The applicants claimed a rebuild for floor damage they attributed to a burst pipe, and the FSP denied most of it as caused by condensation and poor sub-floor ventilation while offering a cash settlement. AFCA found most damage excluded but ordered the settlement increased to $33,678.85 with interest and $1,000 for non-financial loss.

The expert engineer's second report gave a logical cause for the damage, which was excluded under the policy, but the FSP had to pay the reasonable settlement plus mould costs and interest for poor claim handling.

Issues

Subjects and remedies

home or building damagepay claimpay interestpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 473168 Determination Page 1 of 8 Case number: 473168 31 January 2018 1 Overview 1.1 Dispute The applicants lodged a claim under their home insurance policy with the financial services provider (FSP), after they noticed the toilet and bathroom floors at their property were sinking. The applicants advised the damage had been caused by a burst pipe which had been discovered and repaired several years earlier. After assessing the damage to the property, the FSP accepted the applicants’ claim and appointed its contractors to conduct remediation works. However, the FSP stopped work after its contractors identified extensive mould and rot at the property. The FSP says it is not liable for the applicants’ claim because the damage was not caused by the leaking pipe, but by condensation and inadequate sub-floor ventilation (which are excluded from cover under the policy). However, the FSP has offered to cash settle for the applicants for $31,516.23, being the cost of repairing the damage for which it had previously accepted liability, together with an allowance for temporary accommodation. The applicants dispute the FSP’s decision and say all of the damage to their property was caused by the leaking pipe. The applicants are also dissatisfied with how the FSP has handled their claim. 1.2 Issues and key findings Is the FSP liable for the disputed damage? The available information establishes that the disputed damage to the applicants ’ property was not caused by the leaking pipe but by naturally occurring atmospheric conditions exacerbated by the lack of sub-floor ventilation. Damage caused in this manner is not covered under the policy. Accordingly, the FSP is not liable for the applicants ’ claim. Is the FSP’s cash settlement offer fair and reasonable ? The FSP’s cash settlement offer is generally fair and reasonable. However, the cash settlement amount should be increased by $500 to reflect the agreed contribution to mould remediation. The FSP should also pay interest on the settlement amount. Case No: 473168 Determination Page 2 of 8 Are the applicants entitled to compensation? The applicants are entitled to additional compensation of $1,000 for non-financial loss, due to the manner in which the FSP handled their claim. 1.3 Determination This determination is substantially in favour of the FSP. The cash settlement amount offered is generally fair and reasonable. However, the FSP is required to:  increase the settlement amount to $33,678.85 (less excess), to reflect its agreed contribution to the cost of mould remediation  pay interest on the entire cash settlement amount as set out in section 2.2 below  pay the applicants an additional amount of $1,000 as compensation for non- financial loss. Case No: 473168 Determination Page 3 of 8 2 Reasons for determination 2.1 Is the FSP liable for the disputed damage? Policy provides cover for insured events subject to exclusions The applicants are required to show that, on the balance of probabilities, they have suffered a loss caused by a risk insured against under the policy. This is known as a valid (or prima facie ) claim. If the applicants are able to establish a prima facie claim, then the onus shifts to the FSP to show that, on the balance of probabilities, it is entitled to rely on an exclusion under the policy or is otherwise entitled to deny the claim. The applicants’ policy provides cover for damage for loss or damage caused by the events listed in the policy, subject to the conditions and exclusions set out in the policy. The insured events include liquid leaking or bursting from a fixed pipe. The policy contains a general exclusion for damage caused by rising damp, mould, rot, atmospheric conditions or gradual deterioration. FSP’s liability depends on proximate cause of damage The various contractors who inspected the applicants ’ property confirmed there is extensive wet and dry rot and timber decay to the flooring and floor framing. The affected areas include the toilet, bathroom, bedroom, laundry, kitchen and lounge. Mould has also been identified at the property. The applicants consider the damage was caused by a burst pipe in the bathroom wall cavity which was discovered and repaired approximately six or seven years before the claim was lodged. The applicants did not lodge a claim at the time as they were not aware the leak had caused any significant damage. The FSP disputes that the damage to the applicants’ property was caused by water leaking from the burst pipe (or by any other event insured against under the policy). The FSP says the damage occurred over an extended period of time due to the effects of condensation and dry rot on the timber in the sub-floor area. The FSP says the property was susceptible to this kind of damage because the sub-floor had inadequate ventilation. Damage caused in this manner is not covered under the policy. Accordingly, in order to determine the FSP’s liability for the claimed damage, it is necessary to identify the proximate cause of the damage (that is, the real, effective or dominant cause). Contractors have provided differing opinions about cause of damage As outlined above, the applicants say all of the damage to their property was