Home / Financial Firm (Unknown - Insurer) / Determination 472885

Determination 472885

Claim denial for storm or flood damage attributed to poor construction

FirmFinancial Firm (Unknown - Insurer)
Decided2018-06-06
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicants claimed storm or flood damage to their home in November 2016 and March 2017, and the FSP denied both claims. The panel found the damage was caused by poor original construction and subsidence, which is excluded, and awarded no compensation.

The applicants did not establish a prima facie claim from a specific insured event, and the policy excludes damage caused by poor design, materials or workmanship.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 472885 Determination Page 1 of 12 Case number: 472885 6 June 2018 1 Overview 1.1 Dispute The applicants made two claims for damage to the insured property in November 2016 and March 2017. The claims were denied because the FSP says no insured event occurred on either occasion but damage related to pre-existing issues due to deficiencies in construction. The FSP also says its policy specifically excludes cover for damage which existed before the policy commenced and cover for damage caused by rot, seepage, or poor or faulty design specification or workmanship. The applicants dispute the claims denial and want their claims paid. The case manager provided the parties with a recommendation on the issues in dispute. The recommendation was in favour of the FSP. As a recommendation was not accepted by the applicants, the dispute has been referred to the panel for determination. 1.2 Issues and key findings Is the FSP entitled to deny the applicants’ claims? The available material establishes on the balance of probabilities the claimed damage was not caused by an insured event but was caused by long-term subsidence. The subsidence was caused by poor design and workmanship in the construction of the damaged rooms. For these reasons the damage is excluded from cover and the FSP is entitled to deny the claims. Are the applicants entitled to compensation? The available material does not warrant an award of compensation. 1.3 Determination This determination is in favour of the FSP. The FSP is not required to take any further action in relation to the claims or the dispute. Case No: 472885 Determination Page 2 of 12 2 Reasons for decision The panel has decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. The panel has taken into account all the material submitted by the parties, both before and after the recommendation. The panel is satisfied the documentation it has relied on has been provided to both parties. While the parties have raised numerous issues in their submissions, for the purposes of this determination, commentary has been restricted to those issues considered directly relevant to the outcome only. New material provided after recommendation After the recommendation was rejected, there were further submissions and new material was provided. Where relevant, this will be referred to in the determination. 2.1 Is the FSP entitled to deny the applicants’ claims? Applicants must establish a prima facie claim The applicants must establish on the balance of probabilities they have suffered a loss caused by an event or events to which the policy responds. This is known as a prima facie claim. The FSP‟s policy commenced 9 June 2015. The FSP‟s policy provides cover for insured events. In this dispute, the applicants must establish the claimed damage was caused by storm or flood or other insured event. Once so established, the onus shifts to the FSP to prove on the balance of probabilities an exclusion applies if it seeks to deny or limit its liability for the claimed loss. In this dispute, the FSP must establish the loss or damage was caused by the exclusions relied on and set out in supporting section 3 of this determination. The FSP‟s claims notes show the first claim was made in November 2 016. The file note says: “My son told me he could see outside through a crack in his room it started at a hair line crack and has gradually opened up over the last few months. We believe this from water damage we have been through a couple big floods in th e last 24 months”. FSP’s engineers inspected the property after the claims were made After the claim was made, the FSP‟s assessors inspected the property. They noted a drop at the front right hand corner of the house. The FSP then arranged for consulting engineers (JH) to attend and investigate the cause of the damage and determine if the damage was caused by an insured event. JH attended and photographed the property on 1 December 2016. The engineer agreed there was moderate cracking damage to an external wall located under the open veranda to the right hand side of the building. He also agreed there was internal cracking to the lower external walls and ceilings. Case No: 472885 Determination Page 3 of 12 However he attributed this to long-term deflection occurring in the added concrete floor slab. He said this deflection was typical of an unsupported floor slab with no integration of a footing system. He concluded