Delay in processing travel cancellation claim

FirmFinancial Firm (Unknown - Insurer)
Decided2017-10-24
ProductGeneral Insurance · Travel
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$8,854
SourceAFCA PDF

Summary

The applicant's travel cancellation claim was indemnified for $11,145.81, but he sought compensation for delay in processing and lodgment. AFCA found the travel agent was not the FSP's agent for lodgment, the FSP's processing was reasonable, and ordered no compensation.

The FSP is not liable for delay before it received the claim from the travel agent, which was not its agent for lodgment, and it otherwise processed the claim within Code timeframes apart from a minor delay.

Issues

Subjects and remedies

no remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 469909 Determination Page 1 of 7 Case number: 469909 24 October 2017 1 Overview 1.1 Dispute The applicant lodged a travel cancellation claim under his travel insurance policy held with the financial services provider (FSP) after his wife (also covered under the policy) had to undergo a medical procedure which prevented them from travelling. Following an assessment of the claim, the FSP accepted liability and provided indemnity in accordance with the terms of the policy. However, the applicant seeks compensation for financial and non-financial losses incurred as a result of the FSP’s claim handling. He says:  the loss arose in October 2016 but the travel agent (TA), acting as the FSP’s authorised agent, did not formally lodge the claim until December 2016  upon receipt, the FSP did not approve the claim until February 2017, and only after he lodged a claim with VCAT (and disputes with FOS and ASIC). In response, the FSP says TA is not its authorised agent for the purposes of claim lodgement, and it otherwise processed the claim in a timely manner following receipt. 1.2 Issue and key findings Is the FSP required to pay compensation to the applicant? The FSP is not required to pay compensation to the applicant because :  the FSP is not liable for any delay on the part of TA  the FSP processed and approved the claim within two months of receipt, and was entitled to request associated medical information to facilitate this  there is no evidence the VCAT claim lodgment (or dispute lodgment with FOS and/or ASIC) had any bearing on the timeliness or outcome of the claim  the applicant’s consequential financial losses did not arise as a result of the FSP erring in its handling of the claim, and so excluded from cover  the inconvenience suffered by the applicant was not of an unusual degree or extent (from 14 December 2016) as required for an award of compensation for non-financial loss by FOS. 1.3 Determination This determination is in favour of the FSP. The FSP is not required to pay compensation to the applicant. Case No: 469909 Determination Page 2 of 7 2 Reasons for determination 2.1 Is the FSP required to pay compensation to the applicant? FSP has provided indemnity for the applicant’s claim There is no dispute between the parties that the applicant and his wife were unable to undertake a pre-booked overseas trip for medical reasons. Whilst the time taken to process the claim is disputed by the applicant (and discussed below), the FSP has accepted the claim and provided indemnity in the amount of $11,145.81. The claim settlement amount is not disputed by the applicant. Applicant says FSP took an extended period of time to process the claim The applicant says the FSP took an extended period of time to process the claim, and believes that if he had not lodged a claim with VCAT (or disputes with FOS and ASIC), it would remain outstanding. A detailed timeline of events compiled from the available evidence is set out in Section 3 of this determination. The key dates from this timeline can be summarised as follows: Date s Action 5 October 2016  The applicant’s overseas trip is cancelled. Mid - late October 2016  The applicant believed TA was in the process of lodging the claim with the FSP. 14 December 2016  The FSP receives the applicant’s claim form from TA . December to January  The FSP requests (and the applicant provides) medic al documentation. 6 February 2017  The FSP approves the claim int ernally. 7 February 2017  The applicant lodges an application wit h VCAT and a dispute with FOS.  