Determination 468008

Partial denial of storm-related external render damage

FirmFinancial Firm (Unknown - Insurer)
Decided2018-04-30
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$14,709
Non-financial loss—
Amount claimed$83,841
SourceAFCA PDF

Summary

The applicants claimed storm damage to their home, with repair costs around $83,841, and the FSP paid $14,670 and denied most external render damage as long-term thermal movement. AFCA found the storm contributed 25 percent to the render cracking, ordered an additional $14,708.91 with interest, and noted errors in the FSP's expert inspections.

The panel found the cracking pattern pointed mainly to gradual thermal expansion under the gradual deterioration exclusion, but the storm contributed to the storm-facing render so a proportionate contribution was payable.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 468008 Determination Page 1 of 9 Case number: 468008 03 April 2018 1 Overview 1.1 Dispute The applicants lodged a claim on their home insurance policy with the financial services provider (FSP), after their home sustained damage due to a storm event. The FSP admitted the claim, however, a dispute arose over the extent of damage covered under the policy. The FSP believes its liability for the damage to the building is $14,670, however, the applicants say the repair costs are in excess of $80,000 – the bulk of which relates to repairing the granosite render on the property. The FSP does not agree the granosite damage is storm related but rather it is due to long term material expansion and contraction of the blue board linings. The applicants do not agree and rely on engineering reports provided by their own expert which say the cracking is related to the storm event. Further, they say the FSP did not fully assess the damage to the exterior of the property and there have been s everal mistakes made in the FSP’s expert reports. 1.2 Issues and key findings Have the applicants established a claim covered by the terms of the policy? There is no dispute the applicants’ property was damaged by a storm event which occurred on 21 April 2015. The FSP has admitted liability for water damage to parts of the building and also to the applicants’ contents. The applicants have therefore established an insured event under the policy. Is the FSP entitled to rely upon exclusions within the policy? The FSP is entitled to rely upon exclusions within the policy to deny part of the applicants’ claim, in accordance with this determination. 1.3 Determination This determination is partially in favour of the applicants. The FSP is to pay the applicants the additional amount of $14,708.91, to finalise all of its obligations in respect of the claim and this dispute. The FSP is to pay interest on this amount, in accordance with the Insurance Contracts Act 1984 (the Act) from 7 June 2017, until the date the additional payment is made. Case No: 468008 Determination Page 2 of 9 2 Reasons for determination 2.1 Have the applicants established a claim covered by the terms of the policy? Policy provides cover for insured events subject to exclusions The applicants are required to show that, on the balance of probabilities, they have suffered a loss caused by a risk insured against under the policy. If the applicants are able to establish a claim covered by the policy, then the onus shifts to the FSP to show that, on the balance of probabilities, it is entitled to rely on an exclusion under the policy or is otherwise entitled to deny the claim. The policy provides cover for damage to the applicants’ property caused by the insured events listed in the policy (including ‘storm’), subject to the conditions and exclusions set out in the policy. There is no dispute the applicants’ property was damaged during a significant storm event in April 2015. The FSP has accepted liability for damage to the applicants’ contents and also to internal areas of the property damaged by water ingress and some aspects of the external damage. The Panel is therefore satisfied that the applicants have established a claim covered by the terms of the policy. However, the policy also contains a general exclusion for damage caused by wear, tear, atmospheric or climatic conditions, gradual deterioration or arising from ground movement, unless it relates to subsidence occurring within 72 hours of a storm. The issue is whether the FSP has established the application of exclusions to part, if any, of the applica nts’ claim. 2.2 Is the FSP entitled to rely upon exclusions within the policy? FSP expert reports contain errors and omissions The applicants have raised several issues with the FSP expert’s assessments. The claim case notes confirm the applicants told the FSP several times that the experts were missing things when they attended and they wanted someone to come out and go through the scope of works with them. The FSP then increased its original cash settlement offer of $9,944 to $14,670, however, it did not tell the applicants what the amount covered for internal damage. The applicants raised the following concerns in relation to the FSP’s assessment:  the FSP’s agents did not look at the entire property in regards to the external damage  the FSP’s expert report fo r the roof contained photographs that were not the applicants’ property  the engineer’s findings were based on the assumption the property was on a concrete slab, however, it is not. Case No: 468008 Determination Page 3 of 9 The FSP acknowledges the roof report contains incorrect photographs and apologises for the error. However, it says the conclusions are based solely on the photographs of the applicants’ roof, which are also included in the report. The Panel accepts the FSP’s comments, and further notes the decline of the roof repairs does not appear to form part of this dispute. During the dispute process, the Service arranged for the FSP to send its expert back to the applicants’ property to meet with his engineer, so the parties could be satisfied that all damage had been assessed. Unfortunately, due to a breakdown in communication between the FSP and its expert, the site inspector (MK) would only view damage he had previously commented on as he had not been instructed to look at anything new. Despite the presence of the applicants ’ engineer, the FSP’s expert said he would only look at limited areas of the property – none of which were relevant to the additional inspection – and all of which MK had already seen. The FSP acknowledges this was an error on its part, however, a further inspection with the applicants’ engineer could not be organised as he had gone overseas. The FSP therefore commissioned a desktop report from MPA, dated 13 July 2017. Whilst the original report from MPA contains errors, the Panel is of the view that MPA’s subsequent reports clarify the issues in dispute and the likely cause of the damage at the applicants’ property. The Panel has considered the findings of MPA in relation to the locations of the cracks in the granosite, which appear to be along the joins o f the blue board and MPA’s opinion that he would expect to see cracks elsewhere in the property had the building shifted due to ground movement. The Panel agrees with this opinion. Having reviewed all of the exchanged information, the Panel is satisfied that whilst the storm event has contributed to the damage of the building, the likely cause of the bulk of the damage to the external render is thermal expansion and contraction over time and is principally located along the blue board joints beneath the external render. In this regard, the Panel is of the view that had the storm been the principal cause of damage, then the cracks noted would have had a similar pattern, both internally and externally, which they have not. The result is that the FSP is entitled to rely upon the policy exclusions for atmospheric and climatic conditions and the exclusion for gradual deterioration, to deny the bulk of the applicants’ claim in respect of the external damage. For the sake of completeness, the Panel is not satisfied that the damage occurred within 72 hours of the storm event and likely occurred over a much longer period of time. Despite this, the Panel is also of the view that the severity of the storm would likely have contributed to a limited extent to the cracking of the render on the storm-facing side of the building and therefore the FSP should be required to make a contribution to the cost of repair. Case No: 468008 Determination Page 4 of 9 2.3 What is the extent of the FSP’s obligations to the applicants? The quotations provided by the parties differ significantly. The Panel has found it difficult to compare the various quotations. However, having reviewed all of the exchanged material, the Panel accepts that the FSP’s builder’s quote of $14,760 , provides a base on which to determine a fair outcome. Having said that, the Panel wants to ensure that the quote carries an appropriate builder’s margin and reflects the risk which is transferred to the applicants by allowing a cash settlement. In the Pan el’s view a margin of 15% should be added to the FSP’s quote to cover this risk. The amount payable for this part of the claim is therefore $16,974. The Panel is of the view that the storm likely contributed 25% to the cracking of the external render and thus the FSP should contribute 25% of the cost of re-rendering and repainting the house, together with the related costs. The only costing available for the re-rendering of the house is contained in the quote provided by the applicants’ builder. Noting the relevant items from that quote, those items which relate to the re-rendering process include the granosite, $19,680; repainting of the external surface of the house, $12,045; and the cost of scaffolding to facilitate the process, $7,500. Together with GST, the total cost is estimated at $43,147.50. The FSP is required to contribute 25% of that cost, plus a margin of 15%, being $12,404.91. Doing what is fair in all the circumstances and in any effort to bring this dispute to a conclusion, the Panel is satisfied that the FSP should pay the applicants the amount of $29,378.91, less the amount already paid to the applicants - $14,670. Therefore the FSP is required to pay an additional amount of $14,708.91 to finalise its obligations in respect of the claim and this dispute. ( This includes the amount of $90.00, being the difference between the FSP’s assessor’s quote of $14,760 and the FSP’s payment of $14,670 .) The FSP is to pay interest on the additional amount of $14,708.91 from 17 June 2017 to the date of payment. Case No: 468008 Determination Page 5 of 9 3 Supporting information 3.1 FOS approach to this determination This case has been decided on its merits, having regard to what is fair in all the circumstances, the relevant law, good industry practices, codes of practice and previous FOS decisions. There has been a full exchange of all material information relied on for the purpose of this determination and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered. While the parties have raised numerous issues in their submissions, for the purpose of the determination, commentary has been restricted to those issues which are considered directly relevant to the outcome. 