Claim declined for non-cooperation; further mould remediation, slab repairs, contents and accommodation disputed
Text of the determination
Determination
Case No: 476084 Determination Page 1 of 7
Case number: 476084 28 June 2018
1 Overview
1.1 Dispute
The financial services provider (FSP) accepted the applicants‟ claim for water
damage. However, a dispute arose regarding whether further mould remediation,
building repairs or accommodation was required.
A case manager provided the parties with a recommendation on the issues in
dispute. The recommendation was in favour of the applicant. A copy of the
recommendation is attached to this determination.
1.2 Issues and key findings
Were the findings of the recommendation correct?
The findings in the recommendation were correct and adopted in this determination.
Further submissions provided after the recommendation have been considered.
What is the FSP’s liability regarding the claim?
The FSP is liable to address the items set out in section 2.1. This includes additional
costs related to the building, temporary accommodation and contents.
Should the FSP pay compensation to the applicants?
The FSP should pay $3,000 in non-financial loss because the applicants suffered a
substantive degree of inconvenience, interference and delay.
The FSP should also reimburse the applicants‟ expert report fees. Any payment is
limited to $3,000 per report and the applicants providing invoices in support.
1.3 Determination
This determination is in favour of the applicants.
The FSP is to settle the applicants‟ insurance claim as set out in section 2.1
The FSP is to pay $3,000 in non-financial loss and re imburse the applicants‟ expert
reports costs. The latter is subject to a limit of $3,000 per report and the applicants
providing invoices in support.
Case No: 476084 Determination Page 2 of 7
2 Reasons for determination
2.1 Were the findings in the recommendation correct?
I have decided this case on its merits, having regard to the relevant law, good
industry practice, codes of practice and previous FOS decisions. I have taken into
account all the material submitted by the parties, both before and after the
recommendation. I am satisfied that the documentation I have relied on has been
provided to both parties.
I am satisfied that the case manager‟s recommendation contains an accurate
summary of the dispute, the issues to be determined, any applicable paragraphs of
the Terms of Reference and any relevant law.
2.2 What is the FSP’s liability regarding the claim ?
FSP’s reasons for rejecting the recommendation are not substantiated
The FSP rejected the recommendation. The FSP submits the applicants breached
the policy by not co-operating with its request to allow an engineer to inspect the
property regarding the concrete slab moisture issue.
The FSP provided no other submission challenging the case manager‟s reasons.
The FSP‟s position is not persuasive. This claim was lodged on 31 May 2016. The
applicants allowed access to numerous contractors throughout the claim and during
the dispute process. This included assessors, builders, contractors and a chemist.
According to the applicants‟ email dated 6 September 2017, this would have included
around 60 people over a 16 month period. The claim notes are relatively consistent
with this.
Further, the moisture issue to the slab was plainly an issue in dispute the FSP had
been aware of and addressed prior to the applicants lodging the matter with FOS.
Therefore, I accept the FSP had ample opportunity to investigate this issue and
assess its liability. The FSP chose to do so by relying on its position expressed in its
letter dated 23 March 2017 and the opinions it had at the time. The FSP maintained
this position for over four months before the case manager issued her
recommendation.
Given this background, I do not accept any refusal of the applicants to facilitate yet
another inspection following a recommendation adverse to the FSP breaches the
policy. This is because I do not accept the requirement to cooperate applies
indefinitely.
Instead, it is plainly meant to allow the FSP sufficient opportunity to investigate the
claim and determine its liability. Given the above, I am satisfied the applicants
complied with this provision given the amount of times they facilitated inspections
and the fact the FSP had ample opportunity to review this issue.
Therefore, I do not accept the FSP is entitled to deny the claim on this basis.
Case No: 476084 Determination Page 3 of 7
FSP’s liability extends to the concrete sl ab
The FSP says this issue was due to faulty design. This appears to be based on
builder BB‟s reports dated 8 and 10 March 2017. BB identified lack of sealant around
the second storey windows and said this “could” have been a water entry point. BB
also referred to a lack of weep holes in the brickwork.
I note BB does not specifically say these constitute a faulty design. Neither does BB
makes reference to any building standard or practice relevant at the time of
construction that was breached.
The applicant engaged a builder (PM) to review these points. PM concluded the
windows were properly installed. PM also said there are weep holes installed on the
base course.
In addition, PM noted that even if these were the cause of water entry to the slab,
then moisture readings would have increased. They did not.
