Home / Financial Firm (Unknown - Insurer) / Determination 472936
Determination 472936
claim_denial
Summary
The applicants said a relocated house was damaged in delivery and that the broker sold them fake insurance. AFCA found the damage resulted from asbestos removal the contract expressly provided for, so the underwriter could deny the claim and the broker was not liable.
Damage caused by contractually agreed asbestos removal is not an insured loss, so the applicants established no loss caused by either FSP.
Issues
- Claim denial primary · not upheld“The available evidence does not establish that the house incurred any damage other than damage caused by asbestos removal, which the contract expressly provides for.”
- Misleading conduct secondary · not upheld“The applicants have not established that they suffered a loss due to the conduct of FSP 1, so no compensation is payable from FSP 1.”
Subjects and remedies
broker or intermediaryhome or building damageno remedy
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
Determination
Case No: 466326 & 472936 Determination Page 1 of 6
Case number: 466326 and 472936 21 December 2017
1 Overview
1.1 Dispute
The applicants entered a contract with „ MS ‟ for the supply and delivery of a
relocatable house. The contract said MS had insurance, but the applicants could pay
extra for “ contract works insurance ” („the policy‟). The contract said this additional
insurance could be arranged by contacting MS ‟ insurance brokers (FSP 1).
The applicants contacted FSP 1 to arrange the po licy, which was underwritten by
FSP 2.
The applicants say MS delivered the house “ in shocking condition ” , and they want to
make a claim under the policy for damage to the house.
The applicants say FSP 2 told them they need to contact FSP 1 to make a claim, but
FSP 1 refuses to deal with them because it says the applicants are not their client or
the insured party, MS is. The applicants say FSP 1 sold them “ fake insurance ” .
1.2 Issues and key findings
Have the applicants suffered a loss for which the policy provides cover?
The available evidence does not establish that the house incurred any damage, other
than damage caused by asbestos removal, which is expressly provided for in the
contract between the applicants and MS. Therefore, the applicants have not
established that they have suffered a loss and FSP 2 is entitled to deny the claim.
Have the applicants suffered a loss due to a breach of duty by FSP 1?
The applicants have not established that they suffered a loss due to the conduct of
FSP 1. Therefore, the applicants have not established an entitlement to
compensation from FSP 1.
1.3 Determination
This determination is in favour of the FSPs.
FSP 1 is not required to take any further action in relation to the claim.
FSP 2 is not required to take any further action in relation to the claim.
Case No: 466326 & 472936 Determination Page 2 of 6
2 Reasons for determination
2.1 Have the applicants suffered a loss for which the policy provides
cover?
Applicants entered contract for purchase and delivery of house
The applicants entered a contract with MS dated 13 January 2016 for the purchase
and delivery of a moveable house. The contract said MS would sell the house to the
applicants and deliver the house to the applicants‟ property.
The contract states: “ Any visible asbestos will be removed by [MS] but not replaced. ”
The contract also contains a list of items the applicants are said to acknowledge
responsible for, including: “ Rectification works to areas where asbestos removal was
carried out ” .
The contract contains a section titled “Insurance Information” which lists the types of
insurance held by MS. The insurance listed includes a policy held with FSP 2 for
“ Contract Works (optional) ” , said to cover “ House Relocation, Restumping &
Renovating ” . In part, this section states:
NB: Whilst Liability and Marine Transit insurances are implicit in the contract,
Contract Works insurance is offered to clients as an extra to the contract. Should you
require cover in this area, the premium payable is equal to $4.75 per $1,000.00 sum
insured and is an extra on top of the contract price. Contract Works insurance is arranged
upon completion of relevant paperwork, which can be obtained from office staff…
Immediately below this is a section titled “ Notes Regarding Insurance Cover ” :
It is the responsibility of [the applicants] to ensure adequate cover at all times. The
contractor recommends that [the applicants] have sufficient insurance cover to indemnify
[the applicants] for any purchase price plus removal cost of the building. In the event that
[the applicants] requires additional insurance cover for any possible claim at any stage of
the removal, this should be arranged and paid for by [the applicants] prior to
commencement of removal. Any extra cover can be arranged through [the applicants]
preferred insurance company or by contacting [our] insurance brokers:
The contract then states the name and contact details of FSP 1.