3.2 Terms of the policy Policy term Key poin ts What you are covered for – Insured Events Pages 16 - 25 Storm We cover  loss or damage to the building caused by a Storm We do not cover  loss or damage caus ed by erosion, vibration, subsidence, landslip, landslide, mudslide, collapse, shrinkage or any other earth movement, but we will cover loss or damage to the building caused by a landslide or subsidence provide d to have occurred within 72 hours of, and directly becaus e of, a storm and not because of erosion over time, structural fault or design fault What we do not cover – general exclusions Pages 33 - 40 Ground movement Erosion, vibration, subsidence, landslip, landslide, mudslide, collapse, shrinkage or any other earth movement, but we will cover landslide or subsidence that is specifically covered under the insured events:  Storm Wear, tear and gradual deterioration Wear, tear, rust, fading, rising damp. Mould, mildew, corrosion, rot, action of light, atmospheric or climatic conditions or gradual deterioration What do we mean by that? Pages 53 - 55 Storm Means a storm, cyclone or severe atmospheric disturbance. It can be accompanied by strong winds, rain, lightning, hail, snow or dust. Case No: 468008 Determination Page 6 of 9 3.3 Key documents Document Key points Claim Case Note s (FSP) April 2015 – Jan 2017  25.04. 15 – APP lodges claim for DoL 21.04.15, storm damage  09.05. 15 – APP requests make - safe as carpet is mouldy  15.07. 17 – FSP cash settle contents and start to review building damage  05.03. 16 – APP wants someone to contact him re engineer’s report which only advises 1 part of house is damaged. (APP) has had engineer attend who advises 3 parts of the house are damaged  08.04. 16 – reviewed reports, we need to appoint an engineer to see if external walls are covered  08.06. 16 – reviewed report, advises damage not caused by the storm event bu t ‘long term material expansion and contraction of the linings;  04.07. 16 (APP) called not happy wit h amended SoW – he said no one has checked the roof other than the person who did the make - safe. FSP say they have report from LS – APP says LS expert was a carpenter. FSP says it will send someone out to look at the roof.  03.08. 16 (APP) not happy with final settlement offer of $9,944, lots of things missing. APP does not agree with roof report that says no damage. FSP tell APP if he wants to dispute roof he w ill need to get his own report  22.10. 16 – FSP receive APP’s quot e which it does not agree with. APP quote is extensive with non - claimable repairs included such as cracking to the blue board render throughout the house. FSP ask APP for itemised quote – APP does not want to provide this but instead wants assessor to come out and discuss SoW at the property  15.11. 16 – FSP increase offer to $14,760 to include repairs to bathroom reveal and garage skirtings. APP says he will consider settlement in region of $50k – FSP say it cannot consider that.  16.12. 16 – FSP pay cash settlement to APP ($14,670)  16.12. 16 – FSP speak to APP who says he will engage lawyer  23.01. 17 – FSP notified dispute is at FOS. FSP’s expert (LS) Building report 22 - 05 - 15 We believe the following damages are related to the event Internal  plasterboard ceiling & wall in lounge room  MDF skirting in garage  MDF window reveal and architraves in bathroom External  roller doors to garage  decorative disc to gable  transparent acrylic brick Case No: 468008 Determination Page 7 of 9  texture c oating to front veranda  TV antennae will need retuning We believe a separate roof report is required – maintenance issues found during roof ins pection. FSP’s expert (LS) Roof report 2 4 - 0 6 - 15  Inspection of the roof revealed that flashings have recently been sealed to stop water ingress  Inefficient flashings and unsealed joins are causing water ingress  These maintenance issues are the res ponsibility of (APP) and we recommend (APP) arranges for these to be rectified to avoid further resultant damages  Due t o the maintenance issues being the cause of the storm water ingress, we recommend claim be referred to the insurer . FSP’s expert (R) Reins pection report & SoW 29 - 03 - 16  Purpose of visit to determine the extent of internal repairs.  