Text of the determination
Determination
Case No: 473964 Determination Page 1 of 8
Case number: 473964 31 October 2017
1 Overview
1.1 Dispute
The applicant has lodged the dispute on behalf of a partnership which engaged in
farming in Far North Queensland. The partnership held several business accounts
with the Financial Services Provider (FSP).
The dispute is about how the FSP responded to the partnership ’s financial difficulty
and its decision to increase the interest rates or charge excess rates on those
facilities. The difficulty arose as a result of factors including adverse weather and
natural disasters. The applicant says the FSP’s conduct caused the business to
ultimately fail.
The applicant also raised issues that I am unable to consider, pursuant to the FOS
terms of reference, as the partnership was aware of the claims more than six years
prior to the dispute being lodged. I have outlined in greater detail why I cannot
consider these issues in section 3.2 of this determination.
1.2 Issues and key findings
Did the FSP breach its financial difficulty obligations?
The FSP was on notice of the partnership’s financial difficulty following Cyclone Yasi
and provided a three month moratorium on repayments. Following this, the FSP
supported the business with temporary and formalised overdraft limit increases as
well as tolerating informal excesses. In doing so, it met its hardship obligations to the
partnership. The FSP’s response also met the standards of good industry practice.
The FSP was under no obligation to reduce the interest rate in response to the
partnership’s financial difficulty. During the period I have the jurisdiction to review,
any increases in the interest rate occurred as a result of the underlying variable
reference rate changes and the excess rate charges were allowed. Based on all the
available information, the FSP charged interest in accordance with the terms and
conditions of the facilities.
1.3 Determination
This determination is in favour of the FSP. No compensation is payable.
Case No: 473964 Determination Page 2 of 8
2 Reasons for determination
2.1 Did the FSP meet its financial difficulty obligations
The partnership was engaged in farming
The applicant’s partnership (the business), was formed by family members to carry
on farming activities in Far North Queensland. The principal farming activity was
sugar cane which was supplemented with other crop strategies.
Due to a number of factors, one of which being adverse farming activities following
cyclone conditions in 2006, the business experienced cash flow difficulties over
several years.
The FSP provided the following facilities to the business:
A long term Agriculture Finance loan
An overdraft for working capital requirements, with a credit limit that varied on a
seasonal basis.
Facility Amount approved August 2010 Amount approved September 2011
Agri Finance $1,473,539.57 $1,519,479.61
Overdraft $45,000 / $25,000 (seasonally - varied). $150,000 / $105,000 (seasonally - varied)
In January 2011, the FSP increased the customer margin on the interest rate to
reflect its increased lending risk. In February 2011, Cyclone Yasi decimated crop,
farm buildings and equipment that further impacted on the ability of the business to
meet its finance and trading obligations.
The business refinanced both facilities with another lender in March 2012.
The FSP has obligations to work with borrowers experiencing difficulty
Under the code of banking practice, the FSP has obligations to work with borrowers
experiencing financial difficulty. The obligation is not unlimited – a financial services
provider is not required to agree to all requests for assistance or provide assistance
indefinitely.
To meet its obligations, a financial services provider should take steps to understand
the borrower’s circumstances, consider any proposal as well as any reasonable
alternatives and make a decision on what if any assistance is appropriate having
regard to legitimate considerations.
Generally, assistance will be provided by varying the terms of when repayments are
required (e.g. providing a repayment moratorium, extending the term of the loan to
reduce repayments) or providing solutions to deal with arrears (e.g. arrears
capitalisation, repayment arrangements). A lender is under no obligation to vary
interest rates or waive debt where a borrower is experiencing difficulty.
Case No: 473964 Determination Page 3 of 8
If a business is unable to demonstrate its ongoing viability, I would not expect a
financial services provider to accept further risk. In such circumstances, assistance
may take the form of providing the busi ness with a reasonable time to refinance or
working with the business to achieve an orderly winding -up of assets.
The FSP met its financial difficulty obligations
I have reviewed all the material provided by the parties to form a view on whether the
FSP met its financial difficulty obligations.
