Home / Financial Firm (Unknown - Credit) / Determination 467383

Determination 467383

Construction funding not approved after FSP led applicants to plan a six-unit development

FirmFinancial Firm (Unknown - Credit)
Decided2018-08-17
ProductCredit · Home loan
OutcomeFor the complainant in part
Amount awarded$25,679
Non-financial loss$12,000
Amount claimed—
SourceAFCA PDF

Summary

Applicants refinanced loans with the FSP while planning a six-unit development, and the FSP later declined construction finance. AFCA found the FSP misled them and ordered $40,295.65 compensation, including $12,000 non-financial loss, but rejected accrued interest on pre-existing loans and lost expected profits.

Remedy for misleading conduct is measured by what the applicants would have done differently had they known the funding would not be provided, applying the duty to mitigate loss.

Issues

Subjects and remedies

financial hardshippay compensationpay interestpay non financial lossrefund fees or charges

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Case No: 467383 Determination Page 1 of 8 Case number: 467383 17 July 2018 1 Overview 1.1 Dispute The FSP did not approve a loan to fund the Applicants’ property development (loan). They have not been able to fund the development. The applicants are seeking compensation for the loss they have suffered because the FSP misled them into believing that the construction funding would be forthcoming. 1.2 Issues and key findings Did the FSP “ coax ” the applicants? Even if the FSP encouraged the applicants to develop six units instead of three, that was a choice made by the applicants. Did the FSP mislead the applicants about whether it would fund a six unit development? The FSP knew that the applicants were proceeding with a six unit development proposal and that such a proposal needed to be assessed by the small lending department of the FSP. The application for funding should have been made at the same time as the refinance funding. If the applicants knew that construction funding would not be forthcoming earlier, it is more likely than not they would not have refinanced with the FSP What is the applicants’ loss? The applicants are not entitled to all of the interest accrued on the loans they refinanced, or the loss of expected profits. The applicants also had an obligation to minimise their losses by selling one of the properties earlier. The applicants are entitled to compensation as set out in this determination. 1.3 Determination This determination is in favour of the applicants. The FSP should pay the applicants compensation totalling $40,295.65 as set out in the determination. The parties should then talk to each other about how the remaining loans and arrears are to be repaid. Case No: 467383 Determination Page 2 of 8 2 Reasons for determination 2.1 Did the FSP coax the applicants? The FSP did not convince the applicants to build six units The applicants say that they provided information to the FSP staff member who would enter it into a spreadsheet. The spreadsheet was then used to assess the affordability of the project. The applicants say that as a result of entering the information into the spreadsheet, they were persuaded by the FSP to do a six unit development rather than a three unit development. The FSP has not been able to provide such a spreadsheet. In my view, even if the FSP encouraged the applicants to proceed with a six unit development, they did not have to agree to such a proposal. It was the applicants’ choice to do a six unit development rather than three. The principal applicant works in real estate and the applicants had previously completed a development with another lender. They would have a reasonable knowledge of how developments are funded and of what to build. In addition, during 2014, the applicants said that the bank manager: „…completed some modellin g on his computer and on the 20 th of September 2014, he responded with “there may be a deal here but significant amount of extra information required in order to make an informed assessment.” It was open to the applicants to accept or reject any suggestion made by the FSP (if made) to proceed with a six unit development as opposed to a three unit development. However, for the reasons set out below it is my view that the FSP misled the applicants into believing that the bank would finance a six unit development from the outset. 2.2 Did the FSP mislead the applicants about whether it would fund a six unit development? The FSP knew the applicants were planning to build six units It is my view that by early 2015, the FSP knew that the applicants were proceeding with a six unit development, most likely by completing the first three units and then developing the next three units. I reach this view for the following reasons:  The applicants had signed contracts to build six units in November 2014;  The six contracts were provided to the FSP in April 2015;  The email exchange between the applicants and the FSP in April 2015 indicated that the applicants intended to build three units first and then turn to building the next three. What is clear, is that the applicants intended to build all six units, with the second three units starting soon after. For example an email from the applicant that was forwarded to the FSP on 15 April 2015 says: Case No: 467383 Determination Page 3 of 8 “We are looking at building 6 properties 4 at the back and 2 the front … Once 15 is at lock up we need to completed (sic) build on 17 A St with the remaining 3 homes”  In July 2015, the