Determination 478031

Implementation of earlier determination on delayed pool claim; expert report exceeded instructions

FirmFinancial Firm (Unknown - Insurer)
Decided2018-05-17
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$25,000
Non-financial loss$1,500
Amount claimed$50,000
SourceAFCA PDF

Summary

Applicant sought $50,000 for pool replacement after the FSP's delayed claim assessment, and said the FSP's expert exceeded the earlier determination's instructions. AFCA ordered $25,000 including statutory interest and a further $1,500 non-financial compensation, using the expert's $15,000-$20,000 estimate plus 25 per cent.

The FSP's delay worsened the pool damage, so it must cover replacement costs, which are best estimated from the expert's figures with an allowance for contingencies.

Issues

Subjects and remedies

home or building damagepay compensationpay interestpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 478031 Determination Page 1 of 8 Case number: 478031 16 May 2018 1 Overview 1.1 Dispute On 2 September 2016, the Financial Ombudsman Service (FOS) issued a determination (number 427793) partly in favour of the applicant and against the Financial Services Provider (FSP). In part, the determination states: “This determination is partly in favour of the applicant. Should the applicant accept this determination, then within fourteen days of acceptance, the FSP is to:  pay the applicant $1,500 compensation  begin the process to resolve the dispute as described in the determination under the heading “independent expert to inspect pool and surrounds” and the following paragraphs. If the expert’s opinion results in a cash settlement to the applicant, then statutory interest is to be paid on the cash settlement amount from the date this issue was determined by the FSP (in its IDR decision dated 2 November 2015) until the date of payment. Otherwise, the FSP need take no further action in r elation to the claim or the dispute.” The determination was accepted by the applicant and the FSP arranged for an expert to inspect the damaged pool. The applicant says this expert did not follow the instructions given in the determination. The applicant seeks a further determination about the implementation of the original determination and the outcome of the original dispute in determination number 427793. 1.2 Issues and key findings How should the matter be resolved? The available material establishes the FS P’s expert report did not properly address the required issues as stipulated in the original determination. The opinion inappropriately and incorrectly revisited issues which had already been determined. In the circumstances, the available information establishes it is fair in the circumstances the FSP pay to the applicant $25,000 which represents the prejudice suffered by the applicant as a result of the FSP’s delay between the time the claim was made and the time the claim was assessed. The FSP is also to pay a further $1,500 to the applicant for non-financial compensation as after the original determination there has been a further unusual degree or extent of physical inconvenience, time taken to resolve the situation and interference with the applicant ’s expectation of enjoyment or peace of mind. Case No: 478031 Determination Page 2 of 8 1.3 Determination This determination is substantially in favour of the applicant. Should the applicant accept this determination, then within seven days of acceptance of the determination, the FSP is to pay to the applicant:  $25,000 representing the prejudice suffered by the applicant as a result of the FSP’s delay with the original assessment  $1,500 for non-financial loss compensation sustained after the original determination Otherwise, the FSP is not required to take any further action in relation to the claim or the disputes in determinations numbered 427793 and 478031. Case No: 478031 Determination Page 3 of 8 2 Reasons for determination 2.1 How should the matter be resolved? Specific instructions given in the original determination The original dispute involved the failure of the applicant’s pool and consideration of whether this was covered under the terms of the FSP’s home policy. Whilst I did not accept the policy responded to the applicant’s claim, I accepted the applicant had suffered a loss due to the delays by the FSP in inspecting the damage. I was satisfied there was an unacceptable delay between the report of the loss and the eventual assessment. Based on available information at the time of the determination, I was satisfied the pool deteriorated between the time of the loss/claim and the time of the assessment. Based on available information, I was also satisfied if the pool had been assessed at the time of the claim, it could have been repaired. The available information did not assist me in making a determination about the amount of the loss caused by the delay. I had insufficient information to determine the cost to repair the pool at the time of the claim compared to the cost to repair the pool and its surroundings at the time of the assessment. In the circumstances, I set up a mechanism to determine the loss. The FSP was to provide three independent experts for the consideration of the applicant. The applicant could then choose the acceptable candidate, who would conduct an inspection of the pool and also inspect relevant photographs. The FSP said it was only able to source two experts for the applicant’s consideration. This aside, the parties agreed for a suitably qualified expert to inspect the pool and its surrounds. The expert was eventually provided with my requirements to enable the expert to address issues raised in the determination. I stipulated the relevant inspection must: “… include an examination of all photographs provided by the parties of the pool and surrounds taken at the time of the claim and at the time of the assessment. The inspection and assessment must conclusively address the following