Therefore, I do not accept the evidence shows the issues affecting the slab was from
faulty design. Instead, the evidence is consistent with water leaking down the walls to
the ground floor and settling under the flooring. This is consistent with a discussion
the FSP had with a technical assessor on 16 August 2016.
This falls within the policy coverage.
Further, I do not accept there is any merit to the suggestion that the applicants failed
to mitigate their losses. The concrete slab issue, and whether additional mould
remediation is required, needed consideration and investigation by the FSP. These
were completed by the FSP around 23 March 2016. Shortly after this, the applicants
arranged the additional repairs at their own cost.
FSP liable for the mould remediation costs incurred by the applicants
Regarding the mould remediation, I agree that MY‟s evidence is to be preferred. MY
plainly specialises in this area. Whilst ZY does have specialised knowledge to
provide an opinion, it would not appear to match MY.
MY conducted extensive testing around the home and expressed concerns about its
condition. MY referred to an “Australian Mould Guideline” to support their position.
ZY noted this was publi shed by MY. ZY said that under Western Australia‟s
Department of Health guidelines for managing mould and damp related areas, they
say:
“Currently there are no quantitative or qualitative exposure limits … to declare that a premise is
unfit for habitation. Current evidence suggests that the presence any mould or dampness can pose a
health risk, although the level of that risk cannot be quantified.”
MY did discover mould in the home and concluded that additional remediation is
required. The fact her investigation did not identify any specific guideline or law being
breached does not mean her opinion should be dismissed. Particularly when there is
no specific standard applicable and the current guideline notes any presence can
pose a health risk.
Case No: 476084 Determination Page 4 of 7
In such a con text, I accept MY‟s conclusion was logical and consistent with the
available evidence.
Therefore, I accept the FSP is liable for the costs of mould remediation incurred by
the applicants.
FSP is required to pay additional items towards the building claim
Following the recommendation, the applicants provided a number of emails setting
out the costs incurred and extent of losses the FSP should consider. This included:
the cost of mould remediation and drying of concrete totaling $32,780
MY‟s costs for providi ng the mould remediation scope of works and clearance
testing
items deemed non-restorable by the contractor (AW) who conducted the mould
remediation – part of these were set out in an email from the male applicant to
AW dated 11 August 2017 – according to AW, this required 25 bags
non-restorable contents totaling $54,498.57 – this includes the porous items
deemed non-restorable by AW
extra carpet that required disposal and replacement
additional painting costs
other items not addressed by the recommendatio n – this included the stained
toilet, reinstallation of a pantry door, hall stand and skip.
I will address temporary accommodation and contents (excluding carpets) later.
For the building repairs, the FSP allowed $31,405.55. This was based on BB‟s
quotations dated 12 June, 28 September and 8 December 2016. The last quotation
set out the cost of works completed by BB that were included in the two earlier
quotations. Therefore, this amount was deducted from the sum of the two earlier
quotes to arrive at the cash settlement figure.
The applicants have not disputed the amount allowed for the scope of works is
reasonable. However, they say the items set out above should also be paid as they
were not included in the FSP‟s settlement.
Having carefully considered t he available information, I agree with the applicants‟
position regarding the following items:
Item Reasons
Stained toilet Applicants say this was stained from the burst pipe and
remained unrepaired – FSP has not addressed this .
I am satisfied the FSP is liable for this item .
Applicants say their plumber quoted $580 for this item – this
appears reasonable .
Pantry door removed by BB Applicants say this needed to be reinstalled as BB had
removed it .
FSP does not disput e th is was removed.
The cost of reinst alling this does not appear to be allowed in
BB‟s quotes .
The FSP is liable for this item .
Case No: 476084 Determination Page 5 of 7
Applicants seek $200 – this appears reasonable .
Painting and fixing of chips to
walls
FSP allowed $589.05 in its letter dated 23/3/17 .
Applicants noted BB quoted $2,757.70 to repair this .
Applicants‟ position is preferred – it is based on BB‟s
quotation whereas the FSP‟s amount is based on an
estimate unsupported by a cont ractor .
Skip bin This was deducted in BB‟s quot e dated 8/12/16 – applicants
say this is still required for the building works .
FSP has not addressed this – applicants‟ position is
reasonable .
Applicants seeking $816 based on BB‟s quote – this is
reasonable .
