29 July 2016, IG noted original moisture readings from the flooring were taken from the top (which were normal) but subsequent readings from the particleboard substrate showed “elevated moisture was trapped under the hardwood flooring”. The floor outside the island bench had also cupped. IG also suspected more damage would become apparent from the insured eve nt over time. The loss was covered under the terms of the policy and quotes obtained to attend to the work. IG recommended SK attend to the repairs required. The applicants first raised issues regarding SK‟s work in late 2016. This was noted in IG‟s repor t of 16 November 2016. On 22 November 2016, flooring specialist FC provided a report after an inspection of the flooring. FC noted the repairs were generally “of a very good standard”. Whilst conceding the secret nailing method was not used for the entire floor, FC considered this acceptable. The expert further conceded some minor repair work was to be completed. As FC was not privy to the original condition of the flooring or the laying of the subfloor membrane, I consider his opinion on the work to be of limited value. Assessor AA initially provided a report on the property dated 19 July 2016. This report noted the applicants had lived in the home about 13 years and the flooring had been laid in or about 2008. The applicants had no concerns with it prior to the loss. This report noted no strong concerns with the moisture levels in the flooring, though there was evidence of water inundation elsewhere, including around areas of the plasterboard walls. Conceding the presence of water related damage, AA recommended remedial work be undertaken. On 5 December 2016, engineer CR provided a report looking into issues with the home. Relevant to the issue of the floors, CR confirmed numerous defects, including splits in the boards, incorrect fitting, gaps, improper installation techniques. The expert further acknowledges the applicants complaint: „…that the moisture barrier (polythene sheet) is not appropriately overlapped/sealed at the joins, and i s damaged/compromised in place…‟ SK informed CR it had installed the moisture barrier and CR was unable to verify the applicants‟ claims of defective installation of this aspect of the flooring. Outside of Case No: 478235 Determination Page 5 of 9 this, CR accepted there were numerous defects to the floor and rectification of this work was required. A subsequent report compiled by AA and dated 7 April 2017, confirmed the male applicant was dissatisfied with numerous aspects of the work, including (but not limited to):  inadequate installation of the plastic vapour barrier over the concrete floor slab prior to installation of the plywood flooring substrate  uneven gapping to butt ends of the rear door  excessive gapping between floorboards  movement issues and apparent noises in certain areas  a general failure to install the floorboards and surrounds as originally done. To address the applicants‟ concerns, AA appointed FC to consider the work. FC generally considered the work to be of a good standard. Notwithstanding this, issues were present and SK agreed to rectify these, including the gapping, the step detail at the front door, reinstatement of the step down detail and correction of off-set joins. FC confirmed some other issues required attention. AA assumed the slab had been adequately dried by SB. The squeaking in the floor was “clearly apparent” and a confirmed defec t which required rectification. Ultimately, AA suggested the flooring did not require removal and replacement, merely some corrective work to some of the suggested areas. On 6 July 2017, AA provided a further report to consider repair issues, including the suitability of the work conducted to the flooring. AA confirmed the installation was “in contradiction to [the] flooring manufacturer‟s installation recommendations” but expressed the view this does not render the work defective. The expert considered the cost of demolishing and reinstating the work was “not warranted and… unreasonable”. Policy provides specific parameters for replacement The FSP‟s policy broadly provides cover for accidental damage. In relation to repairing items, the policy notes: “When destruction, loss or damage occurs to your Buildings, we will pay the cost of rebuilding your Buildings, or repairing the damaged portions of your Buildings, to the same condition as when they were new.” I am satisfied that the policy provision requires the FSP to reinstate the flooring to the way it was laid. The FSP‟s chosen method of repair is not doing this. Concern over the barrier installed for the flooring The applicants provided photos showing the vapour barrier was not installed in accordance with the manufacturer‟s (BO‟s) standards. Specifically, these standards note: Case No: 478235 Determination Page 6 of 9 “Plywood Fixed to Concrete:  Lay a 200-micron plastic membrane over the whole area and continue up the walls 75mm (to be trimmed later). Overlap joins by 200mm and seal the entire join with duct tape.” The substrate manufacturer (CH) confirmed the substrate in this instance was non- structural plywood and whilst manufactured to “the same standard” it was not in accordance with the requirements of the manufacturer. AA contacted the manufacturer who “confirmed… (it) does not matter if the substrate is non-structural or structural ply” but they will not warrant an overlay flooring product if the vapour barrier has not been installed with 75mm upturn at the walls, was overlapped at the joins by at least 200mm and duct taped at the joins. Looking at the industry standards, AA noted these requirements are “generic in nature” and whilst frequently used, installers with “knowledge and experience” may vary, though this becomes an issue for the installer and not the manufacturer. AA noted the: “Evidence available suggests that current flooring installation will not be covered by any flooring manufacturers’ warranty due to shortfalls in installation procedures, therefore any warranty in the eve nt of flooring failure will be solely appointed to the builder.” The expert concluded the failure of the vapour barrier was “highly improbable, however cannot be discounted”. One of the key indicators will be the drying of the floor slab prior to installation, which AA admitted he was unable to verify. The applicants noted staining to the floor, which SK denied being responsible for. A photo from the time of installation suggests no staining was present, though it is not clear if this is related to the sub-floor issue or not (noting the drying of the slab could not be verified). Another flooring expert, FC, noted it was acceptable to not tape “joins in isolated areas when installing 200 micron black plastic” and, in fact, this would not be possible for this job. FC ventured black plastic is only used “as a safeguard” when a wet or green slab is present. SK admitted in email correspondence of 2 August 2017 it had installed black plastic underneath the existing plywood “as far as is possible. It would be imposs ible to do anything further