the movement damage is a pre- existing issue and not caused by recent claim events. The applicants disagreed with this assessment and provided photographic material. After review, the engineer said the recent events were not prolonged and would not have impacted the underlying subsoils. He remained of the opinion the damaged rooms were poorly constructed and likely incurred prolonged seepage during past weather events. There was a further storm event on the night of 4 March 2017. When the applicants lodged the second claim, the FSP recorded the following: WE WALKED DOWNSTAIRS, AND WE WALKED T HROUGH WATER IN A COUPLE OF ROOMS, THEY LINO FLOORS. THE WATER CAME UP T HROUGH THE FLOOR AND THROUGH THE WALLS. THE WALLS ARE WARPED IN TWO BEDRROOMS DOWNSTAIRS, THE WALL IS CRACKED IN TWO OF THE BEDROOMS .. NO IDEA WHY. THE SKIRTING, WALLS, FLOOR ARE DAMAGED. JH inspected and photographed for property on 9 March 2017 in order to provide a report to the FSP on the cause of the damage. The engineer inspected the damaged bedrooms located at the front right hand corner of the house. The panel notes both reports indicate these bedrooms were the subject of alterations/renovations to the property at an earlier time before the policy commenced. On this second inspection, the garden bed had been excavated and wall cladding removed by the applicants‟ contractor (K) so further information was available to the FSP‟s engineer. The applicants said after recent storm events, water had flowed through under the concrete slab washing away the soils causing subsidence, however the engineer saw no evidence of erosion to suggest water had flowed under the floor slab. The engineer accepted there was cracking damage and subsidence and movement of the floor slab and walls in the two bedrooms downstairs. He found the concrete floor slab and support posts had subsided. He made a number of critical observations about the construction of these rooms including that the slab was constructed on loose uncompacted soil unsuitable to support a slab. The engineer said the builder had not installed a proper foundation system but rather installed inadequate piers and a concrete slab on top. Because of the inadequate design of the foundation system, he said the slab and piers had gradually subsided over time causing the observed damage. The engineer did not accept the applicants‟ contention the subsidence and movement occurred because water flooded under the slab. Rather, the FSP‟s engineer contended the foundation system was inadequate and not installed to adequate depths to resist long-term subsidence. Case No: 472885 Determination Page 4 of 12 He concluded the claimed subsidence and moisture damage to the insured property occurred because of poor original construction. He said the claimed damage was not caused by storm or flood. Further materials and submissions were made by the applicants. In a supplementary report the FSP‟s engineer reiterated the available evidence demons trated the damage had been occurring over a long period of time since the original alteration/renovation. After the recommendation, the applicants obtained a report from an engineer The applicants‟ engineer did not inspect the property. The engineer relied on photographs, material and statements provided by the applicants. He relied on statements about the movement of the veranda posts. And he relied on statements that when the three posts which supported the veranda were removed by the applicants, the depth of the posts below ground level was 1.2m, the concrete surround was sound and the ground was saturated with water. The engineer reviewed rainfall records and described heavy rainfall events in the relevant period between June 2016 and March 2017. Taking these matters into account, but providing a disclaimer, the applicants‟ engineer concluded that it seems likely the soil supporting the post was weakened by water during heavy rainfall causing the soil at the base of the post to fail. The FSP‟s engineer reviewed this report but did not change his view. The FSP‟s engineer was not persuaded there was objective evidence the ground was saturated with water when the post was removed and the posts were installed to a depth of 1.2m. The engineer said it was unlikely water from a single rain period would infiltrate to this depth and cause subsidence of the posts. He said there was no further or new conclusive evidence but the report contained a number of unsubstantiated and disclaimed statements. All engineering opinions are summarised in supporting section 3 of this determination. Damage not caused by flood or escaping water The main focus of the applicants submissions relate to damage being caused by flood or storm. The panel does not accept damage was caused by flood. This is because flood is specifically defined in the policy. “Flood” is defined to mean the covering of normally dry land by water that has escaped from the normal confines of the lake, river, creek, watercourse, reservoir, canal or dam. The available material does not establish a flood event occurred as defined in the FSP‟s policy. The panel accepts there were significant