Regarding other costs incurred by the applicants that were not covered by the FSP‟s
quotations, the FSP is liable for same. This would include:
additional carpets replaced
extra painting
MY‟s costs for providing the mould remediation scope of works and clearance
certificate
any other costs associated with repairing the home.
The applicants are to provide all invoices in support. This is to enable the FSP to
calculate the amount payable when taking into consideration the cash settlement
paid and any possible duplication.
Further, any amount payable by the FSP is subject to interest pursuant to section 57
of the Insurance Contracts Act 1984 (the Act). Interest is payable from when the
costs were incurred by the applicants to when the FSP issues payment.
Temporary accommodation for the applicants’ family and their pets
The applicants did not accept the case manager‟s recommendation that the FSP‟s
liability for temporary accommodation is limited to the costs they incurred.
Instead, the applicants are seeking $36,750 for temporary accommodation. This is to
cover a period of 15 weeks beginning from 1 April and ending on 27 July 2017. The
amount of $2,450 per week is based on the fact the FSP agreed to pay the following
weekly rates during the claim:
$1,800 per week for the applicants‟ family
$350 per week for their pets.
I do not accept the applicants‟ position.
The applicants are entitled to the expenses they incurred in arranging
accommodation for themselves and their pets during the above period. I do not
accept it is appropriate, or fair in all the circumstances, the FSP pay an amount
based on what it paid previously. Particularly if the amount awarded would exceed
the applicants‟ actual expenditure.
Case No: 476084 Determination Page 6 of 7
This is consistent with the fact that if the situation was reversed, and the applicants‟
reasonable expenditure exceeded the amount previously paid by the FSP, then the
FSP would not be able to limit its liability.
Therefore, I accept the FSP is only required to pay for the temporary accommodation
costs incurred by the applicants subject to invoices being provided in suppor t. This
would include their pets‟ accommodation both during this time and the four weeks
period being claimed whilst the buildings works were conducted by the FSP.
The FSP is also to pay interest on any amount payable pursuant to section 57 of the
Act. Interest is payable from when the costs were incurred to when payment is
issued.
Applicants entitled to the contents claimed in their email of 15 September 2017
The applicants provided FOS a copy of an email sent to the FSP dated 15
September 2017. This set out all of the contents items affected by this claim. This is
extensive and totalled $54,498.57.
In this email, the applicants offered the FSP the opportunity to assess all of the items
in the next seven days, following which they proposed to dispose of the items.
Correspondence was exchanged between the parties subsequent to this. This
included the facilitation of the contents being assessed. However, by 8 December
2017, the FSP sent an email to the applicants saying:
it maintained its position to decline the claim on the basis the applicants failed to
co-operate
the contents will not be assessed as the claim was being denied
Given the above, I accept the applicants gave the FSP ample opportunity to review
the contents. The FSP‟s email to the applicants o n 8 December 2017 shows that it
declined to do so. The FSP did so in circumstances when its position to deny the
claim was far from certain.
The applicants‟ position regarding the contents is supported by AW. Further, there is
nothing to refute that the items set out in their list were affected by the claim and are
non-restorable. Therefore, I accept the FSP is liable to pay for the cost of replacing
those items subject to:
the applicants providing reasonable proof value and, where appropriate,
ownership
allowing for any deductions on items already paid for by the FSP.
Once a figure is settled, the FSP should also pay interest on that sum. Interest is
payable from 13 October 2017 until payment is made. I have nominated 13 October
2017 on the basis that it is reasonable to expect the FSP would need about four
weeks to assess the items following the applicants‟ email and issuing payment.
Case No: 476084 Determination Page 7 of 7
2.3 Are the applicants entitled to compensation?
FSP should pay $3,000 in non-financial loss
FOS may decide an FSP should compe nsate an applicant where there has been an
unusual amount of physical inconvenience, time taken to resolve a situation, or
interference with the applicant‟s expectation of enjoyment or peace of mind.
I accept this is the case here given by the following:
mould became an issue due to the FSP‟s contractors failing to use a
dehumidifier – this was expressly acknowledged by the FSP in its email to the
applicants dated 30 August 2016
the extent of mould remediation required was not addressed by the FSP and
had to be managed by the applicants
the existence of mould required the applicants and their young children to move
multiple times – the applicants say they had do this around 16 times
the applicants had to arrange their own temporary accommodation when the
FSP refused to accept MY‟s opinion
the protracted nature of the claim – the claim was lodged on 31 May 2016 and
repairs were not completed over a year later
the FSP deciding to recently deny the claim due to an assertion that the
applicant were not cooperating when there was little basis to do so
These inconveniences would have been significant. Particularly the existence of
mould, the amount of times the applicants and their young children had to move and
the claim timeframe.