unless the entire floor is removed”. The FSP noted the method of repair utilised by SK was standard in matters such as this, where a full replacement of the floor was not necessary and limited to only the affected area. It considers that if a rigid approach to floor replacement was always required, it would be impractical for the industry as relatively minor floor repairs would require more extensive treatment in each case. FSP needs to replace the flooring The applicants seek a cash settlement for the claim as they have lost faith in the FSP‟s ability to properly and fairly attend to the work. Case No: 478235 Determination Page 7 of 9 There is no question the evidence from the FSP shows the floorboards can be repaired and (in the opinion of the assembled experts) potentially completed to a satisfactory standard. In my view, this is not the issue. The issue is whether the chosen method of repair is acceptable, given it does not comply with manufacturer‟s standards and will not return the floor to the state it was in prior to the loss. This creates a problem if the protection under the floor is somehow compromised at any time in the future. With part of the floor following the appropriate guidelines and part not, a potential dispute may develop as to who is responsible. S uch an issue would not be likely if the repairs simply followed the manufacturer‟s guidelines. In my view, the FSP has failed to comply with the terms of its policy. A proper consideration of the damage meant it should have been repaired in accordance with the manufacturing guidelines. To this end, I am satisfied the FSP must re-attend to the work, ensuring these guidelines are adhered to. Therefore, at the applicants‟ discretion, the FSP may either:  repair the damage after engaging a new repairer (not SK) to attend to the work, or  cash settle the applicants based on the provided quote. 2.2 Is any additional settlement required? Additional items of concern raised by the applicants Beyond the flooring problems highlighted by the applicants, they expressed concern over other aspects of repair at the home. As of June 2017, these included additional issues for which they obtained quotes:  paint and plaster works $7,205  reinstatement of kitchen joinery $6,042.07  rectification of work and additional joinery repairs $8,019.92  repair of chipped cook top $792  reimbursement for rental costs 18 April 2017-17 July 2017 $9,882  invoiced work from GA not yet reimbursed $1,166  steam cleaning of home $495  replacement of paint damaged items $1,406.90  house clean $1,320  dry cleaning of doonas $198. Furthermore, the applicants claim the above amounts do not include the preparation for electrical work required to the island bench and additional work to reinstate furniture and other items left in storage. The applicants contend the FSP has not used the applicable (and quoted) wall frame specification in work conducted to the lounge room and this needs to be rectified. Case No: 478235 Determination Page 8 of 9 FSP has agreed to rectify much of the work AA addressed a number of the individual items raised and noted:  the entry/kitchen sliding door requires replacement  he could not verify if the dent damage to the butler‟s pantry cabinet door (which was small) was pre-existing or not and recommended no action. He suggested the scratch damage required touch up painting  the butler‟s pantry sliding door and kitchen/butler‟s pantry door will be replaced by SK  incorrect paint was used by SK and this needs to be addressed  the kitchen north wall was dislodged and needed to be realigned and repaired, with the plasterboard reinstated  minor rectification work to the entry plasterboard is required  an outlet socket near the entry needed to be reinstated  a general clean to remove excessive dust was also required. AA estimated the additional work required would cost $34,906.58. It appears this corrective work was inclusive of the rectifications to the flooring, though it is not clear if this includes the alternate accommodation costs (which will be addressed later). CR also looked at overall defects in relation to the work done at the home. CR accepted the timber and sliding doors should be rectified and recommended reinstatement of the kitchen cabinetry, further plastering and painting work and the reinstatement of relevant appliances. Furniture and other items were held in storage by the FSP for a long period of time and it is not clear as to the status of these items. The FSP has not responded conclusively on much of this disputed material, though it has raised no major objections either. On balance, I consider the FSP should address the work in the manner sought by the applicants. To the extent it is able to attend to the work itself (and the applicants are amenable), I am satisfied the FSP should do this but not utilise SK for the work as it is clear the applicants relationship with this contractor has been strained. If the applicants prefer a cash settlement, the FSP should attend to this based on the quotes submitted by the applicants. The parties are encouraged to work together to resolve outstanding issues. Applicants seek cover for loss of rent Given the flooring is not to an acceptable standard, the applicants have been unable to occupy their home as a family for a significant period of time. They have made alternate arrangements and incurred expense and personal inconvenience. Under the terms of the policy, the applicants seek rental costs of $1,647 per month from 17 April 2017. This will extend until the relevant work is completed (or at least until the home is rendered liveable. The FSP has not challenged the claim for loss of rent or the amount sought. It agrees an amount is payable. The policy allows for cover up to an amount not exceeding Case No: 478235 Determination Page 9 of 9 20% of the building sum insured and this should be sufficient for the parties to come to an arrangement about the suitable amount to cover. Award of compensation is appropriate As a result of the repair difficulties at the home, the applicants have been unable to live together since about October 2016. The female applicant rented a property with the children from this time and has been forced to live apart from her husband. Both applicants have stressed the hardship this arrangement has caused them throughout the dispute. FOS allows compensation awards for non-financial loss in circumstances where: „… an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the [applicants‟] expectation of enjoyment or peace of mind has occurred…‟ In my view, the extent of inconvenience and stress for the applicants in this situation has been manifold. This has been further exacerbated by the FSP‟s approach to resolution, particularly in relation to the flooring, which constituted the majority of the dispute. I am satisfied the FSP should pay an award of compensation at the higher end of the scale in respect of this. To this end, I consider the FSP should pay non-financial loss compensation in the sum of $2,500 to the applicants.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.