rainfall events at various times before the first and second claims. However it is not sufficient for the applicants to contend that at various times over a two-year period rainfall or water running-off or escaping had caused damage, rather the applicants must establish the proximate cause of the claimed damage was from a particular storm event or water escape, as required by the policy, and in line with established insurance law. Case No: 472885 Determination Page 5 of 12 The applicants have made lengthy submissions and provided substantial material including photographs, material from the Bureau of Meteorology, articles, a video showing water inundation on a USB stick. A soil moisture test report was also provided but makes no findings about causation. The panel has carefully reviewed the applicants‟ material but considers the nature of the dispute requires careful attention to the expert opinion provided by the engineers. The panel considers expert opinion in a dispute of this nature is the more persuasive material. The applicants have made a number of criticisms of the FSP‟s engineer including that he was not appropriately qualified and that he was biased and influenced by the FSP‟s assessor. The applicants reported the engineer to the Board of professi onal engineers. Contrary to these allegations, the Board accepted the engineer had academic qualifications in engineering. The Board also did not accept the engineer engaged in unsatisfactory professional conduct. Having reviewed the available material, t he panel accepts the FSP‟s engineers were sufficiently qualified to report on the issues in dispute. The panel considers the available material does not establish bias or unprofessional conduct. Accordingly, the panel is satisfied it can rely on the FSP‟s engineers‟ reports in making this determination. Storm events were not the proximate cause of the claimed damage Having considered the available material, the panel is not persuaded on the balance of probabilities the claimed damage was caused by a storm event in June 2016 or November 2016 or March 2017. In the panel‟s view , on lodging the claims, in order to establish a valid claim, the applicants were required to establish three things: that there was a specific identified weather event (or other insured event); that damage arose from that event; and that event was the proximate cause of the damage. The panel is of the view that the applicants have failed to show these things. In any event, in the panel‟s view, even had the applicants established a val id claim, the available material establishes the probable cause of the claimed damage was the poor manner in which the damaged rooms were constructed. When the FSP‟s engineer first inspected the property in December 2016 he considered the kind of damage he saw was typical of an unsupported floor slab. This view was corroborated in the second inspection in March 2017 by which time the garden beds located along the front corner of the house and cladding had been removed. The panel has carefully considered the photographs attached to the engineer ‟s reports and are satisfied the photographs support the engineer‟s opinions. The panel has carefully considered the applicants‟ engineer‟s report and the applicants‟ submissions about the water under the slab and the impact on the posts. However the panel does not find these submissions and the applicants‟ engineer‟s report sufficiently persuasive. This is because: Case No: 472885 Determination Page 6 of 12  the report is provided sometime after the claim events whereas the FSP‟s engineers‟ reports were contem poraneous with the claim events.  the applicants‟ engineer has not actually inspected the insured property but relies on information provided by the applicants.  the report addresses only one aspect of the insured property‟s construction, namely, the role of the posts in the claim.  while the engineer comments the concrete and steel posts were found to be sound, the engineer makes no comment about the other aspects of the insured property‟s construction and no comment about the crux of the FSP‟s engineers‟ opinions in relation to the unsupported floor slab.  the applicants‟ engineer completed the report with a disclaimer. The FSP is entitled to deny the claims Having carefully considered all available information, the panel is not satisfied on the balance of probabilities the claimed damage was caused by an insured event or the storm events as claimed. Further, the panel is satisfied the available information establishes on the balance of probabilities the claimed damage occurred because of the poor construction of the damaged rooms which cause of damage is excluded from cover. In the circumstances, on the information provided, and for the reasons stated, the panel is satisfied the FSP is entitled to deny the claims. 