Therefore, I consider it fair in all the circumstances that the maximum amount of
$3,000 in non-financial loss be awarded.
Expert report costs should be reimbursed up to $3,000 per report
The applicants have also sought the costs of their expert reports.
Pursuant to paragraph 9.4 of the FOS Terms of Reference, FOS may require an FSP
to contribute to the professional costs incurred by an applicant in the course of their
dispute. FOS will not require the FSP to pay more than $3,000 for a report unless
exceptional circumstances apply.
Th e applicants‟ experts assisted them in substantiating their position regarding the
mould and concrete slab. Therefore, the FSP is required to reimburse the costs of
these reports subject to the applicants providing invoices.
I do not accept exceptional circumstances apply. Whilst I accept the issues required
the assistance of experts, the nature of the issues were not of such a complex nature
that obtaining a report would exceed $3,000. The issues were limited to whether a
home required additional mould remediation and the source of water damage to the
concrete slab.
Therefore, the FSP is not required to pay more than $3,000 for any report.
Recommendation
Case No: 476084 Recommendation Page 1 of 7
Case number: 476084 31 July 2017
3 Overview
3.1 Dispute
After t he financial service provider (FSP) accepted the applicants‟ claim for water
damage, it arranged remediation works and paid for temporary accommodation. It is
not in dispute the FSP‟s works caused mould damage. The parties however disagree
as to whether the FSP is liable for further mould remediation and accommodation.
Additionally, the applicants say the FSP incorrectly denied cover to repair damage to
the property‟s concrete slab.
3.2 Issues and key findings
Is FSP liable for further remediation costs?
Both parties have provided conflicting expert opinions on the need for mould
remediation. On balance, I pr efer the applicants‟ mycology report, because:
I find the applicant‟s expert is suitably qualified
the FSP‟s response to the applicant‟s report is insufficient.
The applicants‟ expert recommended further mould remediation. Given its view is
preferred, it follows the FSP is liable to pay for further mould remediation works.
Additionally, the FSP is also liable for accommodation costs incurred prior to the
specified works.
Is the FSP’s building settlement offer fair and reasonable?
The FSP did not include concrete slab repair costs, because it did not consider an
insured event caused the damage.
However, I find the available information establishes settled water from the insured
event was the proximate cause of damage. Given this, the settlement sum must be
increased to include repairs to the concrete slab.
3.3 Recommendation
This recommendation is in favour of the applicants.
If both parties accept the recommendation, each party is required to undertake the
steps outlined within Section 2.
Case No: 476084 Recommendation Page 2 of 7
4 Reasons for recommendation
4.1 Is FSP liable for further remediation costs?
Parties agree FSP liable for mould remediation
The water leak occurred on 31 May 2016. The applicants notified the FSP of
concerns about remediation methods and subsequent mould growth on 8 June 2016.
There is no dispute the mould arose following the FSP‟s inadequate water drying.
The FSP carried out mould remediation works in February 2017.
The parties remain in dispute as to whether reasonable mould remediation works
have been completed. The applicants say that to mitigate further loss, they have now
arranged for contractors to remediate mould and assert the FSP should cover these
costs.
Conflicting reports as to whether adequate mould remediation has occurred
All available mould tests state remediation is required. The applicant arranged for
swab and air testing by mycologist MY, whose report of August 2016 confirmed the
presence of mould and outlined:
test and analysis methods
potential health effects
the scope and methods for recommended remediation works.
The FSP arranged for swab testing by forensic materials scientists ZY in July 2016
and after remediation works in February 2017. Both reports confirmed the presence
of mould and recommended remediation. They did not contain a method or scope for
these works.
In March 2017, the FSP advised the applicants the property was habitable and it had
decided to cash settle the claim, including $3,000 for the applicant to arrange mould
clearance testing. The applicants disputed the mould remediation works were
adequate.
Given this, the applicants arranged for MY to complete a clearance test report in May
2017. This report stated the same remediation works were needed as recommended
in the August 2016 report, and contained the following observations:
- it appears no structural drying was performed
- kitchen/living area still shows elevated levels of mould spores
- it is not clear if any cleaning of [contents] had been performed
- still a very musty odour was noticed.