It appears a complaint was also lodged with ASIC on or around this date. 8 February 2017  The FSP advises the applicant the claim has been accepted and appears to have trans ferred funds that same day. Applicant seeks compensation for time taken to process the claim On the basis of time taken by TA (acting as the FSP’s agent) and the FSP to lodge and process the claim respectively, the applicant seeks the following financial and non-financial compensation:  the cost of lodging the VCAT claim in the amount of $458.60 Case No: 469909 Determination Page 3 of 7  interest on the total claim amount in the amount of $287.19 (based upon an overdraft rate of 9.5% per annum)  loss of earnings (based upon a professional charge out rate of $275) and non- financial loss for the stress suffered in the amount of $8,108.40 The applicant also seeks for the FSP and TA to be penalised for their inaction in processing the claim. FOS unable to consider an award for punitive damages With regards to the applicant seeking the FSP and TA to be penalised for a perceived inaction in processing the claim, it is beyond the jurisdiction of FOS to consider any award for punitive damages. FOS may award compensation for financial and non-financial losses Under the Terms of Reference (TOR), FOS may award compensation (capped at $3,300) for consequential financial loss suffered by an applicant in connection with their claim. However, where a policy specifically excludes cover for consequential losses (as in this case), any such losses must have occurred as a result of the way in which the FSP handled the claim, as opposed to being a consequence of the claim itself. In addition, FOS can award up to $3,000 for non-financial loss if the FSP caused the applicant to suffer an unusual degree or extent of inconvenience, delay or interference. It is important to note that an award for non-financial loss is based on an unusual degree or extent. This would not encompass the normal degree of inconvenience a person would suffer when lodging an insurance claim or when in a dispute with their insurer. FOS takes a very conservative approach when considering any award of compensation. FSP not liable for any perceived delay caused by TA There appears to be no dispute that the FSP only received the applicant’s claim form from TA on (or around) 14 December 2016. Considering the loss arose back in October 2016, the applicant believes the FSP itself is responsible for this delay because TA was acting as its authorised agent. The FSP says it holds no such responsibility because:  TA is its agent to the extent of selling the policy only  any subsequent claim needs to be lodged by the applicant, or a representative acting on his behalf  details of how to lodge a claim are outlined in the policy documentation  any assistance provided by TA during the claim lodgment process is provided in TA’s capacity as the applicant’s agent, not the FSP’s. I accept from the available evidence that TA was not an agent of the FSP for the purpose of compiling and lodging the applicant’s claim. Case No: 469909 Determination Page 4 of 7 For this reason, I am not satisfied the FSP is responsible or liable for any perceived delay in the formal lodgement of the applicant’s claim. Therefore, this determination will consider the FSP’s processing of the claim from the point in time the claim was lodged with it, that being on (or around) 14 December 2016. FSP says claim processed in a timely manner following receipt With regards to its processing of the claim, the FSP does acknowledge a General Insurance Code of Practice (the Code) related delay of three days (13 working days as opposed to 10 working days) in requesting completion of the associated medical authority form. However, it says all other timeframes were well within associated Code timeframes. The timeline of events in Section 3 reference the associated Code timeframes. Further, the FSP says its acceptance of the claim was not due to the VCAT application, rather it followed completion of the medical assessment in early February 2017. In support of this assertion, the FSP refers to a claim file note of 6 February 2017, which states: “High cost claim $$ 11.9K $$ Opinion back from CMC Prof [initials] New condition after relevant time (single trip) Approved for reimbursement, less applicable XS” FSP did not err in its overall claim handling Having considered the available evidence, I am not satisfied the FSP erred in its overall handling of the claim because:  the FSP cannot be held liable for any perceived delay in lodgment of the claim by TA  the claim was accepted within two months of claim lodgment  the FSP was entitled to request associated medical information in order to assess the claim in line with both the Product Disclosure Statement and the Code  the FSP kept the applicant reasonably informed (and provided contact details) as to the progress of the claim and (with the one exception detailed above) in line with Code requirements  there is no evidence the applicant lodging a claim with VCAT (or complaint with FOS or ASIC) had any bearing on the FSP’s claim approval, and which occurred internally the day prior to the applicant lodging the VCAT claim. FSP