Home / Financial Firm (Unknown - Insurer) / Determination 476934
Determination 476934
Storm-damaged underground stormwater and sewer pipes claim declined
Summary
The FSP refused to pay for repairs to storm-damaged underground pipes. AFCA found the storm was the proximate cause, the exclusions did not apply, and ordered payment of $4276.90 plus interest. The determination's summary states $4272.90, an apparent typo.
The FSP could not prove the pipes sat in fill, so the defects exclusion failed, and the storm was the dominant cause of the pipe damage.
Issues
- Claim denial primary · upheld“The FSP cannot rely on the exclusions in the policy. The FSP must pay the claim.”
Subjects and remedies
home or building damagenatural disasterpay claimpay interest
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
Determination
Case No: 476934 Determination Page 1 of 5
Case number: 476934 30 January 2018
1 Overview
1.1 Dispute
Sewerage and stormwater pipes broke at the applicant’s home. She had them
repaired and claimed the cost of the repair from her insurer, the FSP. The FSP
refused to pay, saying that the applicant had not established a claim. The applicant
does not accept this, and wants the FSP to pay the claim.
1.2 Issues and key findings
Does the FSP have to pay the claim?
The proximate cause of the damage to the pipes was a storm. The FSP cannot rely
on the exclusions in the policy. The FSP must pay the claim.
1.3 Determination
This determination is in favour of the applicant.
The FSP must pay the applicant $4272.90, plus interest from 27 March 2017.
Case No: 476934 Determination Page 2 of 5
2 Reasons for determination
2.1 Does the FSP have to pay the claim?
Stormwater and sewage pipes were damaged
In April 2015, there was a sto rm which affected the applicant’s home. The storm
brought unusually heavy rains. In the immediate aftermath of the storm, the
applicant noticed cracking in the paving surrounding her pool.
The applicant’s house is on a very steeply sloping block. The po ol is at the back of
the block. The pool is rectangular, with its long side running basically east to west.
The slope of the block also runs down from east to west. On the western edge of the
pool is a strip of paving, then some open ground, and then a large retaining wall.
The damaged pipes were located in the area of open ground between the edge of
the pool paving and the retaining wall. The damage to the pipes was first noticed in
around October 2015, when sewage was noted to be leaking into the property of the
downhill neighbour to the west.
The applicant had repairs to the stormwater and sewage completed. The total cost
of the repairs was $4276.90, comprising
Excavator hire 814.00
Concrete cutting 973.90
Plumber 2489.00
The applicant’s claim , although previously much broader in scope, is now limited to
those three invoices.
Policy covered certain events with some exclusions
The applicant’s policy is a defined events policy. This means the policy only responds
where one or more of the listed insured events causes loss or damage to the
property, subject to any exclusions. The listed events include ‘storm’, defined as
follows:-
• A violent wind including a tornado or named cyclone; or
• rain, hail or snow of unusual volume, force or duration.
It is not persistent bad weather or heavy or persistent rain by itself.
At the relevant time, the applicant also had Optional Cover for accidental damage.
The policy has a number of exclusions:-
What is not covered
…
Your building and/or contents are not covered under this Optional Cover or loss of damage
as described in the General Exclusions listed on page 75 to 78.
On page 75 of the policy is this:-
Case No: 476934 Determination Page 3 of 5
Under this policy there is no cover provided for any loss, damage or liability caused directly
or indirectly by or in any way connected with:
1. Defects, structural or design faults, faulty workmanship or faulty design
…
5. Water, including rainwater, after it has disappeared beneath the surface of the land at your
insured address ;
…
8. Subsidence or landslide (except in the case of the Insured Events ‘Earthquake’ and
‘Explosion’ claims)
Applicant has established insured event
The applicant carries the initial onus to establish the loss and damage claimed is
covered by the terms and conditions of the policy. The onus then shifts to the FSP to
show that it is entitled to rely on an exclusion under the policy or is otherwise entitled
to deny the claim.
A large amount of evidence has been provided to FOS about various damage to the
applicant’s home. Most of the evidence concerns the cause of damage to the
retaining wall, which is no longer claimed by the applicant (perhaps because
retaining walls are not covered under the ‘storm’ event ). Most of the evidence is not
relevant to the cause of the damage to the sewage and stormwater pipes.
The applicant provided a letter from her plumber (APS), which states:
[APS] completed an inspection at the above property on the 3/11/2015 to find the
stormwater pipes had broken and come apart due to land subsidence.
The FSP provided three reports by an engineering company, S. The first report by S,
dated 27 August 2015, says:-
Inadequate compaction of the retained fill material, combined with a recent abnormal heavy
rain event is subsequently deemed to be the primary cause for recorded cracking to the
concrete pool surround.
According to the Australian Government Bureau of Meteorology, over a two day period
between21 st and 22 nd April 2015 a total of 243.0mm rainfall was recorded at the Belmont
WWTP weather station (1.1km from Belmont), with a highest single day rainfall of 125.0mm
on the 22 nd . Due to this abnormal amount of rainfall and very steep north to south
topography of the land, large volumes of water will have flowed over the concrete tiled pool
surround area to the uncovered soil between the southern edge of the pool and retaining
wall.
Granular fill material, which is assumed to be contained behind the southern boundary
retaining wall is prone to subsidence should it not be appropriately compacted. If
abnormally s aturated, the bond (commonly referred to as “bridges) between the granular fill
particles can fail. The shear capacity is in turn reduced and subsidence occurs. The
recorded 50mm to 70mm drop in level along the southern edge of the pool is therefore
attributable to the combination of abnormally heavy rainfall in April 2015, and inadequately
compacted granular fill material.