applicant emailed the FSP advising that the Council had given planning approval for all six units. The FSP says that it told the applicants that the branch could only approve construction finance for three units and that if they wanted to proceed to build all six units, the loan application would need to be dealt with by the FSP’s small business lending department. For the reasons stated above, it is my view that the applicants clearly intended, and the FSP knew, that they intended to build six units. Even if all six units were not to be built at the same time, the second three units would be built soon after the first the first three. In substance, the plan was to build six units. As such, the FSP should have referred the applicants’ loan application to the FSP’s small business unit from the outset. Despite this, the loan application remained with the branch. The first part of the loan application wa s to refinance the applicants’ existing loans with other lenders to the FSP. The next part was to provide construction funding. The refinance Notwithstanding that it was clear to the FSP that the applicants intended to build six units (even as a 2 x 3 proposition) the refinance application was submitted on the basis that they applicants planned to build only three. The FSP’s credit submission dated 28 April 2015 says: “They have two blocks of residential land … of which the council have provided written confirmation to build 3 dwellings” The facilities were obtained to:  refinance existing debts with another lender in the amount of $36,000 and $490,000  refinance an existing loan of $140,000 with another lender and  obtain an additional $90,000 under the line of credit. The refinance was approved in May 2015 and completed in August 2015. As noted above, most of the loan was to refinance existing liabilities and to the extent that those liabilities existed, the applicants have not suffered a loss. Instead of owing those loans to the previous lenders, they owed them to the FSP. Once the existing loans were refinanced, the FSP then submitted a loan for the building approval. It is not clear to me why this was not done earlier – either at or before the time of the refinance. When the application for a loan to build was submitted by the FSP, it appears it was still being submitted on the basis that the applicants wanted to build three units, even though it was well known to the FSP that the applicants intended to build six units. For example, the entry in the FSP’s notes for 20 August 2018 says: Case No: 467383 Determination Page 4 of 8 “ Purpose to Build 3 x new Resi Investment properties ” The FSP ultimately decided that they did not want to lend to find the construction of the units, whether that be three or six. It is also noted that if the plan was to build six units, the application should have been made to the FSP’s small business lending area from the outset. In my view, the FSP misled the applicants into believing that if they refinanced, there was a very good chance that the FSP would fund the development of six units. At the very least, in my view, it would have been good banking practice to assess the construction finance application either before or simultaneo usly with the application to refinance. 2.3 What is the applicants’ loss The remedy for misleading conduct is not to make the promise come true – that is for the FSP to provide the construction funding – but to ask what the applicants would have done differently if they had known before they refinanced, that the FSP would not provide construction funding. In my view, what the applicants would have done differently had they known by 27 May 2015 (when the FSP gave conditional approval for the refinance) that the FSP would not provide construction funding, the applicants:  would not have refinanced with the FSP  would have made enquiries with other lenders, only to find that they could not get funding;  having made those enquiries, minimised their loss by selling the property. Claims for loss that are not made out The applicants have claimed they are entitled to the following items for their loss:  The interest that has accrued on their loans from 2015 to date;  The loss of opportunity to make a profit on a sma ller development Interest on pre-existing loans is not a loss The applicants are not entitled to interest on the loans that were refinanced (except as outlined below) because these loans already existed before the FSP refinanced. As these loans already existed, so did their liability to pay interest on the amounts borrowed. The liability merely moved from one lender to another. While the applicants would not have borrowed the additional $90,000 in 2015, they have not used the additional available funds on loan 2784. While the account balance for this loan has increased, it is because interest has continued to accrue on the amount refinanced and no payments have been made. Even if the FSP had not refinanced the existing facility, the applicants still had the liability to make payments even if they had not been misled. Case No: 467383 Determination Page 5 of 8 Loss of expected profits are not recoverable The remedy for misleading conduct is not to make the promise come true – that is the provision of finance, followed by the construction and ultimate sale of the units. Rather the question is what the applicants could have done differently had they know the true situation. When the FSP declined the first construction loan application, the applicants and the FSP continued to negotiate to see if a deal could be