To assist in my consideration of how the FSP responded to the business’ hardship , I
have also obtained advice from the FOS Banking Specialist (the specialist) on
whether the FSP’s conduct was in line with good indus try practice of how a lender
should work to assist primary-producers experiencing difficulty as a result of a natural
disaster. The specialist has had extensive experience in the banking and financial
services industry, and regularly provides FOS with advice about banking and
financial services practice and procedure, and what constitutes good industry
practice.
I have outlined in section 3.3 below a chronology of the assistance provided by the
FSP. In my view, the FSP met its financial difficulty obligations by providing timely
and ongoing disaster relief assistance. In particular, the FSP:
provided an initial three month repayment moratorium in 2011 to assist the
partnership with the immediate impact of Cyclone Yasi
continued to support the business over the following year with informal,
temporary and formalised limit increases to the Overdraft, based on continued
viability of farming enterprise and/or receipt of monies from third party insurance
companies
had regard to the circumstances of the business in considering whether and
how to assist the business and
refrained from taking any enforcement or recovery action in circumstances
where the facilities would have been in default. It instead provided the
accommodations noted above.
The specialist has also reviewed the FSP’s conduct and formed the view that the
FSP did not act contrary to good agri-business practice in the banking industry. The
specialist provided analysis and opinion which I accept and summarise below:
The information provided by the FSP shows that the cash flow strain that the
business was under had been evident throughout 2009/2010 and was not
abating in early 2011 prior to Cyclone Yasi, which further compounding the
trading position. The 2010 management accounts provided in February 2011
did little to reduce the FSP’s concerns
On 1 June 2011, the business completed an extensive business plan in which it
detailed the family’s history in the region (dating back to early 1900s), its cur rent
situation due to Cyclone Yasi, the impact of Cyclone Yasi on the industry and its
forecasts and projected trading out to July 2012. The planned strategy for debt
repayment included more favourable trading conditions returning better net
profit before tax and asset sales
Case No: 473964 Determination Page 4 of 8
The FSP responded appropriately to the circumstances created by Cyclone
Yasi by providing short term assistance and was tolerant of regular account
excesses thereafter. However, seven months later, in September 2011, it was
appropriate to critically review the ongoing viability of the Business and in
particular its strategy to reduce its debt exposure
The immediate working requirements for the business involved the ratification of
an overdraft credit limit of $150,000, which was to be cleared from anticipated
and overdue insurance payouts in the vicinity of $200,000. In September 2011,
the FSP approved the new Overdraft limit and continuance of the Agriculture
Finance loan term. It did not increase the credit risk margin beyond that advised
in January 2011.
The specialist does not consider that the FSP acted contrary to good agri-
business practice in reviewing the affected farming operation after the period of
providing disaster relief assistance in and from 2011. The FSP acted prudently
and diligently in its relationship dealings with the business. It was continuing to
provide support when the business chose to refinance.
Based upon my review of the FSP’s response to the business’ hardship and taking
into account the opinion of the specialist, I consider that the FSP met its financial
difficulty obligations to the partnership and acted in a manner consistent with good
industry practice.
The FSP did not make an error when implementing the moratorium
The applicant says that the FSP made an error by not placing the repayments
deferred under the moratorium to the end of the loan. The applicants say that instead
the FSP took a double repayment at the end of the moratorium in 2011.
The repayment moratorium granted by the FSP, as detailed in its letter of 11
February 2011, provided for the January, February and March 2011 repayments due
on the Agriculture Finance loan to be deferred until 2040 and the loan extended by
three months to accommodate this deferral. As per the letter, repayments were
required to recommence on 20 April 2011. The required monthly repayment was
$11,845.90.
As at the date of the FSP’s letter, the business had not made the repayment due on
20 January 2011, and this along with the next two repayments were deferred as per
the FSP ’s assistance package. On 15 February 2011, the business made a
repayment of $1,241.05 to clear existing non-deferred arrears. This repayment was
made from overdraft funds and the business agreed to this repayment being made as
part of another assistance measure that temporarily increased the overdraft limit from
$45,000 to $85,000.