Applicants contacted FSP 1 to purchase insurance
The applicants contacted FSP 1 to purchase the optional contract works insurance
referred to in the contract.
MS holds a construction insurance policy with FSP 2. FSP 1 arranged for the policy
to be endorsed with the applicants ‟ names and the details of the contract .
The applicants signed a “ contract works insurance declaration ” and emailed it to FSP
1 on 4 March 2016. FSP 1 produced an “ endorsement invoice ” dated 4 March 2016.
FSP 2 produced a “ policy endorsement ” dated 6 March 2016 stating that MS‟ policy
had been amended to include the applicants. All of these documents include the
applicants‟ names , and the address the house was to be delivered to, but all list MS
as the “ insured ” .
Case No: 466326 & 472936 Determination Page 3 of 6
The endorsement invoice was addressed to MS, but the invoiced sum of $599.50
was paid to FSP 1 by the applicants. Email records indicate the payment was made
on 9 March 2016.
Policy doesn’t cover water, wind, or damage incurred in transit
The endorsement invoice says the policy doesn‟t cover water damage, weather perils
(including wind and storms), or damage to any home whilst in transit. On 4 March
2016, the applicants sent an email asking FSP 1 to explain these exclusions.
On 5 March 2016, FSP 1 emailed a response to the applicants stating:
Unfortunately this is the only cover available, with the restrictions that apply, did you sp eak
to [MS] about your concerns?
On 7 March 2016, the applicants emailed FSP 1:
Well as I remember very clearly I signed the contract for all the above reason in the
endorsement. As per our conversation you quoted specifically for min, vandalism, fire etc.
So I am so confused why suddenly the contract omits all of the above.
Applicants made claim under policy
On 8 March 2016, the applicants emailed FSP 1 asking to cancel the policy. FSP 1
replied asking the applicants to confirm that there was no damage to the house that
could be claimable under the policy.
On 9 March 2016, the applicants emailed FSP 1:
I will email you pictures of the house before and after the relocation. [MS] claimed that was
the result of asbestos removal by a qualified trader. I will put forward a claim and see what
is covered under our insurance. I have also just made payment. In the mean time please do
not cancel this policy.
On 15 March 2016, the applicants emailed FSP 1 stating : “ The house arrived on
Monday morning [7 March 2016] in such a bad condition. ”
On 21 March 2016, the applicants sent an email to FSP 1 making the following
allegations:
MS “ completely demolished and vandalised our house inside and outside ”
“ In the contract it says clearly [MS] needed to remove only visually asbestos but
instead of visual they ripped the house completely ”
The house should have been placed at the rear of the property. Instead, MS
“ dumped ” the house on the driveway, leaving part of the house encroaching on
the neighbouring property. MS now refuses to move the house
MS left a “ huge knife ” stabbed into a wall of the house as a “ threatening
message ”
MS left the house with no roof, and now refuses to put the roof on the house
MS deliberately missed a deadline set by the local council, and this is causing
the applicants “ heaps of problems ” .
On 22 March 2016, FSP 1 emailed the applicants:
Please direct all further enquiries on this matter directly to [MS] by way of a letter of
demand holding them responsible for the damages to your property.
This is not a matter [FSP 1] can assist you with.
Case No: 466326 & 472936 Determination Page 4 of 6
Expert reports describe condition of house
The applicants rely on a report dated 2 February 2016 by „ LC ‟ , engineer. LC
inspected the house on 18 January 2016, before the house was delivered, in order to
certify that the building was suitable for relocation. LC‟s report states as follows:
The interior walls and ceilings are in “ fair condition ” , but need cleaning and
repainting
The exterior walls and kitchen are in “ fair condition ”
The bathroom is in “ good fair condition ”
The house overall was “ in good condition with no sign of structural failure or
degradation of the visible main structural members ” .