During periods of normal rainfall events, the degree of saturation to the granular fill material
has been insufficient to induce failure. This, in my opinion, explains why cracking and
movement has only occurred after the most recent rainfall event.
The second report by S, dated 9 August 2016, says:-
Based upon the aforementioned information and that contained within our initial Engineers
Report, dated 27 th August 2015, cracking and movement of the tiled pool surround is
attributed to inadequate compaction of the backfill material that subsequently failed during
the April 2015 heavy rainfall event.
Case No: 476934 Determination Page 4 of 5
…
Fractured pipework at the south-west corner of the property is attributed to failure of the
inadequately compacted fill material, which subsided due to the April 2015 heavy rain
events. As the fill material subsided, it will have deflected the pipework beyond its
design limits; ultimately resulting in the reported fracturing.
The third report by S, dated 17 February 2017, which said:-
The assumption that the pipework was laid within fill material that was placed in order to
construct the residence is a fair and reasonable assumption to make. The Insured indicated
on site that the pipework repair was approximately 2 metres deep which may actually place
it within the original natural soil profile. The Insured believed he had photographs of the
trench excavation which we requested in order to clarify whether the pipes were in fill or in
the original soil profile. We have not received these photographs yet.
It is my opinion that the leaking stormwater and sewer pipes had been leaking for an
extended period of time prior to the claimed event which is likely to have affected the
foundation of the retaining wall resulting in the bowing of the wall.
It is my opinion that the leaking stormwater and sewer has further contributed to settlement
of the filled soils causing damage to the southern end of the pool coping.
The applicant provided a report by AES, an engineering company, which said:-
Comments by the repair contractor to the owner indicated that the pipework failure was not
of recent origin.
…
It is not clear where [S] obtained the information that fill exists under the sewer and
stormwater pipework to allow failure by settlement. This would appear to be a gross
assumption
…
We note that as no pre-purchase report was carried out no movement was noted in the
pool surrounds at that time ie 14 years after construction and the owner reports that no
defects were observed until after April storms.
If compaction was poor movement would have been observed prior to the storm event.
Evidence indicates that no settlement had occurred to the pools surrounds prior to the April
storm disputing the conclusion that the material under the slab was inadequately
compacted.
Excess stormwater and sewerage behind the retaining wall resulted from a failed
stormwater and sewerage management system explaining both the defects in the wall and
pavement settlement.
AES provided further opinions in an email to the applicant in around January 2017:-
The likely scenario as to the damage of the damage of the stormwater and sewer pipework
is an inundation of stormwater, surface, subterranean and piped into the area in question
causing saturation of the pipe support material exacerbated by washout of the same
support material caused by the extreme storm event of April 2015.
This has resulted in damage to the stormwater pipework and then as a consequence the
sewer pipework.
The applicant provided a report by her husband GT, who is also an engineer, which
says:-
Our inspection indicates that no settlement had occurred to the pool surround prior the April
Storm, disputing the [S] conclusion that the material under the slab was inadequate. Having
observed the material under the slab, I can confirm the [S] assumption is incorrect.
Additionally no representative from [S] attended the site to confirm this during the repairs
phase.
Case No: 476934 Determination Page 5 of 5
Excess stormwater and sewerage behind the retaining wall resulted from a failed
stormwater and sewerage management system explaining both the defects in the wall and
pavement settlement.
The Insurance Council of Australia declared the April 2015 weather event a
catastrophe. I am satisfied it was a storm within the meaning of the policy.
The experts agree that the pipes were damaged at the time of the storm.
Accordingly, I am satisfied that the applicant has established an insured event. The
insurer must prove one of the exclusions applies to defeat the claim.
Proximate cause of damage to the pipes was storm
There are three exclusions the insurer might rely on – underground water, subsidence
and defects. The terms of each exclusion are set out above.
The experts agree that underground water caused subsidence, which in turn led to
the pipes breaking.
The experts do not agree on whether defects – namely inadequately compacted fill –
played a part. S says it did, or at least that it might have. AES and the applican t’s
husband say it did not.
S’s final view on the part played by inadequately compacted fill is equivocal. He was
not sure that the pipes were laid within fill material:-
The assumption that the pipework was laid within fill material that was placed in order to
construct the residence is a fair and reasonable assumption to make. The Insured indicated
on site that the pipework repair was approximately 2 metres deep which may actually place
it within the original natural soil profile. The Insured believed he had photographs of the
trench excavation which we requested in order to clarify whether the pipes were in fill or in
the original soil profile. We have not received these photographs yet.
The applicant’s husband says that he saw the pipes and that they we re not within fill
material. Because he is an interested party, his opinion needs to be approached with
caution. However, I note that photographs of the broken pipes in situ were made
available to the FSP, and no further opinion from S has been provided.
The FSP has not established that the pipes were in fill material. It follows that the
FSP cannot rely on the defects exclusion.
I am satisfied that damage around the pool, including the area around the pipes, only
became apparent after the storm. The area had remained undamaged for the
roughly fifteen previous years since its construction. The movement of water
underground, until the storm, was not sufficient to cause subsidence or to damage
the pipes. In all of the circumstances, I am satisfied that the proximate cause of the
damage to the pipes was the storm.
FSP must pay the claim
The FSP must pay the claim. The amount to be paid is $4276.90, plus interest in
accordance with s57 of the Insurance Contracts Act from 27 March 2017, being the
date the FSP rejected the claim for damage to the pipes.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.