done, but by March 2016, it was abundantly clear that the FSP could not provide finance. The applicants have said that they have been unable to obtain funding to proceed with the development from another lender. Given that the applicants could not obtain funding, the development was never going to proceed and the expected profit would not eventuate. If funding were available for a smaller development, the applicants should have undertaken that development a lot sooner that they have. However, no development has been done. While they did expect to make that profit, the law does not provide compensation for loss of expectation. Applicants had an obligation to minimise their loss Having discovered that the FSP would not provide finance, and that they could not obtain suitable finance from another lender, it is my view that the applicants should have mitigated their losses by selling one or both of the properties. In my view, the most logical thing to do, having regard to the obligation to minimise their loss, was for the applicants to sell one of the properties and use the funds to reduce their liability to the FSP. Applicants’ loss is $ 40,295.65 For the following reasons, and having regard to the applicants’ obligation to minimise their loss, I am of the view that the applicants are entitled to compensation totalling $40,295.65. Refinance costs to be refunded The applicants would not have incurred the refinance costs of $661, being the following items charged to loan 2784: Item Amount Government Title Search Fee $53 Registration Fee - Mortgage $304 Discharge of Mortgage Fee $304 Total $661 Case No: 467383 Determination Page 6 of 8 The amount to be refunded is $761, being the $661 plus interest at 5% for three years. Applicants should have sold six months earlier In my view, having discovered that the FSP would not provide finance and that no other finance was available, the applicants should have sold one of the properties. If the FSP had assessed the construction funding in May 2015, this sale process would have happened six months earlier than it should have. If the applicants sold the property and used the funds to reduce their liability to the FSP, they would have saved six months’ worth of interest. This is calculated as follows: Loan Number and interest rate Amount 2629 (4.43%) $10,853.50 0391 (5.43%) $3, 978 .00 (includes $125 being the facility fee for six months) 2784 (4.43%) $886 Total $15, 717 .50 The FSP is also to pay interest at 5% on this amount for two years, on the basis that the property would have sold in 2016. The total amount to be paid is $17,289.25. Holding costs for six months In addition, they could have avoided the holding costs for that period. In my view, therefore the FSP should also pay the applicants’ holding costs for six months: Item Amount Rates $605 Land Tax $300 Water rates $300 Building Insurance $200 Total $1,405 The FSP should refund $1,615, being $1,405 plus interest at $70 per annum for three years. Case No: 467383 Determination Page 7 of 8 Approval fees “thrown away” The applicants also incurred costs in getting council approval for the development. Item Amount Land division $1,273.60 Community division $1,301.80 Council approval $1,000 Proposed plan Prep, DAC lodgement $1,320 Total $4,895.40 As it is my view that the applicants should have mitigated their loss by selling the property, these costs have been “thrown away” and should be refunded in full, together with interest for three years at $245 per annum. The total amount to be refunded is $5,630.40. Cost of restoring the title to two separate titles As part of the plan to construct the units, the applicants consolidated the title to the two properties. The applicants wish subdivide the property back into two titles so the parents can conti nue to reside in the property and the other sold. The FSP should pay $3,000 to assist in this process. This amount should be paid to directly to the applicants. Non-financial loss In my view, the applicants are also entitled to non-financial loss of $3,000 each (total $12,000) of which $9,000 is to be applied to the loans as set out below. The remaining $3,000 is to be paid directly to Mr PS, as he is not a borrower to any of the existing loans. The loans going forward The current balances of the loans (as at 17 July 2018) are as follows: Loan Number Balance Arrears 2629 $543,750.94 $ 53,750.94 0391 184,924.84 Nil 2784 45,135.49 $ 6,960.45 Case No: 467383 Determination Page 8 of 8 Of the $40,295.65 compensation payable, $6,000 is to be paid directly to one or more of the applicants. The remaining $34,295.65 is to be paid as follows:  $6,960.45 is to be paid to loan 2784 to clear the arrears  $27,335.20 is to be paid to loan 2629, reducing the arrears to $26,415.74. The applicants should contact the FSP within 14 days of accepting this determination to discuss an arrangement to repay the arrears. The applicants should provide a statement of their current financial position and a proposal as to how the arrears can be paid. One solution may be for the applicants to make the minimum monthly payments for six months and if all payments are made, the FSP would capitalise the arrears and either increase the monthly payments or extend the loan term, depending on the applicants’ current financial posi tion. If the parties are unable to come to an arrangement and the applicants are still in financial difficulty, the applicants can lodge a new dispute about how the loans are to be repaid in the future.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.