Damage to granosite is t o be determined by engineer (cause)  In front lounge room one glass block in the window needs to be replaced, several will need to be removed to get the damaged block  SoW - $14,760. FSP’s expert (MPA) Engineering report 06 - 06 - 16  We observed several cracks in the external granosite coating, however most of these cracks appeared old  We observed a damaged glazed brick window. Insured indicated this was caused by tree branch impact. If the undamaged bricks cannot be salvaged the whole window may need to be replaced  We observed the blue board had been damaged at the south western side. Ins ured advised this was impacted by an object. We recommend repairing to match existing. We also observed several cracks along the blue board joints in this area most of which appeared old  The cracking to the external granosite has occurred primarily along the blue board joints beneath it.  In our opinion this has occurred over time due to thermal expansion and contraction. FSP IDR (AS) Correspondence 05 - 12 - 16 ‘During my review I discussed the report findings with (MPA) so as to clarify their findings further. It was confirmed they do not consider the external cracking has been caused by the storm event as the property was built on a concrete base as oppo sed to stumps, so would be less susceptible to ground movement issues.’ FSP’s expert (MPA) Supplement ary report 10 - 05 - 17  We accept the customer’s advice that the building is constructed on a different footing system, apart from the garage, which has a co ncrete floor  Notwithstanding, the actual footing arrangements for the house were not material to the conclusion we formed  The cracking to the structure is independent to the footing type and does not cause us to alter the conclusions we Case No: 468008 Determination Page 8 of 9 reached in the original reports. FSP Email corres pondence 15 - 05 - 17  We have received confirmation the 3 phot os have been added to the DPS report in error, and have not been relied upon in any of the findings . FSP’s expert (MPA) Engineering report 13 - 07 - 17  We have review ed (APP’s expert) SE’s report of January 2016 and an updated version of this report following our engineer’s (MK) reinspection dated 24. 05.17  Does not agree with SE report as it does not discuss mechanics of how cracking has only occurred along the externa l blue board joints  If footing movement of building had occurred because of a storm, we would expect some cracking to the external wall linings however this was not seen during our visit  The pattern of cracking does not indicate the damage has occurred due to footing movement. External blue board cracks were observed throughout the perimeter. If damage occurred due to footing movement, we would expect more cracks adjacent to typical locations such as wall openings which are more susceptible to crack due to footing movements.  We would also expect reversal movement in the observed cracks as the soil moisture dries out. We did not observe this during our visits. APP’ s expert (SE ) Structural r eport undated  Site inspections conducted October 2015 and 30.01.16  Visual inspection only  Purpose of the inspection was to determine the cause of the damage and provide a SoW  Preliminary report only External damage  Decorative disc to gable requires replacement  Trans parent acrylic brick requires replacement  Granosite textu re coat has incurred wides pread damage around dwelling’s full perimeter - further ingress of water following damage has/will exacerbate the damage to the external skin of the dwelling  Granosite to columns on eastern elevation are more severely damaged It is most probable that the damage to the external granosite has been caused by a combination of foundation movement from the April 2015 storm/flood followed by a continual ingress of stormwater during and following the April 2015 event Internal damage  Damage to internal linings in main bedroom, garage, family room, and bathroom.  Water damage is evidence in ceiling linings, archit raves, wall Case No: 468008 Determination Page 9 of 9 linings and skirting boards It is most probable that the damage to the internal linings has been caused by roof damage during the April 2015 storm event followed by a continual ingress of stormwater during and following the April 2015 event. Applicant’ s expert ( SE ) Revised report undated  Meeting with FSP expert (MK) on 24.05.17  This meeting proved fruitless as MK had bee n instructed to inspect/report on only a small number of minor as pects of the damage  Major as pects of the damage, as report ed by SE in the February 2016 report were not inspected by MK as he informed (APP) that he had not been instructed to do so External Damage  It is evident that external granosite damage is more severe in areas where the external walls were less protected from the storm and from airborne debris during the high winds  The argument that the granosite cracking has been caused by thermal expan sion is flawed as the Southern elevation of the dwelling exhibits more severe damage than the northern elevation. APP’ s expert (BB) Itemised q uot e 07 - 06 - 17  Repair damaged fac ades to southern and nort hern side of garage  Remove and replace blueboard cladding eastern side  Replace approx. 30m of external mouldex mouldings  Granosite to entire house  Replace 32m of 66x18mm skirting to garage  Repair water damage to ceiling lounge room  Replace reveal and architraves to bathroom  Replace damaged Perspex block window  Paint garage walls ceilings and new skirtings  Paint lounge walls and ceilings throughout  Paint external house  6 weeks of scaffolding  Total $83,841.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.