The business did not resume repayments as required on 20 April 2011 – instead the
next repayment was made on 20 May 2011. The FSP assigned this repayment to the
repayment due on 20 April 2011, which meant that the May 2011 repayment
remained outstanding. The double repayment in June 2011 brought the account back
in order.
Although in some cases is may be inappropriate for a financial services provider to
take a double repayment from a borrower experiencing financial difficulty, in this case
Case No: 473964 Determination Page 5 of 8
the double repayment came from the Overdraft account resulting in a nil net change
in the business’ overall debt.
The repayment being made from overdraft funds is consistent with how the FSP
chose to support the business following the end of the three month moratorium,
being further overdraft accommodation as opposed to further moratoria on the
Agriculture Finance loan. The FSP was entitled to provide its assistance in this
manner and did not breach any specific obligation by virtue of taking the double
payment in June 2011.
The FSP was under no obligation to reduce the interest rate
The applicant disputes the FSP’s decision to increase the interest rate in January
2011 and at later dates while the applicant was experiencing difficulty. As outlined in
section 3.2 of this determination below, I am unable to consider a dispute about the
January 2011 increase as the claim was known more than six years prior to the FOS
dispute being lodged.
Under the facility contract, the interest rate payable was expressed as being the
Business Mortgage Index – a variable reference rate – plus or minus a customer
margin. The January 2011 increase was a variation of the customer margin, causing
an effective increase of 2.11 percent per annum on each facility. Although the
interest rate changed at later dates as the applicant has pointed to, these later
changes were due to variations in the underlying Business Mortgage Index rate and
were not customer-specific variations – i.e. changes to the customer margin.
Where a loan is a variable rate loan, a financial services provider is entitled to charge
interest as it varies, even where a borrower is experiencing financial difficulty. There
is no obligation to fix a variable rate or refrain from passing on an increase of the
reference rate in these circumstances. A financial services provider is also under no
obligation to reduce the interest rate it is charging to assist a borrower who is
experiencing difficulty. It follows that the FSP did not breach an obligation it owed the
borrower in these regards, during the period I have the jurisdiction to review (14
March 2011 onwards).
The applicant also disputed excess interest charged on the Overdraft. The FSP
charged a higher rate for borrowings above the overdraft limit. This was not a default
rate, but a different rate for excess borrowi ngs accommodated in an informal
overdraft facility. Pursuant to the Overdraft contract, the FSP was entitled to charge
this higher excess rate. Although the FSP was entitled to charge this higher rate, by
providing temporary and formalised overdraft limit increases throughout 2011 and
2012, the FSP’s assistance went some way to reduce the excess interest burden on
the business. This is in line with the FSP having provided the business with
appropriate assistance.
Case No: 473964 Determination Page 6 of 8
3 Supporting information
3.1 Decision basis and process
All parties have had a reasonable opportunity to provide submissions to FOS about
the issues in dispute and respond to the submissions put forward by the other party.
I have considered all the material submitted by the parties in order to reach my
decision. I am satisfied that the material I relied upon in reaching my findings has
been exchanged between the parties.
I have determined this dispute on the basis of what I consider is fair in all the
circumstances. I had regard to legal principles, applicable industry codes or guidance
as to practice, good industry practice and previous relevant decisions of FOS or its
predecessors.
3.2 Matters that fall outside the FOS terms of reference
I cannot consider issues relating to the FSP’s refinance of the QRAA loan
The applicant says that the FSP lent irresponsibly or inappropriately when it required
an existing QRAA loan to be refinanced into the FSP’s lending in late 2009. The
applicant says that the FSP’s refinancing of the QRAA loan was irresponsible or
inappropriate as it was on worse terms, being that the QRAA loan was interest free
whereas the FSP charged interest for this portion of the lending. I understand that the
FSP required the QRAA lending to be repaid to accommodate its security
requirements.