points: 1 what damage was sustained to the pool and surrounds at the time of the claim 2 could the pool and surrounds been repaired at the time of the claim 3 if so, what would have been the costs of repairs at the time of the claim 4 what damage was sustained to the pool and surrounds at the time of the assessment 5 could the pool have been repaired at the time of the assessment 6 if so, what would have been the costs of repairs at the time of assessment 7 has the delay between the time of the claim and the time of the assessment worsened the damage to the pool and surrounds and increased the costs of repairs to the pool and surrounds.” Finally, as part of the determination, I concluded: “If it is the expert’s opinion the delay has worsened the damage to the pool and surrounds resulting in an increase in the cost of repairs from the time of the claim to the cost of repairs Case No: 478031 Determination Page 4 of 8 at the time of the assessment, then the FSP is to cash settle the applicant the difference between the cost of repairs at the time of claim and the cost of repairs at the time of assessment.” Specific instructions were also given for the further settlement of the claim, should the expert considered it necessary. Consideration of the FSP’s expert report obtained after the determination The FSP arranged for the building consultant MC to inspect the applicant’s pool and surrounds. A report was prepared dated 14 November 2016. As a result of the report, the FSP made no settlement offer to the applicant. I am of the view MC exceeded the scope of its engagement on several fronts. MC challenged the applicant on the reported date of loss. MC then formed a view significant damage was done to the pool prior to the storm. The expert considered and provided opinions on these issues, which had already determined by FOS. It was not in dispute there was a storm event in July 2015. Whilst MC suggests the only rainfall event for the month was on 12 July 2015 and damage to the pool was present the day earlier, his conclusion overlooks the fact rainfall data for a day is based on the previous day’s falls, calculated to 9.00am on the day listed. This means the rainfall listed for 12 July 2015 had fallen over the previous 24 hours to 9.00am the morning of 12 July 2015. By extension, the photograph of damage from 11 July 2015 (showing damage already present to the pool) probably shows the damage caused by the storm, not prior to it. There is no time stamp on the aerial image. Leaving aside investigation of this nature was not required, nor part of MC’s brief, I consider conclusions about the value of this information are incorrect. Such an approach is of concern as:  it was not the task of MC to investigate such factors  MC’s conclusions are probably wrong based on a misinterpretation of the available evidence, and  this likely prejudiced the balance of MC’s conclusions about the loss. MC noted areas of the pool supports were heavily corroded but I consider this is to be expected in a structure which has (partially) stood in a damaged and deteriorating state for around 18 months at the time of MC’s inspection. Notwithstanding the aforementioned problems, some aspects of the report are noteworthy. MC says: “In my opinion, had the liner [of the pool] been patch repaired and the apparently minimal wall deflection as shown in the [photographic] image of 11 July 2015 been treated and stabilised prior to the rain event, a limited warranty repair might have been offered by an applicator. However, I would need to have an image of the pool wall condition as at 11 July 2015 to confirm this to have been practical.” The above statement supports the contention the initial damage was minimal and potentially repairable for a small unspecified amount (noting the damage present at that time was probably not caused prior to the rain event). Case No: 478031 Determination Page 5 of 8 MC also said the cost to remove and replace the existing pool would be about $15,000 to $20,000. No actual quote was provided. Expert has not acted within instructions set out in the original determination The main purpose of the MC report was to determine the consequences of the delay between the claim being made and the assessment, and the extent of prejudice to the ap plicant because of this delay. MC’s report exceeds the scope of his instructions and deals with matters already determined by me in the original determination which determination was based on available information at that time. It was not MC’s brief to revisit the facts upon which the original determination was made. In any event, as MC has probably incorrectly concluded the damage occurred prior to the storm, his value as an expert is compromised. And his opinion has not addressed the specific requirements of the determination. In the determination, I accepted photographs showed the pool and surrounds had deteriorated between the time of the initial claim and the FSP’s eventual assessment. The FSP acknowledged the delay in the assessment was its fault. The determination therefore accepted the FSP's delay had prejudiced the applicant. The available information established had the claim been assessed promptly and had the applicant been advised of the policy response promptly, he would have been in a position to mitigate his loss. MC agrees the initial observed damage w as “apparently minimal”. Therefore the available information causes me to conclude the FSP is responsible for most of the damage. The FSP should cover the costs to replace the pool and surrounds The applicant has insisted since the claim was made he had advice the tear in the lining could have been patched at minimal expense. Given the time which has elapsed since the original claim, and the opportunity to repair the pool at minimal expense has passed, I accept the pool is probably now a total loss. As the full extent of the FSP’s liability for the damage cited from the original determination