2.2 Are the applicants entitled to compensation? Compensation only paid in some circumstances FOS‟s Terms of Reference allow the payment of compensation (capped at $3,000) for non-financial loss. FOS may decide an FSP should compensate an applicants for such loss only where there has been an unusual amount of physical inconvenience, time taken to resolve a situation, or interference with the applicants‟ expectation of enjoyment or peace of mind. The applicants have complained about the FSP‟s claims conduct. T hey say their children were harmed by asbestos in the damaged rooms and the FSP and/or the FSP‟s engineers failed to advise the applicants of the risk. The FSP says the applicants arranged the removal of the cladding and the applicants‟ contractor did not test the cladding. The material provided (including the FSP‟s file notes) show the following timeline:  22 November 2016 first claim made  1 December 2016 FSP‟s engineer inspected  6 December 2016 FSP‟s engineer‟s report  7 December 2016 decision to deny first claim  7 December 2016 file note to send engineer‟s report to client  11 December 2016 applicants requested engineer‟s report  11 December 2016 file note to send engineer‟s report with rejection letter  14 December 2016 rejection letter sent Case No: 472885 Determination Page 7 of 12  20 December 2016 re- sent rejection letter and engineer‟s report to correct email  23 December 2016 re- sent letter and engineer‟s report  25 January 2017 file note in which applicants refer to engineer‟s report  4/5 March 2017 second claim event  7 March 2017 contractor K quotes to excavate and remove external cladding  8 March 2017 second claim made  8 March 2017 cladding removed The first report from the FSP‟s engineer shows the FSP‟s engineer suspected the lower external wall was likely clad with asbestos cement sheeting. The inspection was made by the engineer on 1 December 2016 and, after several aborted attempts, his first report was provided to the applicants on or about 23 December 2016. At this time, the panel is satisfied the applicants were aware of the contents of the report and were aware the FSP‟s engineer suspected the lower external wall was likely clad with asbestos cement sheeting. The FSP‟s file notes show on 8 March 2017 the FSP and the applicant had a conversation regarding the work done by the applicants‟ contractor K. The applicant advised K had removed the wall linings. The file note indicates K did not have a copy of the engineer‟s report and the applicants did not know if K had tested the wall linings before removing them. FSP’s conduct doe s not warrant an award of compensation The available material shows the applicants were aware of the potential for asbestos to be in the cement sheeting over 2 months before the cement sheeting was removed. No available material shows the FSP or the FSP‟s assessors or engineers caused any of the cement sheeting to be disturbed, knew the sheeting was to be removed by the applicants or told the applicants the cement sheeting was safe. In the circumstances, while the panel accepts this issue would have been extremely disturbing and upsetting for the applicants, the panel does not accept the FSP‟s conduct has disturbed or interfered with the applicants‟ expectation of enjoyment or peace o f mind. Further, the material provided shows the FSP assessed and made decisions in relation to both claims in a timely manner. In the circumstances, the panel does not accept an award of compensation is warranted. Case No: 472885 Determination Page 8 of 12 3 Supporting information 3.1 FOS Approach This dispute has been the subject of a FOS recommendation and due to the nature of the dispute has proceeded to determination by a panel. The panel consists of an ombudsman and two panel members with extensive experience in insurance industry matters and consumer complaints. It is an accepted principle of general insurance law that an insured bears the onus to establish on the balance of probabilities that they have suffered a loss caused by an event to which the policy responds. This is known as a prima facie claim. Once so established, the onus shifts to the insurer to prove on the balance of probabilities that an exclusion applies if it seeks to deny or limit its liability for the loss. 3.2 Relevant policy extracts The relevant policy extracts are referred to in the correspondence between the parties, in the recommendation and in the FSP‟s Notice of Response dated 31 March 2017. Both the policy document and the Notice have been exchanged with the applicants. What do these words mean? Insured event means an event for which you can make a claim under your policy. Exclusions General exclusions General exclusions apply to all sections of your policy and describe circumstances where your policy will not provide cover for any loss, damage or liability arising directly or indirectly from any cause noted below. We will not pay for death or bodily injury to any person, or loss or damage to property caused directly or indirectly by: 11. mould, rot, damp or the effects of the climate or weather; 10. rising damp or seepage of water from the ground; 14. poor or faulty design specification, materials, plan or workmanship; Home cover exclusions Home cover exclusions apply to all sections of your policy and describe circumstances where your policy will not provide cover for any loss, damage or liability arising directly or indirectly from any cause noted below. We will not pay for: 1. repair of any damage that existed prior to the start date of the policy; Case No: 472885 Determination Page 9 of 12 3.3 Key reports 3.1 Key points FSP’s engineer (JH) Report 6 December 2016  Lower ground floor modified to enclose and use as rooms the original double garage area and space under the veranda to the right - hand side of the house.  