Home / Financial Firm (Unknown - Credit) / Determination 477601

Determination 477601

Progress payments to builder and change of loan repayments during construction

FirmFinancial Firm (Unknown - Credit)
Decided2017-10-04
ProductCredit · Home loan
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

Borrowers building a home with a construction loan complained that the FSP wrongly paid builder progress claims, failed to share a valuation or inspect the works, and changed repayments early, after the builder defrauded them. AFCA found the FSP acted on the borrowers' signed instructions and loan terms and ordered no compensation.

The FSP was entitled to rely on the borrowers' signed payment instructions, owed no duty to inspect or share its security valuation, and could change repayments under the loan terms after two years.

Issues

Subjects and remedies

scamno remedy

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Case No: 477601 Determination Page 1 of 6 Case number: 477601 4 October 2017 1 Overview 1.1 Dispute In 2014, the Financial Services Provider (FSP) provided the applicants with a construction loan (the loan) to enable them buy land and build on the property. The applicants say the FSP:  breached obligations it owed to them when it made the progress payments to the builder  was obliged to share a property valuation it obtained in 2015 and alert them to problems with the construction and  should not have changed the loan repayments to principal and interest before the construction was completed. 1.2 Issues and key findings Did the FSP make any error when it made the progress payments? The FSP did not make any error when it made the progress payments to the builder as authorised by the applicants and in accordance with the agreed schedule . The FSP was not obliged to inspect the property prior to making payments. Was the FSP obliged to contact the applicants about its valuation? The FSP obtained a valuation of the property in March 2015 for its own purposes following the assignment of the building contract to a new builder. The valuation did not oblige the FSP to contact the applicants about the progress of the construction for the reasons set out in section 2. Did the FSP make any error when it changed the loan repayments? The FSP did not make any error when it changed the loan repayments from “ interest only ” to principal and interest. The terms and conditions of the loan allowed for a change in the repayment type and amount if the building works were not completed within two years. 1.3 Determination The determination is in favour of the FSP. The FSP is not required to provide compensation to the applicants. Case No: 477601 Determination Page 2 of 6 2 Reasons for determination 2.1 Did the FSP make any error when it made the progress payments? The applicants authorised the FSP to make the payments to the builder The applicants‟ contract with their builder required them to make six payments totalling $284,900. Under the terms and conditions of the loan, the applicants were responsible for ensuring the building was progressing satisfactorily before the builder was paid. The loan terms and conditions clearly place this responsibility on the applicants. The relevant sections are set out in section 3.2 below. The FSP funded the loan upon receipt of signed written instructions from the applicants. The available information shows that the builder sent invoices with photographic evidence to the applicants in line with the buildi ng contract. The applicants signed the invoices and forwarded them to the FSP to authorise payment to the builder on their instructions. The FSP was entitled to rely on the applicants‟ instructions to make the relevant payments. The applicants ’ conditions were met prior to payment for the enclosed stage There was a long delay following the completion of the frame stage in July 2014 until May 2015, when the new builder invoiced the applicants for payment of the enclosed stage. The applicants signed the invoice on 20 May 2015, with the following two conditions to be satisfied prior to the FSP making the payment to the builder:  on-site building insurances forwarded to, and approved by, the FSP (first condition)  any other documentation and evidence that this enclosed stage of the contract has satisfactory evidence of being completed as provided by the builder (second condition). The FSP satisfied the first condition when it received correspondence on 21 May 2015 confirming insurance was held. The FSP says:  it contacted the applicants after receiving the signed invoice  the applicants told the FSP not to pay the invoice until they had received further photographic evidence from the builder that the work had been completed to the required level  the applicants received further photographic evidence from the builder and advised the FSP they were satisfied the works had been completed. The FSP subsequently made the relevant payment to the builder four weeks after receiving the invoice. If these conditions were not satisfied, it would have been reasonable for the applicants to dispute this payment at the time, if not soon after, it was made. The applicants did not dispute the payment at that time, which confirms the conditions were satisfied before the FSP made the enclosed stage payment to the builder in accordance with their instructions. Case No: 477601 Determination Page 3 of 6 The FSP did not breach any obligation owed to the applicants The applicants say the FSP should have inspected the property prior to each progress payment to the builder to verify the building works had been completed. While the FSP did not physically inspect the property prior to each progress payment to the builder, neither did the applicants. The FSP was under no such obligation in the terms and conditions of the loan and it was the applicants ‟ responsibility to check on the progress of the build before authorising payment. In addition, the FSP‟s policy states the FSP was not obliged to complete property inspections prior to release of each progress payment. The applicants may have wanted the FSP to assume responsibility for ensuring the building works were completed. However, the loan terms and conditions do not show this was the agreed arrangement between the FSP and the applicants. In general, a financial services provider that is a bank or credit provider does not have a „fiduciary‟ duty or responsibility to its customer. This means that it is not obliged to conduct due diligence on a customer‟s proposed investment or project. A fiduciary responsibility arises only where the bank ‟s role is seen to extend beyond that of finance provider and into the area of advice or where the bank agrees to provide a dedicated exercise of its judgment for the customer‟s interests alone and not in any way for its own benefit. That was not the case in the circumstances of this dispute. There is no information to show that the FSP assumed any responsibility to conduct due diligence on the applicants‟ behalf or act solely in their interests. Accordingly the FSP did not need to, and was not expected to, investigate the applicant‟s decision to approve the progress payments to the builder. 