The applicants have provided a report dated 2 August 2017 b y „ VT ‟ , engineer. VT
inspected the house on 26 July 2017 and reviewed LC‟s report. VT‟s report is
supported by photographs of the house. VT‟s report concludes as follows:
Based on our inspection… for purpose of this report for the substantial loss and damages
done to the relocated house by [MS], it is clear that the house will require a major
refurbishment and repairs to restore it back to the original fairly good condition of the house
when it was first purchased from [MS].
FSP 2 has provided a report dated 12 October 2017 by „ MB ‟ , engineer. FSP 2
instructed MB to report on the condition of the house, and whether it showed signs of
damage from:
asbestos removal
vandalism by MS or anyone else
water damage after delivery.
MB inspected the house on 12 September 2017. MB reviewed photographs of the
house taken before and after delivery, and the reports by LC and VT. MB‟s report
concludes as follows:
„Asbestos - related products‟ have been removed from the house. These
products include ceiling sheeting, wall linings, and vinyl flooring. Kitchen fixtures
have been removed in order to allow the removal of wall linings and flooring
There is no sign of vandalism. The asbestos -related products have been
removed in a way that does not damage the framing. The kitchen fixtures were
not damaged by their removal and can be reinstated
There are visible signs of water staining to the ceiling boards in two of the
bedrooms. MB could not determine when or why the staining occurred
The house shows signs of wear and tear, such as flaking paint and worn
floorboards.
Damage to house consistent with asbestos removal
Having considered the evidence provided by all parties, the Panel accepts that the
appearance of the house was worse after delivery than before delivery. However, the
available evidence indicates that the damage incurred in the delivery of the house
was caused by the removal of asbestos.
The contract between the applicants and MS states that MS will remove any visible
asbestos from the house. The contract says that MS will not replace what is
Case No: 466326 & 472936 Determination Page 5 of 6
removed, and recti fication work following asbestos removal is the applicants‟
responsibility.
MB has explained that everything removed from the house was necessary for
asbestos removal, and the asbestos removal was done in a way that did not cause
any unnecessary damage. The applicants have not provided any evidence to refute
MB‟s conclusions.
Applicants have not established entitlement under policy
I am not satisfied that the house incurred any damage in the process of being
delivered to the applicants, other than what was expressly provided for in the contract
between the applicants and MS. Therefore, the applicants have not established that
they have suffered a loss, and FSP 2 is entitled to deny the claim.
2.2 Have the applicants suffered a loss due to a breach of duty by FSP
1?
Applicants have not established insurable loss
In order to establish an entitlement to recovery from FSP 1, the applicants must
establish that they have suffered a loss due to the conduct of FSP 1.
As stated above, the applicants have not established that they have suffered a loss.
The damage to the applicants‟ house was caused by the removal of asbestos, which
is expressly provided for in the contract between the applicants and MS. This
damage would not be covered under any insurance policy the applicants could have
obtained prior to the delivery of the house.
The available evidence does not establish that the applicants have suffered a loss
that would have been covered under an insurance policy they could have obtained.
Therefore, the applicants cannot establish that they lost the opportunity to obtain
such a policy due to the conduct of FSP 1.
Case No: 466326 & 472936 Determination Page 6 of 6
3 Supporting information
3.1 FOS approach to this dispute
A full exchange of the relevant information has taken place between the parties and
each party has had the opportunity to address any issue raised.
All of the provided material has been read and considered. The parties have raised
numerous issues in their submissions. For the purpose of this determination,
commentary is restricted to only those issues considered relevant.
3.2 Both applicants represented by one applicant
For the purposes of this determination, submissions made by one applicant have
been treated as if they had been made by both applicants.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.