External wall under the open veranda to the right - hand side of the house has noticeable movement and cr acks.  Lower external wall constructed under suspended veranda slab supported by columns incorporated int o the infill external wall which is timber framed and clad with cement sheeting (likely to be asbestos cement sheeting).  Floor slabs to lower rooms vary in level.  Photographs show previous modification to ground floor slabs.  Lower concrete floor slab under veranda area has a number of toppings to raise the floor height for changes in use over the years.  Photographs show a raised garden bed outside the ext ernal wall.  Steel pipe column is continuous from upper floor through the lower floor and concealed within the lower external wall.  Photographs show movement gaps and cracking damage described as very slight to moderate.  Photograph is annotated in relation to the steel bas eplate to column protruding past the internal corner of the wall.  Because of the garden bed the footing system was not seen.  Noted lack of any weather protection to the wall.  Water can enter the wall cavity by capillary action from under the veranda slab (no drip feed evident to underside of suspended veranda floor slab) or through the omission of window flas hings above external window heads.  Level survey completed across the surface of the upper level timber floors and confirmed movement in the original building is not significant.  Moderate cracking is confined to the external wall and is because of deflection occurring in the concrete floor slab which is typical of an unsupported floor slab with no integration of a footing or beam system.  Internal cracking to the lower walls and ceilings is becaus e of long - term deflection occurring in the added conc rete floor slab which preceded the flood events.  Deflection in the new section of the floor slab is because of “as built” deficiencies during construction evidenced by modifications done to the slab over time.  Timber wall framing susceptible to termites and moisture but damage can be assessed if external cladding removed.  M ovement and cracking occurring in the external wall to the lower level h abitable rooms along the right hand side of the dwelling is a result of deflection in a non - structural ground floor slab which has been raised above the existing ground line about 400mm but remains concealed by the garden bed.  Movement damage to the wall i s a pre - existing issue and unrelated Case No: 472885 Determination Page 10 of 12 to the flood events. FSP’s engineer (JH) Report 1 0 March 2017  Inspected damaged bedrooms located to the front right corner of the house on 9 March 2017. Applicants‟ builder had now removed the garden beds located along the front corner of the house and the wall cladding also now removed .  Area under the balcony was enclosed and turned into bedrooms. Enclosed area originally patio and front entrance.  After flood or rain water applicants suggested wat er flows through under the concrete slab washing the soils, causing subsidence.  Now garden bed removed, edge of the slab could be seen and there was a gap below the concret e. No evidence of erosion to suggest wat er flowed under the floor slab .  Photographs show the gap to the underside of the slab and a steel post pier described as failed.  Timber wall bottom plates were decayed along the entire length of the wall. Decay was aged and was made wet every time the outside walls got wet ever since the wall was installed.  Original garden beds higher than the slab. Weep holes in brick work buried so water could flow in and become trapped. No presence of a slab edge rebate or flashing system.  Conc rete slab was supported by piers.  In the wall cavity was the original round hollow section steel posts which supported the suspended concrete balcony above and continued through to the roof. Foundations of the base of the posts have cracked. Post footings were too small. A gap at the top of a post and the un derside of the suspended concrete balcony slab indicated subsidence of post foundations.  Inspection of the bedrooms showed a deviation of the floor slabs which could be felt underfoot.  Deviations between the transition from the original house slab and the old patio slab since utilised for bedrooms.  Installer had cut the cornice around the post plate in the bedroom. Steel post had subsided which was pulling down the cornice moulding.  Skirting boards had been cut down to suit the change in floor levels.  Hyd raulic level survey was undertaken which showed a variation of floor levels (about 45mm) around the base of the three supporting posts.  While the level of the floor was just inside acceptable tolerances, the floor levels in the loc ation of the three steel posts are outside accepted tolerances.  