2.2 Was the FSP obliged to contact the applicants about its valuation? The valuation was for the FSP’s purpose s, not for the applicants In March 2015, the FSP obtained a valuation of the property following assignment of the building contract to a new builder. The FSP sought the valuation for security purposes, that is, to assess the value of the property in case it had to sell the property to recover the debt. Clause 11.5 of the terms and conditions (set out in section 3.2 below) states that a valuation completed by the FSP is solely for its own purposes and the valuation will not be disclosed to the applicants. The FSP does not have a legal obligation to provide a copy of the valuation to the applicants or disclose its contents to the applicants. Where the customer otherwise appears to know what they are doing and provides direct instructions to their bank, a bank will only be liable if it fails to act where a reasonable and honest banker would have considered there was a real possibility that its customer might be being defrauded. However in this case, there were no indications in the valuation that a fraud was being perpetrated on the applicants by the builder. The valuation was thorough and provided a great deal of information. On page 6 it stated that the construction was at frame stage and the flooring and decking needed Case No: 477601 Determination Page 4 of 6 replacing as it had been exposed to rain events. The comments were not sufficient to raise concerns about the FSP‟s security position. There was a delay of five months between the appointment of the new builder and the valuation. The deterioration due to the weather was not out of the ordinary, and would not give rise to any reason why the FSP should report this to the applicants in circumstances where the FSP was entitled to assume the applicants were already aware of the building progress . The applicants were also entitled to obtain their own valuation if they required one. There was nothing contained in the valuation that obliged the FSP to have contacted the applicants. 2.3 Did the FSP make any error when it changed the loan repayments? The loan terms and conditions allowed for the repayments to be changed The applicants say the FSP should continue “ interest only ” repayments on the loan until the construction has been completed. The FSP loan terms and conditions at clause HL3.1 (set out below) states:  the loan repayments can be changed from “ interest only ” to principal and interest and  the remaining funding cancelled, if the building works have not been completed within two years of the date of the loan contract. The loan contract was dated 16 January 2014. The loan repayments were changed to principal and interest and the remaining funding cancelled in early 2017. The FSP did not breach any obligations when it changed the loan repayments and cancelled the remaining funding from the loan account. Case No: 477601 Determination Page 5 of 6 3 Supporting information 3.1 Timeline of events Date Event Loan Drawing 26 November 2013 Fixed Price Buil ding Contract for $284,900 signed (Builder: Contract Build) 16 January 2014 Loan contract issued 3 February 2014 Property settlement completed $104,996.40 4 July 2014 P roperty valuation completed for FSP 9 July 2014 Progress Payment – S lab & Frame stages released to builder ($99,715) $66,093.60 16 October 2014 Building Contract – Deed of Assignment signed (Contract Build to Line Constructions) 24 March 2015 Property valuation completed for FSP 17 June 2015 Progress Payment – E nclosed stage released to builder ($71,225) $71,225 11 September 2015 Progress Payment – F ixing stage released to builder ($56,980) $56,980 February 2016 Applicants discover fraud by the builder 3.2 Relevant Terms and Conditions Clause HL3.2 of the loan terms and conditions: We fund the loan by paying the loan drawings in accordance with written instructions signed by you or the person (if any) you have authorised under a loan author ity given pursuant to clause 3.7 or at our discretion, in accordance with your or their electronic or verbal instructions (for example when you instruct us to pay following a request for payment by a contract builder or a sub-contractor). Clause 11.5 of the loan terms and conditions: If any of our officers, or any other person engaged by us, at our expense carries out any inspection or valuation of the property offered as Security Property or which is subject to a Security, they do so for our purposes only and not on your behalf. Any reports made as a result of an inspection or valuation done at our expense is our exclusive property and will not be disclosed to you. When we inspect or value a property, or do anything as a result of an inspection or valuation, or pay any Loan drawing under clause HL3, we are not obliged to tell you anything we learn and make no representation to you about the condition of the land, the construction of any building or the standard or value of any building on the property or the uses to which the property may be put. Clause HL3.1 of the loan terms and conditions: You must commence drawing the Loan within 6 months of the Disclosure Date and complete all Building Works within 24 months of that date. If you don’t, we can choose not to fund the Case No: 477601 Determination Page 6 of 6 Loan, or the remainder of the Loan, and to give you one month’s written notice requiring you to start repaying in accordance with clause HL5.4 from a specified date. You will not have to start repaying until any interest only period stated at Item HLA expires.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.