The applicants maintained their request the FSP carry out the remediation works
recommended in MY‟s reports. The FSP declined and in May 2017 arranged for ZY
to complete a review of MY‟s clearance test report.
ZY‟s review of MY‟s test refutes the conclusion the property has mould contamination
to an extent requiring further remediation. In reaching this conclusion, the review
report relies upon:
MY‟s swab tests returning „low‟ fungal concentration results
Case No: 476084 Recommendation Page 3 of 7
MY‟s air tests showing lower fungal concentrations in the activity room compared
with outside
the absence of state government issued exposure limits for unsafe mould levels
the assertion there is no evidence to classify the house as uninhabitable or a
health hazard to normal occupants
the lack of a university qualification for mycology.
On balance, t he applicant’s expert is preferred
I have closely considered all the mould test reports and ZY‟s review of the clearance
test. I accept ZY‟s observation that „one cannot expect the indoor quality to be any
better‟ than the outdoors .
However, I note the clearance test returned fungal concentrations markedly lower in
concentration in the activity room than the living/kitchen location. I am therefore
unable to accept ZY‟s conclusions that, as the activity room (and therefore indoor
average overall) showed lower fungal concentration than outdoors, the contents of
MY‟s clearance test „do not present a „proper assessment of the data‟ .
I am not persuaded by ZY‟s suggestions that a mycologist‟s assessments lack
plausibility due to an absence of:
state government thresholds outlining mould safety limits
university courses titled „mycology‟.
Additionally, the FSP accepted MY‟s opinion earlier in the claim. It is therefore
unclear why it now challenges the validity of MY‟s qualifications (as indicated by the
later bullet point above).
On balance, I am of the view that MY‟s reports are to be preferred. I am satisfied
these reports establish sufficient doubts about the conclusions reached in ZY‟s
reports.
The FSP liable for further remediation costs
In MY‟s May 2017 re port, it outlined the steps required to remediate the mould. The
applicants informed FOS on 27 July 2017, that a contractor has completed those
remediation steps.
As outlined above, MY‟s opinion and conclusions are to be preferred. It follows
therefore that the FSP is liable to either:
pay the contractor directly (upon receipt of the quote/invoice from the applicants),
or
reimburse the applicants for the costs they paid to the contractor (upon receipt of
the paid invoice from the applicants).
Either way, the FSP is to take this action within seven days from when it is in receipt
of the quote/invoice.
Additionally, the FSP said in its letter dated 23 March 2017 to the applicants that it
would pay $3,000 for „final testing‟. Irrespective of whether the parti es agree to this
recommendation, the FSP should make the $3,000 payment within seven days of
this recommendation (if the FSP is yet to do so).
Case No: 476084 Recommendation Page 4 of 7
FSP to reimburse applicants for incurred accommodation costs
It is not in dispute that the FSP has paid the appli cants‟ temporary accommodation
costs until 31 March 2017. The FSP has however not paid past this date as it
considers the property habitable.
However for the reasons set out above, I do not consider the property is habitable
until the mould remediation occurs. As this did not occur until 27 July 2017, the FSP
is liable for the accommodation costs incurred by the applicants during the period 1
April 2017 to 27 July 2017.
The applicants are to furnish the FSP with the accommodation costs they are
seeking reimbursement for. For clarity, these costs will include any costs incurred in
accommodating the applicant‟s pets during the above mentioned period.
The FSP is to reimburse the applicant within seven days of receiving the paid
invoices.
4.2 Is the FSP’s buildin g settlement offer fair and reasonable?
FSP’s building settlement excludes slab damage
On 23 March 2017 the FSP offered the following building cash settlement:
$31,405.55 for floor removal repairs
$220 for dust cleaning in an upstairs bedroom
$589.05 for repairs to chipping to the walls (caused by contractors).
The applicants have indicated they are willing to accept cash settlement of the
building repairs. However, they dispute the sum offered and seek inclusion of repairs
to the property‟s foundational c oncrete slab. They say that to mitigate further loss,
they have now arranged for contractors to repair the slab. They argue the FSP
should cover these costs.
FSP bears onus to show damage not caused by insured event
The parties do not dispute the applicants have established a prima facie claim for
damage to the concrete slab. It is established insurance law that the FSP now bears
the onus of showing, on the balance of probabilities, the policy excludes the claimed
loss or it is otherwise not covered.