Conc rete floor slab and support posts have subsided. Slab is constructed on loose uncompacted soil unsuitable to support a slab but builder did not install a foundation system. Rather there is installation of piers an d the concret e slab on top.  Piers not founded deep into stable ground and piers not adequately sized. As foundation system under designed, over time the slab and piers have gradually subsided causing cracking and floor level differentials. Case No: 472885 Determination Page 11 of 12  Removed cladding exposes the timber wall framing which is decayed. No evidence of slab edge flashing or rebate. Water on the wall runs down, hits the slab, flows under the cladding and wets the timber bottom plat e.  Timber in wall framing is decay ed bec ause of original po or construction.  The engineer suggested certain remedial works.  C onc rete slab has been constructed without a conventional foundation system meaning that the original builder anticipat ed the subgrade subsidence .  Assessment of the piers supporting the slab and steel posts revealed that they are undersized and not installed to an adequat e depth to resist long term subsidence.  S ubsidence and moisture damage to the dwelling has occurred because of poor original construction and has been a long - term issue as ev idenced by the skirting boards cut to suit the out of level floor.  N o evidence of damage to the slab or wall frame which can be attributed to an isolated rain period, storm or flood. FSP’s engineer (JH) Supplement ary report 1 6 May 2017  Historical rec ords and photographs show house converted from a patio and ent ranc e into bedrooms sometime between 2000 and 2016/7.  Estimate conversion carried out about 10 years ago because of the age of the timbers in the walls.  For reasons stated, timber rotting and subsidence is not recent damage but a long - term issue.  At the time of original construction, building codes would not have covered this type of slab. But after that patio slab was converted to bedrooms, then Council approval showing works met current codes and regulations would have been required.  To provide support for the new bedrooms, the existing slab and foundations should have been upgraded and certified by a structural engineer.  Available evidence demonstrates that the moisture to the c laimed area has been occurring for a long period of time ever since the original conversion of the patio to bedrooms.  C ould not see evidence of abnormal moisture to the sub grade under the concrete floor slab.  No obvious erosion or escarpments of the sub grade material isolated to a dedicated flow pat h of the wat er. No highly saturated soil as no „muddy „appearance to demonstrate the presence of moisture. Applicants’ engineer (PC) R eport 1 September 2017  Applicants‟ engineer provided a disclaimer as he did not inspect the property but relied on the observations of others. He viewed photographs of the veranda in 1999, other phot ographs referred to and relied on observations about the gaps in the veranda posts in November 2016 and March 2017 provided by th e applicants.  Applicants advised they had removed and replaced all three posts which support the veranda.  Applicants advised the dept h of the posts below ground level was Case No: 472885 Determination Page 12 of 12 1.2m and the concrete surround was sound on the ground saturated with water.  Engineer sets out rainfall records described as heavy rainfall events in the period June 2016 – March 2017.  Relying on the saturated ground conditions observed during replacement of the posts and the heavy rainfall events particularly when the increasing gap at the top of post 1 was noticed, “seems likely soil supporting the post was weakened by the passage of water into it during heavy rainfall causing the soil at the base of the post to fail.” FSP’s engineer (JH) Supplement ary report 25 September 2017  Comment ed on the applicants‟ report and noted the disclaimer.  No objective evidenc e the ground was saturated with water when post removed and no objective evidence the posts were installed to a dept h of 1. 2m.  Having stated the post and concret e were sound, the a pplicants‟ engineer had not viewed them.  Unlikely wat er from a single rain period would infiltrate to a depth of more than 1.2m and cause subsidence of posts.  No further or new conclusive evidence to alter opinion as report contains a number of unsubstant iated disclaimed statements.  Available evidence from investigations shows subsidence to the posts and slab occurred due to poor construction over a long period of time and was unrelated to a single weather event. 3.4 Other relevant material considered and relied on  Correspondence between the parties.  Parties‟ submissions and emails and all attachments to all submissions both before and after the recommendation.  Photographic material and USB stick from applicants.  FSP‟s photographs.  Engineers‟ reports provided by both parties.  Applicants‟ material in relation to the complaint to the Board of Professional Engineers of Queensland.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.