caused by the burst pipe in the cavity wall between the bathroom and the toilet. The applicants say: Case No: 473168 Determination Page 4 of 8  the pipe was leaking for an unknown period of time, spraying water inside the wall cavity on the floor behind the bath  the flooring soaked up water, causing moisture to spread throughout the property  water was transferred from the swollen flooring into the timber joists and beams of the sub-floor, leading to rot, timber decay and mould growth. The applicants have provided a quotation from their builder (B) for a total rebuild of the property (at an estimated cost of $268,000). In his quotation, B states that a long term leak at the property has resulted in a large build-up of moisture and mould to the sub-structure of the house, causing swelling and delamination of the flooring, rotting of the floor joists, bearers and wall plates and rising damp to the wall linings. The FSP disputes that the claimed damage was caused by leaking water, based on the findings of its engineer (FE), who inspected the property on two occasions after the claim was lodged. In February 2016, FE was appointed by the FSP to determine the cause of the damage to the flooring in the toilet and bathroom area (which was the subject of the applicants’ initial claim). In his initial report, FE concluded that the damage to the flooring was caused by the burst pipe. The FSP accepted liability for the claim on this basis. However, FE also noted that the moist atmosphere due to the inadequate ventilation of the sub-floor space had contributed to dry rot on the underside of the floor joists. Accordingly, the FSP required the applicants to take measures to improve the sub - floor ventilation before it agreed to authorise the repairs. During the early stages of the repair process, it was discovered that the damage to the flooring and sub-floor structure was more extensive than previously realised and extended well beyond the toilet and bathroom area. Following his second inspection in October 2016, FE revised his previous opinion. In his second report, FE concluded that the timber decay had been caused by a combination of poorly managed condensation formed from water vapour and dry rot. FE considered that the inadequacy of the sub-floor ventilation prevented sufficient air circulation within the sub-floor space to dry the timber framing and flooring and reduce the relative humidity. He advised that the high levels of humidity would have generated mould growth. Given the nature and extent of the damage, FE stated that the leaking pipe several years earlier would have made an insignificant contribution. Disputed damage was caused by excluded factors Having carefully reviewed the available information, the panel is satisfied that the disputed damage to the applicants’ property was caused by naturally occurring atmospheric conditions exacerbated by the lack of sub -floor ventilation (and not by the effects of leaking water). Case No: 473168 Determination Page 5 of 8 The panel considers that, as an engineer, FE is appropriately qualified to determine the cause of the damage. FE’s second report provides a detailed and logical explanation as to the mechanism by which the damage occurred – that is, due to the build-up of moisture caused by water vapour condensing in the inadequately ventilated sub-floor area. The panel considers that the findings in FE’s report are consistent with the observed facts. Among other things, the panel notes that:  the timber framing was found to be damp when the repairs commenced in August 2016, despite a number of years having passed since the original leak  investigations carried out by the FSP’s plumber (O) confirmed there was no ongoing leak. O considered the damage had occurred over an extended period of time due to rising damp caused by inadequate control of moisture under the house  the damage was extensive and widespread throughout the property, rather than being localised in the vicinity of the leaking pipe. The panel has given careful consideration to the fact that FE reversed his original conclusion. However, the panel is satisfied that FE had a reasonable basis for doing so. FE’s first inspection was focussed on the specific area of damage which was the subject of the applicants’ initial claim. Further, as noted i n his report, he was able to inspect the floor framing across a broader area due to the severe lack of crawl space. By the time he carried out his second inspection, the flooring in the bedroom and laundry had been removed, which meant FE was able to inspect a far greater area of the sub-floor. The nature and extent of the damage observed by FE during his second inspection led to him revising his conclusions. In particular, FE noted that the extent of the damage to the sub-floor in the bathroom area was not significantly different than that in other parts of the house. The applicants have queried various aspects of FE’s findings. However, the panel is satisfied that the detailed responses provided by FE adequately address the issues raised. The applicants have not provided a report from an equivalently qualified engineer which refutes FE’s findings. While the applicants’ builder (B) has stated that the damage was caused by a water leak, his report is brief and does not address any of the issues raised in FE’s report. The applicants say the FSP’s denial of liability for the disputed damage was influenced by a report relating to another property which was mistakenly provided to them. However, the panel does not accept this was the case. FSP is not liable for disputed damage For the reasons outlined above, the panel considers that the disputed damage to the applicants’ property was not caused by the effects of water leaking from the damaged pipe (or by any other insured event under the policy). Case No: 473168 Determination Page 6 of 8 Accordingly, the FSP is not liable for the disputed damage. The applicants say that section 46 of the Insurance Contracts Act 1984 (Cth) operates to prevent the FSP from denying their claim, on the basis that they were not aware of the issues with the sub-floor ventilation. Section 46 prevents an insurer from relying on a policy exclusion which operates by reference to a defect which existed before the policy was taken out, in circumstances where the insured was not aware (and a reasonable person in the circumstances could not be expected to have been aware) of the defect at that time. However, section 46 has no application in the present case as the FSP does not need to rely on a policy exclusion in order to deny liability for the disputed damage. It is sufficient that the FSP has shown that the disputed damage was not caused by the leaking pipe (or any other insured event). 