The applicant lodged the FOS dispute on 14 March 2017. The loan that required the
discharge of QRAA securities at settlement was approved by the FSP on 31
December 2009 and the elements of the claim were known to the partnership at that
time. As this claim for loss occurred more than six years prior to the dispute
lodgement, pursuant to the FOS terms of reference, I am unable to consider a
dispute about the lending decision.
I cannot consider the FSP’s interest rates increase of January 2011
The applicant disputes the FSP’s entitlement to increase the interest rate under the
contract during difficult times including January 2011.
The FSP by letter dated 5 January 2011, notified the partnership that due to the
increased credit risk of providing the business with funding, the interest rates on the
facilities would increase. The interest rates before and after 5 January 2011 are
shown in the following table:
Facility Previ ous interest rate Subsequent interest rate
Agri culture
Finance facility
Business Mortgage Index (BMI) minus
customer margin of 0.63% pa
BMI plus customer margin of
1.48% pa
Case No: 473964 Determination Page 7 of 8
Overdraft Business Mortgage Index (BMI) minus
customer margin of 0.48% pa
BMI plus customer margin of
1.63% pa
As noted in the table, the interest rate on each facility increased by 2.11 percentage
points by way of a variation of the customer margin.
The interest rate increases were communicated and implemented more than six
years prior to the FOS dispute being lodged. The partnership was aware of the
elements of the claim over six years prior to lodging the dispute. Accordingly,
pursuant to FOS terms of reference I am unable to consider whether the FSP were
entitled to increase the customer margin at that time.
I do note however that a financial services provider is generally entitled to vary the
customer margin to price in risk in the context of business lending.
3.3 Review of internal diary notes – Chronology of assistance
Date Rele vant event
1 February 2011 (two days prior to
Cyclone Yasi impacting the area)
T he b usiness’ relationship manager in a report to his credit team
noted that:
the Overdraft and the Agri culture Finance loan were in arrears
o ne of the partner’s consumer home loans had been in arrears
for 103 days
these matters would be addressed in the review due 31 March
2011 when the impact of Yasi would also be addressed .
3 February 2011 Cyclone Yasi impacts the area
10 February 2011 The FSP approved a temporary overdraft limit of $60, 000
(+$15, 000) with review by 31 March pending meeting and setting
of appropriate l imits under flood package.
14 February 2011 The FSP noted deferral of 3 months repayments on Agri
business term facility (part of Disaster relief package) wit h next
scheduled repayment due May 2011.
15 February 2011 After meeting between the FSP and the business, the FSP
agreed to increase the formal limit of $45,000 to $80, 000 for 3
months under flood relief assistance package.
May 2011 T he overdraft limit reverted to $45,000 (Dr >$80,000) but the
FSP noted that it would agree to cover up to maximum $105,000
pending receipt of insurance claims of $200,000 that were yet to
be received.
June 2011 Limit $45,000 Dr$93,557 – FSP approved temporary overdraft
limi t of $115,000 for 30 days as the b usiness was still awaiting
i nsurance claims (disput e lodged with FOS re ins urance delays).
August 2011 FSP approves overdraft of $150,000 until 1/12/11 pending
insurance claims.
Case No: 473964 Determination Page 8 of 8
14 September 2011 commentary from meeting : 80% of cane crop cut...return cane
looking healthy…Letter of Offer discussed…customers have
signed LOO
25 November 2011 Local shire copy FSP in on Notice of Intention to Sell Land
regarding land securing the FSP’s lending for rates and interest
outstand ing over 3 years and amounting to $51,111. The failure
to pay the monies owed to the shire council would represent a
default under the FSP’s mortgage documents.
19 December 2011 FSP grants extension to OD limit of $150,000 until 31 December
2011. Business preparing updated cash flows to determine future
needs .
5 January 2012 Overdraft balance $136, 860 Dr, Limit nil (expired 31/12) . FSP
reluctantly agrees to extend OD limit to 31 Jan 12.
27 February 2012 FSP received discharge instructions regarding pending refinance
to OFI
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.