The FSP asserts water from the insured event did not cause the damage. Rather the
FSP says the damage occurred by a separate window leak, and the said leak
occurred due to faulty house design. In particular, the FSP says:
the absence of window sealants, which they say caused a separate leak
the building lacks weepholes, causing water to travel down on to the slab.
The FSP says the policy does not respond where faulty house design causes the
damage.
It is therefore necessary to determine whether the FSP has shown, on the balance of
probabilities, the alleged faulty house design was the proximate cause of the
damage.
Case No: 476084 Recommendation Page 5 of 7
The proximate cause is the effective, dominant or operative cause of the damage.
Where there are several causes of a claimed loss identified in a dispute, FOS
considers each cause to determine the active, predominant cause which set the
chain of events in motion leading to the loss.
Conflicting reports on cause of slab damage
The parties do not dispute water from the insured event leaked down walls to the
ground floor and then settled under the flooring and onto the concrete slab. The
FSP‟s technical assessor (MM) noted in August 2016 that „water was trapped under
the flooring all this time‟ and that it „should have been pulled up‟ during water damage
remediation.
Repairs were subsequently delayed by disputes over mould remediation. MM
subsequently advised the applicants in January 2017 that the concrete slab was still
wet like ly due to a leak from upstairs and not from the insured event. The applicants‟
appointed a building practitioner (PM) to assess the damage. PM concludes the
damage occurred due to the insured event.
The parties‟ expert reports are summarised in Section 3.1.
Available information supports proximate cause of damage to slab
I have closely considered all the material both parties have provided in support of
their positions. The FSP‟s building and plumbing expert state water „could have‟
entered by a window, and that water travelling through the brickworks‟ cavities was
„causing the additional dampness‟. I am not satisfied these comments establish, on
the balance of probabilities, that either a window leak and/or faulty design were
proximate causes of water sitting on the slab.
Instead, the contemporaneous comments made by the FSP‟s technical assessor
persuade me. These comments say water sat undried from the insured event on the
concrete slab. Comments subsequently made by the applicant‟s building expert (PM)
support this view. Additionally, PM states onsite testing and applicable building codes
refute the FSP‟s position that design defects and window leaks were present.
Considering all available material, I am satisfied the proximate cause of damage to
the concrete slab was the insured event.
FSP’s settlement offer not fair o r reasonable in the circumstances
For the above reasons, the FSP has not established it is entitled to decline cover for
damage to the concrete slab. As its settlement sum does not include any amount for
repairs, I cannot accept this offer is fair and reasonable in the circumstances.
Material received from the FSP asserts an insured is responsible for mitigating their
loss, which I accept. However, I am unable to accept the FSP‟s suggestions the
applicants failed to mitigate their losses, given I am satisfied that:
concrete slab repairs/settlement were unreasonably declined
building repairs were necessarily delayed by mould remediation disputes.
Case No: 476084 Recommendation Page 6 of 7
To the contrary, the information persuades me the applicants proactively took steps
to mitigate damage to their property. These steps include putting the FSP on notice
of potential mould damage and the applicants‟ health concerns, and arranging expert
reports.
FSP required to include concrete slab damage in settlement
For the above reasons, the FSP is not entitled to deny its liability for the concrete
slabs repairs. The applicants have already undertaken said repairs.
In this circumstance, the applicants are to provide the quote/invoice to the FSP for its
consideration. The FSP in turn is required to settle the repairs, pursuant to the terms
and conditions of the policy.
Case No: 476084 Recommendation Page 7 of 7
5 Supporting information
5.1 Parties’ expert reports
Expert Report comments
FSP’s plumbing expert (BP)
08 - 03 - 2017
window could be an entry point of water
FSP’s building expert (BB)
10 - 03 - 17
damage is result of rain water entering cavity via the front
window and seeping ont o slab , causing the additional
dampness
no silicon seal on window, this could cause leak
Applicant’s building expert (PM)
13 - 03 - 2017
slab‟s wetness is consistent with flooded rooms still drying
window is not leaking
wall slightly moist due to absorption from saturated slab
PM’s second report
23 - 05 - 2017
window still not leaking
dust in the cavity undisturbed by running/ dripping water
cavity clean and dry
no evidence moisture enters via windows/ brickwork
silicon seal between window and brick not required as
installation tight and correct under building codes
weep hole installation complies with building codes