Home / Financial Firm (Unknown - Insurer) / Determination 473067

Determination 473067

Denial of fascia damage claim for faulty workmanship

FirmFinancial Firm (Unknown - Insurer)
Decided2017-10-02
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant's home insurance claim for a detached fascia was denied for faulty workmanship based on a builder's report. AFCA found the evidence insufficient and ordered an independent expert inspection, with the FSP to re-assess its claim decision.

The onus was on the FSP to prove the faulty workmanship exclusion, and its evidence was insufficient, but the applicant's refusal of a re-inspection prevented a fair adverse finding.

Issues

Subjects and remedies

home or building damagereassess claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 473067 Determination Page 1 of 4 Case number: 473067 31 August 2017 1 Overview 1.1 Dispute In October 2015, the applicant lodged a claim under his home insurance policy held with the financial services provider (FSP) following strong winds which he says resulted in a section of fascia detaching from the property. The FSP denied the claim in rel iance upon its builder’s report which states the cause of damage was faulty workmanship, and so excluded from cover under the policy. The applicant disagrees with the FSP’s decision saying:  its claim decision was based upon a biased assessment report  there is no supporting evidence to substantiate the builder’s finding that the damage resulted from faulty workmanship. The applicant says the damage should be re-assessed by an independent builder. 1.2 Issue and key findings Was the FSP entitled to deny the applic ant’s claim ? There is insufficient evidence to determine, on the balance of probabilities, whether the FSP was entitled to deny the claim on the basis of faulty workmanship. For this reason, an independent and appropriately qualified roofer/builder is to be appointed (as outlined in Section 2) to determine and report on whether the damage claimed is a result of faulty workmanship. The cost of this inspection is to be covered by the FSP. The FSP is to then re-assess its claim decision in light of this additional information. 1.3 Determination This determination is substantially in favour of the applicant. An appropriately qualified independent roofer/builder is to be appointed to re-assess the damage claimed as outlined in Section 2 of this determination. The cost of this inspection is to be covered by the FSP. If dispute still remains between the parties following this further inspection, the parties are at liberty to re-approach FOS to make a determination regarding the final claim decision in light of the new information. Case No: 473067 Determination Page 2 of 4 2 Reasons for determination 2.1 W as the FSP entitled to deny the applicant’s claim ? No dispute the applicant’s property has sustained damage There is no dispute between the parties that the applicant’s property has suffered damage in the form of a section of fascia detaching from the property. The applicant says this occurred during a storm event in 2015. FSP relies upon assessment report and policy exclusion to deny the claim In denying the applicant’s claim, the FSP relies upon the report pr ovided by its appointed builder, who in part states: “Inspection of the fascia found that the fixing was inadequate with a timber block installed behind the cable attachment point. The metal fascia is a later fitment to the hous e and has inadequate support. … This section of fascia requires re-s ecuring by way of installing extra timber framing behind the fascia. … The damage is due to faulty workmans hip in the installation of the fascia which has resulted in a lack of support to the electricity cable bracket.” Based upon these findings, the FSP relies upon the following policy exclusion to deny the claim: “Under this policy there is no cover for any loss, damage … in any way connected with: 1. defects, structural or design faults, faulty workmanship or faulty design” The FSP also says the associated meteorological records do not show any strong winds or storm activity occurring on the reported date of loss. Applicant says issue lies with fascia and not the service bracket The applicant disagrees with the builder’s findings and says :  the electrical cable attachment point itself is not damaged at all, and so the associated installation rules referred to by the FSP are irrelevant to this dispute  the damage is the detachment of the solid timber fascia board away from the roof, and so associated fascia installation rules are relevant to this dispute which the FSP has not provided  the metal fascia referred to by the builder just covered the timber board for decorative purposes, and the soffit remains in tact  the builder only took photographs from the ground as opposed to climbing up to physically inspect the fascia board. For these reasons the applicant says the FSP should not be able to rely upon the builder’s findings to deny the claim , and an independent assessment should be undertaken. Case No: 473067 Determination Page 3 of 4 FSP offered to appoint another roofer/builder to assess the damage The FSP says it has been unable to obtain further information regarding the applicant’s concerns from the builder who originally attended the property because no longer works for the building company. On this basis, and accepting further information / clarification was required, the FSP offered to appoint another roofer/builder from a different company to re-assess the damage. However, the applicant declined this offer saying he would not trust any builder appointed by the FSP. As a result, the FSP says it was unable to further the claim decision without such re- attendance. Applicant has not provided any expert evidence to challenge FSP’s findings The FSP advised the applicant it would consider any report provided by an expert appointed by the applicant himself. However, it says the applicant declined to provide any such report due to the cost involved. Applicant declined FSP’s ex -gratia offer of $500 Whilst maintaining its claim decision, the FSP offered the applicant an ex-gratia (goodwill) payment of $500 in an attempt to resolve the dispute. The applicant declined the offer, and which has since been withdrawn by the FSP. FSP required to establish policy exclusion The FSP has only recently provided meteorological records regarding any strong winds / storm activity around the time of the loss. It does not appear to have relied upon such evidence prior to this point in time, rather upon its builder’s finding and policy exclusion for faulty workmanship. Therefore, I am not satisfied the FSP can now rely upon any suggestion that the applicant has not established a valid claim under the policy. For this reason, the onus remains with the FSP to establish, on the balance of probabilities, the damage claimed is a result of faulty workmanship. Original FSP evidence insufficient to establish policy exclusion I note the FSP has not provided associated fascia installation rules or guidelines to support the builder’s findings, and as requested by the applicant during the course of the claim. I do note the FSP has made reference to electricity cable service brackets installation rules during the course of the claim. However, these simply reference fascia boards to the extent of how such brackets should be affixed to timber behind fascia boards. It also appears, considering the original builder has since left, a further site visit will be required in order to establish the exact nature of the fascia board fixings. Case No: 473067 Determination Page 4 of 4 Ordinarily, this would mean the FSP is unable to rely upon the policy exclusion for faulty workmanship. However, in this instance the FSP has acted reasonably in offering to undertake a further re-assessment at no cost to the applicant. In my view, the applicant’s refusal in allowing this to occur has prejudiced the FSP’s ability to re- assess its claim decision in light of the applicant’s concerns. For this reason, it would not be fair in all the circumstances to make an adverse finding against the FSP at this point in time. Parties to agree on findings of an independent expert For the reasons discussed above, I am not satisfied the available evidence is sufficient to make a determination as to whether the FSP was entitled to deny the claim for reasons of faulty workmanship. Therefore, considering both parties agree further information is required, upon acceptance of this determination the parties are to undertake the following actions:  within 14 days of this determination being accepted, the FSP is required to provide the name and associated qualifications of three independent experts (builder/roofer) who are able to determine whether the damage to the fascia board is a result of faulty workmanship  within seven days, the applicant is to advise the FSP of his preferred expert  the parties are then to agree mutually agreeable date (within a reasonable timeframe) for the inspection to be undertaken  following this inspection, the expert is to provide a written report confirming his findings within a reasonable timeframe , and the FSP to re-assess its claim decision in light of this additional information (and any further information provided by the applicant). For the sake of brevity:  the FSP’s claim acceptance / denial is limited to the expert’s findings as to faulty workmanship (as opposed to any other excluded cause that may be identified) considering this was the basis of the original claim denial  in the unlikely event the parties are unable to reasonably agree upon an expert, they may approach FOS to elect one on their behalf  if dispute still remains between the parties following this further inspection, the parties are at liberty to re-approach FOS to make a determination regarding the final claim decision in light of the new information.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.