has not been quantified (and the evidence it has obtained says the damage was minimal in the first instance), I am satisfied it is fair the FSP should now cover all the costs to remove and replace the pool. MC estimated these costs to be $15,000-$20,000. The applicant requested $50,000 but the available material does not substantiate that amount. In support of his position, after the original determination, the applicant provided a letter from his real estate agent. The letter said if the applicant replaced the pool and repaired the backyard the agent would increase the asking price by $40,000. The applicant did not replace the pool or repair the backyard. The applicant says potential purchasers were unimpressed by the state of the backyard. The applicant also says because of this, the home was sold for much less than the listing price. Case No: 478031 Determination Page 6 of 8 Even if I were to accept these contentions, I do not accept these contentions are strictly relevant to the assessment of the loss in this dispute. This is because there are many issues which may dictate the eventual sale price of a home. While I accept the deteriorated condition of the pool and surrounds may have affected the eventual sale price, I do not accept this is the best available evidence of the loss caused by the FSP’s delay in assessing the claim. I consider the best available evidence is the estimate provided by MC. Fair the FSP pay to the applicant $25,000 As it is clear the relationship between the parties has deteriorated to the point where it would not be practicable for them to work together, and in view of the available evidence which shows the property has been sold, it is fair in the circumstances the FSP cash settle the applicant. No proper itemised valuation was obtained to remove and replace the pool and the surrounds. Therefore, MC’s estimate may not necessarily be complete. To account for costs which may not have been considered in the estimate from MC, and to ensure the applicant is not unfairly left with what would have been additional unknown costs and contingencies, I am satisfied it is fair there be an allowance of an additional 25% on MC’s estimate. The additional allowance takes into account the allowance for statutory interest. In addition, even if I were to accept the deteriorated condition of the pool adversely affected the eventual sale price of the home, I am satisfied to award anything further would in effect be double compensation for the applicant’s loss. In conclusion, for the reason stated, I am satisfied the available information establishes it is fair in the circumstances the FSP pay the applicant $25,000 including statutory interest to indemnify the applicant for the prejudice caused by the FSP’ s delay in assessing the claim. FSP is also to pay further non-financial compensation of $1,500 FOS has the power under clause 9.3 of its Terms of Reference to award compensation in circumstances where an applicant has experienced: “…an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with [his] expectation of enjoyment or peace of mind…” Such compensation for non-financial loss is capped at no more than $3,000. FOS typically understands any applicant will experience a degree or extent of inconvenience in any claim and expects applicants to take a robust approach to this. I accept the applicant has been subject to a significant amount of inconvenience, an unacceptable timeframe for resolution of the dispute and considerable interference with his expectation of enjoyment and peace of mind. In the original determination, an award of $1500 compensation was made and has been paid by the FSP. Case No: 478031 Determination Page 7 of 8 However, I accept the applicant has been adversely affected by the handling of the dispute after the original determination as well. The FSP failed to make three experts available for the applicant’s choice, as stipulated by me in the determination. Further to this, the report obtained from MC exceeded the bounds of the brief and caused considerable angst and further inconvenience for the applicant. Despite encouragement from FOS to try to resolve the dispute with the applicant, an addendum to the original determination was required. Taking all matters into account, I am satisfied it is fair in the circumstances the FSP pay a further amount of compensation for its claims handling after the original determination. The FSP is to pay to the applicant a further $1,500 compensation. Case No: 478031 Determination Page 8 of 8 3 Supporting information 3.1 FOS Approach As advised to the parties, FOS has considered it appropriate to expedite the dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. This is because of the nature and complexity of the matter. Accordingly, this dispute has not been the subject of a FOS recommendation and has proceeded directly to determination. This is an addendum to the determination 427793 issued on 2 September 2016. The purpose of this addendum is not to revisit issues previously considered in the original determination but to review and determine issues which arose out of the determination or which require clarification. There has been a full exchange of all material information relied on for the purposes of this addendum and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered for the purposes of this addendum. This addendum has been decided on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. While the parties have raised numerous issues in their submissions, for the purposes of this addendum, commentary has been restricted to those issues considered directly relevant to the outcome only. 3.2 Other relevant material considered and relied on  Determination 427793.  Material provided by the parties both before and after determination 427793.  MC report 14 November 2016.  Parties’ submissions, emails, photographs and all attachments to all submissions in this determination.  Correspondence between the parties.