2.2 Is the FSP’s cash settlement offer fair and reasonable? Cash settlement amount is generally fair and reasonable As outlined above, the FSP accepted liability for the damage to the bathroom and toilet which was the subject of the initial claim. The FSP also accepted liability for repairing certain damage to the bedroom and laundry, even after it had received FE’s re vised report which recommended liability should be denied. The claim notes suggest this was because the relevant areas had already been stripped out by the FSP’s contractors. The FSP has offered to cash settle the applicants for a total of $33,178.85 (less the applicable excess), made up of:  $13,940 for the estimated cost of repairing the damage to the toilet, bathroom, bedroom and laundry areas, based on a quotation provided by its builder (A)  $2,511.23 for the replacement of water and mould damaged carpets and blinds, based on quotations provided by its suppliers  $662.62 for the costs of electricity required to power the humidifiers used by the FSP’s contractors during the mould remediation process  $16,065, representing the cost of 15 weeks temporary accommodation while the relevant repairs are carried out. Based on the available information, the panel is satisfied that the cash settlement offered by the FSP is generally fair and reasonable. The applicants say the cash settlement amount is not sufficient to repair all of the damage to their property and to fund their costs of temporary accommodation while the repairs are carried out. However, for the reasons outlined above, the panel is satisfied that the bulk of the damage was not caused by factors which are covered under the policy. The FSP is not required to fund the costs of temporary accommodation where the policy does not provide cover for the damage being repaired. Case No: 473168 Determination Page 7 of 8 Cash settlement amount should be increased to reflect mould treatment The FSP’s claim notes reflect that its cash settlement offer was intended to include an additional amount of $500 for mould remediation. Accordingly, the cash settlement should be increased to include this amount. The FSP is also required to pay interest on the cash settlement amount at the rate set out in section 57 of the Act for the period from 25 November 2016 until the payment date. The FSP initially advised the applicants that they could accept part of the settlement payment only (eg for temporary accommodation) and continue to pursue the remainder of their claim. However, the FSP did not make it sufficiently clear to the applicants that they could accept the entire amount and still continue their dispute. In these circumstances, the panel considers interest should be paid. 2.3 Are the applicants entitled to compensation? FOS can award compensation for non-financial loss Under its Terms of Reference, FOS may award compensation (capped at $3,000) for non-financial loss where an applicant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind. Applicants are entitled to additional compensation of $1,000 The FSP has recognised that there were delays during the claim process due to the requirement to appoint various trades to complete assessments and has agreed that the claim could have been managed more effectively. The FSP ’s internal dispute resolution department awarded the applicants compensation of $500 for the stress and inconvenience suffered during the claim process. The claim history indicates there were significant delays, including a delay of over three months between the FSP’s loss adjuster attending the property and the initial engineer’s re port being received. The panel also considers that the FSP should have communicated with the applicants more clearly during the claim process, particularly given the complicated circumstances of the claim. These factors, as well as the mistaken report provided to the applicants, caused additional stress and inconvenience. The panel considers that the circumstances justify an additional award of $1,000 as compensation for non-financial loss. Case No: 473168 Determination Page 8 of 8 3 Supporting information 3.1 FOS approach to this dispute This dispute has not been the subject of a FOS recommendation. Due to the nature of the dispute, it has been referred directly to a panel for determination, in line with the Operational Guidelines to the FOS Terms of Reference. The panel consists of an Ombudsman and two representatives with consumer and insurance experience. The panel has decided this case based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions (which are not binding). There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. The panel has reviewed and considered all of the material provided by the parties. While the parties have raised numerous issues in their submissions, for the purposes of this determination, the panel has restricted its commentary to those issues that it considers directly relevant to the outcome only.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.