not required to provide compensation for to the applicant As discussed above, whilst I accept the applicant’s loss arose back in October 2016, I can only consider the FSP’s conduct from the point in time when it received the claim. With regards to the applicant’s claim for the VCAT claim lodgement fee, interest and lost earnings, I am not satisfied the FSP is liable to pay compensation for these. Case No: 469909 Determination Page 5 of 7 This is because (as discussed above) FOS can only award such compensation where the losses occurred as a result of the way in which the FSP handled the applicant’s claim . For the reasons set out above, I am not satisfied the losses occurred as a result of the FSP erring in its claim handling and as such, are specifically excluded from cover under the policy. With regards to the applicant’s claim for non -financial loss, I am again not satisfied the FSP is liable to pay associated compensation. I accept the applicant suffered a level of inconvenience as a result of the claim process. However, as discussed above FOS takes a very conservative approach when considering any such award. In this instance, I am not satisfied the inconvenience suffered was of an unusual degree or extent (from 14 December 2016) as required for such an award. For these reasons, the FSP is not required to pay the applicant any compensation. Case No: 469909 Determination Page 6 of 7 3 Supporting information 3.1 Timeline of events Date s Action 5 October 2016  The applicant’s o verseas trip (due to depart on 14 October 2016) is cancelled. Mid - late October 2016  The applicant believes the claim is being lodged with the FSP on his behalf by TA . 29 November 2016  The date of signature of the claim form (although disputed by the applicant on the basis it is not his handwriting).  TA says she attended the applicant’s home earlier this month to complete the form. 14 December 2016  The FSP receives the applicant’s claim form. 19 December 2016  The FSP sends a claim rec eipt acknowledgment applicant and advic e it is being referred to th e medical team for review. (Three work ing days from claim receipt – Code compliant)  The applicant replie s to the FSP queryi ng the delay as he believed TA lodged the claim three weeks ago. 5 January 2017  The FSP requests completion of a medical authority f orm in order to obtain further medical information required to process the claim. (Thirt een work ing days from claim receipt – three work ing days outside Code compliance) 9 January 2017  The FSP receives the signed medical aut hority form.  The applicant also expresses his dissatisfaction with the claim processing timeframes , and requests the FSP process the claim immediately to avoid being issued with legal proceedings. 17 January 2017  The FSP sends a m edical authority receipt acknowledgment and claim progre ss update to the applicant with a request for specific referral information and reports regarding the applicant wife’s medical procedure. (Six work ing days – Code compliant)  The applicant replies to the FSP advising he will be instigating legal proceedings via his solicitor. 18 January 2017  Further medical information is received from the applicant wife’s general practitioner. 24 January 2017  Travel agent calls the FSP, and provided with an update. 31 January 2017  Travel agent calls the FSP, and provided with an update. 1 February 2017  The FSP advises its medical team is reviewing associated information. Case No: 469909 Determination Page 7 of 7 (Eleven work ing days – Code compliant)  The applicant advises that in addition to instigating legal proceedings to purs ue claim indemnity, costs and interest, he will be lodging a complaint with FOS and ASIC. 6 February 2017  Internal FSP claim authorisation. 7 February 2017  The applicant advises that in addition to lodging a complaint with FOS and ASIC, he has just lodged a claim with VCAT (now withd rawn). 8 February 2017  Applicant’s dispute file opened by FOS.  The FSP advises it will provide indemnit y in the amount of $11, 145.81 , and appears to have been transferred funds that same day.  The FSP notes one amendment cost was not approved because the p olicy only covers amendment or cancellation costs, not both. (Five work ing days – Code compliant) 3.2 Policy provisions Policy Conditions … Claims … You must at Your own expense, supply any documents in support of Your claim which We may request, such as … medical certificates and You must co-operat e fully in the assessment or investigation of Your claim. … General Exclusions We Will Not Pay For: …  claims involving consequential loss of any kind including loss of enjoyment or any financial loss not specifically covered in the policy.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.